QLDIn ForceAct
Building Industry Fairness (Security of Payment) Act 2017
sec.92Consequences of not paying adjudicated amount
Start here
Get a plain-English read of sec.92
Turn the raw legal text into a practical explanation grounded in Building Industry Fairness (Security of Payment) Act 2017.
### sec.92 Consequences of not paying adjudicated amount
If the respondent fails to pay the whole or any part of the adjudicated amount to the claimant as required under section 90 , the claimant may give the respondent written notice of the claimant’s intention to suspend carrying out construction work, or supplying related goods and services, under the construction contract under section 98 .
The notice about suspending work must state that it is made under this Act.
(sec.92-ssec.1) If the respondent fails to pay the whole or any part of the adjudicated amount to the claimant as required under section 90 , the claimant may give the respondent written notice of the claimant’s intention to suspend carrying out construction work, or supplying related goods and services, under the construction contract under section 98 .
(sec.92-ssec.2) The notice about suspending work must state that it is made under this Act.