The Developer's adjudication applications
15 The Developer has previously submitted two adjudication applications under the Act naming the Owner as respondent, both of which were refused on the basis that the adjudicator lacks jurisdiction because there is no "construction contract" between the Owner and the Developer. It is a jurisdictional requirement of an adjudication application under s 17 of the Act that the payment claim in respect of which adjudication is sought is a claim made under a "construction contract" as defined in s 4.
16 First, on 13 October 2021, the Developer submitted an adjudication application in respect of a payment claim dated 6 September 2021 to an authorised nominating authority under the Act. The Developer's submissions in support of the adjudication application stated that the effect of the oral agreements between the relevant parties was that the development land would be owned by the Owner, the Developer would develop the site and the Developer would engage the Builder to perform building works. It was said that there was a construction contract between the Developer and the Builder. The amount claimed from the Owner was nearly $4 million.
17 The appointed adjudicator was Stuart Wood. Mr Wood issued a determination dated 25 October 2021. He found that the arrangement between the Developer and the Owner is not a "construction contract" consistent with the definition given in s 4 of the Act. He also found that even if it were a construction contract, under s 7(3)(c) it is exempt from the application of the Act because the parties had entered into loan agreements and/or indemnities as referred to in that provision.
18 Secondly, on 7 October 2022, the Developer submitted an adjudication application in respect of a payment claim dated 7 September 2022 to Resolution Institute, an authorised nominating authority. In the application, the Developer claimed approximately $8.44 million. In its submissions in support of the adjudication application it characterised the relationship between it and the Owner as follows:
(1) The adjudication application concerns construction work and related goods and services "provided by the [Developer] on behalf of the [Owner] in respect of the design and construction" of the project.
(2) The Developer is the project development company and responsible for "providing development and building advisory services including managing [the Builder's] performance of the construction Project and the planning of the Project", engaging or instructing all consultants and sales and marketing service providers for the Project, and attempting to obtain finance for the Owner from a lender for the Project.
(3) The Developer engaged the Builder as contractor to carry out the construction works.
(4) There was a joint venture agreement for the project which included that the "development company would be the [Developer], a SPV [to] manage and undertake the development on the [Owner's] behalf" and the Builder would "be engaged to physically construct the Project under a building contract".
(5) There was a project development agreement by which the Owner engaged the Developer "to provide, procure and manage the goods services, know-how and infrastructure for the Project" (sic). The nature of the agreement was:
(a) The [Developer] would be the project development company of the Project, and that this role included causing the project to be constructed (through contractors) and providing development and building advisory services including managing the Builder's performance of the construction of the Project, reporting to the [Owner] (including Roger and Isaac) and the planning of the Project, engaging or instructing all consultants and sales and marketing service providers for the Project, and attempting to obtain finance from a lender for the Project;
(b) The [Developer] would manage the payment of all costs and expenses associated with the Project at first instance;
(c) The [Owner] would pay or reimburse the [Developer] for all the costs, expenses or liabilities that the [Developer] incurred in respect to the Project or in its role as project development company;
(d) The [Owner] would also pay the [Developer] $150,000 project management fee in addition to any costs, expenses or liability it incurred.
(6) The Owner has not paid the Developer in full for "the Contract Works carried out by the Builder".
(7) The contract is a construction contract under the Act "because it relates to the [Developer] performing construction work and providing goods and services to the [Owner]".
(8) The Developer provided related goods and services as referred to in the Act because it provided to the Owner the construction of the project, labour to carry out construction work, architectural and related professional services in relation to the construction work, and building and engineering advisory services in relation to the construction work.
19 Barry Tozer was the appointed adjudicator. Mr Tozer issued an adjudication dated 24 October 2022. The adjudication canvassed the parties' respective submissions and evidence with regard to whether the relevant contract is a construction contract within the meaning of the Act. Mr Tozer found as follows:
42. I find that the [Developer] did not directly perform any construction work or provide related goods and services and the agreement between the [Developer] and the [Owner] was not a 'construction contract' or arrangement as required by s 5 or s 6 of the Act.
20 Mr Tozer found in the alternative that if his finding that there was no construction contract was incorrect, in any event the contract was "excluded from the operation of the Act under s 7(3)(c)(iii)".
21 On 4 November 2022, the Developer advised Resolution Institute that it withdrew its adjudication application of 7 October 2022. At the same time, it made a new adjudication application to Resolution Institute and requested that Mr Tozer not be appointed to adjudicate the new application. The Developer explained that it considered Mr Tozer's determination not to be a valid determination under the Act. On that basis, it said that Mr Tozer had failed to determine the application within the time allowed by s 21(3) and that it was entitled to submit a new application.
22 Submissions made on behalf of the Developer in support of the new application explained that the Developer was entitled to make a new application under s 26(1)(b) because Mr Tozer had failed to determine the application within the time allowed by s 21(3). Two independent reasons, each said on its own to be sufficient to justify the contention that no determination had been made, were identified.
23 First, it was said that Mr Tozer had not determined the application that was before him because he had decided that he lacked jurisdiction. As, on his view, there was no "application" to determine, he did not "determine" any such application - he issued a "non-determination".
24 Secondly, it was said that Mr Tozer's determination was invalid ab initio because Mr Tozer erroneously concluded that there was an absence of a jurisdictional fact, viz the existence of a "construction contract", when in fact that jurisdictional fact existed. It is submitted on behalf of the Developer to me that the determination was invalid and a nullity on account of jurisdictional error by Mr Tozer, namely that he asked himself the wrong question. The submission is that he asked whether the Developer had itself, or "directly", performed construction work whereas he should have asked himself whether the Developer had "undertaken to carry out construction work".
25 In its submissions in support of the new adjudication application, the Developer also said that Mr Tozer's conclusion that the contract was excluded from the operation of the Act by the exemption in s 7(3)(c)(iii) was incorrect. It submitted that Mr Tozer made a legal error because the effect of that provision is to exclude from the operation of the Act only the provisions of the contract that are found to fall within the provision, ie, that provide an indemnity with respect to construction work carried out, and not the contract as a whole. The Developer submits to me that the result is that the adjudicator must disregard the indemnity provisions of the contract but still adjudicate the payment claim.
26 It is submitted on behalf of the Developer to me that Mr Tozer's conclusion with regard to the exclusion of the contract or arrangement from the Act by s 7(3)(c)(iii) was also, by his error of law, infected by jurisdictional error. The decision was therefore a nullity and could be ignored.
27 The Owner then filed and served an interlocutory application seeking urgent injunctive relief against Resolution Institute to prevent it from referring the new application to an adjudicator for adjudication under s 17(6). To that, Resolution Institute responded by agreeing to refrain from referring the new adjudication application to an adjudicator pending the determination of the interlocutory application. The Developer responded by withdrawing the adjudication application from Resolution Institute and, on 30 November 2022, submitting it to a different authorised nominating authority, namely Australian Building & Construction Dispute Resolution Service Pty Ltd (ABCDRS).
28 On 1 December 2022, ABCDRS confirmed receipt of the application for adjudication and stated that it would proceed to appoint an adjudicator.
29 As it happens, the parties received the notification from ABCDRS while they were before me in a case management hearing. On the oral application of the Owner, to which the Developer quite properly offered no opposition, I immediately made orders restraining ABCDRS from referring the adjudication application to an adjudicator for a period of seven days to enable a fresh interlocutory application and evidence to be filed and served, and for the interlocutory application to be heard. That period was later extended for a few more days.
30 ABCDRS is cited as a respondent to the interlocutory application but it has quite properly not opposed the relief and abides the Court's decision.