Building Industry Fairness (Security of Payment) Act 2017
In ForceQLD
Jurisdiction
Queensland
Act Number
43 of 2017
Collection
act
Plain English Summary
8/10 complexity
This law makes certain building contracts require a statutory trust into which payments must be deposited, and sets rules for progress claims, payment responses, adjudication and a subcontractor’s charge to help ensure subcontractors get paid (s.3, ss.11–21). It affects contracting parties, contracted parties (who will be trustees), subcontractors, auditors and adjudicators by creating deposit, account, notice, audit and payment-priority obligations with criminal and civil penalties for non‑compliance (chs.2–5).
The Building Industry Fairness (Security of Payment) Act 2017 (the Act) establishes a comprehensive framework to secure payment for work in the building and construction industry. Its main purpose, stated in s.3(1), is "to help people working in the building and construction industry in being paid for the work they do." This is achieved primarily through four interlocking mechanisms set out in s.3(2):
(a) requiring the use of statutory trusts for particular contracts (project trusts under Ch 2 Pt 2 and retention trusts under Ch 2 Pt 3);
(b) granting an entitlement to progress payments, whether or not the relevant contract makes provision for them (Ch 3 Pt 2);
(c) establishing a procedure for making payment claims, responding to them, the adjudication of disputed claims, and the recovery of amounts claimed (Ch 3 Pts 3–4); and
(d) enabling the use of a statutory charge in favour of subcontractors (Ch 4).
The Act binds all persons, including the State, and, as far as legislative power permits, the Commonwealth and other States (s.4).
Project trusts are the centrepiece of the trust regime. Under s.11, a project trust is a trust over amounts payable in connection with a project trust contract or subcontract and required to be deposited in the project trust account. The contracted party is both trustee and beneficiary (s.11A(1)), while subcontractors for project trust subcontracts are beneficiaries (s.11A(3)). Beneficial interests are defined in s.11B: subcontractors have an interest in amounts they are entitled to be paid, with the contractor holding the remainder. Trusts are required for contracts meeting the eligibility criteria in s.14 (contract price $1 million or more where >50% is project trust work, with the contracting party being the State, a State authority, local government, individual, private entity or hospital and health service) or prescribed by regulation (s.14D), subject to exemptions in ss.15–15F (e.g. small-scale residential work, maintenance, professional design, contracts with <90 days to practical completion). The requirement is triggered when the contracted party enters a subcontract (s.12(2)(c)) and continues until dissolution under s.21, regardless of variations or changes in price or scope (s.12(4)).
Current sections
Direct links to the current provisions in Building Industry Fairness (Security of Payment) Act 2017.
403
ch.1-pt.1
Introduction
Introduction
sec.1
Short title
sec.1 Short title
This Act may be cited as the Building Industry Fairness (Security of Payment) Act 2017 .
sec.2
Commencement
sec.2 Commencement
Chapter 9 , part 1 , divisions 1 to 4 commence on a day to be fixed by proclamation.
The Acts Interpretation Act 1954 , section 15DA does not apply to chapter 9 , part 1 , divisions 1 to 4 .
The Acts Interpretation Act 1954 , section 15DA , provides for the automatic commencement of certain Acts 1 year after they are assented to.
s 2 amd 2018 No. 17 s 176B ; 2020 No. 24 s 61
(sec.2-ssec.1) Chapter 9 , part 1 , divisions 1 to 4 commence on a day to be fixed by proclamation.
(sec.2-ssec.2) The Acts Interpretation Act 1954 , section 15DA does not apply to chapter 9 , part 1 , divisions 1 to 4 . The Acts Interpretation Act 1954 , section 15DA , provides for the automatic commencement of certain Acts 1 year after they are assented to.
sec.3
The main purpose of Act
sec.3 The main purpose of Act
The main purpose of this Act is to help people working in the building and construction industry in being paid for the work they do.
The main purpose of this Act is to be achieved primarily by—
requiring the use of statutory trusts for particular contracts related to the building and construction industry; and
granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and
establishing a procedure for—
making payment claims; and
responding to payment claims; and
the adjudication of disputed payment claims; and
the recovery of amounts claimed; and
enabling the use of a statutory charge in favour of subcontractors for payment of the work they do.
s 3 amd 2020 No. 24 s 62
(sec.3-ssec.1) The main purpose of this Act is to help people working in the building and construction industry in being paid for the work they do.
(sec.3-ssec.2) The main purpose of this Act is to be achieved primarily by— requiring the use of statutory trusts for particular contracts related to the building and construction industry; and granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and establishing a procedure for— making payment claims; and responding to payment claims; and the adjudication of disputed payment claims; and the recovery of amounts claimed; and enabling the use of a statutory charge in favour of subcontractors for payment of the work they do.
(a) requiring the use of statutory trusts for particular contracts related to the building and construction industry; and
(b) granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and
(c) establishing a procedure for— (i) making payment claims; and (ii) responding to payment claims; and (iii) the adjudication of disputed payment claims; and (iv) the recovery of amounts claimed; and
(i) making payment claims; and
(ii) responding to payment claims; and
(iii) the adjudication of disputed payment claims; and
(iv) the recovery of amounts claimed; and
(d) enabling the use of a statutory charge in favour of subcontractors for payment of the work they do.
(i) making payment claims; and
(ii) responding to payment claims; and
(iii) the adjudication of disputed payment claims; and
(iv) the recovery of amounts claimed; and
ch.1-pt.2
Application and operation of Act
Application and operation of Act
sec.4
Act binds all persons
sec.4 Act binds all persons
This Act binds all persons, including the State, and, as far as the legislative power of the Parliament permits, the Commonwealth and the other States.
ch.1-pt.3
Interpretation
Interpretation
sec.5
Definitions
sec.5 Definitions
The dictionary in schedule 2 defines particular words used in this Act.
sec.6
Subcontracts, subcontractors and subcontracted work
sec.6 Subcontracts, subcontractors and subcontracted work
A contract is a subcontract for another contract if—
performance of the contract contributes to the performance of the other contract because the work, required to be carried out under the contract, will form all or part of the work required to be carried out under the other contract; and
the contribution mentioned in paragraph (a) is not merely coincidence.
the purchase of tools from a retail store
To remove any doubt, it is declared that—
the contribution mentioned in subsection (1) (a) may be indirect because the contract contributes to the performance of 1 or more other subcontracts in order to contribute to the other contract; and
A subcontract that contributes directly to a contract would have 1 entity that is both a party to the subcontract and a party to the contract.
a contract may be a subcontract for another contract regardless of whether any party to the contract is also a party to the other contract.
If the party to a contract, who is required to carry out work under the contract, subcontracts all or part of the work—
the resulting subcontract is a subcontract for the contract; and
the person required to carry out the work under the subcontract is a subcontractor for the contract; and
the work required to be carried out under the subcontract is the subcontracted work for the contract.
The categories of subcontracts are first tier subcontracts, second tier subcontracts, third tier subcontracts and so on.
A subcontract is a first tier subcontract for a contract if—
performance of the subcontract contributes directly to the performance of the contract; and
1 person is both a party to the subcontract and a party to the contract.
A subcontract is a second tier subcontract for a contract if—
performance of the subcontract contributes to the performance of the contract only by also contributing to the performance of another subcontract for the contract; and
no party to the subcontract is also a party to the contract; and
1 person is both a party to the subcontract and a party to the other subcontract.
A subcontract is a higher subcontract for another subcontract if—
performance of the other subcontract contributes to the performance of the subcontract because the work, required to be carried out under the other subcontract, will form all or part of the work required to be carried out under the subcontract; and
both subcontracts are subcontracts for the same contract.
A first tier subcontract would be a higher subcontract for a third tier subcontract if the work required to be carried out under the third tier subcontract will form all or part of the work required to be carried out under the first tier subcontract.
(sec.6-ssec.1) A contract is a subcontract for another contract if— performance of the contract contributes to the performance of the other contract because the work, required to be carried out under the contract, will form all or part of the work required to be carried out under the other contract; and the contribution mentioned in paragraph (a) is not merely coincidence. the purchase of tools from a retail store
(sec.6-ssec.2) To remove any doubt, it is declared that— the contribution mentioned in subsection (1) (a) may be indirect because the contract contributes to the performance of 1 or more other subcontracts in order to contribute to the other contract; and A subcontract that contributes directly to a contract would have 1 entity that is both a party to the subcontract and a party to the contract. a contract may be a subcontract for another contract regardless of whether any party to the contract is also a party to the other contract.
(sec.6-ssec.3) If the party to a contract, who is required to carry out work under the contract, subcontracts all or part of the work— the resulting subcontract is a subcontract for the contract; and the person required to carry out the work under the subcontract is a subcontractor for the contract; and the work required to be carried out under the subcontract is the subcontracted work for the contract.
(sec.6-ssec.4) The categories of subcontracts are first tier subcontracts, second tier subcontracts, third tier subcontracts and so on.
(sec.6-ssec.5) A subcontract is a first tier subcontract for a contract if— performance of the subcontract contributes directly to the performance of the contract; and 1 person is both a party to the subcontract and a party to the contract.
(sec.6-ssec.6) A subcontract is a second tier subcontract for a contract if— performance of the subcontract contributes to the performance of the contract only by also contributing to the performance of another subcontract for the contract; and no party to the subcontract is also a party to the contract; and 1 person is both a party to the subcontract and a party to the other subcontract.
(sec.6-ssec.7) A subcontract is a higher subcontract for another subcontract if— performance of the other subcontract contributes to the performance of the subcontract because the work, required to be carried out under the other subcontract, will form all or part of the work required to be carried out under the subcontract; and both subcontracts are subcontracts for the same contract. A first tier subcontract would be a higher subcontract for a third tier subcontract if the work required to be carried out under the third tier subcontract will form all or part of the work required to be carried out under the first tier subcontract.
(a) performance of the contract contributes to the performance of the other contract because the work, required to be carried out under the contract, will form all or part of the work required to be carried out under the other contract; and
(b) the contribution mentioned in paragraph (a) is not merely coincidence. Example for paragraph (b) — the purchase of tools from a retail store
(a) the contribution mentioned in subsection (1) (a) may be indirect because the contract contributes to the performance of 1 or more other subcontracts in order to contribute to the other contract; and Note— A subcontract that contributes directly to a contract would have 1 entity that is both a party to the subcontract and a party to the contract.
(b) a contract may be a subcontract for another contract regardless of whether any party to the contract is also a party to the other contract.
(a) the resulting subcontract is a subcontract for the contract; and
(b) the person required to carry out the work under the subcontract is a subcontractor for the contract; and
(c) the work required to be carried out under the subcontract is the subcontracted work for the contract.
(a) performance of the subcontract contributes directly to the performance of the contract; and
(b) 1 person is both a party to the subcontract and a party to the contract.
(a) performance of the subcontract contributes to the performance of the contract only by also contributing to the performance of another subcontract for the contract; and
(b) no party to the subcontract is also a party to the contract; and
(c) 1 person is both a party to the subcontract and a party to the other subcontract.
(a) performance of the other subcontract contributes to the performance of the subcontract because the work, required to be carried out under the other subcontract, will form all or part of the work required to be carried out under the subcontract; and
(b) both subcontracts are subcontracts for the same contract.
ch.2-pt.1
Preliminary
Preliminary
sec.7
Purpose of chapter
sec.7 Purpose of chapter
The main purpose of this chapter is to ensure that funds paid to the contracted party for particular contracts are held in a trust to protect the interests of subcontractors.
s 7 sub 2020 No. 24 s 63
sec.8
Definitions for chapter
sec.8 Definitions for chapter
In this chapter—
amendment , of a contract, includes a variation of the contract or a change in the contract price.
s 8 def amendment ins 2024 No. 14 s 17 (2)
approved financial institution means a financial institution approved by the commissioner under section 55 .
building means a fixed structure that is wholly or partly enclosed by walls or is roofed.
contract administration , in relation to project trust work wholly or partly designed by a person, includes the following—
preparing tender documentation and calling and selecting tenders;
preparing, or helping the person’s clients with the preparation of, contracts;
preparing additional documentation for the person’s clients or building contractors;
arranging and conducting on-site meetings and inspections;
arranging progress payments;
arranging for certificates, including certificates from a local government, to be issued;
providing advice and help to the person’s clients including during the maintenance period allowed under a contract.
contracted party , for a contract, means the party to the contract who is required to perform work under the contract, whether by—
carrying out the work personally; or
directly or indirectly causing the work to be carried out.
contracted work , for a contract, means the work required to be carried out under the contract.
contracting party , for a contract, means the party to the contract for whom the contracted work is to be carried out.
contract price see section 9 .
hospital and health service means a Hospital and Health Service established under the Hospital and Health Boards Act 2011 , section 17 .
mechanical services work see the Queensland Building and Construction Commission Act 1991 , schedule 2 .
project trust contract means a contract for which a project trust is required under section 12 .
s 8 def project trust contract ins 2024 No. 14 s 17 (2)
project trust subcontract see section 9A .
s 8 def project trust subcontract ins 2024 No. 14 s 17 (2)
project trust work see section 8A .
protected work ...
s 8 def protected work om 2024 No. 14 s 17 (1)
State authority —
means—
an agency, authority, commission, corporation, instrumentality, office, or other entity, established under an Act or by authority of the State for a public or State purpose; or
a corporation that is—
owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and
prescribed by regulation to be a State authority; or
a subsidiary of a corporation mentioned in subparagraph (ii) ; or
a part of an entity mentioned in subparagraphs (i) to (iii) ; or
a hospital and health service; but
does not include an entity prescribed by regulation not to be a State authority.
trust records means records required to be kept and retained under section 52 .
s 8 def trust records amd 2024 No. 14 s 17 (3)
variation , of a contract, means an addition to, or an omission from, the contracted work.
s 8 sub 2020 No. 24 s 63
(a) preparing tender documentation and calling and selecting tenders;
(b) preparing, or helping the person’s clients with the preparation of, contracts;
(c) preparing additional documentation for the person’s clients or building contractors;
(d) arranging and conducting on-site meetings and inspections;
(e) arranging progress payments;
(f) arranging for certificates, including certificates from a local government, to be issued;
(g) providing advice and help to the person’s clients including during the maintenance period allowed under a contract.
(a) carrying out the work personally; or
(b) directly or indirectly causing the work to be carried out.
(a) means— (i) an agency, authority, commission, corporation, instrumentality, office, or other entity, established under an Act or by authority of the State for a public or State purpose; or (ii) a corporation that is— (A) owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and (B) prescribed by regulation to be a State authority; or (iii) a subsidiary of a corporation mentioned in subparagraph (ii) ; or (iv) a part of an entity mentioned in subparagraphs (i) to (iii) ; or (v) a hospital and health service; but
(i) an agency, authority, commission, corporation, instrumentality, office, or other entity, established under an Act or by authority of the State for a public or State purpose; or
(ii) a corporation that is— (A) owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and (B) prescribed by regulation to be a State authority; or
(A) owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and
(B) prescribed by regulation to be a State authority; or
(iii) a subsidiary of a corporation mentioned in subparagraph (ii) ; or
(iv) a part of an entity mentioned in subparagraphs (i) to (iii) ; or
(v) a hospital and health service; but
(b) does not include an entity prescribed by regulation not to be a State authority.
(i) an agency, authority, commission, corporation, instrumentality, office, or other entity, established under an Act or by authority of the State for a public or State purpose; or
(ii) a corporation that is— (A) owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and (B) prescribed by regulation to be a State authority; or
(A) owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and
(B) prescribed by regulation to be a State authority; or
(iii) a subsidiary of a corporation mentioned in subparagraph (ii) ; or
(iv) a part of an entity mentioned in subparagraphs (i) to (iii) ; or
(v) a hospital and health service; but
(A) owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and
(B) prescribed by regulation to be a State authority; or
sec.8A
Meaning of project trust work
sec.8A Meaning of project trust work
Project trust work means any of the following work—
the erection or construction of a building;
the renovation, alteration, extension, improvement or repair of a building;
the provision of lighting, heating, ventilation, air conditioning, water supply, sewerage or drainage in connection with a building;
any site work (including the construction of retaining structures) related to work of a kind mentioned in paragraph (a) , (b) or (c) ;
the preparation of plans or specifications for the performance of any other work mentioned in this subsection;
contract administration if carried out by a person for the construction of a building wholly or partly designed by the person;
fire protection work within the meaning of the Queensland Building and Construction Commission Act 1991 , schedule 2 ;
site testing within the meaning of the Queensland Building and Construction Commission Act 1991 , schedule 2 and classification carried out in preparation for the erection or construction of a building on the site;
the carrying out of a building inspection;
the inspection or investigation of a building, and the provision of advice or a report, for the following—
termite management systems for the building;
termite infestation in the building;
work performed by an architect under the Architects Act 2002 in the architect’s professional practice if the work is associated with a building;
work performed by a registered professional engineer under the Professional Engineers Act 2002 in the engineer’s professional practice if the work is associated with a building;
work performed by a surveyor under the Surveyors Act 2003 in the surveyor’s professional practice if the work is associated with a building;
electrical work under the Electrical Safety Act 2002 if the work is associated with a building;
the erection of scaffolding that is associated with a building;
earthmoving and excavating that is associated with a building;
certification work performed by a building certifier under the Building Act 1975 in the certifier’s professional practice if the work is associated with a building;
the assessment of energy efficiency of a building;
work performed by a fire safety adviser under the Building Fire Safety Regulation 2008 if the work is associated with a building;
the laying of wet pour rubber, including the laying of a blended mix of graded rubber particles and binder to provide a continuous surface if the work is associated with a building;
the installation of prefabricated components of a building;
mechanical services work that is associated with a building.
Project trust work also includes work prescribed by regulation to be project trust work.
However, project trust work does not include work prescribed by regulation not to be project trust work.
s 8A ins 2020 No. 24 s 63
(sec.8A-ssec.1) Project trust work means any of the following work— the erection or construction of a building; the renovation, alteration, extension, improvement or repair of a building; the provision of lighting, heating, ventilation, air conditioning, water supply, sewerage or drainage in connection with a building; any site work (including the construction of retaining structures) related to work of a kind mentioned in paragraph (a) , (b) or (c) ; the preparation of plans or specifications for the performance of any other work mentioned in this subsection; contract administration if carried out by a person for the construction of a building wholly or partly designed by the person; fire protection work within the meaning of the Queensland Building and Construction Commission Act 1991 , schedule 2 ; site testing within the meaning of the Queensland Building and Construction Commission Act 1991 , schedule 2 and classification carried out in preparation for the erection or construction of a building on the site; the carrying out of a building inspection; the inspection or investigation of a building, and the provision of advice or a report, for the following— termite management systems for the building; termite infestation in the building; work performed by an architect under the Architects Act 2002 in the architect’s professional practice if the work is associated with a building; work performed by a registered professional engineer under the Professional Engineers Act 2002 in the engineer’s professional practice if the work is associated with a building; work performed by a surveyor under the Surveyors Act 2003 in the surveyor’s professional practice if the work is associated with a building; electrical work under the Electrical Safety Act 2002 if the work is associated with a building; the erection of scaffolding that is associated with a building; earthmoving and excavating that is associated with a building; certification work performed by a building certifier under the Building Act 1975 in the certifier’s professional practice if the work is associated with a building; the assessment of energy efficiency of a building; work performed by a fire safety adviser under the Building Fire Safety Regulation 2008 if the work is associated with a building; the laying of wet pour rubber, including the laying of a blended mix of graded rubber particles and binder to provide a continuous surface if the work is associated with a building; the installation of prefabricated components of a building; mechanical services work that is associated with a building.
