Natural justice
49In this case, the adjudicator clearly considered that the objection to jurisdiction was valid at the level of principle. That is to say, he seems to have considered that if there were in truth five adjudication applications relating to the one payment claim arising under the one contract, then there would be a jurisdictional issue.
50The adjudicator dealt with this at paras 27 to 40 of the reasons annexed to his determination. I set out paragraphs 27 to 38, which constitute the essence of his reasoning:
27. This application is one of five Adjudication Applications submitted by the Claimant to the Authorised Nominating Authority. Each application was submitted separately by the Claimant on 24 November 2011.
28. Applications 620 to and including 623 relate to the one contract, namely the platform resurfacing contract, in accordance with the Respondent's submissions. They all refer to being part of a progress claim numbered 18, as submitted by the Claimant to the Respondent on 31 October 2011. Application 624 is obviously not related to the previous 4 claims given its unique contract number.
29. Progress claim 18 is a reference number contained on each Payment Claim. The subsequent individual tax invoices associated with the individual Payment Claims contain a unique reference number which ultimately is associated to each individual Adjudication Application. The fact that each refers to being a part of progress claim 18 is more of a reference to the claims relation with the head contract. Each Payment Claim made under the Act is unique to a separable and specific contract, which I shall explain in due course.
30. The Act prevents a Claimant submitting more than one Payment Claim in any one reference period under the contract.
31. The Respondent contends that, to the extent progress claim 18 is one single Payment Claim, the Claimant is only entitled to submit one application to adjudication under section 17 of the Act in relation to that Payment Claim.
32. The Respondent concludes that noting in the Act entitles a claimant to subdivide any one Payment Claim and issue numerous Adjudication Applications to be determined at the same time.
33. Section 17 of the Act contemplates one adjudication application for each Payment Claim for each reference date under a contract.
34. The Construction Contract is made up of 25 separable portions with each portion relating to a different specified railway station.
35. It is clear that the parties wished to treat each station as a separable and independent portion of the contract, with individually assigned contract values for each station. The Construction Contract states that the tender price for each of the separable parts must be independent and separable.
36. It is apparent that the parties intention was to treat each of the 25 independent railway stations as completely separate components of an overall global contract for the resurfacing works. In fact the contract specifically identifies the 25 independent components.
37. I am satisfied that there were five different payment claims pertaining to 5 different contracts (governed by a head contract) giving rise to the five separate Adjudication Applications.
38. I am satisfied that the Construction Contract contemplated that in relation to invoicing, progress claims and subsequent payments, each of the 25 railway stations were to be treated in isolation and as a separate contract, to be governed by the terms of the head contract, namely Contract No. CW5090, Platform Resurfacing Program 2009/10.
51It will be seen that the adjudicator reasoned, based on the existence of separable parts of the works, that there were in fact 25 separate contracts: one for each separable part of the works.
52That is not an approach that either party had taken. It was not referred to at all in the payment claim, the payment schedules, the adjudication application or the adjudication response. Nor is it an approach adopted by Nebax in this court. Mr Smith, in my view entirely correctly, accepted that there was but one contract. If that concession had not been made, I would so hold: the language of the various parts of the contract documents to which I have referred makes it clear.
53In those circumstances, it seems to me, the adjudicator dealt with the objection as to jurisdiction on a basis for which neither party had contended. It is not disputed that he did not give either party notice of his intention to do so, or offer them an opportunity to be heard on the point.
54The obligation to provide natural justice, in relation to the Act, has been considered in a number of cases. I set out the relevant principles, as I understood them, in my decision Watpac Constructions NSW Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 at [141] to [147]. For convenience, and since I remain of the view set out in those paragraphs, I incorporate them into these reasons:
[141] Hodgson JA discussed natural justice, in the scheme of the Act, in Brodyn at 441-442 [55]. His Honour said in that paragraph that an adjudication determination will be void if, among other things, "there is a substantial denial of the measure of natural justice that the Act requires to be given".
