© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2022] NSWCA 82
Court of Appeal (NSW)
2022-05-04
Ward P, Leeming JA, White JA, Brereton JA
Original judgment source is linked above.
on 6 Holdings Ltd v Industrial Relations Commission of New South Wales (2004) 60 NSWLR 558; [2004] NSWCA 200 Southern Han Breakfast Point Pty Ltd (in Liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52 TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93 Texts Cited: Lewison and Hughes, The Interpretation of Contracts in Australia (2012, Thomson Reuters) Category: Principal judgment Parties: BSA Advanced Property Solutions (Fire) Pty Ltd (Appellant) Ventia Australia Pty Ltd (First Respondent) Edward Smithies/Australian Solutions Centre (Second Respondent) Representation: Counsel: Mr M Christie SC/Mr D Hume (Appellant) Mr L Shipway/Mr D Byrne (First Respondent)
Solicitors: Vincent CCL Pty Ltd t/as Vincent Young (Appellant) Pinsent Masons (First Respondent) File Number(s): 2021/00364260 Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Equity - Commercial List Citation: [2021] NSWSC1534 Date of Decision: 30 November 2021 Before: Rees J File Number(s): 2021/98498
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] In April 2016, Ventia Australia Pty Ltd ("Ventia") entered into an agreement with the NSW Land and Housing Corporation to provide various services for social housing properties. On 3 May 2016, Ventia entered into a subcontract with BSA Advanced Property Solutions (Fire) Pty Ltd ("BSA") for BSA to provide fire protection and maintenance services at the properties. Clause 2.1(a) of the subcontract provided that "the Subcontractor must execute and complete the Services … in accordance with the terms of the Agreement". Clause 2.1(b) provided that "the terms set out in Annexure 4 will form part of this agreement". Relevantly, Annexure 4 cl (b) stated that "[a] separate Agreement will come into existence each time [Ventia] issues a Work Order". On 8 February 2021, BSA served on Ventia a claim for a progress payment pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act"). The payment claim was made with respect to 25 invoices issued with respect to five work orders. On 22 February 2021, Ventia served a payment schedule which asserted, inter alia, that the payment claim was invalid. Ventia contended that the payment claim did not comply with the Act because it was made with respect to multiple construction contracts and did not identify a single reference date. On 31 March 2021, an adjudicator found that the payment claim was valid because it was made in relation to only one construction contract. The adjudicator concluded that Annexure 4 cl (b) was inconsistent with the general contract provisions, which did not contemplate separate agreements for each work order. On 30 November 2021, the Supreme Court quashed the adjudicator's determination. The primary judge found that (i) each work order constituted a separate agreement and (ii) the Act precluded the service of a payment claim in relation to construction work performed under more than one contract. On appeal, the primary issues before the Court were whether: (1) the Act required that a payment claim could relate to work done under only one construction contract (the "one contract" rule); (2) if there be a "one contract" rule, that is a precondition to the validity of a payment claim; and (3) there was, for the purposes of the Act, one construction contract between BSA and Ventia. The Court (Ward P, Leeming, White and Brereton JJA, and Basten AJA) held, upholding the appeal: Issues 1 and 2: the "one contract" rule (1) An entitlement to a progress payment arises in respect of construction work carried out under a contract. The legislative purpose is to ensure that persons carrying out construction work obtain regular payments. The legislation defines "construction contract" as including both a contract and some other arrangement, which directs attention to the carrying out of the work rather than the source of the obligation to carry out the work: [36]. Building and Construction Industry Security of Payment Act 1999 (NSW), ss 3, 4, 8, referred