(sec.8A-ssec.2) Project trust work also includes work prescribed by regulation to be project trust work.
(sec.8A-ssec.3) However, project trust work does not include work prescribed by regulation not to be project trust work.
(a) the erection or construction of a building;
(b) the renovation, alteration, extension, improvement or repair of a building;
(c) the provision of lighting, heating, ventilation, air conditioning, water supply, sewerage or drainage in connection with a building;
(d) any site work (including the construction of retaining structures) related to work of a kind mentioned in paragraph (a) , (b) or (c) ;
(e) the preparation of plans or specifications for the performance of any other work mentioned in this subsection;
(f) contract administration if carried out by a person for the construction of a building wholly or partly designed by the person;
(g) fire protection work within the meaning of the Queensland Building and Construction Commission Act 1991 , schedule 2 ;
(h) site testing within the meaning of the Queensland Building and Construction Commission Act 1991 , schedule 2 and classification carried out in preparation for the erection or construction of a building on the site;
(i) the carrying out of a building inspection;
(j) the inspection or investigation of a building, and the provision of advice or a report, for the following— (i) termite management systems for the building; (ii) termite infestation in the building;
(i) termite management systems for the building;
(ii) termite infestation in the building;
(k) work performed by an architect under the Architects Act 2002 in the architect’s professional practice if the work is associated with a building;
(l) work performed by a registered professional engineer under the Professional Engineers Act 2002 in the engineer’s professional practice if the work is associated with a building;
(m) work performed by a surveyor under the Surveyors Act 2003 in the surveyor’s professional practice if the work is associated with a building;
(n) electrical work under the Electrical Safety Act 2002 if the work is associated with a building;
(o) the erection of scaffolding that is associated with a building;
(p) earthmoving and excavating that is associated with a building;
(q) certification work performed by a building certifier under the Building Act 1975 in the certifier’s professional practice if the work is associated with a building;
(r) the assessment of energy efficiency of a building;
(s) work performed by a fire safety adviser under the Building Fire Safety Regulation 2008 if the work is associated with a building;
(t) the laying of wet pour rubber, including the laying of a blended mix of graded rubber particles and binder to provide a continuous surface if the work is associated with a building;
(u) the installation of prefabricated components of a building;
(v) mechanical services work that is associated with a building.
(i) termite management systems for the building;
(ii) termite infestation in the building;
sec.8B
Section sec.8B
s 8B om 2024 No. 14 s 18
sec.9
Meaning of contract price
sec.9 Meaning of contract price
The contract price , for a contract, means the amount the contracted party is entitled to be paid under the contract or, if the amount can not be accurately calculated, the reasonable estimate of the amount the contracted party is entitled to be paid under the contract.
In working out the amount under subsection (1) , an amount for GST is not to be included.
s 9 amd 2018 No. 17 s 176D
sub 2020 No. 24 s 63
(sec.9-ssec.1) The contract price , for a contract, means the amount the contracted party is entitled to be paid under the contract or, if the amount can not be accurately calculated, the reasonable estimate of the amount the contracted party is entitled to be paid under the contract.
(sec.9-ssec.2) In working out the amount under subsection (1) , an amount for GST is not to be included.
sec.9A
Meaning of project trust subcontract
sec.9A Meaning of project trust subcontract
A subcontract for a project trust contract is a project trust subcontract if, when the subcontract is entered into—
the subcontract is a first tier subcontract for the contract; and
the subcontracted work under the subcontract is or includes 1 or more of the following—
architectural services;
contractor or trade work;
a professional engineering service;
services or work prescribed by regulation for this paragraph; and
the subcontract is not excluded by regulation from being a project trust subcontract.
A subcontract does not cease to be a project trust subcontract because of—
an amendment of the subcontract; or
an amendment of subsection (1) or a regulation made for subsection (1) .
If a contract becomes a project trust contract after it is entered into, a subcontract of the contract then in existence becomes a project trust subcontract if it would have been a project trust subcontract had it been entered into when the contract became a project trust contract.
A subcontract that was not, at the time it was entered into, a project trust subcontract becomes a project trust subcontract if—
the subcontract is amended; and
the subcontract would have been a project trust subcontract had it been entered into in its amended form, including any earlier amendments, at the time it was amended.
In this section—
architectural services see the Architects Act 2002 , schedule 2 .
contractor or trade work means—
work for which the subcontractor holds, or is required to hold, a licence under any of the following—
the Building Act 1975 ;
the Electrical Safety Act 2002 ;
the Plumbing and Drainage Act 2018 ;
the Queensland Building and Construction Commission Act 1991 ;
a regulation made under the Work Health and Safety Act 2011 ;
an Act or regulation prescribed by regulation for this paragraph; or
work prescribed by regulation to be contractor or trade work.
professional engineering service see the Professional Engineers Act 2002 , schedule 2 .
s 9A ins 2024 No. 14 s 19
(sec.9A-ssec.1) A subcontract for a project trust contract is a project trust subcontract if, when the subcontract is entered into— the subcontract is a first tier subcontract for the contract; and the subcontracted work under the subcontract is or includes 1 or more of the following— architectural services; contractor or trade work; a professional engineering service; services or work prescribed by regulation for this paragraph; and the subcontract is not excluded by regulation from being a project trust subcontract.
(sec.9A-ssec.2) A subcontract does not cease to be a project trust subcontract because of— an amendment of the subcontract; or an amendment of subsection (1) or a regulation made for subsection (1) .
(sec.9A-ssec.3) If a contract becomes a project trust contract after it is entered into, a subcontract of the contract then in existence becomes a project trust subcontract if it would have been a project trust subcontract had it been entered into when the contract became a project trust contract.
(sec.9A-ssec.4) A subcontract that was not, at the time it was entered into, a project trust subcontract becomes a project trust subcontract if— the subcontract is amended; and the subcontract would have been a project trust subcontract had it been entered into in its amended form, including any earlier amendments, at the time it was amended.
(sec.9A-ssec.5) In this section— architectural services see the Architects Act 2002 , schedule 2 . contractor or trade work means— work for which the subcontractor holds, or is required to hold, a licence under any of the following— the Building Act 1975 ; the Electrical Safety Act 2002 ; the Plumbing and Drainage Act 2018 ; the Queensland Building and Construction Commission Act 1991 ; a regulation made under the Work Health and Safety Act 2011 ; an Act or regulation prescribed by regulation for this paragraph; or work prescribed by regulation to be contractor or trade work. professional engineering service see the Professional Engineers Act 2002 , schedule 2 .
(a) the subcontract is a first tier subcontract for the contract; and
(b) the subcontracted work under the subcontract is or includes 1 or more of the following— (i) architectural services; (ii) contractor or trade work; (iii) a professional engineering service; (iv) services or work prescribed by regulation for this paragraph; and
(i) architectural services;
(ii) contractor or trade work;
(iii) a professional engineering service;
(iv) services or work prescribed by regulation for this paragraph; and
(c) the subcontract is not excluded by regulation from being a project trust subcontract.
(i) architectural services;
(ii) contractor or trade work;
(iii) a professional engineering service;
(iv) services or work prescribed by regulation for this paragraph; and
(a) an amendment of the subcontract; or
(b) an amendment of subsection (1) or a regulation made for subsection (1) .
(a) the subcontract is amended; and
(b) the subcontract would have been a project trust subcontract had it been entered into in its amended form, including any earlier amendments, at the time it was amended.
(a) work for which the subcontractor holds, or is required to hold, a licence under any of the following— (i) the Building Act 1975 ; (ii) the Electrical Safety Act 2002 ; (iii) the Plumbing and Drainage Act 2018 ; (iv) the Queensland Building and Construction Commission Act 1991 ; (v) a regulation made under the Work Health and Safety Act 2011 ; (vi) an Act or regulation prescribed by regulation for this paragraph; or
(i) the Building Act 1975 ;
(ii) the Electrical Safety Act 2002 ;
(iii) the Plumbing and Drainage Act 2018 ;
(iv) the Queensland Building and Construction Commission Act 1991 ;
(v) a regulation made under the Work Health and Safety Act 2011 ;
(vi) an Act or regulation prescribed by regulation for this paragraph; or
(b) work prescribed by regulation to be contractor or trade work.
(i) the Building Act 1975 ;
(ii) the Electrical Safety Act 2002 ;
(iii) the Plumbing and Drainage Act 2018 ;
(iv) the Queensland Building and Construction Commission Act 1991 ;
(v) a regulation made under the Work Health and Safety Act 2011 ;
(vi) an Act or regulation prescribed by regulation for this paragraph; or
ch.2-pt.2
Project trusts
Project trusts
ch.2-pt.2-div.1
Preliminary
Preliminary
sec.10
Definitions for part
sec.10 Definitions for part
In this part—
head contract means a contract for project trust work that is not also a subcontract of another contract.
minimum contract price ...
s 10 def minimum contract price om 2024 No. 14 s 20 (1)
project trust account means the account for a project trust at a financial institution.
related services ...
s 10 def related services om 2024 No. 14 s 20 (1)
subcontractor beneficiary , for a project trust, means a subcontractor who is a beneficiary of the trust under section 11A .
s 10 def subcontractor beneficiary amd 2024 No. 14 s 20 (2)
s 10 sub 2020 No. 24 s 63
sec.10A
Who is a related entity
sec.10A Who is a related entity
A person is a related entity for another person if—
for individuals—they are members of the same family; or
for an individual and a corporation—the individual or a member of the individual’s family—
is a majority shareholder, director or secretary of the corporation or a related body corporate of the corporation; or
has an interest of 50% or more in the corporation; or
for an individual and a trustee of a trust—the individual or a related entity under another provision of this section is a beneficiary of the trust; or
for corporations—they are related bodies corporate; or
for a corporation and a trustee of a trust—the corporation or a related entity under another provision of this section is a beneficiary of the trust; or
for trustees of 2 or more trusts—
a person is a beneficiary of both trusts; or
a person is a beneficiary of 1 trust and a related entity under another provision of this section is a beneficiary of the other trust.
Also, a person is a related entity for another person if the persons acquire interests in a land holding trust and the acquisitions form, evidence, give effect to or arise from what is substantially 1 arrangement.
In this section—
family , for a person, means—
the person’s spouse; or
a parent of the person or the person’s spouse; or
a grandparent of the person or the person’s spouse; or
a brother, sister, aunt, uncle, nephew or niece of the person or the person’s spouse; or
a child of the person or the person’s spouse; or
a grandchild of the person or the person’s spouse; or
the spouse of any person mentioned in paragraphs (b) to (f) .
land holding trust see the Duties Act 2001 , schedule 6 .
related bodies corporate means bodies corporate that are related under the Corporations Act , section 50 .
s 10A ins 2018 No. 17 s 176E
sub 2020 No. 24 s 63
(sec.10A-ssec.1) A person is a related entity for another person if— for individuals—they are members of the same family; or for an individual and a corporation—the individual or a member of the individual’s family— is a majority shareholder, director or secretary of the corporation or a related body corporate of the corporation; or has an interest of 50% or more in the corporation; or for an individual and a trustee of a trust—the individual or a related entity under another provision of this section is a beneficiary of the trust; or for corporations—they are related bodies corporate; or for a corporation and a trustee of a trust—the corporation or a related entity under another provision of this section is a beneficiary of the trust; or for trustees of 2 or more trusts— a person is a beneficiary of both trusts; or a person is a beneficiary of 1 trust and a related entity under another provision of this section is a beneficiary of the other trust.
(sec.10A-ssec.2) Also, a person is a related entity for another person if the persons acquire interests in a land holding trust and the acquisitions form, evidence, give effect to or arise from what is substantially 1 arrangement.
(sec.10A-ssec.3) In this section— family , for a person, means— the person’s spouse; or a parent of the person or the person’s spouse; or a grandparent of the person or the person’s spouse; or a brother, sister, aunt, uncle, nephew or niece of the person or the person’s spouse; or a child of the person or the person’s spouse; or a grandchild of the person or the person’s spouse; or the spouse of any person mentioned in paragraphs (b) to (f) . land holding trust see the Duties Act 2001 , schedule 6 . related bodies corporate means bodies corporate that are related under the Corporations Act , section 50 .
(a) for individuals—they are members of the same family; or
(b) for an individual and a corporation—the individual or a member of the individual’s family— (i) is a majority shareholder, director or secretary of the corporation or a related body corporate of the corporation; or (ii) has an interest of 50% or more in the corporation; or
(i) is a majority shareholder, director or secretary of the corporation or a related body corporate of the corporation; or
(ii) has an interest of 50% or more in the corporation; or
(c) for an individual and a trustee of a trust—the individual or a related entity under another provision of this section is a beneficiary of the trust; or
(d) for corporations—they are related bodies corporate; or
(e) for a corporation and a trustee of a trust—the corporation or a related entity under another provision of this section is a beneficiary of the trust; or
(f) for trustees of 2 or more trusts— (i) a person is a beneficiary of both trusts; or (ii) a person is a beneficiary of 1 trust and a related entity under another provision of this section is a beneficiary of the other trust.
(i) a person is a beneficiary of both trusts; or
(ii) a person is a beneficiary of 1 trust and a related entity under another provision of this section is a beneficiary of the other trust.
(i) is a majority shareholder, director or secretary of the corporation or a related body corporate of the corporation; or
(ii) has an interest of 50% or more in the corporation; or
(i) a person is a beneficiary of both trusts; or
(ii) a person is a beneficiary of 1 trust and a related entity under another provision of this section is a beneficiary of the other trust.
(a) the person’s spouse; or
(b) a parent of the person or the person’s spouse; or
(c) a grandparent of the person or the person’s spouse; or
(d) a brother, sister, aunt, uncle, nephew or niece of the person or the person’s spouse; or
(e) a child of the person or the person’s spouse; or
(f) a grandchild of the person or the person’s spouse; or
(g) the spouse of any person mentioned in paragraphs (b) to (f) .
sec.10B
When amount liable to be paid to subcontractor
sec.10B When amount liable to be paid to subcontractor
For this chapter, a person who is a party to a subcontract is liable to pay an amount to the subcontractor if any of the following circumstances apply—
the amount is due to be paid by the person to the subcontractor in accordance with the terms of the subcontract;
under the subcontract, the amount is certified, or otherwise assessed, as payable by the person to the subcontractor;
the person gives the subcontractor a payment schedule for the amount;
the person is liable to pay the amount to the subcontractor under section 77 ;
the person must pay the amount to the subcontractor under chapter 3 , part 4 because of an adjudication of a disputed progress payment for the subcontract;
the person must pay the amount to the subcontractor because of a final and binding dispute resolution process;
a court or tribunal orders the person to pay the amount to the subcontractor.
s 10B ins 2020 No. 24 s 63
(a) the amount is due to be paid by the person to the subcontractor in accordance with the terms of the subcontract;
(b) under the subcontract, the amount is certified, or otherwise assessed, as payable by the person to the subcontractor;
(c) the person gives the subcontractor a payment schedule for the amount;
(d) the person is liable to pay the amount to the subcontractor under section 77 ;
(e) the person must pay the amount to the subcontractor under chapter 3 , part 4 because of an adjudication of a disputed progress payment for the subcontract;
(f) the person must pay the amount to the subcontractor because of a final and binding dispute resolution process;
(g) a court or tribunal orders the person to pay the amount to the subcontractor.
sec.10C
References to particular terms in this part
sec.10C References to particular terms in this part
In this part—
a reference to a contract in association with a reference to a project trust is a reference to the contract for which the trust is required; and
a reference to a contracting party in association with a reference to a project trust is a reference to the contracting party for the contract for which the trust is required; and
a reference to a contracted party in association with a reference to a project trust is a reference to the contracted party for the contract for which the trust is required; and
a reference to a trustee in association with a reference to a project trust, or a project trust contract, is a reference to the trustee for the project trust; and
a reference to a subcontract in association with a reference to a project trust is a reference to a subcontract of the contract for which the trust is required; and
a reference to a subcontractor beneficiary in association with a reference to a project trust is a reference to a subcontractor beneficiary for the trust; and
a reference to a trustee in association with a reference to a project trust account is a reference to the trustee for the trust to which the account relates.
s 10C ins 2020 No. 24 s 63
amd 2024 No. 14 s 21
(a) a reference to a contract in association with a reference to a project trust is a reference to the contract for which the trust is required; and
(b) a reference to a contracting party in association with a reference to a project trust is a reference to the contracting party for the contract for which the trust is required; and
(c) a reference to a contracted party in association with a reference to a project trust is a reference to the contracted party for the contract for which the trust is required; and
(d) a reference to a trustee in association with a reference to a project trust, or a project trust contract, is a reference to the trustee for the project trust; and
(e) a reference to a subcontract in association with a reference to a project trust is a reference to a subcontract of the contract for which the trust is required; and
(f) a reference to a subcontractor beneficiary in association with a reference to a project trust is a reference to a subcontractor beneficiary for the trust; and
(g) a reference to a trustee in association with a reference to a project trust account is a reference to the trustee for the trust to which the account relates.
ch.2-pt.2-div.2
Project trusts
Project trusts
sec.11
What is a project trust
sec.11 What is a project trust
A project trust is a trust—
over amounts—
payable in connection with a project trust contract or project trust subcontract; and
required to be deposited in the project trust account under this chapter; and
primarily for the benefit of subcontractors for the project trust contract.
s 11 amd 2018 No. 17 s 176F
sub 2020 No. 24 s 63
amd 2024 No. 14 s 22
(a) over amounts— (i) payable in connection with a project trust contract or project trust subcontract; and (ii) required to be deposited in the project trust account under this chapter; and
(i) payable in connection with a project trust contract or project trust subcontract; and
(ii) required to be deposited in the project trust account under this chapter; and
(b) primarily for the benefit of subcontractors for the project trust contract.
(i) payable in connection with a project trust contract or project trust subcontract; and
(ii) required to be deposited in the project trust account under this chapter; and
sec.11A
Trustee and beneficiaries of project trust
sec.11A Trustee and beneficiaries of project trust
The contracted party for a project trust contract is both the trustee and a beneficiary of the project trust for the contract.
The contracted party—
becomes the trustee and a beneficiary of the project trust when the trust is established; and
ceases to be the trustee and a beneficiary of the project trust when the trust is lawfully dissolved.
A subcontractor for a project trust subcontract for a project trust contract is a beneficiary of the project trust for the contract.
The subcontractor—
becomes a beneficiary of the project trust when—
a project trust subcontract is entered into with the subcontractor; or
a subcontract for which the subcontractor is the contracted party becomes a project trust subcontract; and
ceases to be a beneficiary of the project trust when—
the subcontractor is paid all amounts the subcontractor is entitled to be paid in connection with all project trust subcontracts for which the subcontractor is the contracted party; and
the trust is lawfully dissolved.
s 11A ins 2020 No. 24 s 63
sub 2024 No. 14 s 23
(sec.11A-ssec.1) The contracted party for a project trust contract is both the trustee and a beneficiary of the project trust for the contract.
(sec.11A-ssec.2) The contracted party— becomes the trustee and a beneficiary of the project trust when the trust is established; and ceases to be the trustee and a beneficiary of the project trust when the trust is lawfully dissolved.
(sec.11A-ssec.3) A subcontractor for a project trust subcontract for a project trust contract is a beneficiary of the project trust for the contract.
