[2021] NSWSC 1557
Supreme Court of NSW
2020-12-01
Henry J
Original judgment source is linked above.
ild Constructions (Aust) Pty Ltd (No 2) (2016) 95 NSWLR 157; [2016] NSWCA 379 Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52 TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93 Trinco (NSW) Pty Ltd v Alpha A Group Pty Ltd [2018] NSWSC 239 Vis Constructions Pty Ltd v Cockburn [2006] QSC 416 Texts Cited: Nil Category: Principal judgment Parties: Crown Green Square Pty Ltd (ACN 161 698 148) (First Plaintiff) Sathio Investments Pty Limited (ACN 138 087 939) (Second Plaintiff) Crown Cornerstone Investments Pty Limited (ACN 138 199 112) (Third Plaintiff) Crown Group Construction Pty Ltd (ABN 91135 132 884) (Fourth Plaintiff) Transport for New South Wales (ABN 18 804 239 602) (First Defendant) Sydney Trains (ABN 38 284 779 682) (Second Defendant) Rail Corporation New South Wales (ABN 59 325 778 353) (Third Defendant) Representation: Counsel: L Shipway (Plaintiffs) T Breakspear SC (Defendants)
Solicitors: Johnson Winter & Slattery (Plaintiffs) Clayton Utz (Defendants) File Number(s): 2020/125579 Publication restriction: Nil
Judgment
Relevant provisions of the SoP Act
Facts
July 2015: Development Approval
Development Agreement
April 2016 - February 2017: Post-Development Agreement services designs
March - September 2017: Tunnel and new entrance services designs meetings
November 2017 - November 2018: Process to obtain approvals for services design drawings
February 2019: The Honeywell contract
September 2019 - March 2020: Practical completion of Tunnel Works and demands for payment for Link Works
Issue 1 - Was there a construction contract for some or all of the Link Works?
Legal principles - "other arrangement" under the SoP Act
Submissions
Consideration
Issue 2 - Is the 26 March Claim a payment claim?
Issue 3 - Is the 26 March Claim a second payment claim in respect of the same reference date as a previous payment claim?
Issue 4 - Does the 26 March Claim seek payment in relation to two construction contracts?
Costs and orders
Endnote
Crown Green Square Pty Ltd
Transport for NSW
[2020] ACTSC 231
[2013] QSC 4
[2016] SASC 156
[2015] HCA 37
[2006] QSC 416
(2005) 63 NSWLR 385
(2009) 74 NSWLR 190
(2017) 261 CLR 544
(2014) 251 CLR 640
(2017) 94 NSWLR 606
(2015) 256 CLR 104
(2017) 95 NSWLR 82
(2018) 264 CLR 1
(2016) 95 NSWLR 157
(2016) 260 CLR 340