[142] Any entitlement to natural justice must accommodate the scheme of the Act, including the extremely compressed timetable provided for the submission of payment schedules, adjudication applications, and adjudication responses; and the limited time (subject to the consent of the parties, which they may give or withhold at their will) for an adjudicator to determine an application. It must also accommodate the fact that, in many cases, claimants and respondents will prepare their documents themselves, and will not avail themselves of legal advice in doing so.
[143] In Musico v Davenport [2003] NSWSC 977, I said at [107]
that where an adjudicator is minded to decide a dispute on a basis for which neither party has contended, then natural justice requires the adjudicator to notify the parties of that intention, so that they could put submissions on it.
[144] However, as I pointed out in John Goss at 716 [42], "the concept of materiality is inextricably linked to the measure of natural justice that the Act requires parties to be given in a particular case." That meant, I said, that the principles of natural justice "could not... require an adjudicator to give the parties an opportunity to put submissions on matters that were not germane to his or her decision".
[145] I see no reason to depart from those views; and neither party submitted that I should. In particular, I think, my insistence on materiality is consistent with the reference by Hodgson JA in Brodyn to "substantial denial... of natural justice."
[146] In this context, Gleeson CJ said in Re Minister for Immigration and Multicultural Affairs ; ex parte Lam (2003) 214 CLR 1 at 13 - 14 [37] that fairness is not abstract but practical. His Honour said that "[w]hether one talks in terms of procedural fairness or natural justice, the concern of the law is to avoid practical injustice". To like effect, Kirby J said in Minister for Immigration and Ethnic Affairs v Wu Shan Liang (1996) 185 CLR 259 at 291 that the court should not undertake the task of "combing through the words of the decision-maker with a fine appellate tooth-comb [sic], against the prospect that a verbal slip will be found warranting" the intervention of the court.
[147] I accept, however, that the court should not be too ready to find that a denial of natural justice was immaterial; that it had no real or practical effect; or that (in the present context) there was nothing that could have been put on the point in question. But it remains the case, I think, that the denial of natural justice must be material, and that submissions that could have been put might have had some prospect of changing the adjudicator's mind on the point.
55Prima facie, therefore, the adjudicator did deprive the parties - in particular
RailCorp - of natural justice. Was that material? Could submissions have been put that might have persuaded him to change his mind? In my view, each of those questions should be answered "yes".
56Had the matter been raised, it would have been open to RailCorp to take the adjudicator to the relevant portions of the contract to which I have referred already; in particular, the insistence, in the letter of 15 December 2009, that there was one contract for the specified lump sum; and the insistence and the acceptance, in the form of tender, that the contract was to be constituted by the tender documents as specified. It would also have been open to RailCorp to take the adjudicator in more detail to the provisions of Part B2 of the tender schedule, and to the relevant provisions of the contract, to show him the purposes for which the contract works under the one contract were it to be divided into separable portions.
57The adjudicator may or may not have accepted those submissions. If he did, he should not have concluded, for the reasons that he did, that he had jurisdiction. If he did not, then on the view I have taken, it would not matter because, as I have said, he could not determine his own jurisdiction conclusively. But the salient point is that as proceeding as he did, the adjudicator deprived RailCorp of the opportunity to put submissions, that in my view, would have had force and, indeed, should have persuaded him to a view different to the one that in fact he expressed.
58Thus, I conclude, there was a material denial of natural justice.
59It is clear that a material denial of natural justice renders the determination void. That proposition is supported by the authorities (including Brodyn and Chase ) and was not controverted.
60As I have said, Mr Smith submitted that it would have been open to his client to rely on the so-called direction, and on the submission of separate individual tax invoices each described as a payment claim, to argue that there would have been, or were, separate reference dates under the one contract. I do not think that this argument is sound. But the point is not whether or not it is sound. The point is, as I have indicated, whether the parties were given an opportunity to address the issue. Certainly, I am not persuaded that the argument is indubitably correct, so that the loss of the ability to put submissions had no practical consequence in terms of outcome. I say that for reasons that I think I have indicated, including of course that the proposition is inconsistent both with the language of the contract and with s 13(5) of the Act, and I have grave doubts that the power vested in the contract administrator to give directions could be intended to vary the contract, let alone to set at nought, a mandatory requirement of the Act.