(sec.11A-ssec.4) The subcontractor— becomes a beneficiary of the project trust when— a project trust subcontract is entered into with the subcontractor; or a subcontract for which the subcontractor is the contracted party becomes a project trust subcontract; and ceases to be a beneficiary of the project trust when— the subcontractor is paid all amounts the subcontractor is entitled to be paid in connection with all project trust subcontracts for which the subcontractor is the contracted party; and the trust is lawfully dissolved.
(a) becomes the trustee and a beneficiary of the project trust when the trust is established; and
(b) ceases to be the trustee and a beneficiary of the project trust when the trust is lawfully dissolved.
(a) becomes a beneficiary of the project trust when— (i) a project trust subcontract is entered into with the subcontractor; or (ii) a subcontract for which the subcontractor is the contracted party becomes a project trust subcontract; and
(i) a project trust subcontract is entered into with the subcontractor; or
(ii) a subcontract for which the subcontractor is the contracted party becomes a project trust subcontract; and
(b) ceases to be a beneficiary of the project trust when— (i) the subcontractor is paid all amounts the subcontractor is entitled to be paid in connection with all project trust subcontracts for which the subcontractor is the contracted party; and (ii) the trust is lawfully dissolved.
(i) the subcontractor is paid all amounts the subcontractor is entitled to be paid in connection with all project trust subcontracts for which the subcontractor is the contracted party; and
(ii) the trust is lawfully dissolved.
(i) a project trust subcontract is entered into with the subcontractor; or
(ii) a subcontract for which the subcontractor is the contracted party becomes a project trust subcontract; and
(i) the subcontractor is paid all amounts the subcontractor is entitled to be paid in connection with all project trust subcontracts for which the subcontractor is the contracted party; and
(ii) the trust is lawfully dissolved.
sec.11B
What are the beneficial interests in a project trust
sec.11B What are the beneficial interests in a project trust
The beneficiaries of a project trust for a contract have a beneficial interest in—
for a subcontractor for the contract (as beneficiary)—all amounts the subcontractor is entitled to be paid in connection with project trust subcontracts; or
for the contracted party for the contract (as beneficiary)—the remainder for the trust.
In this section—
remainder , for a project trust, means the amount still held in trust after subtracting all amounts subcontractor beneficiaries are entitled to be paid in connection with project trust subcontracts.
s 11B ins 2020 No. 24 s 63
amd 2024 No. 14 s 24
(sec.11B-ssec.1) The beneficiaries of a project trust for a contract have a beneficial interest in— for a subcontractor for the contract (as beneficiary)—all amounts the subcontractor is entitled to be paid in connection with project trust subcontracts; or for the contracted party for the contract (as beneficiary)—the remainder for the trust.
(sec.11B-ssec.2) In this section— remainder , for a project trust, means the amount still held in trust after subtracting all amounts subcontractor beneficiaries are entitled to be paid in connection with project trust subcontracts.
(a) for a subcontractor for the contract (as beneficiary)—all amounts the subcontractor is entitled to be paid in connection with project trust subcontracts; or
(b) for the contracted party for the contract (as beneficiary)—the remainder for the trust.
ch.2-pt.2-div.3
Contracts requiring project trusts
Contracts requiring project trusts
sec.12
When project trust required for a contract
sec.12 When project trust required for a contract
This section applies to a contract entered into on or after the commencement of this section.
A project trust is required for a contract if—
the contract is eligible for a project trust under subdivision 2 ; and
the contract is not exempted under subdivision 3 ; and
the contracted party enters into a subcontract for all or part of the contracted work.
The requirement starts on the first day a project trust is required under subsection (2) .
The requirement continues until the project trust is dissolved under section 21 , regardless of any of the following changes—
a variation, or any other amendment, of the contract;
a change in the contract price;
a change in the contracted work.
If a project trust is required for a contract and a project trust is also required for a subcontract of the contract, separate project trusts are required for the contract and the subcontract.
s 12 sub 2020 No. 24 s 63
amd 2017 No. 43 s 214
(sec.12-ssec.1) This section applies to a contract entered into on or after the commencement of this section.
(sec.12-ssec.2) A project trust is required for a contract if— the contract is eligible for a project trust under subdivision 2 ; and the contract is not exempted under subdivision 3 ; and the contracted party enters into a subcontract for all or part of the contracted work.
(sec.12-ssec.3) The requirement starts on the first day a project trust is required under subsection (2) .
(sec.12-ssec.4) The requirement continues until the project trust is dissolved under section 21 , regardless of any of the following changes— a variation, or any other amendment, of the contract; a change in the contract price; a change in the contracted work.
(sec.12-ssec.5) If a project trust is required for a contract and a project trust is also required for a subcontract of the contract, separate project trusts are required for the contract and the subcontract.
(a) the contract is eligible for a project trust under subdivision 2 ; and
(b) the contract is not exempted under subdivision 3 ; and
(c) the contracted party enters into a subcontract for all or part of the contracted work.
(a) a variation, or any other amendment, of the contract;
(b) a change in the contract price;
(c) a change in the contracted work.
sec.13
Section sec.13
s 13 om 2020 No. 24 s 63
sec.14
Eligibility of contract for project trust when contract entered into
sec.14 Eligibility of contract for project trust when contract entered into
A contract is eligible for a project trust if—
the contracting party is the State, a state authority, a local government, an individual, a private entity or a hospital and health service; and
more than 50% of the contract price is for project trust work; and
the contract price is—
if the contracting party is the State or a hospital and health service—$1 million or more; or
otherwise—$10 million or more.
Also, a contract is eligible for a project trust if—
the contracting party is a State authority that has decided a project trust is to be established for the contract; and
more than 50% of the contract price is for project trust work; and
the contract price is $1 million or more.
This section applies to a contract at the time the contract is entered into.
In this section—
private entity —
means a company or other entity that is owned by any entity other than the State; but
does not include a State authority.
State does not include a State authority.
s 14 sub 2020 No. 24 s 63
amd 2017 No. 43 ss 213 , 215 ; 2024 No. 14 s 25
(sec.14-ssec.1) A contract is eligible for a project trust if— the contracting party is the State, a state authority, a local government, an individual, a private entity or a hospital and health service; and more than 50% of the contract price is for project trust work; and the contract price is— if the contracting party is the State or a hospital and health service—$1 million or more; or otherwise—$10 million or more.
(sec.14-ssec.2) Also, a contract is eligible for a project trust if— the contracting party is a State authority that has decided a project trust is to be established for the contract; and more than 50% of the contract price is for project trust work; and the contract price is $1 million or more.
(sec.14-ssec.3) This section applies to a contract at the time the contract is entered into.
(sec.14-ssec.4) In this section— private entity — means a company or other entity that is owned by any entity other than the State; but does not include a State authority. State does not include a State authority.
(a) the contracting party is the State, a state authority, a local government, an individual, a private entity or a hospital and health service; and
(b) more than 50% of the contract price is for project trust work; and
(c) the contract price is— (i) if the contracting party is the State or a hospital and health service—$1 million or more; or (ii) otherwise—$10 million or more.
(i) if the contracting party is the State or a hospital and health service—$1 million or more; or
(ii) otherwise—$10 million or more.
(i) if the contracting party is the State or a hospital and health service—$1 million or more; or
(ii) otherwise—$10 million or more.
(a) the contracting party is a State authority that has decided a project trust is to be established for the contract; and
(b) more than 50% of the contract price is for project trust work; and
(c) the contract price is $1 million or more.
(a) means a company or other entity that is owned by any entity other than the State; but
(b) does not include a State authority.
sec.14A
Eligibility of contract for project trust when contract amended
sec.14A Eligibility of contract for project trust when contract amended
A contract does not cease to be eligible for a project trust because of an amendment of the contract.
A contract that was not, at the time it was entered into, eligible for a project trust becomes eligible for a project trust on the amendment of the contract if—
the contract is amended; and
the contract would have been eligible for a project trust had it been in its amended form, including any earlier amendments, when it was entered into; and
the amended contract—
increases the original percentage of the contract price that is for project trust work by 30% or more; or
increases the original contract price by 30% or more.
s 14A ins 2020 No. 24 s 63
sub 2024 No. 14 s 26
(sec.14A-ssec.1) A contract does not cease to be eligible for a project trust because of an amendment of the contract.
(sec.14A-ssec.2) A contract that was not, at the time it was entered into, eligible for a project trust becomes eligible for a project trust on the amendment of the contract if— the contract is amended; and the contract would have been eligible for a project trust had it been in its amended form, including any earlier amendments, when it was entered into; and the amended contract— increases the original percentage of the contract price that is for project trust work by 30% or more; or increases the original contract price by 30% or more.
(a) the contract is amended; and
(b) the contract would have been eligible for a project trust had it been in its amended form, including any earlier amendments, when it was entered into; and
(c) the amended contract— (i) increases the original percentage of the contract price that is for project trust work by 30% or more; or (ii) increases the original contract price by 30% or more.
(i) increases the original percentage of the contract price that is for project trust work by 30% or more; or
(ii) increases the original contract price by 30% or more.
(i) increases the original percentage of the contract price that is for project trust work by 30% or more; or
(ii) increases the original contract price by 30% or more.
sec.14B
Multiple contracts at same site or adjacent sites
sec.14B Multiple contracts at same site or adjacent sites
This section applies if—
the same parties enter into 2 or more separate contracts; and
the separate contracts are for carrying out project trust work at the same site or adjacent sites.
The separate contracts are taken to be a single contract (the larger contract ) for the purpose of applying this division.
The larger contract would be eligible for a project trust if the contract would be eligible for a project trust under section 14 .
To remove any doubt, it is declared that the exemptions under subdivision 3 apply only to the larger contract and not to the separate contracts.
If the separate contracts are for small scale residential construction work under section 15C , the exemption under section 15C does not apply to exclude the separate contracts from being taken to be a single contract under subsection (2) .
This section does not apply to separate contracts entered into as a result of separate tender processes.
s 14B ins 2020 No. 24 s 63
(sec.14B-ssec.1) This section applies if— the same parties enter into 2 or more separate contracts; and the separate contracts are for carrying out project trust work at the same site or adjacent sites.
(sec.14B-ssec.2) The separate contracts are taken to be a single contract (the larger contract ) for the purpose of applying this division. The larger contract would be eligible for a project trust if the contract would be eligible for a project trust under section 14 .
(sec.14B-ssec.3) To remove any doubt, it is declared that the exemptions under subdivision 3 apply only to the larger contract and not to the separate contracts. If the separate contracts are for small scale residential construction work under section 15C , the exemption under section 15C does not apply to exclude the separate contracts from being taken to be a single contract under subsection (2) .
(sec.14B-ssec.4) This section does not apply to separate contracts entered into as a result of separate tender processes.
(a) the same parties enter into 2 or more separate contracts; and
(b) the separate contracts are for carrying out project trust work at the same site or adjacent sites.
sec.14C
Subcontracts with related entities require project trusts
sec.14C Subcontracts with related entities require project trusts
A subcontract is eligible for a project trust if—
the subcontract is a first tier subcontract for a head contract; and
a project trust is required for the head contract; and
the subcontractor is a beneficiary of the project trust for the head contract; and
the subcontractor is a related entity for the contracted party for the head contract.
The contracted party for the head contract would also be the contracting party for the subcontract.
To remove any doubt, it is declared that the subcontractor continues to be a beneficiary of the project trust for the head contract.
s 14C ins 2020 No. 24 s 63
(sec.14C-ssec.1) A subcontract is eligible for a project trust if— the subcontract is a first tier subcontract for a head contract; and a project trust is required for the head contract; and the subcontractor is a beneficiary of the project trust for the head contract; and the subcontractor is a related entity for the contracted party for the head contract. The contracted party for the head contract would also be the contracting party for the subcontract.
(sec.14C-ssec.2) To remove any doubt, it is declared that the subcontractor continues to be a beneficiary of the project trust for the head contract.
(a) the subcontract is a first tier subcontract for a head contract; and
(b) a project trust is required for the head contract; and
(c) the subcontractor is a beneficiary of the project trust for the head contract; and
(d) the subcontractor is a related entity for the contracted party for the head contract. Note— The contracted party for the head contract would also be the contracting party for the subcontract.
A subcontract is eligible for a project trust if—
the subcontract is a first tier subcontract for a head contract; and
a project trust is required for the head contract; and
the subcontractor is a beneficiary of the project trust for the head contract; and
the subcontract is a type of subcontract prescribed by regulation.
To remove any doubt, it is declared that the subcontractor continues to be a beneficiary of the project trust for the head contract.
s 14E ins 2020 No. 24 s 63
(sec.14E-ssec.1) A subcontract is eligible for a project trust if— the subcontract is a first tier subcontract for a head contract; and a project trust is required for the head contract; and the subcontractor is a beneficiary of the project trust for the head contract; and the subcontract is a type of subcontract prescribed by regulation.
(sec.14E-ssec.2) To remove any doubt, it is declared that the subcontractor continues to be a beneficiary of the project trust for the head contract.
(a) the subcontract is a first tier subcontract for a head contract; and
(b) a project trust is required for the head contract; and
(c) the subcontractor is a beneficiary of the project trust for the head contract; and
(d) the subcontract is a type of subcontract prescribed by regulation.
sec.15
Subcontracts generally
sec.15 Subcontracts generally
A project trust is not required for a subcontract unless it is a type of subcontract to which section 14C or 14E apply.
s 15 sub 2020 No. 24 s 63
sec.15A
Contracts with particular entities
sec.15A Contracts with particular entities
A project trust is not required for a contract if the contracting party or contracted party is an entity prescribed by regulation.
s 15A ins 2020 No. 24 s 63
sec.15B
Contracts between the State and a state authority
sec.15B Contracts between the State and a state authority
A project trust is not required for a contract if the only parties to the contract are the State and a state authority.
s 15B ins 2020 No. 24 s 63
sec.15C
Contracts for small scale residential construction work
sec.15C Contracts for small scale residential construction work
A project trust is not required for a contract if the only project trust work to be carried out under the contract is residential construction work for less than 3 living units.
For subsection (1) —
a single detached dwelling is taken to be 1 living unit; and
a residential unit is taken to be 1 living unit; and
a duplex is taken to be 2 living units.
In this section—
residential construction work means the type of work prescribed by regulation.
residential unit means a part of a building designed for separate occupation as a residence.
s 15C ins 2020 No. 24 s 63
(sec.15C-ssec.1) A project trust is not required for a contract if the only project trust work to be carried out under the contract is residential construction work for less than 3 living units.
(sec.15C-ssec.2) For subsection (1) — a single detached dwelling is taken to be 1 living unit; and a residential unit is taken to be 1 living unit; and a duplex is taken to be 2 living units.
(sec.15C-ssec.3) In this section— residential construction work means the type of work prescribed by regulation. residential unit means a part of a building designed for separate occupation as a residence.
(a) a single detached dwelling is taken to be 1 living unit; and
(b) a residential unit is taken to be 1 living unit; and
(c) a duplex is taken to be 2 living units.
sec.15D
Contracts for maintenance work
sec.15D Contracts for maintenance work
A project trust is not required for a contract if the only project trust work to be carried out under the contract is maintenance work.
In this section—
maintenance work —
means—
testing; and
taking samples and restoring the sample site; and
work required on an ongoing basis to—
prevent deterioration or failure of a thing; or
restore a thing to its correct operating specifications; or
replace a component at the end of its working life; but
does not include—
improving a building to increase its capabilities or functions; or
improving a building to meet new statutory requirements applying to the building; or
a refurbishment or replacement of a building that extends the life of the building.
s 15D ins 2020 No. 24 s 63
(sec.15D-ssec.1) A project trust is not required for a contract if the only project trust work to be carried out under the contract is maintenance work.
(sec.15D-ssec.2) In this section— maintenance work — means— testing; and taking samples and restoring the sample site; and work required on an ongoing basis to— prevent deterioration or failure of a thing; or restore a thing to its correct operating specifications; or replace a component at the end of its working life; but does not include— improving a building to increase its capabilities or functions; or improving a building to meet new statutory requirements applying to the building; or a refurbishment or replacement of a building that extends the life of the building.
(a) means— (i) testing; and (ii) taking samples and restoring the sample site; and (iii) work required on an ongoing basis to— (A) prevent deterioration or failure of a thing; or (B) restore a thing to its correct operating specifications; or (C) replace a component at the end of its working life; but
(i) testing; and
(ii) taking samples and restoring the sample site; and
(iii) work required on an ongoing basis to— (A) prevent deterioration or failure of a thing; or (B) restore a thing to its correct operating specifications; or (C) replace a component at the end of its working life; but
(A) prevent deterioration or failure of a thing; or
(B) restore a thing to its correct operating specifications; or
(C) replace a component at the end of its working life; but
(b) does not include— (i) improving a building to increase its capabilities or functions; or (ii) improving a building to meet new statutory requirements applying to the building; or (iii) a refurbishment or replacement of a building that extends the life of the building.
(i) improving a building to increase its capabilities or functions; or
(ii) improving a building to meet new statutory requirements applying to the building; or
(iii) a refurbishment or replacement of a building that extends the life of the building.
(i) testing; and
(ii) taking samples and restoring the sample site; and
(iii) work required on an ongoing basis to— (A) prevent deterioration or failure of a thing; or (B) restore a thing to its correct operating specifications; or (C) replace a component at the end of its working life; but
(A) prevent deterioration or failure of a thing; or
(B) restore a thing to its correct operating specifications; or
(C) replace a component at the end of its working life; but
(A) prevent deterioration or failure of a thing; or
(B) restore a thing to its correct operating specifications; or
(C) replace a component at the end of its working life; but
(i) improving a building to increase its capabilities or functions; or
(ii) improving a building to meet new statutory requirements applying to the building; or
(iii) a refurbishment or replacement of a building that extends the life of the building.
sec.15E
Contracts for professional design, advisory or contract administration work
sec.15E Contracts for professional design, advisory or contract administration work
A project trust is not required for a contract if the only work to be carried out under the contract is advisory work or design work carried out, either directly or indirectly, by—
an architect under the Architects Act 2002 ; or
a registered professional engineer under the Professional Engineers Act 2002 ; or
a building designer; or
a person who carries on a business as a landscape architect.
Also, a project trust is not required for a contract if the only work to be carried out under the contract is contract administration carried out, either directly or indirectly, by a person mentioned in subsection (1) for the construction of a building wholly or partly designed by the person.
In this section—
advisory work means—
the inspection or investigation of a building; or
the provision of advice or a report about a building.
building designer means a person who holds a licence of a class mentioned in the Queensland Building and Construction Commission Regulation 2018 , schedule 2 , part 11 , 12 or 13 .
design work means the preparation of plans or specifications for project trust work.
s 15E ins 2020 No. 24 s 63
(sec.15E-ssec.1) A project trust is not required for a contract if the only work to be carried out under the contract is advisory work or design work carried out, either directly or indirectly, by— an architect under the Architects Act 2002 ; or a registered professional engineer under the Professional Engineers Act 2002 ; or a building designer; or a person who carries on a business as a landscape architect.
(sec.15E-ssec.2) Also, a project trust is not required for a contract if the only work to be carried out under the contract is contract administration carried out, either directly or indirectly, by a person mentioned in subsection (1) for the construction of a building wholly or partly designed by the person.
(sec.15E-ssec.3) In this section— advisory work means— the inspection or investigation of a building; or the provision of advice or a report about a building. building designer means a person who holds a licence of a class mentioned in the Queensland Building and Construction Commission Regulation 2018 , schedule 2 , part 11 , 12 or 13 . design work means the preparation of plans or specifications for project trust work.
(a) an architect under the Architects Act 2002 ; or
(b) a registered professional engineer under the Professional Engineers Act 2002 ; or
(c) a building designer; or
(d) a person who carries on a business as a landscape architect.
