QLDIn ForceAct
Building Industry Fairness (Security of Payment) Act 2017
sec.73Due date for payment
Start here
Get a plain-English read of sec.73
Turn the raw legal text into a practical explanation grounded in Building Industry Fairness (Security of Payment) Act 2017.
### sec.73 Due date for payment
A progress payment under a construction contract becomes payable—
if the contract provides for the matter—on the day on which the payment becomes payable under the contract; or
A ‘pay when paid’ provision in a construction contract has no effect, see section 74 .
A provision in a construction management trade contract or subcontract providing for payment of a progress payment later than 25 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67U .
A provision in a commercial building contract providing for payment of a progress payment later than 15 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67W .
if the contract does not provide for the matter—on the day that is 10 business days after the day a payment claim for the progress payment is made under part 3 .
Interest for a construction contract is payable on the unpaid amount of a progress payment that has become payable at the greater of the following rates—
the rate stated in the contract;
the rate prescribed under the Civil Proceedings Act 2011 , section 59 (3) for a money order debt.
However, for a construction contract to which the Queensland Building and Construction Commission Act 1991 , section 67P applies because it is a building contract, interest is payable at the penalty rate under that section.
Each of the following construction contracts are taken to be a contract to which subsection (1) (b) applies—
a construction contract that includes a ‘pay when paid’ provision;
a construction management trade contract or subcontract mentioned in the Queensland Building and Construction Commission Act 1991 , section 67U ;
a commercial building contract mentioned in the Queensland Building and Construction Commission Act 1991 , section 67W .
In this section—
‘pay when paid’ provision , of a construction contract, see section 74 .
(sec.73-ssec.1) A progress payment under a construction contract becomes payable— if the contract provides for the matter—on the day on which the payment becomes payable under the contract; or A ‘pay when paid’ provision in a construction contract has no effect, see section 74 . A provision in a construction management trade contract or subcontract providing for payment of a progress payment later than 25 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67U . A provision in a commercial building contract providing for payment of a progress payment later than 15 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67W . if the contract does not provide for the matter—on the day that is 10 business days after the day a payment claim for the progress payment is made under part 3 .
(sec.73-ssec.2) Interest for a construction contract is payable on the unpaid amount of a progress payment that has become payable at the greater of the following rates— the rate stated in the contract; the rate prescribed under the Civil Proceedings Act 2011 , section 59 (3) for a money order debt.
(sec.73-ssec.3) However, for a construction contract to which the Queensland Building and Construction Commission Act 1991 , section 67P applies because it is a building contract, interest is payable at the penalty rate under that section.
(sec.73-ssec.4) Each of the following construction contracts are taken to be a contract to which subsection (1) (b) applies— a construction contract that includes a ‘pay when paid’ provision; a construction management trade contract or subcontract mentioned in the Queensland Building and Construction Commission Act 1991 , section 67U ; a commercial building contract mentioned in the Queensland Building and Construction Commission Act 1991 , section 67W .
(sec.73-ssec.5) In this section— ‘pay when paid’ provision , of a construction contract, see section 74 .
- (a) if the contract provides for the matter—on the day on which the payment becomes payable under the contract; or Notes— 1 A ‘pay when paid’ provision in a construction contract has no effect, see section 74 . 2 A provision in a construction management trade contract or subcontract providing for payment of a progress payment later than 25 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67U . 3 A provision in a commercial building contract providing for payment of a progress payment later than 15 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67W .
- 1 A ‘pay when paid’ provision in a construction contract has no effect, see section 74 .
- 2 A provision in a construction management trade contract or subcontract providing for payment of a progress payment later than 25 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67U .
- 3 A provision in a commercial building contract providing for payment of a progress payment later than 15 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67W .
- (b) if the contract does not provide for the matter—on the day that is 10 business days after the day a payment claim for the progress payment is made under part 3 .
- 1 A ‘pay when paid’ provision in a construction contract has no effect, see section 74 .
- 2 A provision in a construction management trade contract or subcontract providing for payment of a progress payment later than 25 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67U .
- 3 A provision in a commercial building contract providing for payment of a progress payment later than 15 business days is void, see the Queensland Building and Construction Commission Act 1991 , section 67W .
- (a) the rate stated in the contract;
- (b) the rate prescribed under the Civil Proceedings Act 2011 , section 59 (3) for a money order debt.
- (a) a construction contract that includes a ‘pay when paid’ provision;
- (b) a construction management trade contract or subcontract mentioned in the Queensland Building and Construction Commission Act 1991 , section 67U ;
- (c) a commercial building contract mentioned in the Queensland Building and Construction Commission Act 1991 , section 67W .