to. (2) The legislation states where the contract is to govern and provides a default position where a matter is not provided for by the contract. Questions of compliance are matters for an adjudicator who must have regard to the contractual provisions when determining a dispute. The Act does not contain an implied jurisdictional limitation on the functions of the adjudicator: [23]-[25], [37]-[39], [51]. All Seasons Air Pty Ltd v Regal Consulting Services Pty Ltd [2017] NSWCA 289; Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd (2010) 78 NSWLR 393; [2010] NSWCA 190, applied. Building and Construction Industry Security of Payment Act 1999 (NSW), ss 3, 8, 14, 17, 21, 22, referred to. (3) Further, the putative "one contract" rule is imprecise. The scope of commercial arrangements under which goods and services may be supplied is expansive: [40]. (4) Even if a payment claim may relate to only one construction contract with one reference date, the validity of a payment claim is not conditioned on the existence of one construction contract: [36], [52]. Ausipile Pty Ltd v Bothar Boring and Tunnelling (Australia) Pty Ltd [2021] QCA 223; Nepean Engineering Pty Ltd v Total Process Services Pty Ltd (in liq) (2005) 64 NSWLR 462; [2005] NSWCA 409; TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 93; Rail Corporation of NSW v Nebax Constructions Australia Pty Ltd [2012] NSWSC 6; Matrix Projects (Qld) Pty Ltd v Luscombe [2013] QSC 4, discussed. (5) It is strongly arguable that there is no "one contract" rule and that s 13(1) permits a person to serve a payment claim in relation to an entitlement under more than one contract so long as the claim is referable to one reference date: [52]. Issue 3: Number of construction contracts (6) Contractual terms, such as Annexure 4 cl (b), do not determine the relationship of the parties with respect to the statutory scheme under which payment claims may be made: [80]. Lewis v Bell (1985) 1 NSWLR 731; Radaich v Smith (1959) 101 CLR 209; [1959] HCA 45; Fearnley v Australian Fisheries Management Authority [2006] FCAFC 3, applied. Building and Construction Industry Security of Payment Act 1999 (NSW), s 34, referred to. (6) Annexure 4 cl (b) was inconsistent with other provisions in the subcontract and did not create a separate contract for each work order. The subcontract required BSA to identify the "the part of the Fee claimed in relation to work orders worked on for that payment claim", allowing that a payment claim may refer to multiple work orders. Provisions for set-offs and defect rectification did not refer to separate contracts by which the work must be undertaken in relation to each work order. The subcontract also provided for variations to services that had not been requested under a work order: [82]-[84], [94]. (7) Re Webster did not assist in determining whether the subcontract was an agreement or a standing offer. What constitutes a "construction contract" under the Act may be different from an "agreement" under s 44(v) of the Constitution. In any event, Re Webster is not authoritative as to the operation of s 44(v) of the Constitution: [89]-[91]. Re Day [No 2] (2017) 263 CLR 201; [1975] HCA 22, referred to; Re Webster (1975) 132 CLR 270 at 282; [1975] HCA 22, not followed.
Judgment
Salient background
Reasoning of primary judge
Statutory scheme
Absence of basis for a jurisdictional constraint
Discussion in case law
Reasoning of primary judge
The contractual provisions
Assessment of contractual documentation
Standing offers
Conclusion - claim under one contract
Orders
Endnotes
Amendments 13 February 2023 - Minor typographical errors. Included attachment. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 13 February 2023
BSA Advanced Property Solutions (Fire) Pty Ltd
Ventia Australia Pty Ltd
[2021] QCA 223
[2013] QSC 4
[2017] HCA 14
(2004) 61 NSWLR 421
(2010) 78 NSWLR 393
(2006) 225 CLR 180
(2010) 239 CLR 531
(1985) 1 NSWLR 731
(2005) 64 NSWLR 462
(2017) 61 NSWLR 421
(2018) 264 CLR 1
(1959) 101 CLR 209
(2017) 263 CLR 201
(1975) 132 CLR 270
(2004) 60 NSWLR 558
(2016) 260 CLR 340
(2009) 74 NSWLR 190
(2004) 218 CLR 471
(2001) 207 CLR 21
[2010] HCA 1
[2001] HCA 44