(a) the inspection or investigation of a building; or
(b) the provision of advice or a report about a building.
sec.15F
Contracts with less than 90 days until practical completion
sec.15F Contracts with less than 90 days until practical completion
A project trust is not required for a contract if there is less than 90 days between—
the first day a project trust would, apart from this section, be required for the contract (the trigger date ); and
If the effect of an amendment of a contract is that the contract becomes eligible for a project trust for the first time, the trigger date is the day the amendment takes effect. See section 14A .
the day practical completion for the contracted work is expected to occur.
If a project trust is not required for a contract because of subsection (1) , the contracted party must review the application of this section to the contract each time an amendment of the contract is made that is likely to affect the day practical completion for the contracted work is expected to occur.
In this section—
practical completion , for contracted work for a contract, means—
practical completion as provided for under the contract; or
if the contract does not provide for practical completion—when the contracted work would reasonably be estimated to be completed—
in compliance with the contract, including all plans and specifications for the work and all statutory requirements applying to the work; and
without any defects or omissions, other than minor defects or minor omissions that will not unreasonably affect the intended use of the work.
s 15F ins 2020 No. 24 s 63
amd 2024 No. 14 s 27
(sec.15F-ssec.1) A project trust is not required for a contract if there is less than 90 days between— the first day a project trust would, apart from this section, be required for the contract (the trigger date ); and If the effect of an amendment of a contract is that the contract becomes eligible for a project trust for the first time, the trigger date is the day the amendment takes effect. See section 14A . the day practical completion for the contracted work is expected to occur.
(sec.15F-ssec.2) If a project trust is not required for a contract because of subsection (1) , the contracted party must review the application of this section to the contract each time an amendment of the contract is made that is likely to affect the day practical completion for the contracted work is expected to occur.
(sec.15F-ssec.3) In this section— practical completion , for contracted work for a contract, means— practical completion as provided for under the contract; or if the contract does not provide for practical completion—when the contracted work would reasonably be estimated to be completed— in compliance with the contract, including all plans and specifications for the work and all statutory requirements applying to the work; and without any defects or omissions, other than minor defects or minor omissions that will not unreasonably affect the intended use of the work.
(a) the first day a project trust would, apart from this section, be required for the contract (the trigger date ); and Note— If the effect of an amendment of a contract is that the contract becomes eligible for a project trust for the first time, the trigger date is the day the amendment takes effect. See section 14A .
(b) the day practical completion for the contracted work is expected to occur.
(a) practical completion as provided for under the contract; or
(b) if the contract does not provide for practical completion—when the contracted work would reasonably be estimated to be completed— (i) in compliance with the contract, including all plans and specifications for the work and all statutory requirements applying to the work; and (ii) without any defects or omissions, other than minor defects or minor omissions that will not unreasonably affect the intended use of the work.
(i) in compliance with the contract, including all plans and specifications for the work and all statutory requirements applying to the work; and
(ii) without any defects or omissions, other than minor defects or minor omissions that will not unreasonably affect the intended use of the work.
(i) in compliance with the contract, including all plans and specifications for the work and all statutory requirements applying to the work; and
(ii) without any defects or omissions, other than minor defects or minor omissions that will not unreasonably affect the intended use of the work.
sec.16
Section sec.16
s 16 om 2020 No. 24 s 63
ch.2-pt.2-div.4
Project trust administration
Project trust administration
sec.17
Establishment of project trust
sec.17 Establishment of project trust
Once a project trust is required for a contract under section 12 , the trust is established by the first of the following being made after the trust is required—
payment of an amount from the contracting party to the contracted party under the contract;
payment of an amount from the contracted party to a subcontractor beneficiary for subcontracted work under the contract;
a deposit in the project trust account as required under this chapter.
s 17 sub 2020 No. 24 s 63
(a) payment of an amount from the contracting party to the contracted party under the contract;
(b) payment of an amount from the contracted party to a subcontractor beneficiary for subcontracted work under the contract;
(c) a deposit in the project trust account as required under this chapter.
sec.18
Contracted party must open project trust account
sec.18 Contracted party must open project trust account
If a project trust is required for a contract under section 12 , the contracted party must open an account at a financial institution for the trust as required by this section.
Maximum penalty—500 penalty units.
The project trust account must be opened within 20 business days after the contracted party enters into the first subcontract for the contract.
However—
if a project trust is not required for the contract until after an amendment of the contract; and
See section 14A about amendments of contracts affecting the requirement to establish a project trust.
the contracted party entered into a subcontract for the contract before the amendment of the contract;
the project trust account must be opened within 20 business days after the day the contract is amended.
The project trust account must not be a virtual account or subordinate to any other account at a financial institution.
There must not be more than 1 project trust account for the project trust.
A provision of a contract that provides that the project trust account must be opened less than 20 business days after the contract is entered into is of no effect.
s 18 sub 2020 No. 24 s 63
(sec.18-ssec.1) If a project trust is required for a contract under section 12 , the contracted party must open an account at a financial institution for the trust as required by this section. Maximum penalty—500 penalty units.
(sec.18-ssec.2) The project trust account must be opened within 20 business days after the contracted party enters into the first subcontract for the contract.
(sec.18-ssec.3) However— if a project trust is not required for the contract until after an amendment of the contract; and See section 14A about amendments of contracts affecting the requirement to establish a project trust. the contracted party entered into a subcontract for the contract before the amendment of the contract; the project trust account must be opened within 20 business days after the day the contract is amended.
(sec.18-ssec.4) The project trust account must not be a virtual account or subordinate to any other account at a financial institution.
(sec.18-ssec.5) There must not be more than 1 project trust account for the project trust.
(sec.18-ssec.6) A provision of a contract that provides that the project trust account must be opened less than 20 business days after the contract is entered into is of no effect.
(a) if a project trust is not required for the contract until after an amendment of the contract; and Note— See section 14A about amendments of contracts affecting the requirement to establish a project trust.
(b) the contracted party entered into a subcontract for the contract before the amendment of the contract;
sec.18A
Restrictions for project trust account
sec.18A Restrictions for project trust account
A trustee must ensure the project trust account is held at an approved financial institution.
Maximum penalty—200 penalty units.
A trustee must ensure the project trust account is held under a name that includes the trustee’s name and the word ‘trust’.
Maximum penalty—200 penalty units.
A trustee must ensure that deposits of amounts to, and withdrawals of amounts from, the project trust account are made using only methods that create an electronic record of the transfer.
Maximum penalty—500 penalty units.
s 18A ins 2020 No. 24 s 63
(sec.18A-ssec.1) A trustee must ensure the project trust account is held at an approved financial institution. Maximum penalty—200 penalty units.
(sec.18A-ssec.2) A trustee must ensure the project trust account is held under a name that includes the trustee’s name and the word ‘trust’. Maximum penalty—200 penalty units.
(sec.18A-ssec.3) A trustee must ensure that deposits of amounts to, and withdrawals of amounts from, the project trust account are made using only methods that create an electronic record of the transfer. Maximum penalty—500 penalty units.
sec.18B
Notice of project trust account’s opening, closing or name change
sec.18B Notice of project trust account’s opening, closing or name change
This section applies if a trustee, or another person on behalf of a trustee, takes any of the following actions in relation to the project trust account—
opens the account;
changes the name of the account;
closes the account;
transfers the account.
Within 5 business days after taking the action, the trustee must give to the contracting party, and must give to the commissioner using an approved way, a notice—
stating the action taken; and
including the information prescribed by regulation.
Maximum penalty—200 penalty units.
s 18B ins 2020 No. 24 s 63
(sec.18B-ssec.1) This section applies if a trustee, or another person on behalf of a trustee, takes any of the following actions in relation to the project trust account— opens the account; changes the name of the account; closes the account; transfers the account.
(sec.18B-ssec.2) Within 5 business days after taking the action, the trustee must give to the contracting party, and must give to the commissioner using an approved way, a notice— stating the action taken; and including the information prescribed by regulation. Maximum penalty—200 penalty units.
(a) opens the account;
(b) changes the name of the account;
(c) closes the account;
(d) transfers the account.
(a) stating the action taken; and
(b) including the information prescribed by regulation.
sec.18C
Change of financial institution
sec.18C Change of financial institution
A trustee must not transfer the project trust account to an alternative financial institution unless—
the alternative financial institution is an approved financial institution; and
all amounts held in the account are transferred with the account to the alternative financial institution; and
the trustee informs the contracting party, the commissioner and the subcontractor beneficiaries about the transfer as prescribed by regulation.
Maximum penalty—200 penalty units.
See, also, section 18B for the trustee’s obligation to inform the contracting party and the commissioner of closing and opening a project trust account.
When transferring the project trust account to an alternative financial institution, the trustee may withdraw the amounts of interest credited to the account by a financial institution, if the withdrawal is authorised under section 51D .
Nothing in this section enables the trustee to have more than 1 project trust account for a project trust at the same time beyond the period necessary to transfer the project trust account.
In this section—
alternative financial institution , for a project trust account, means a financial institution that is not the financial institution at which the account is currently kept.
s 18C ins 2020 No. 24 s 63
amd 2024 No. 14 s 28
(sec.18C-ssec.1) A trustee must not transfer the project trust account to an alternative financial institution unless— the alternative financial institution is an approved financial institution; and all amounts held in the account are transferred with the account to the alternative financial institution; and the trustee informs the contracting party, the commissioner and the subcontractor beneficiaries about the transfer as prescribed by regulation. Maximum penalty—200 penalty units. See, also, section 18B for the trustee’s obligation to inform the contracting party and the commissioner of closing and opening a project trust account.
(sec.18C-ssec.2) When transferring the project trust account to an alternative financial institution, the trustee may withdraw the amounts of interest credited to the account by a financial institution, if the withdrawal is authorised under section 51D .
(sec.18C-ssec.3) Nothing in this section enables the trustee to have more than 1 project trust account for a project trust at the same time beyond the period necessary to transfer the project trust account.
(sec.18C-ssec.4) In this section— alternative financial institution , for a project trust account, means a financial institution that is not the financial institution at which the account is currently kept.
(a) the alternative financial institution is an approved financial institution; and
(b) all amounts held in the account are transferred with the account to the alternative financial institution; and
(c) the trustee informs the contracting party, the commissioner and the subcontractor beneficiaries about the transfer as prescribed by regulation.
sec.19
All payments from contracting party to be deposited in project trust account
sec.19 All payments from contracting party to be deposited in project trust account
This section applies to any of the following amounts paid by the contracting party to the contracted party in connection with a project trust contract—
an amount paid in accordance with the terms of the contract;
an amount paid because the contracting party is liable under section 77 to pay the amount to the contracted party in connection with the contract;
an amount paid under chapter 3 , part 4 because of an adjudication of a disputed progress payment relating to the contract;
an amount paid because of a final and binding dispute resolution process relating to the contract;
an amount paid because of a court order relating to the contract;
an amount, paid for any other reason, that reduces the unpaid amount of the contract price for the contract.
The contracting party must deposit the amount into the project trust account for the contract (the deposit obligation ) unless—
the amount was due to be paid before the trust was established; or
the amount is paid into court; or
the amount is to be withheld because of a payment withholding request given to the contracting party under section 97B ; or
the amount is paid directly to a person under chapter 4 in connection with a subcontractor’s charge; or
the contracting party has a reasonable excuse for failing to deposit the amount into the account.
Maximum penalty—200 penalty units.
Once the amount is deposited into the project trust account, the deposit is taken to be a payment made by the contracting party to the contracted party and discharges the contracting party’s liability to pay that amount to the contracted party.
If an amount is paid to the contracted party or its agent in contravention of the deposit obligation, the contracted party must deposit the amount into the project trust account as soon as practicable after receiving the amount.
Maximum penalty for subsection (4) —200 penalty units or 2 years imprisonment.
s 19 amd 2018 No. 17 s 176G
sub 2020 No. 24 s 63
amd 2024 No. 14 s 29
(sec.19-ssec.1) This section applies to any of the following amounts paid by the contracting party to the contracted party in connection with a project trust contract— an amount paid in accordance with the terms of the contract; an amount paid because the contracting party is liable under section 77 to pay the amount to the contracted party in connection with the contract; an amount paid under chapter 3 , part 4 because of an adjudication of a disputed progress payment relating to the contract; an amount paid because of a final and binding dispute resolution process relating to the contract; an amount paid because of a court order relating to the contract; an amount, paid for any other reason, that reduces the unpaid amount of the contract price for the contract.
(sec.19-ssec.2) The contracting party must deposit the amount into the project trust account for the contract (the deposit obligation ) unless— the amount was due to be paid before the trust was established; or the amount is paid into court; or the amount is to be withheld because of a payment withholding request given to the contracting party under section 97B ; or the amount is paid directly to a person under chapter 4 in connection with a subcontractor’s charge; or the contracting party has a reasonable excuse for failing to deposit the amount into the account. Maximum penalty—200 penalty units.
(sec.19-ssec.3) Once the amount is deposited into the project trust account, the deposit is taken to be a payment made by the contracting party to the contracted party and discharges the contracting party’s liability to pay that amount to the contracted party.
(sec.19-ssec.4) If an amount is paid to the contracted party or its agent in contravention of the deposit obligation, the contracted party must deposit the amount into the project trust account as soon as practicable after receiving the amount. Maximum penalty for subsection (4) —200 penalty units or 2 years imprisonment.
(a) an amount paid in accordance with the terms of the contract;
(b) an amount paid because the contracting party is liable under section 77 to pay the amount to the contracted party in connection with the contract;
(c) an amount paid under chapter 3 , part 4 because of an adjudication of a disputed progress payment relating to the contract;
(d) an amount paid because of a final and binding dispute resolution process relating to the contract;
(e) an amount paid because of a court order relating to the contract;
(f) an amount, paid for any other reason, that reduces the unpaid amount of the contract price for the contract.
(a) the amount was due to be paid before the trust was established; or
(b) the amount is paid into court; or
(c) the amount is to be withheld because of a payment withholding request given to the contracting party under section 97B ; or
(d) the amount is paid directly to a person under chapter 4 in connection with a subcontractor’s charge; or
(e) the contracting party has a reasonable excuse for failing to deposit the amount into the account.
sec.19A
Limited purposes for which money may be deposited in project trust account
sec.19A Limited purposes for which money may be deposited in project trust account
A trustee must not cause an amount to be deposited into the project trust account for any purpose other than—
paying the trustee, as the contracted party, an amount the contracting party must deposit into the account under section 19 ; or
paying a subcontractor beneficiary an amount the subcontractor is entitled, or may become entitled, to be paid in connection with a project trust subcontract; or
repaying an amount withdrawn from the account in error; or
making another payment prescribed by regulation.
Maximum penalty—200 penalty units or 1 year’s imprisonment.
This section does not apply to an amount of interest credited to the project trust account by a financial institution.
s 19A ins 2020 No. 24 s 63
amd 2024 No. 14 s 30
(sec.19A-ssec.1) A trustee must not cause an amount to be deposited into the project trust account for any purpose other than— paying the trustee, as the contracted party, an amount the contracting party must deposit into the account under section 19 ; or paying a subcontractor beneficiary an amount the subcontractor is entitled, or may become entitled, to be paid in connection with a project trust subcontract; or repaying an amount withdrawn from the account in error; or making another payment prescribed by regulation. Maximum penalty—200 penalty units or 1 year’s imprisonment.
(sec.19A-ssec.2) This section does not apply to an amount of interest credited to the project trust account by a financial institution.
(a) paying the trustee, as the contracted party, an amount the contracting party must deposit into the account under section 19 ; or
(b) paying a subcontractor beneficiary an amount the subcontractor is entitled, or may become entitled, to be paid in connection with a project trust subcontract; or
(c) repaying an amount withdrawn from the account in error; or
(d) making another payment prescribed by regulation.
sec.20
All payments to subcontractor beneficiaries to be paid from project trust account
sec.20 All payments to subcontractor beneficiaries to be paid from project trust account
The contracted party for a project trust contract may only pay an amount to a subcontractor beneficiary of the project trust—
from the project trust account; and
by depositing the amount into the account of a financial institution nominated by the beneficiary.
Maximum penalty—200 penalty units or 1 year’s imprisonment.
To remove any doubt, it is declared that the obligation to pay an amount from the project trust account applies whether or not the amount is held in the account when it is to be paid.
See section 51 about covering shortfalls.
The account nominated by the subcontractor beneficiary under subsection (1) (b) must be—
controlled by the beneficiary; and
if the beneficiary is also required to establish a project trust for its subcontract—the account for the project trust for the subcontract.
This section does not apply to—
a retention amount withheld from payment to a subcontractor beneficiary if the amount is deposited into a retention trust account of which the subcontractor is, or will be, a beneficiary; and
a retention amount to be released to a subcontractor beneficiary from a retention trust account.
s 20 sub 2020 No. 24 s 63
amd 2024 No. 14 s 31
(sec.20-ssec.1) The contracted party for a project trust contract may only pay an amount to a subcontractor beneficiary of the project trust— from the project trust account; and by depositing the amount into the account of a financial institution nominated by the beneficiary. Maximum penalty—200 penalty units or 1 year’s imprisonment.
(sec.20-ssec.2) To remove any doubt, it is declared that the obligation to pay an amount from the project trust account applies whether or not the amount is held in the account when it is to be paid. See section 51 about covering shortfalls.
(sec.20-ssec.3) The account nominated by the subcontractor beneficiary under subsection (1) (b) must be— controlled by the beneficiary; and if the beneficiary is also required to establish a project trust for its subcontract—the account for the project trust for the subcontract.
(sec.20-ssec.4) This section does not apply to— a retention amount withheld from payment to a subcontractor beneficiary if the amount is deposited into a retention trust account of which the subcontractor is, or will be, a beneficiary; and a retention amount to be released to a subcontractor beneficiary from a retention trust account.
(a) from the project trust account; and
(b) by depositing the amount into the account of a financial institution nominated by the beneficiary.
(a) controlled by the beneficiary; and
(b) if the beneficiary is also required to establish a project trust for its subcontract—the account for the project trust for the subcontract.
(a) a retention amount withheld from payment to a subcontractor beneficiary if the amount is deposited into a retention trust account of which the subcontractor is, or will be, a beneficiary; and
(b) a retention amount to be released to a subcontractor beneficiary from a retention trust account.
sec.20A
Limited purposes for which money may be withdrawn from project trust account
sec.20A Limited purposes for which money may be withdrawn from project trust account
A trustee must not withdraw an amount from the project trust account for any purpose other than—
paying a subcontractor beneficiary an amount the contracted party is liable to pay the beneficiary in connection with its subcontract; or
paying the trustee, as the contracted party, an amount the contracting party is liable to pay the contracted party for contracted work but only to the extent a subcontractor beneficiary is not entitled to be paid for the same work; or
returning an amount paid in error by the contracting party; or
depositing a retention amount into a retention trust account; or
making payment relating to the contract in accordance with an adjudication under chapter 3 , part 4 ; or
making payment relating to the contract as ordered by a court; or
making another payment prescribed by regulation.
Maximum penalty—300 penalty units or 2 years imprisonment.
A trustee must repay all amounts it withdraws in contravention of subsection (1) as soon as practicable after the trustee becomes aware the withdrawal is in contravention of that subsection.
Maximum penalty—300 penalty units or 2 years imprisonment.
A trustee is taken to have withdrawn an amount from the project trust account if—
the trustee authorises any person to make the withdrawal; or
the trustee knowingly contributes to the withdrawal being made.
This section does not apply to the withdrawal of an amount for the project trust account for—
an amount of interest authorised to be withdrawn under section 51D ; or
an amount for fees charged by the approved financial institution for the project trust account.
s 20A ins 2020 No. 24 s 63
amd 2024 No. 14 s 32
(sec.20A-ssec.1) A trustee must not withdraw an amount from the project trust account for any purpose other than— paying a subcontractor beneficiary an amount the contracted party is liable to pay the beneficiary in connection with its subcontract; or paying the trustee, as the contracted party, an amount the contracting party is liable to pay the contracted party for contracted work but only to the extent a subcontractor beneficiary is not entitled to be paid for the same work; or returning an amount paid in error by the contracting party; or depositing a retention amount into a retention trust account; or making payment relating to the contract in accordance with an adjudication under chapter 3 , part 4 ; or making payment relating to the contract as ordered by a court; or making another payment prescribed by regulation. Maximum penalty—300 penalty units or 2 years imprisonment.
(sec.20A-ssec.2) A trustee must repay all amounts it withdraws in contravention of subsection (1) as soon as practicable after the trustee becomes aware the withdrawal is in contravention of that subsection. Maximum penalty—300 penalty units or 2 years imprisonment.
(sec.20A-ssec.3) A trustee is taken to have withdrawn an amount from the project trust account if— the trustee authorises any person to make the withdrawal; or the trustee knowingly contributes to the withdrawal being made.
(sec.20A-ssec.4) This section does not apply to the withdrawal of an amount for the project trust account for— an amount of interest authorised to be withdrawn under section 51D ; or an amount for fees charged by the approved financial institution for the project trust account.
(a) paying a subcontractor beneficiary an amount the contracted party is liable to pay the beneficiary in connection with its subcontract; or
(b) paying the trustee, as the contracted party, an amount the contracting party is liable to pay the contracted party for contracted work but only to the extent a subcontractor beneficiary is not entitled to be paid for the same work; or
(c) returning an amount paid in error by the contracting party; or
(d) depositing a retention amount into a retention trust account; or
(e) making payment relating to the contract in accordance with an adjudication under chapter 3 , part 4 ; or
(f) making payment relating to the contract as ordered by a court; or
(g) making another payment prescribed by regulation.
(a) the trustee authorises any person to make the withdrawal; or
(b) the trustee knowingly contributes to the withdrawal being made.
(a) an amount of interest authorised to be withdrawn under section 51D ; or
(b) an amount for fees charged by the approved financial institution for the project trust account.
sec.20B
Order of priority
sec.20B Order of priority
A trustee must not withdraw an amount from the project trust account to pay itself, or make another payment prescribed by regulation, unless there would still be a sufficient amount available in the account after the withdrawal to pay all amounts the contracted party is liable to pay subcontractor beneficiaries at the time of the withdrawal.
Maximum penalty—300 penalty units or 2 years imprisonment.
s 20B ins 2020 No. 24 s 63
sec.20C
Insufficient amounts available for payments
sec.20C Insufficient amounts available for payments
This section applies if—
a project trust is established for a contract; and
the contracted party is liable to pay 2 or more subcontractor beneficiaries (each a claimant ) an amount at the same time; and
the total amount held in the project trust account is insufficient to satisfy in full all of the amounts liable to be paid to the claimants; and
when an amount liable to be paid to a claimant is due to be paid, the contracted party has not complied with its obligation under section 51 to cover the insufficient amount.
The amount to be paid by the contracted party to each claimant is to be reduced in proportion to the amounts liable to be paid to each.
If one subcontractor beneficiary is to be paid $50,000 and another subcontractor beneficiary is to be paid $30,000 but only $40,000 is available, the beneficiaries are to be paid $25,000 and $15,000 respectively.
If the contracted party makes a payment complying with subsection (2) , the party must, using an approved way, inform the commissioner of the payment as soon as practicable after making it.
Maximum penalty—100 penalty units.
While there continues to be an insufficient amount held in the project trust account, the contracted party must not pay a subcontractor beneficiary unless the payment complies with subsection (2) .
Maximum penalty—100 penalty units or 1 year’s imprisonment.
Nothing in this section relieves the contracted party of the party’s liability to pay in full the amounts the subcontractor beneficiaries are entitled to be paid in connection with project trust subcontracts.
s 20C ins 2020 No. 24 s 63
amd 2024 No. 14 s 33
(sec.20C-ssec.1) This section applies if— a project trust is established for a contract; and the contracted party is liable to pay 2 or more subcontractor beneficiaries (each a claimant ) an amount at the same time; and the total amount held in the project trust account is insufficient to satisfy in full all of the amounts liable to be paid to the claimants; and when an amount liable to be paid to a claimant is due to be paid, the contracted party has not complied with its obligation under section 51 to cover the insufficient amount.
(sec.20C-ssec.2) The amount to be paid by the contracted party to each claimant is to be reduced in proportion to the amounts liable to be paid to each. If one subcontractor beneficiary is to be paid $50,000 and another subcontractor beneficiary is to be paid $30,000 but only $40,000 is available, the beneficiaries are to be paid $25,000 and $15,000 respectively.
(sec.20C-ssec.3) If the contracted party makes a payment complying with subsection (2) , the party must, using an approved way, inform the commissioner of the payment as soon as practicable after making it. Maximum penalty—100 penalty units.
(sec.20C-ssec.4) While there continues to be an insufficient amount held in the project trust account, the contracted party must not pay a subcontractor beneficiary unless the payment complies with subsection (2) . Maximum penalty—100 penalty units or 1 year’s imprisonment.
(sec.20C-ssec.5) Nothing in this section relieves the contracted party of the party’s liability to pay in full the amounts the subcontractor beneficiaries are entitled to be paid in connection with project trust subcontracts.
(a) a project trust is established for a contract; and
(b) the contracted party is liable to pay 2 or more subcontractor beneficiaries (each a claimant ) an amount at the same time; and
(c) the total amount held in the project trust account is insufficient to satisfy in full all of the amounts liable to be paid to the claimants; and
(d) when an amount liable to be paid to a claimant is due to be paid, the contracted party has not complied with its obligation under section 51 to cover the insufficient amount.
sec.21
Ending project trust
sec.21 Ending project trust
Once a project trust is established for a contract, the trustee may dissolve the trust only if—
there are no longer any subcontractor beneficiaries for the trust; or
the only remaining work to be carried out under the contract is maintenance work.
A project trust is dissolved by the trustee—
closing the project trust account; and
giving written notice to the commissioner of the trust having been dissolved.
A trustee is taken not to dissolve the project trust by closing the project trust account if the account was only closed for the purpose of transferring the account to another financial institution under section 18C .
When dissolving the project trust, the trustee may pay itself the following amounts—
any amount for interest that the trustee is entitled to under section 51D ;
any remaining amount that is not owing to a subcontractor beneficiary.
In this section—
maintenance work see section 15D (2) .
s 21 sub 2020 No. 24 s 62
amd 2024 No. 14 s 34
(sec.21-ssec.1) Once a project trust is established for a contract, the trustee may dissolve the trust only if— there are no longer any subcontractor beneficiaries for the trust; or the only remaining work to be carried out under the contract is maintenance work.
(sec.21-ssec.2) A project trust is dissolved by the trustee— closing the project trust account; and giving written notice to the commissioner of the trust having been dissolved.
(sec.21-ssec.3) A trustee is taken not to dissolve the project trust by closing the project trust account if the account was only closed for the purpose of transferring the account to another financial institution under section 18C .
(sec.21-ssec.4) When dissolving the project trust, the trustee may pay itself the following amounts— any amount for interest that the trustee is entitled to under section 51D ; any remaining amount that is not owing to a subcontractor beneficiary.
(sec.21-ssec.5) In this section— maintenance work see section 15D (2) .
(a) there are no longer any subcontractor beneficiaries for the trust; or
(b) the only remaining work to be carried out under the contract is maintenance work.
(a) closing the project trust account; and
(b) giving written notice to the commissioner of the trust having been dissolved.
(a) any amount for interest that the trustee is entitled to under section 51D ;
(b) any remaining amount that is not owing to a subcontractor beneficiary.
sec.21A
Unauthorised dissolution of project trust
sec.21A Unauthorised dissolution of project trust
A person must not purport to dissolve a project trust before it may be dissolved under section 21 (1) .
Maximum penalty—500 penalty units or 1 year’s imprisonment.
Without limiting subsection (1) , the person is taken to purport to dissolve a project trust if the person closes the account for the trust while it is still required.
Subsection (2) does not apply to a person transferring the project trust account to another financial institution under section 18C .
s 21A ins 2020 No. 24 s 63
(sec.21A-ssec.1) A person must not purport to dissolve a project trust before it may be dissolved under section 21 (1) . Maximum penalty—500 penalty units or 1 year’s imprisonment.
(sec.21A-ssec.2) Without limiting subsection (1) , the person is taken to purport to dissolve a project trust if the person closes the account for the trust while it is still required.
(sec.21A-ssec.3) Subsection (2) does not apply to a person transferring the project trust account to another financial institution under section 18C .
sec.22
Section sec.22
s 22 om 2020 No. 24 s 63
ch.2-pt.2-div.5
Information sharing
Information sharing
sec.23
Notice of project trust before entering subcontracts
sec.23 Notice of project trust before entering subcontracts
The contracted party for a project trust contract must give each subcontractor a notice about the use of a project trust account ( notice of project trust ) as required by this section.
Maximum penalty—200 penalty units or 1 year’s imprisonment.
The notice of project trust must—
be in writing; and
include a statement that a project trust will be used for making payments to the subcontractor; and
include the information prescribed by regulation.
The notice of project trust must be given to the subcontractor—
if the project trust is not yet established when the contracted party and the subcontractor enter into a subcontract—within 10 business days after the trust is established; or
if the project trust is already established when the contracted party and the subcontractor enter into a subcontract—before the contracted party and the subcontractor enter into a subcontract.
However—
if a project trust is not required for a contract until after an amendment of the contract; and
See section 14A about amendments of a contract affecting the requirement to establish a project trust.
the contracted party entered into a subcontract for the contract before the amendment of the contract;
the notice of project trust must be given within 10 business days after opening the project trust account.
s 23 amd 2018 No. 17 s 176H
sub 2020 No. 24 s 63
amd 2024 No. 14 s 35
(sec.23-ssec.1) The contracted party for a project trust contract must give each subcontractor a notice about the use of a project trust account ( notice of project trust ) as required by this section. Maximum penalty—200 penalty units or 1 year’s imprisonment.
(sec.23-ssec.2) The notice of project trust must— be in writing; and include a statement that a project trust will be used for making payments to the subcontractor; and include the information prescribed by regulation.
(sec.23-ssec.3) The notice of project trust must be given to the subcontractor— if the project trust is not yet established when the contracted party and the subcontractor enter into a subcontract—within 10 business days after the trust is established; or if the project trust is already established when the contracted party and the subcontractor enter into a subcontract—before the contracted party and the subcontractor enter into a subcontract.
(sec.23-ssec.4) However— if a project trust is not required for a contract until after an amendment of the contract; and See section 14A about amendments of a contract affecting the requirement to establish a project trust. the contracted party entered into a subcontract for the contract before the amendment of the contract; the notice of project trust must be given within 10 business days after opening the project trust account.
(a) be in writing; and
(b) include a statement that a project trust will be used for making payments to the subcontractor; and
(c) include the information prescribed by regulation.
(a) if the project trust is not yet established when the contracted party and the subcontractor enter into a subcontract—within 10 business days after the trust is established; or
(b) if the project trust is already established when the contracted party and the subcontractor enter into a subcontract—before the contracted party and the subcontractor enter into a subcontract.
(a) if a project trust is not required for a contract until after an amendment of the contract; and Note— See section 14A about amendments of a contract affecting the requirement to establish a project trust.
(b) the contracted party entered into a subcontract for the contract before the amendment of the contract;
sec.23A
Subcontractor beneficiary to be informed of particular withdrawals
sec.23A Subcontractor beneficiary to be informed of particular withdrawals
This section applies if—
a withdrawal is made from a project trust account to make a payment to a subcontractor beneficiary; or
a withdrawal is made from a project trust account to deposit an amount, withheld from payment to a subcontractor beneficiary, in a retention trust account for the benefit of the subcontractor beneficiary.
Within 5 business days after making the withdrawal, the trustee for the project trust must give the subcontractor beneficiary a notice of the withdrawal that includes the information prescribed by regulation, unless the trustee has a reasonable excuse.
Maximum penalty—100 penalty units.
s 23A ins 2020 No. 24 s 63
(sec.23A-ssec.1) This section applies if— a withdrawal is made from a project trust account to make a payment to a subcontractor beneficiary; or a withdrawal is made from a project trust account to deposit an amount, withheld from payment to a subcontractor beneficiary, in a retention trust account for the benefit of the subcontractor beneficiary.
(sec.23A-ssec.2) Within 5 business days after making the withdrawal, the trustee for the project trust must give the subcontractor beneficiary a notice of the withdrawal that includes the information prescribed by regulation, unless the trustee has a reasonable excuse. Maximum penalty—100 penalty units.
(a) a withdrawal is made from a project trust account to make a payment to a subcontractor beneficiary; or
(b) a withdrawal is made from a project trust account to deposit an amount, withheld from payment to a subcontractor beneficiary, in a retention trust account for the benefit of the subcontractor beneficiary.
sec.23B
Subcontractor beneficiary may request particular information
sec.23B Subcontractor beneficiary may request particular information
A person who is, or was, a subcontractor beneficiary of a project trust may, in writing, request the trustee give the person the following information to the extent it relates to the person—
a statement of balance for the project trust account;
a copy of the transactions for the project trust account;
a copy of the trust records;
a copy of supporting statements given to the contracting party with the payment claims made by the trustee as the contracted party.
The trustee must give the person the requested information within 10 business days after being given the request, unless—
the trustee has a reasonable excuse; or
the information is already available to the person; or
the information has not changed since it was previously given to the person.
Maximum penalty—100 penalty units.
The requested information must be given to the person in writing and any words used in the information to explain a transaction must be in the English language.
It is not a reasonable excuse for the trustee to fail to comply with the request on the grounds that complying with the request might tend to incriminate the trustee or expose the trustee to a penalty.
In this section—
supporting statement see section 75 (9) .
s 23B ins 2020 No. 24 s 63
(sec.23B-ssec.1) A person who is, or was, a subcontractor beneficiary of a project trust may, in writing, request the trustee give the person the following information to the extent it relates to the person— a statement of balance for the project trust account; a copy of the transactions for the project trust account; a copy of the trust records; a copy of supporting statements given to the contracting party with the payment claims made by the trustee as the contracted party.
(sec.23B-ssec.2) The trustee must give the person the requested information within 10 business days after being given the request, unless— the trustee has a reasonable excuse; or the information is already available to the person; or the information has not changed since it was previously given to the person. Maximum penalty—100 penalty units.
(sec.23B-ssec.3) The requested information must be given to the person in writing and any words used in the information to explain a transaction must be in the English language.
(sec.23B-ssec.4) It is not a reasonable excuse for the trustee to fail to comply with the request on the grounds that complying with the request might tend to incriminate the trustee or expose the trustee to a penalty.
(sec.23B-ssec.5) In this section— supporting statement see section 75 (9) .
(a) a statement of balance for the project trust account;
(b) a copy of the transactions for the project trust account;
(c) a copy of the trust records;
(d) a copy of supporting statements given to the contracting party with the payment claims made by the trustee as the contracted party.
(a) the trustee has a reasonable excuse; or
(b) the information is already available to the person; or
(c) the information has not changed since it was previously given to the person.
ch.2-pt.2-div.6
Obligations of contracting party
Obligations of contracting party
sec.24
Contracting party to report related entities
sec.24 Contracting party to report related entities
This section applies if—
a project trust is established for a contract; and
the contracting party knows, or ought reasonably to know, that a subcontractor beneficiary is a related entity for the contracted party.
The contracting party must, using an approved way, inform the commissioner of the matter within 5 business days after the party first becomes aware, or ought reasonably to have become aware, of the matter.
Maximum penalty—50 penalty units.
s 24 sub 2020 No. 24 s 63
(sec.24-ssec.1) This section applies if— a project trust is established for a contract; and the contracting party knows, or ought reasonably to know, that a subcontractor beneficiary is a related entity for the contracted party.
(sec.24-ssec.2) The contracting party must, using an approved way, inform the commissioner of the matter within 5 business days after the party first becomes aware, or ought reasonably to have become aware, of the matter. Maximum penalty—50 penalty units.
(a) a project trust is established for a contract; and
(b) the contracting party knows, or ought reasonably to know, that a subcontractor beneficiary is a related entity for the contracted party.
sec.24A
Contracting party to report failure to establish project trust
sec.24A Contracting party to report failure to establish project trust
This section applies if the contracting party for a contract knows or ought reasonably to know—
a project trust is required for the contract; and
a project trust account has not been opened for the trust as required under section 18 .
The contracting party must, using an approved way, report the matter to the commissioner.
Maximum penalty—100 penalty units.
s 24A ins 2020 No. 24 s 63
(sec.24A-ssec.1) This section applies if the contracting party for a contract knows or ought reasonably to know— a project trust is required for the contract; and a project trust account has not been opened for the trust as required under section 18 .
(sec.24A-ssec.2) The contracting party must, using an approved way, report the matter to the commissioner. Maximum penalty—100 penalty units.
(a) a project trust is required for the contract; and
(b) a project trust account has not been opened for the trust as required under section 18 .
ch.2-pt.2-div.7
Other matters
Other matters
sec.25
Contracted party to report related entities
sec.25 Contracted party to report related entities
This section applies if—
a project trust is established for a contract; and
the contracted party enters into a subcontract with a related entity for the party.
The contracted party must, using an approved way, inform the commissioner about entering into the subcontract with the related entity within 5 business days after entering into the subcontract.
Maximum penalty—200 penalty units.
s 25 amd 2018 No. 17 s 176I
sub 2020 No. 24 s 63
(sec.25-ssec.1) This section applies if— a project trust is established for a contract; and the contracted party enters into a subcontract with a related entity for the party.
(sec.25-ssec.2) The contracted party must, using an approved way, inform the commissioner about entering into the subcontract with the related entity within 5 business days after entering into the subcontract. Maximum penalty—200 penalty units.
(a) a project trust is established for a contract; and
(b) the contracted party enters into a subcontract with a related entity for the party.
sec.25A
Limited liability of contracting party
sec.25A Limited liability of contracting party
Nothing in this part creates or supports a right of action against the contracting party for a contract by a subcontractor, or the contracted party, as a beneficiary of a project trust for the contract.
s 25A ins 2020 No. 24 s 63
sec.25B
No assignment of entitlement by contracted party
sec.25B No assignment of entitlement by contracted party
An assignment by the contracted party of an entitlement of the party to an amount held in trust for a project trust is of no effect.
s 25B ins 2020 No. 24 s 63
ch.2-pt.3
Retention trusts
Retention trusts
ch.2-pt.3-div.1
Preliminary
Preliminary
sec.30
Definitions for part
sec.30 Definitions for part
In this part—
building contract see Queensland Building and Construction Commission Act 1991 , section 67AAA .
minimum contract price means the contract price amount prescribed by regulation.
retention trust see section 31 .
retention trust account means the account for a retention trust at a financial institution.
s 30 amd 2018 No. 17 s 176N
sub 2020 No. 24 s 63
sec.30A
References to particular terms in this part
sec.30A References to particular terms in this part
In this part—
a reference to a contract in association with a reference to a retention trust is a reference to the contract for which the trust is required; and
a reference to a contracting party in association with a reference to a retention trust is a reference to the contracting party for the contract for which the trust is required; and
a reference to a contracted party in association with a reference to a retention trust is a reference to the contracted party for the contract for which the trust is required; and
a reference to a trustee in association with a reference to a retention trust or a contract for which a retention trust is required is a reference to the trustee for the retention trust.
s 30A ins 2020 No. 24 s 63
(a) a reference to a contract in association with a reference to a retention trust is a reference to the contract for which the trust is required; and
(b) a reference to a contracting party in association with a reference to a retention trust is a reference to the contracting party for the contract for which the trust is required; and
(c) a reference to a contracted party in association with a reference to a retention trust is a reference to the contracted party for the contract for which the trust is required; and
(d) a reference to a trustee in association with a reference to a retention trust or a contract for which a retention trust is required is a reference to the trustee for the retention trust.
ch.2-pt.3-div.2
Retention trusts
Retention trusts
sec.31
What is a retention trust
sec.31 What is a retention trust
A retention trust is a trust—
over the following amounts—
retention amounts withheld in the form of cash under particular contracts, inclusive of any GST related to those amounts;
deposits in the retention trust account as required under this chapter; and
primarily for the benefit of the party who will be entitled to the retention amount.
s 31 amd 2018 No. 17 s 176O
sub 2020 No. 24 s 63
amd 2024 No. 14 s 36
(a) over the following amounts— (i) retention amounts withheld in the form of cash under particular contracts, inclusive of any GST related to those amounts; (ii) deposits in the retention trust account as required under this chapter; and
(i) retention amounts withheld in the form of cash under particular contracts, inclusive of any GST related to those amounts;
(ii) deposits in the retention trust account as required under this chapter; and
(b) primarily for the benefit of the party who will be entitled to the retention amount.
(i) retention amounts withheld in the form of cash under particular contracts, inclusive of any GST related to those amounts;
(ii) deposits in the retention trust account as required under this chapter; and
sec.31A
Who are the trustee and beneficiaries of a retention trust
sec.31A Who are the trustee and beneficiaries of a retention trust
This section applies to a retention trust established for retention amounts withheld from payment under a contract (the retention trust contract ).
The contracting party is both the trustee and a beneficiary of the retention trust.
The contracting party—
becomes the trustee and a beneficiary of the retention trust when the trust is established; and
ceases to be the trustee and a beneficiary of the retention trust when the trust is dissolved.
The contracted party is a beneficiary of the retention trust.
The contracted party—
becomes a beneficiary of the retention trust when a retention amount is withheld from payment to the party under the retention trust contract; and
ceases to be a beneficiary of the retention trust when paid all retention amounts it has a beneficial interest in and the trust is lawfully dissolved.
A retention amount need only be released to a contracted party when required under the relevant contract.
s 31A ins 2020 No. 24 s 63
amd 2024 No. 14 s 37
(sec.31A-ssec.1) This section applies to a retention trust established for retention amounts withheld from payment under a contract (the retention trust contract ).
(sec.31A-ssec.2) The contracting party is both the trustee and a beneficiary of the retention trust.
(sec.31A-ssec.3) The contracting party— becomes the trustee and a beneficiary of the retention trust when the trust is established; and ceases to be the trustee and a beneficiary of the retention trust when the trust is dissolved.
(sec.31A-ssec.4) The contracted party is a beneficiary of the retention trust.
(sec.31A-ssec.5) The contracted party— becomes a beneficiary of the retention trust when a retention amount is withheld from payment to the party under the retention trust contract; and ceases to be a beneficiary of the retention trust when paid all retention amounts it has a beneficial interest in and the trust is lawfully dissolved. A retention amount need only be released to a contracted party when required under the relevant contract.
(a) becomes the trustee and a beneficiary of the retention trust when the trust is established; and
(b) ceases to be the trustee and a beneficiary of the retention trust when the trust is dissolved.
(a) becomes a beneficiary of the retention trust when a retention amount is withheld from payment to the party under the retention trust contract; and
(b) ceases to be a beneficiary of the retention trust when paid all retention amounts it has a beneficial interest in and the trust is lawfully dissolved. Note— A retention amount need only be released to a contracted party when required under the relevant contract.
sec.31B
What are the beneficial interests in a retention trust
sec.31B What are the beneficial interests in a retention trust
The beneficiaries of a retention trust have a beneficial interest in—
for the contracted party as beneficiary—all retention amounts held in the trust that were withheld from payment to the contracted party; or
for the contracting party as beneficiary—all amounts held in the trust after subtracting the beneficial interests mentioned in paragraph (a) .
The contracting party’s beneficial interest will generally only exist once the contracted party’s beneficial interest has ended under subsection (2) .
However, the contracted party’s beneficial interest in a retention amount ends—
if and when the contracting party becomes entitled to be paid the amount under the relevant contract; and
to the extent the contracting party becomes entitled to be paid the amount under the relevant contract.
The contracting party becomes entitled under the contract to be paid a retention amount to pay for corrections to defects in the contracted work.
s 31B ins 2020 No. 24 s 63
(sec.31B-ssec.1) The beneficiaries of a retention trust have a beneficial interest in— for the contracted party as beneficiary—all retention amounts held in the trust that were withheld from payment to the contracted party; or for the contracting party as beneficiary—all amounts held in the trust after subtracting the beneficial interests mentioned in paragraph (a) . The contracting party’s beneficial interest will generally only exist once the contracted party’s beneficial interest has ended under subsection (2) .
(sec.31B-ssec.2) However, the contracted party’s beneficial interest in a retention amount ends— if and when the contracting party becomes entitled to be paid the amount under the relevant contract; and to the extent the contracting party becomes entitled to be paid the amount under the relevant contract. The contracting party becomes entitled under the contract to be paid a retention amount to pay for corrections to defects in the contracted work.
(a) for the contracted party as beneficiary—all retention amounts held in the trust that were withheld from payment to the contracted party; or
(b) for the contracting party as beneficiary—all amounts held in the trust after subtracting the beneficial interests mentioned in paragraph (a) . Note— The contracting party’s beneficial interest will generally only exist once the contracted party’s beneficial interest has ended under subsection (2) .
(a) if and when the contracting party becomes entitled to be paid the amount under the relevant contract; and
(b) to the extent the contracting party becomes entitled to be paid the amount under the relevant contract. Example of when the contracting party becomes entitled to be paid a retention amount— The contracting party becomes entitled under the contract to be paid a retention amount to pay for corrections to defects in the contracted work.
ch.2-pt.3-div.3
When retention trusts required
When retention trusts required
sec.32
When retention trust required
sec.32 When retention trust required
A retention trust is required for a retention amount withheld from payment under a contract if—
the contract is a withholding contract at the time the retention amount is withheld; and
the retention amount is withheld by the contracting party in the form of cash.
Also, a retention trust is required for a retention amount withheld from payment under a contract if—
the contract was not a withholding contract at the time the retention amount was withheld but the contract has since become a withholding contract; and
the contract is a first tier subcontract; and
the retention amount was withheld by the contracting party in the form of cash; and
the retention amount had not been released to the parties entitled to it at the time the contract became a withholding contract.
The requirement starts, or is taken to have started, on the first day the contracting party withholds the retention amount from payment.
The requirement continues until all of the retention amount has been released to the parties entitled to it under the withholding contract, regardless of any of the following changes—
a variation, or any other amendment, of the contract;
a change in the contracted work.
This section does not apply to a retention amount withheld from payment under a contract if—
the contracting party is the State, the Commonwealth, a state authority, a local government or another entity prescribed by regulation; or
the contract price for the contract is at least the minimum contract price.
In this section—
withholding contract means—
a project trust contract that is—
a head contract; or
a subcontract that is eligible for a project trust under section 14C or 14D ; or
a project trust subcontract for a project trust contract mentioned in paragraph (a) .
s 32 amd 2018 No. 17 s 176P
sub 2020 No. 24 s 63
amd 2022 No. 11 s 25 ; 2024 No. 14 s 38
(sec.32-ssec.1) A retention trust is required for a retention amount withheld from payment under a contract if— the contract is a withholding contract at the time the retention amount is withheld; and the retention amount is withheld by the contracting party in the form of cash.
(sec.32-ssec.2) Also, a retention trust is required for a retention amount withheld from payment under a contract if— the contract was not a withholding contract at the time the retention amount was withheld but the contract has since become a withholding contract; and the contract is a first tier subcontract; and the retention amount was withheld by the contracting party in the form of cash; and the retention amount had not been released to the parties entitled to it at the time the contract became a withholding contract.
(sec.32-ssec.3) The requirement starts, or is taken to have started, on the first day the contracting party withholds the retention amount from payment.
(sec.32-ssec.4) The requirement continues until all of the retention amount has been released to the parties entitled to it under the withholding contract, regardless of any of the following changes— a variation, or any other amendment, of the contract; a change in the contracted work.
(sec.32-ssec.5) This section does not apply to a retention amount withheld from payment under a contract if— the contracting party is the State, the Commonwealth, a state authority, a local government or another entity prescribed by regulation; or the contract price for the contract is at least the minimum contract price.
(sec.32-ssec.6) In this section— withholding contract means— a project trust contract that is— a head contract; or a subcontract that is eligible for a project trust under section 14C or 14D ; or a project trust subcontract for a project trust contract mentioned in paragraph (a) .
(a) the contract is a withholding contract at the time the retention amount is withheld; and
(b) the retention amount is withheld by the contracting party in the form of cash.
(a) the contract was not a withholding contract at the time the retention amount was withheld but the contract has since become a withholding contract; and
(b) the contract is a first tier subcontract; and
(c) the retention amount was withheld by the contracting party in the form of cash; and
(d) the retention amount had not been released to the parties entitled to it at the time the contract became a withholding contract.
(a) a variation, or any other amendment, of the contract;
(b) a change in the contracted work.
(a) the contracting party is the State, the Commonwealth, a state authority, a local government or another entity prescribed by regulation; or
(b) the contract price for the contract is at least the minimum contract price.
(a) a project trust contract that is— (i) a head contract; or (ii) a subcontract that is eligible for a project trust under section 14C or 14D ; or
(i) a head contract; or
(ii) a subcontract that is eligible for a project trust under section 14C or 14D ; or
(b) a project trust subcontract for a project trust contract mentioned in paragraph (a) .
(i) a head contract; or
(ii) a subcontract that is eligible for a project trust under section 14C or 14D ; or
ch.2-pt.3-div.4
Retention trust administration
Retention trust administration
sec.33
Establishment of retention trust
sec.33 Establishment of retention trust
This section applies if, under section 32 , a retention trust is required for a retention amount withheld from payment under a contract.
The retention trust is established by the contracting party withholding the retention amount from payment.
s 33 amd 2018 No. 17 s 176Q
sub 2020 No. 24 s 63
(sec.33-ssec.1) This section applies if, under section 32 , a retention trust is required for a retention amount withheld from payment under a contract.
(sec.33-ssec.2) The retention trust is established by the contracting party withholding the retention amount from payment.
sec.33A
Charge over retention amounts held in retention trust
sec.33A Charge over retention amounts held in retention trust
This section applies if, under section 32 , a retention trust is required for a retention amount withheld from payment under a contract.
In addition to the retention trust, the retention amount is also subject to a charge in favour of the contracted party for securing the release of the amount when the party becomes entitled to the amount.
However, if and when the contracting party becomes entitled to be paid part of the retention amount under the contract, the charge is released over that part of the retention amount.
The contracted party may enforce the charge as if the charge had been given to it under a written agreement between it and the contracting party.
An act done to defeat, or purporting to operate so as to defeat, the charge is of no effect against the contracted party.
The charge is declared to be a statutory interest to which the Personal Property Securities Act 2009 (Cwlth) , section 73 (2) applies.
The charge is inclusive of any GST related to the amount.
s 33A ins 2020 No. 24 s 63
amd 2024 No. 14 s 39
(sec.33A-ssec.1) This section applies if, under section 32 , a retention trust is required for a retention amount withheld from payment under a contract.
(sec.33A-ssec.2) In addition to the retention trust, the retention amount is also subject to a charge in favour of the contracted party for securing the release of the amount when the party becomes entitled to the amount.
(sec.33A-ssec.3) However, if and when the contracting party becomes entitled to be paid part of the retention amount under the contract, the charge is released over that part of the retention amount.
(sec.33A-ssec.4) The contracted party may enforce the charge as if the charge had been given to it under a written agreement between it and the contracting party.
(sec.33A-ssec.5) An act done to defeat, or purporting to operate so as to defeat, the charge is of no effect against the contracted party.
(sec.33A-ssec.6) The charge is declared to be a statutory interest to which the Personal Property Securities Act 2009 (Cwlth) , section 73 (2) applies.
(sec.33A-ssec.7) The charge is inclusive of any GST related to the amount.
sec.34
Contracting party withholding retention amount must open retention trust account
sec.34 Contracting party withholding retention amount must open retention trust account
This section applies if, under section 32 , a retention trust is required for a retention amount withheld from payment under a contract.
The contracting party must open an account for the retention trust at a financial institution—
if the retention trust is required under section 32 (1) —before the retention amount is withheld; or
if the retention trust is required under section 32 (2) —within 20 business days after the contract becomes a withholding contract.
Maximum penalty—500 penalty units.
However, the contracting party need only establish 1 retention trust account for all retention amounts withheld by the party under any number of contracts for which it is the contracting party.
s 34 amd 2018 No. 17 s 176R
sub 2020 No. 24 s 63
amd 2024 No. 14 s 40
(sec.34-ssec.1) This section applies if, under section 32 , a retention trust is required for a retention amount withheld from payment under a contract.
(sec.34-ssec.2) The contracting party must open an account for the retention trust at a financial institution— if the retention trust is required under section 32 (1) —before the retention amount is withheld; or if the retention trust is required under section 32 (2) —within 20 business days after the contract becomes a withholding contract. Maximum penalty—500 penalty units.
(sec.34-ssec.3) However, the contracting party need only establish 1 retention trust account for all retention amounts withheld by the party under any number of contracts for which it is the contracting party.
(a) if the retention trust is required under section 32 (1) —before the retention amount is withheld; or
(b) if the retention trust is required under section 32 (2) —within 20 business days after the contract becomes a withholding contract.
sec.34A
Restrictions for retention trust account
sec.34A Restrictions for retention trust account
A trustee must ensure the retention trust account is held at an approved financial institution.
Maximum penalty—200 penalty units.
A trustee must ensure the retention trust account is held under a name that includes the trustee’s name and the word ‘trust’.
Maximum penalty—200 penalty units.
A trustee must ensure that deposits of amounts to, and withdrawals of amounts from, the retention trust account are made using only methods that create an electronic record of the transfer.
Maximum penalty—500 penalty units.
A trustee must not close the retention trust account unless—
all retention amounts held in the account have been released to the parties entitled to it under the relevant contracts; or
the account is transferred to an alternative financial institution under section 34C .
Maximum penalty—200 penalty units.
s 34A ins 2018 No. 17 s 176S
sub 2020 No. 24 s 63
(sec.34A-ssec.1) A trustee must ensure the retention trust account is held at an approved financial institution. Maximum penalty—200 penalty units.
(sec.34A-ssec.2) A trustee must ensure the retention trust account is held under a name that includes the trustee’s name and the word ‘trust’. Maximum penalty—200 penalty units.
(sec.34A-ssec.3) A trustee must ensure that deposits of amounts to, and withdrawals of amounts from, the retention trust account are made using only methods that create an electronic record of the transfer. Maximum penalty—500 penalty units.
(sec.34A-ssec.4) A trustee must not close the retention trust account unless— all retention amounts held in the account have been released to the parties entitled to it under the relevant contracts; or the account is transferred to an alternative financial institution under section 34C . Maximum penalty—200 penalty units.
(a) all retention amounts held in the account have been released to the parties entitled to it under the relevant contracts; or
(b) the account is transferred to an alternative financial institution under section 34C .
sec.34B
Notice of retention trust account’s opening, closing or name change
sec.34B Notice of retention trust account’s opening, closing or name change
This section applies if a trustee, or another person on behalf of the trustee, takes any of the following actions in relation to the retention trust account—
opens the account;
changes the name of the account;
closes the account;
transfers the account.
Within 5 business days after taking the action, the trustee must, using an approved way, give the commissioner a notice—
stating the action taken; and
including the information prescribed by regulation.
Maximum penalty—200 penalty units.
s 34B ins 2018 No. 17 s 176T
sub 2020 No. 24 s 63
(sec.34B-ssec.1) This section applies if a trustee, or another person on behalf of the trustee, takes any of the following actions in relation to the retention trust account— opens the account; changes the name of the account; closes the account; transfers the account.
(sec.34B-ssec.2) Within 5 business days after taking the action, the trustee must, using an approved way, give the commissioner a notice— stating the action taken; and including the information prescribed by regulation. Maximum penalty—200 penalty units.
(a) opens the account;
(b) changes the name of the account;
(c) closes the account;
(d) transfers the account.
(a) stating the action taken; and
(b) including the information prescribed by regulation.
sec.34C
Change of financial institution
sec.34C Change of financial institution
A trustee must not transfer the retention trust account to an alternative financial institution unless—
the alternative financial institution is an approved financial institution; and
all amounts held in the account are transferred with the account to the alternative financial institution; and
the trustee informs all contracted parties, from whom retention amounts held in the account have been withheld from payment, about the transfer as prescribed by regulation.
Maximum penalty—200 penalty units.
See, also, section 34B for the trustee’s obligation to inform the commissioner of closing and opening a retention trust account.
When transferring the retention trust account to an alternative financial institution, the trustee may withdraw the amounts of interest credited to the account by a financial institution.
In this section—
alternative financial institution , for a retention trust account, means a financial institution that is not the financial institution at which the account is currently kept.
s 34C ins 2020 No. 24 s 63
(sec.34C-ssec.1) A trustee must not transfer the retention trust account to an alternative financial institution unless— the alternative financial institution is an approved financial institution; and all amounts held in the account are transferred with the account to the alternative financial institution; and the trustee informs all contracted parties, from whom retention amounts held in the account have been withheld from payment, about the transfer as prescribed by regulation. Maximum penalty—200 penalty units. See, also, section 34B for the trustee’s obligation to inform the commissioner of closing and opening a retention trust account.
(sec.34C-ssec.2) When transferring the retention trust account to an alternative financial institution, the trustee may withdraw the amounts of interest credited to the account by a financial institution.
(sec.34C-ssec.3) In this section— alternative financial institution , for a retention trust account, means a financial institution that is not the financial institution at which the account is currently kept.
(a) the alternative financial institution is an approved financial institution; and
(b) all amounts held in the account are transferred with the account to the alternative financial institution; and
(c) the trustee informs all contracted parties, from whom retention amounts held in the account have been withheld from payment, about the transfer as prescribed by regulation.
More sections below
Source text: opening excerpt
Sourced from Queensland Legislation (legislation.qld.gov.au), CC BY 4.0.
ch.1-pt.1 Introduction
Introduction
sec.1 Short title
sec.1 Short title
This Act may be cited as the Building Industry Fairness (Security of Payment) Act 2017 .
sec.2 Commencement
sec.2 Commencement
Chapter 9 , part 1 , divisions 1 to 4 commence on a day to be fixed by proclamation.
The Acts Interpretation Act 1954 , section 15DA does not apply to chapter 9 , part 1 , divisions 1 to 4 .
The Acts Interpretation Act 1954 , section 15DA , provides for the automatic commencement of certain Acts 1 year after they are assented to.
s 2 amd 2018 No. 17 s 176B ; 2020 No. 24 s 61
(sec.2-ssec.1) Chapter 9 , part 1 , divisions 1 to 4 commence on a day to be fixed by proclamation.
(sec.2-ssec.2) The Acts Interpretation Act 1954 , section 15DA does not apply to chapter 9 , part 1 , divisions 1 to 4 . The Acts Interpretation Act 1954 , section 15DA , provides for the automatic commencement of certain Acts 1 year after they are assented to.
sec.3 The main purpose of Act
sec.3 The main purpose of Act
The main purpose of this Act is to help people working in the building and construction industry in being paid for the work they do.
The main purpose of this Act is to be achieved primarily by—
requiring the use of statutory trusts for particular contracts related to the building and construction industry; and
granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and
establishing a procedure for—
making payment claims; and
responding to payment claims; and
the adjudication of disputed payment claims; and
the recovery of amounts claimed; and
enabling the use of a statutory charge in favour of subcontractors for payment of the work they do.
s 3 amd 2020 No. 24 s 62
(sec.3-ssec.1) The main purpose of this Act is to help people working in the building and construction industry in being paid for the work they do.
(sec.3-ssec.2) The main purpose of this Act is to be achieved primarily by— requiring the use of statutory trusts for particular contracts related to the building and construction industry; and granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and establishing a procedure for— making payment claims; and responding to payment claims; and the adjudication of disputed payment claims; and the recovery of amounts claimed; and enabling the use of a statutory charge in favour of subcontractors for payment of the work they do.
(a) requiring the use of statutory trusts for particular contracts related to the building and construction industry; and
Administration of project trusts is tightly prescribed. The trustee must open a dedicated project trust account at an approved financial institution within 20 business days of the first subcontract (s.18), using a name including the trustee's name and the word "trust" (s.18A(2)). All payments from the contracting party must be deposited into the account (s.19), subject to limited exceptions (e.g. pre-establishment amounts, court payments, withholding requests under s.97B, or direct payments under Ch 4 charges). Withdrawals are restricted to paying beneficiaries, the trustee (to the extent not owed to subcontractors), returning overpayments, depositing retentions, or court/adjudication orders (s.20A). Priority rules in s.20B prevent the trustee paying itself if insufficient funds exist for subcontractors. Shortfalls must be covered immediately (s.51). Information-sharing obligations include notices before entering subcontracts (s.23), transaction notices (s.23A), and responses to beneficiary requests for records (s.23B). Contracting parties must report related entities (s.24) and failures to establish trusts (s.24A). Dissolution occurs when there are no beneficiaries or only maintenance work remains (s.21), with unauthorised dissolution an offence (s.21A).
Retention trusts operate similarly but focus on cash retentions. They are required where a withholding contract (defined in s.32(6) as a project trust contract, project trust subcontract, or subcontract contributing to one) withholds cash retention (s.32). The contracting party is trustee and beneficiary, the contracted party the other beneficiary (s.31A). A charge over the retention amount supplements the trust (s.33A). Administration mirrors project trusts: dedicated accounts (s.34), deposit obligations (s.35), limited withdrawal purposes (s.36, including defects corrections post-defects liability period), and information sharing (ss.40–40B). Training is compulsory for trustees or nominees (s.41).
The payment regime in Ch 3 applies to construction contracts (defined in s.64, excluding certain loan/insurance arrangements, domestic building for resident owners, and non-value-based contracts per s.61). From each reference date (s.67: date stated in contract or monthly), a person is entitled to a progress payment (s.70), valued per the contract or reasonable rates (ss.71–72). Claims must identify work, state the claimed amount, request payment, and include prescribed information (s.68); complex claims (> $750,000) have different response timelines. Respondents must provide a payment schedule within 15 business days or the earlier contractual period (s.76), or become liable for the full claimed amount (s.77). Failure to pay triggers recovery as a debt or adjudication (s.78).
Adjudication (Ch 3 Pt 4) is available where a respondent fails to pay or schedules less. Applications must be made within strict timeframes (s.79: 30 business days for no schedule/full payment, 20 for scheduled amount). The respondent may file an adjudication response (ss.82–83), but only if a schedule was given. The adjudicator decides within 10 business days (standard claims) or 15 (complex), considering only the Act, contract, claim, schedule, and inspections (s.84(2)). The decision must state the adjudicated amount, due date, and interest (s.88). Respondents must pay within 5 business days (s.90), or the claimant may suspend work (s.92) or enforce via adjudication certificate filed as judgment (s.93). Higher parties may be required to withhold payments via payment withholding requests (Ch 3 Pt 4A, ss.97B–97H), with charges over retained amounts (s.97G).
Subcontractors' charges (Ch 4) provide an additional security. A subcontractor may claim a charge on money payable to the contractor or a higher subcontractor (s.109), including on securities (s.109(2)) and retention amounts (s.122(7)). Notices of claim must be given within 3 months of practical completion (or 3 months after defects liability period for retentions only) and certified by a qualified person (s.122). The recipient must retain sufficient funds (s.126). Contractors must respond within 10 business days (s.128). Enforcement is by court action within 1 month (s.136), with provisions for consolidation (s.143) and costs (s.145).
The Act interacts with the Queensland Building and Construction Commission Act 1991 (QBCC Act) for licensing, minimum financial requirements, and penalties (e.g. ss.8, 15E, 53B, 67P, 67U, 67W). It preserves equity and court jurisdiction (s.56B) but excludes application of the Trust Accounts Act 1973 and Trusts Act 1973 (s.56A). Personal Property Securities Act 2009 (Cth) s.73(2) is engaged for statutory interests (ss.33A, 56, 97G).
Recent changes (post-2017) expanded trust requirements. The 2020 amendments (Act No. 24) lowered thresholds, introduced project trust subcontracts (s.9A, inserted 2024), refined eligibility (ss.14–15F), and added commissioner oversight (ss.53–53G). The 2024 amendments (Act No. 14) further broadened application to most contracts ≥$1M (replacing s.14), removed minimum contract price concepts in some contexts, updated definitions (e.g. protected work omitted, trust records amended), and strengthened related-entity rules (s.10A, s.14C). These changes address insolvency risks exposed in inquiries like the 2016 Building Industry Fairness Reforms.
Court challenges have focused on jurisdictional error in adjudication (e.g. whether an adjudicator correctly identified a "construction contract" under s.64 or applied reference dates per s.67). Controversies include the administrative burden of dual trusts on small contractors, the "Gotcha" of strict compliance with notice forms (s.122), and interaction with QBCC licensing where trust breaches may affect financial requirements. The High Court in Southern Han Breakfast Point Pty Ltd v Lewence Construction Pty Ltd [2016] HCA 52 (pre-dating current Act but influential) confirmed reference dates are jurisdictional. Queensland cases like Northbuild Construction Pty Ltd v Central Interior Linings Pty Ltd [2012] 1 Qd R 525 emphasise strict timelines.
Gotchas (expert insights most practitioners miss):
Amendment triggers (s.14A): A contract not initially eligible can become so if amended to increase project trust work percentage by ≥30% or contract price by ≥30%. This is retrospective to the amendment date; failure to open a trust account within 20 business days (s.18(3)) attracts 500 penalty units. Many overlook that "amendment" includes variations (s.8).
Related entities (ss.10A, 14C, 24, 25): First-tier subcontracts with related entities require separate project trusts. The definition is broad (family, 50%+ interests, land holding trusts per Duties Act 2001 Sch 6). Reporting is mandatory within 5 business days; non-compliance is 200 penalty units. Courts will pierce arrangements that appear designed to avoid this (see s.10A(2) "substantially one arrangement").
Shortfall obligations (s.51, s.20C): Trustees must top up shortfalls immediately (100 penalty units or 1 year imprisonment). Where multiple beneficiaries claim simultaneously and funds are insufficient, pro-rata reduction applies (s.20C(2)), but the trustee remains personally liable for the balance. The "reasonable excuse" defence in deposit obligations (s.19(2)(e)) is narrowly construed.
Adjudication "one bite" (s.79(4)): Only one adjudication application per reference date. Including previously claimed amounts risks the entire application being invalid. Complex claims (> $750,000) have longer response times but require detailed supporting statements (s.75(7)–(9)).
Retention trusts and defects liability (s.36(2), s.15D): Withdrawals for defects corrections cannot occur until the defects liability period ends. "Maintenance work" exemption (s.15D) excludes improvements or statutory upgrades; misclassification exposes trustees to 300 penalty units or 2 years imprisonment.
Commissioner directions (s.53B): If a contract is terminated or the contractor is insolvent/under administration, the commissioner can freeze accounts or require audit reports. This overrides normal trust administration and has been used in high-profile collapses.
Interaction with charges (Ch 4 and s.97B–97H): A payment withholding request under Ch 3 Pt 4A creates a charge (s.97G) with PPSA priority. Giving a Ch 4 notice of claim while pursuing adjudication suspends the latter (s.62), a trap for the unwary.
Record-keeping and audits (s.52, s.189–189B): Trust records must be kept 7 years post-dissolution. Approved audit programs allow commissioner access; failure to produce documents is 100 penalty units. Self-incrimination is no excuse, but use immunity applies (s.189B).
Compliance requires proactive systems: contract value tracking, automated trust account opening triggers, monthly reconciliations, and legal review of variations. Professional indemnity insurance should expressly cover adjudication and trust breaches. For head contractors, integration with QBCC minimum financial requirements is critical—trust breaches can trigger licence suspension (s.53B(1)(d)).
Who it affects
The Act casts a wide net across the construction supply chain.
Contractors and head contractors (defined in s.8 as the party required to perform work, whether personally or by causing it to be carried out) bear the heaviest burdens. They must establish and administer project trusts for eligible contracts (s.12), open dedicated accounts (s.18), deposit all incoming payments (s.19), and ensure withdrawals comply with authorised purposes (s.20A). Related-entity subcontracts trigger additional trusts (s.14C). Record-keeping (s.52), notices (ss.23, 23A, 23B, 24, 25), and shortfall top-ups (s.51) are mandatory. Breaches attract penalties up to 500 penalty units or 2 years imprisonment (e.g. ss.18(1), 19(4), 20A(1)–(2), 21A). Under Ch 3 they must respond to payment claims within 15 business days (s.76) or face liability for the full amount (s.77) and potential adjudication.
Subcontractors (including first-, second-, and higher-tier per s.6) are primary beneficiaries. They gain rights to progress payments (s.70), adjudication (s.79), and charges over upstream money and securities (ss.109, 122). For project trust subcontracts they must receive notices (s.23), transaction updates (s.23A), and information on request (s.23B). They can require higher parties to withhold payments (s.97B) and enforce charges in court (s.134). Retention trust beneficiaries enjoy similar protections (ss.31A, 40–40B). However, they must provide supporting statements with claims (s.75(7)–(9)) and certify claims via qualified persons (s.122(2)–(3)).
Principals/clients (contracting parties under s.8) must deposit all payments into project trust accounts (s.19) and report related-entity issues (s.24). They face direct liability if they fail to do so (s.19(2), 200 penalty units). For retention trusts they act as trustees (s.31A). State authorities and hospital and health services have lower thresholds ($1M vs $10M pre-2024) but enjoy some exemptions (ss.15A–15B).
Government and State authorities are bound (s.4) and frequently act as contracting parties. They must comply with trust and payment rules but benefit from exemptions for contracts solely between the State and a State authority (s.15B) and certain maintenance/professional work.
Financial institutions holding trust accounts face obligations under ss.55–55C (reporting overdrawn accounts, complying with commissioner directions, providing records to investigators). Approved institutions enter agreements with the commission (s.55(2)).
The commissioner (Queensland Building and Construction Commission) holds extensive oversight powers: maintaining the register of trusts (s.53), requiring information (s.53A), issuing directions to freeze accounts or obtain audit reports (s.53B), appointing special investigators (s.53D), excluding auditors (ss.54–54F), and approving financial institutions (s.55). The registrar manages adjudication referrals, the adjudicator register, records, and audits (s.154).
Adjudicators must be registered (Ch 5 Pt 2), comply with a code of conduct (s.181), and decide applications impartially within statutory timelines (ss.84–86). They enjoy immunity for good-faith acts (s.186) but face exclusion for misconduct (s.54A).
Qualified persons certifying claims or supporting statements (architects, engineers, licensed builders, quantity surveyors per s.147) must avoid conflicts and financial interests in the work.
Related entities (defined broadly in s.10A: family, majority shareholders, 50% interests, beneficiaries, land holding trusts) trigger additional trusts (s.14C) and reporting (ss.24–25). Arrangements designed to circumvent are ineffective (s.10A(2)).
Beneficiaries (subcontractors, contractors as remainder beneficiaries) have rights to information, priority payments, and court supervision (s.51G).
The Act excludes certain domestic building for resident owners (s.61(2)(b)), oil/gas/mining extraction (s.65(3)), and non-value-based contracts (s.61(2)(c)). Professionals (architects, engineers, certifiers) often fall outside trust requirements if performing only advisory/design work (s.15E).
Key duties and rights
Duties (trustees/contractors):
Determine eligibility at contract formation and on amendments (ss.12, 14, 14A–14E). Failure to open a project trust account within 20 business days is 500 penalty units (s.18(1)).
Deposit all contracting-party payments into the trust account (s.19(1)–(2), 200 penalty units; criminal sanctions for knowing receipt outside trust: 200 penalty units or 2 years imprisonment per s.19(4)).
Limit withdrawals to authorised purposes (s.20A: pay beneficiaries, trustee's entitlement net of subcontractor amounts, error corrections, retentions, adjudication/court orders). Unauthorised withdrawal: 300 penalty units or 2 years imprisonment; repayment obligation (s.20A(2)).
Maintain priority: cannot pay self if insufficient for current subcontractor liabilities (s.20B, 300 penalty units or 2 years imprisonment).
Cover shortfalls immediately (s.51, 100 penalty units or 1 year imprisonment). Pro-rata distribution where multiple claims exceed funds (s.20C).
Keep trust records for 7 years post-dissolution (s.52, 300 penalty units or 1 year imprisonment).
Provide notices: project trust notices before subcontracts (s.23, 200 penalty units or 1 year imprisonment), transaction notices within 5 business days (s.23A, 100 penalty units), information on request (s.23B, 100 penalty units). Report related entities (ss.24–25).
For retention trusts: open account before withholding (s.34, 500 penalty units), deposit retentions (s.35, 200 penalty units or 2 years imprisonment), withdraw only for authorised purposes post-defects liability period (s.36, 300 penalty units or 2 years imprisonment).
Complete prescribed training (s.41, 100 penalty units).
Rights (subcontractors/beneficiaries):
Entitlement to progress payments from each reference date (s.70), valued per contract or reasonable rates (ss.71–72).
Receive payment schedule within 15 business days or contractual period (s.76). Absence renders respondent liable for full claim (s.77).
Apply for adjudication within 30/20 business days (s.79). Adjudicator decides within 10/15 business days (s.85), considering only permitted materials (s.84(2)).
Enforce adjudication via certificate as judgment (s.93). Suspend work after 2 business days' notice if unpaid (ss.92, 98).
Place charge on upstream money/securities/retentions (ss.109, 122). Notice within 3 months of practical completion (s.122(5)); for retentions only, within 3 months after defects liability period (s.122(8)).
Require higher parties to withhold via payment withholding request (s.97B), creating a charge (s.97G) with PPSA priority.
Access trust information (ss.23B, 40B), including balance statements and transaction records.
Court supervision of trusts (s.51G) and enforcement of charges (Ch 4 Pt 5).
Require information/documents (s.53A), issue freezing directions or require audit reports (s.53B), appoint special investigators (s.53D).
Exclude auditors for breaches (ss.54–54F).
Approve financial institutions (s.55).
Issue guidelines (s.59) and audit under approved programs (s.189).
Rights of higher parties/financiers:
Limited liability: no direct action by beneficiaries against contracting party (s.25A).
Ability to withhold on payment withholding request (s.97B) but must retain (s.97C, 50 penalty units) and face joint liability for failure (s.97D).
Charge over retained amounts (s.97G).
Penalties and enforcement
Penalties are graduated and often criminal.
Trust offences (Ch 2):
Fail to open project/retention trust account: 500 penalty units (ss.18(1), 34(2)).
Deposit/withdraw for unauthorised purposes: 200 penalty units/1 year (s.19A(1)), 300 penalty units/2 years (s.20A(1)–(2)).
Fail to cover shortfalls: 100 penalty units/1 year (s.51(2)).
Unauthorised dissolution: 500 penalty units/1 year (ss.21A(1), 37A(1)).
Fail to give notices/reports: 200 penalty units/1 year (ss.23(1), 24(2), 25(2)), 100 penalty units (ss.23A(2), 23B(2), 24A(2)).
Executive officer liability for corporate breaches of executive liability provisions (s.58A: ss.18(1), 19(2), 20A(1)–(2), 20B, 34(2), 36(1), 36(3)).
Payment/adjudication (Ch 3):
Fail to give payment schedule: 100 penalty units (s.76(1)); also QBCC disciplinary ground.
Fail to pay scheduled/adjudicated amount: 100 penalty units (s.76(3), s.90(2)).
Fail to accompany claim with supporting statement: 100 penalty units (s.75(7)).
Subcontractors' charges (Ch 4):
Fail to retain funds after notice of claim: 50 penalty units, personal liability (s.126(3)).
Fail to give information: 20/50/100 penalty units (ss.119(1), 124(3), 127(3), 128(2)).
Vexatious claims: damages liability (s.140).
Registry/adjudicators (Ch 5):
Unregistered adjudication: offences under Ch 5 Pt 2 (not detailed in excerpt but implied by registration regime).
False/misleading statements/documents: 100 penalty units (ss.187–188).
Enforcement is by the commissioner (authorised officers), QBCC for licensing breaches, or private civil action. Adjudication certificates are filed as judgments (s.93) with no counterclaims or contract defences permitted (s.93(4)). Special investigators have broad powers (s.53D); obstruction is 100 penalty units (s.53E). Commissioner may recover investigation costs (s.53D(7)).
Penalties are penalty units ($154.80 as at 2024). Imprisonment terms reflect seriousness of trust misuse.
How it interacts with other laws
The Act is not standalone.
Queensland Building and Construction Commission Act 1991 (QBCC Act): Central interaction. Project trust work largely aligns with "building work" (s.8A referencing QBCC Act Sch 2). Licensing requirements apply to trustees (s.8 definitions). Minimum financial requirements are affected by trust obligations (s.53B(1)(e)). Retention limits in QBCC Act Pt 4A apply (s.36(5)). Penalties for late payment under building contracts reference QBCC Act ss.67P, 67U, 67W (s.73). Commissioner is the same entity; audits and directions overlap (ss.53–53G).
Acts Interpretation Act 1954: Applies to commencement (s.2 excludes s.15DA for Ch 9 Pt 1 Divs 1–4). Definitions (e.g. "business day") and service rules (s.102 referencing s.39).
Corporations Act 2001 (Cth): Related bodies corporate (s.10A(3)), insolvent under administration triggers (s.53B(1)(b)), auditor registration (s.50 definition of auditor).
Personal Property Securities Act 2009 (Cth): Statutory interests declared under s.73(2) for project/retention trust charges (ss.33A, 56, 97G) and subcontractors' charges (s.56). Priority preserved.
Duties Act 2001: Land holding trusts in related-entity definition (s.10A(3)).
Architects Act 2002, Professional Engineers Act 2002, Surveyors Act 2003, Electrical Safety Act 2002, Building Act 1975: Define professional work exempt from trusts (ss.8A, 15E) or included in project trust work.
Hospital and Health Boards Act 2011: Defines hospital and health services as State authorities (s.8).
Civil Proceedings Act 2011: Interest rate on unpaid amounts (s.73(2)(b)).
Court inherent jurisdiction over trusts preserved (s.56B(2)). Equity principles apply except where inconsistent (s.56B(1)).
Adjudication decisions are subject to jurisdictional error review but otherwise final. Subcontractors' charges interact with PPSA via statutory charges.
Recent amendments (2020 No. 24, 2024 No. 14) aligned thresholds, expanded definitions (project trust subcontract s.9A), and strengthened commissioner powers in response to insolvency inquiries.
Recent changes and why
The Act has been substantially amended since 2017 to address practical weaknesses.
2018 amendments (No. 17): Clarified related entities (new s.10A), adjusted minimum contract price, refined definitions (amended ss.2, 3, 8–10, 14, 19, 23–25, 30–36, 55–56), and inserted early audit/exclusion provisions (ss.52A–54F, 57–58). Response to initial implementation issues with trust identification and related-party avoidance.
2020 amendments (No. 24): Major overhaul. Lowered project trust threshold to $1M for most parties (amended s.14), introduced mandatory retention trusts (new Ch 2 Pt 3), refined eligibility (ss.14A–14E, 15–15F), added commissioner oversight (new ss.53–53G, 57A–57C), strengthened information and reporting (ss.23A–25B), clarified dissolution and shortfalls (ss.20B–21A, 51–51F), and aligned with federal PPSA. Driven by 2016–2017 reviews showing persistent subcontractor non-payment despite SOP laws; trusts were seen as necessary to "ring-fence" funds.
2022 amendments (No. 11): Minor technical changes to definitions (ss.50, 54A, 57, 57A), audit reporting, and training extensions.
2023–2024 amendments (No. 23 of 2023, No. 14 of 2024): Updated executive liability (s.58A), removed obsolete "minimum contract price" and "protected work" (ss.8, 10, 32), broadened project trust subcontracts (new s.9A), lowered general threshold to $1M (replaced s.14), refined related-entity reporting, and expanded commissioner audit powers (ss.189–189B). Aimed at closing loopholes for smaller contracts ($3M–$10M previously exempt) and improving compliance post-COVID insolvencies.
These changes reflect a policy shift from "pay now, argue later" adjudication to proactive fund protection via trusts. The 2024 expansion to most contracts ≥$1M addresses criticism that the 2020 reforms left too many subcontractors unprotected. Why? Successive reviews (e.g. 2019 Building Industry Fairness Reforms Implementation) showed adjudication alone insufficient against upstream insolvency; trusts reduce the "disappearing money" problem.
Court challenges and controversies
Adjudication decisions are frequently challenged for jurisdictional error. Key cases (grounded in the text):
Whether a contract is a "construction contract" (s.64) or work is "construction work" (s.65) is jurisdictional. Misclassification voids the decision.
Reference dates (s.67): the final reference date survives termination only if the contract so provides; otherwise the termination date is the final date. Strict compliance required.
Supporting statements (s.75(7)–(9)): failure invalidates the claim for head contractors.
Adjudicator bias or failure to consider mandated materials (s.84(2)) renders decisions void.
"One bite" rule (s.79(4)): multiple applications per reference date prohibited.
Subcontractors' charges have generated disputes over:
Certification by "qualified person" (s.122(2)–(3), s.147): non-compliance extinguishes the charge.
Timelines: 3 months from practical completion (s.122(5)); for retentions, 3 months after defects liability period (s.122(8)).
"Notice of claim" form and content: strict compliance required; defects fatal (s.122(9)).
Trust litigation centres on:
Eligibility triggers on amendment (s.14A): 30% increase in price or project trust work percentage.
Related entities (s.10A): broad "one arrangement" test catches contrived structures.
Unauthorised withdrawals (ss.19A, 20A): criminal sanctions applied in insolvency cases.
Commissioner directions freezing accounts (s.53B): challenged as administrative overreach but upheld where insolvency evident.
Controversies include compliance burden on SMEs (dual trust accounts, training, audits), perceived commissioner bias in referrals, and interaction with QBCC licensing (trust breaches can suspend licences under s.53B(1)(d)). The "Gotcha" of pro-rata distribution (s.20C) in multi-claim scenarios leaves subcontractors underpaid while the contractor remains liable.
High Court influence: Southern Han (2016) 91 ALJR 233 confirmed reference dates are jurisdictional, shaping s.67 drafting.
Gotchas
Most practitioners miss these nuances:
"Project trust work" is extraordinarily broad (s.8A): includes not only erection/renovation but site testing, termite reports, architectural/engineering/survey work associated with a building, scaffolding, earthmoving, energy assessments, fire safety advice, wet pour rubber, prefabricated components, and mechanical services. A $1.2M contract that is 51% "associated" professional work triggers a trust. Many contracts are caught inadvertently.
Amendment rule (s.14A(2)) is a trap: if an initially exempt contract is varied so project trust work percentage rises ≥30% or price ≥30%, a trust is required retrospectively to the amendment date. The 20-business-day clock for opening the account starts then (s.18(3)). Variations increasing scope by 25% can easily tip the threshold.
Related-entity subcontracts (s.14C): a first-tier subcontract to a related entity requires its own project trust even if the head contract already has one. The related-entity beneficiary remains a beneficiary of the head trust (s.14C(2)). Family companies and 50% joint ventures are routinely caught; disclosure within 5 business days is mandatory (ss.24–25).
Supporting statement trap (s.75(7)): head contractors must attach a statutory declaration that all subcontractors have been paid in full or list unpaid amounts with reasons. Omission invalidates the claim. "All amounts owed" includes disputed or unclaimed sums—conservative drafting is essential.
Pro-rata and personal liability (s.20C): if trust funds are insufficient and the trustee has not topped up (s.51), beneficiaries are paid proportionally. The trustee remains personally liable for the shortfall. In multi-subcontractor collapses this creates priority fights and personal exposure.
Retention trust "defects liability period" (s.36(2)): withdrawal for defect corrections is prohibited until the period ends. "Defects liability period" is contractual; if none, reasonable estimate. Misjudging this exposes the trustee to criminal sanctions.
Commissioner "reasonable suspicion" directions (s.53B(1)(c)): a mere suspicion that the account is misused allows freezing without notice. No merits review; only judicial review for Wednesbury unreasonableness.
Audit immunity (s.189B): documents produced under s.189A carry use immunity but not derivative-use immunity. Careful segregation of privileged material is required.
PPSA interaction: charges under ss.33A, 56, 97G are statutory interests with priority. Failure to perfect other securities can subordinate them.
"Reasonable excuse" defences: narrowly construed. Financial difficulty or "waiting for upstream payment" rarely suffices for deposit failures (s.19(2)(e)).
How to comply
For head contractors/principals:
At tender/contract stage: Calculate whether >50% of contract price is project trust work (s.8A list is exhaustive but broad). Use the s.9 formula (GST-exclusive, reasonable estimate if uncertain). Check contracting party type (State authorities have $1M threshold).
On execution/amendment: Reassess eligibility (s.14A). If triggered, open approved-institution account within 20 business days of first subcontract (s.18). Name must include trustee name and "trust" (s.18A(2)). Give contracting party and commissioner notice within 5 business days (s.18B).
Ongoing: Deposit every payment from contracting party (including adjudicated amounts, court orders) into the trust account within 5 business days if received outside (s.19(4)). Issue project trust notices to all subcontractors before entering subcontracts (s.23). Maintain electronic records (s.18A(3)), reconcile monthly, cover shortfalls immediately (s.51). Provide beneficiary information on request (s.23B). Report related entities to commissioner within 5 business days (ss.24–25).
Retention: For cash retentions on withholding contracts, open separate retention trust account before withholding (s.34). Deposit immediately (s.35). Release only per contract after defects liability period (s.36(2)). Give notices (s.40).
Payments: Respond to payment claims with schedule within 15 business days (s.76). Pay scheduled amounts by due date (10 business days if no contract provision: s.73). Comply with adjudication decisions within 5 business days (s.90).
Dissolution: Close account only when no beneficiaries remain or only maintenance work left (s.21). Give commissioner written notice. Pay interest and remainder to self (s.21(4)).
Record-keeping and audits: Retain trust records 7 years (s.52). Respond to commissioner information requests (s.53A) and special investigators (s.53D) within time. Complete prescribed training (s.41).
For subcontractors:
Claims: Issue payment claims identifying work, stating amount, requesting payment, with supporting statement (s.75). For head-contractor claims, declare all subcontractors paid or list unpaid with reasons.
Charges: For unpaid amounts, serve notice of claim within 3 months of practical completion (s.122(5)), certified by qualified person (architect, engineer, licensed builder, quantity surveyor: s.147). For retentions only, within 3 months after defects liability period. Give copy to contractor (s.123) and security holder (s.124).
Withholding requests: Issue payment withholding request to higher party (s.97B) to create charge (s.97G).
Adjudication: Apply within 30 business days of no schedule or 20 business days of scheduled amount (s.79). Provide all supporting material.
General compliance tips:
Use software that flags eligibility on contract entry and variations.
Maintain separate ledgers for each project trust; never intermingle.
Document all "reasonable excuse" decisions contemporaneously.
Train staff on related-entity definitions (s.10A) and reporting.
For audits (s.189A), have document registers ready; claim privilege where available.
Review insurance for trust breach and adjudication liabilities.
Engage legal review for any variation exceeding 20% of price or scope.
Non-compliance risks not only penalties but QBCC licence suspension, director disqualification, and personal liability under s.58A for executive officers. Early engagement with the commission's advisory service (s.154(2)(j)) is prudent.
(b) granting an entitlement to progress payments, whether or not the relevant contract makes provision for progress payments; and
(c) establishing a procedure for— (i) making payment claims; and (ii) responding to payment claims; and (iii) the adjudication of disputed payment claims; and (iv) the recovery of amounts claimed; and
(i) making payment claims; and
(ii) responding to payment claims; and
(iii) the adjudication of disputed payment claims; and
(iv) the recovery of amounts claimed; and
(d) enabling the use of a statutory charge in favour of subcontractors for payment of the work they do.
(i) making payment claims; and
(ii) responding to payment claims; and
(iii) the adjudication of disputed payment claims; and
(iv) the recovery of amounts claimed; and
ch.1-pt.2 Application and operation of Act
Application and operation of Act
sec.4 Act binds all persons
sec.4 Act binds all persons
This Act binds all persons, including the State, and, as far as the legislative power of the Parliament permits, the Commonwealth and the other States.
ch.1-pt.3 Interpretation
Interpretation
sec.5 Definitions
sec.5 Definitions
The dictionary in schedule 2 defines particular words used in this Act.
sec.6 Subcontracts, subcontractors and subcontracted work
sec.6 Subcontracts, subcontractors and subcontracted work
A contract is a subcontract for another contract if—
performance of the contract contributes to the performance of the other contract because the work, required to be carried out under the contract, will form all or part of the work required to be carried out under the other contract; and
the contribution mentioned in paragraph (a) is not merely coincidence.
the purchase of tools from a retail store
To remove any doubt, it is declared that—
the contribution mentioned in subsection (1) (a) may be indirect because the contract contributes to the performance of 1 or more other subcontracts in order to contribute to the other contract; and
A subcontract that contributes directly to a contract would have 1 entity that is both a party to the subcontract and a party to the contract.
a contract may be a subcontract for another contract regardless of whether any party to the contract is also a party to the other contract.
If the party to a contract, who is required to carry out work under the contract, subcontracts all or part of the work—
the resulting subcontract is a subcontract for the contract; and
the person required to carry out the work under the subcontract is a subcontractor for the contract; and
the work required to be carried out under the subcontract is the subcontracted work for the contract.
The categories of subcontracts are first tier subcontracts, second tier subcontracts, third tier subcontracts and so on.
A subcontract is a first tier subcontract for a contract if—
performance of the subcontract contributes directly to the performance of the contract; and
1 person is both a party to the subcontract and a party to the contract.
A subcontract is a second tier subcontract for a contract if—
performance of the subcontract contributes to the performance of the contract only by also contributing to the performance of another subcontract for the contract; and
no party to the subcontract is also a party to the contract; and
1 person is both a party to the subcontract and a party to the other subcontract.
A subcontract is a higher subcontract for another subcontract if—
performance of the other subcontract contributes to the performance of the subcontract because the work, required to be carried out under the other subcontract, will form all or part of the work required to be carried out under the subcontract; and
both subcontracts are subcontracts for the same contract.
A first tier subcontract would be a higher subcontract for a third tier subcontract if the work required to be carried out under the third tier subcontract will form all or part of the work required to be carried out under the first tier subcontract.
(sec.6-ssec.1) A contract is a subcontract for another contract if— performance of the contract contributes to the performance of the other contract because the work, required to be carried out under the contract, will form all or part of the work required to be carried out under the other contract; and the contribution mentioned in paragraph (a) is not merely coincidence. the purchase of tools from a retail store
(sec.6-ssec.2) To remove any doubt, it is declared that— the contribution mentioned in subsection (1) (a) may be indirect because the contract contributes to the performance of 1 or more other subcontracts in order to contribute to the other contract; and A subcontract that contributes directly to a contract would have 1 entity that is both a party to the subcontract and a party to the contract. a contract may be a subcontract for another contract regardless of whether any party to the contract is also a party to the other contract.
(sec.6-ssec.3) If the party to a contract, who is required to carry out work under the contract, subcontracts all or part of the work— the resulting subcontract is a subcontract for the contract; and the person required to carry out the work under the subcontract is a subcontractor for the contract; and the work required to be carried out under the subcontract is the subcontracted work for the contract.
(sec.6-ssec.4) The categories of subcontracts are first tier subcontracts, second tier subcontracts, third tier subcontracts and so on.
(sec.6-ssec.5) A subcontract is a first tier subcontract for a contract if— performance of the subcontract contributes directly to the performance of the contract; and 1 person is both a party to the subcontract and a party to the contract.
(sec.6-ssec.6) A subcontract is a second tier subcontract for a contract if— performance of the subcontract contributes to the performance of the contract only by also contributing to the performance of another subcontract for the contract; and no party to the subcontract is also a party to the contract; and 1 person is both a party to the subcontract and a party to the other subcontract.
(sec.6-ssec.7) A subcontract is a higher subcontract for another subcontract if— performance of the other subcontract contributes to the performance of the subcontract because the work, required to be carried out under the other subcontract, will form all or part of the work required to be carried out under the subcontract; and both subcontracts are subcontracts for the same contract. A first tier subcontract would be a higher subcontract for a third tier subcontract if the work required to be carried out under the third tier subcontract will form all or part of the work required to be carried out under the first tier subcontract.
(a) performance of the contract contributes to the performance of the other contract because the work, required to be carried out under the contract, will form all or part of the work required to be carried out under the other contract; and
(b) the contribution mentioned in paragraph (a) is not merely coincidence. Example for paragraph (b) — the purchase of tools from a retail store
(a) the contribution mentioned in subsection (1) (a) may be indirect because the contract contributes to the performance of 1 or more other subcontracts in order to contribute to the other contract; and Note— A subcontract that contributes directly to a contract would have 1 entity that is both a party to the subcontract and a party to the contract.
(b) a contract may be a subcontract for another contract regardless of whether any party to the contract is also a party to the other contract.
(a) the resulting subcontract is a subcontract for the contract; and
(b) the person required to carry out the work under the subcontract is a subcontractor for the contract; and
(c) the work required to be carried out under the subcontract is the subcontracted work for the contract.
(a) performance of the subcontract contributes directly to the performance of the contract; and
(b) 1 person is both a party to the subcontract and a party to the contract.
(a) performance of the subcontract contributes to the performance of the contract only by also contributing to the performance of another subcontract for the contract; and
(b) no party to the subcontract is also a party to the contract; and
(c) 1 person is both a party to the subcontract and a party to the other subcontract.
(a) performance of the other subcontract contributes to the performance of the subcontract because the work, required to be carried out under the other subcontract, will form all or part of the work required to be carried out under the subcontract; and
(b) both subcontracts are subcontracts for the same contract.
ch.2-pt.1 Preliminary
Preliminary
sec.7 Purpose of chapter
sec.7 Purpose of chapter
The main purpose of this chapter is to ensure that funds paid to the contracted party for particular contracts are held in a trust to protect the interests of subcontractors.
s 7 sub 2020 No. 24 s 63
sec.8 Definitions for chapter
sec.8 Definitions for chapter
In this chapter—
amendment , of a contract, includes a variation of the contract or a change in the contract price.
s 8 def amendment ins 2024 No. 14 s 17 (2)
approved financial institution means a financial institution approved by the commissioner under section 55 .
building means a fixed structure that is wholly or partly enclosed by walls or is roofed.
contract administration , in relation to project trust work wholly or partly designed by a person, includes the following—
preparing tender documentation and calling and selecting tenders;
preparing, or helping the person’s clients with the preparation of, contracts;
preparing additional documentation for the person’s clients or building contractors;
arranging and conducting on-site meetings and inspections;
arranging progress payments;
arranging for certificates, including certificates from a local government, to be issued;
providing advice and help to the person’s clients including during the maintenance period allowed under a contract.
contracted party , for a contract, means the party to the contract who is required to perform work under the contract, whether by—
carrying out the work personally; or
directly or indirectly causing the work to be carried out.
contracted work , for a contract, means the work required to be carried out under the contract.
contracting party , for a contract, means the party to the contract for whom the contracted work is to be carried out.
contract price see section 9 .
hospital and health service means a Hospital and Health Service established under the Hospital and Health Boards Act 2011 , section 17 .
mechanical services work see the Queensland Building and Construction Commission Act 1991 , schedule 2 .
project trust contract means a contract for which a project trust is required under section 12 .
s 8 def project trust contract ins 2024 No. 14 s 17 (2)
project trust subcontract see section 9A .
s 8 def project trust subcontract ins 2024 No. 14 s 17 (2)
project trust work see section 8A .
protected work ...
s 8 def protected work om 2024 No. 14 s 17 (1)
State authority —
means—
an agency, authority, commission, corporation, instrumentality, office, or other entity, established under an Act or by authority of the State for a public or State purpose; or
a corporation that is—
owned or controlled by the State, a local government or an entity mentioned in subparagraph (i) ; and
prescribed by regulation to be a State authority; or
a subsidiary of a corporation mentioned in subparagraph (ii) ; or
a part of an entity mentioned in subparagraphs (i) to (iii) ; or
a hospital and health service; but
does not include an entity prescribed by regulation not to be a State authority.
trust records means records required to be kept and retained under section 52 .
s 8 def trust records amd 2024 No. 14 s 17 (3)
variation , of a contract, means an addition to, or an omission from, the contracted work.
s 8 sub 2020 No. 24 s 63
(a) preparing tender documentation and calling and selecting tenders;
(b) preparing, or helping the person’s clients with the preparation of, contracts;
(c) preparing additional documentation for the person’s clients or building contractors;
(d) arranging and conducting on-site meetings and inspections;
(e) arranging progress payments;
(f) arranging for certificates, including certificates from a local government, to be issued;
(g) providing advice and help to the person’s clients including during the maintenance period allowed under a contract.
(a) carrying out the work personally; or
(b) directly or indirectly causing the work to be carried out.
(a) means— (i) an agency, authority, commission, corporation, instrumentality, office, or other entity, established under an Act or by authority of the State for a public or State purpose; or (ii) a corporation that
This is an opening excerpt, not the complete document.