[2017] NSWCA 113
Court of Appeal (NSW)
2017-05-05
Beazley ACJ, Basten JA, Meagher JA, Ball J
Original judgment source is linked above.
Solicitors: HWL Ebsworth (Appellant) Marsdens Law Group (Respondent) File Number(s): 2017/80346 Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Equity - Technology and Construction List Citation: [2017] NSWSC 166 Date of Decision: 6 March 2017 Before: Ball J File Number(s): 2017/46031
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
headnote [This headnote is not to be read as part of the judgment] In 2015, Fairfield City Council sought to undertake major road works involving the upgrade of sections of Wetherill Street, Wetherill Park. The Council and Abergeldie Contractors Pty Ltd ("the contractor") entered into a contract for this purpose on 18 August 2015. The terms of the contract allowed the contractor to make progress payment claims in accordance with the Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act"). It was accepted by both parties that the existence of a valid "reference date", as defined in s 8(2) of the Act, was a precondition to the service of a valid payment claim. The contract provided that after "practical completion" of the works, which was a defined term, there were two reference dates. The first of these was the 28th day of the month "immediately after practical completion". On 16 September 2016, the project manager for the contractor wrote to the Council indicating that the contractor was of the view that practical completion had been achieved on that date. The letter requested that the Council's superintendent issue a certificate of practical completion in accordance with the contract. On 25 November 2016, the superintendent issued a certificate of practical completion which indicated that practical completion for the relevant work had been achieved on 16 September 2016. On the same day, 25 November, the contractor sent a payment claim to the superintendent. On 7 December 2016 the Council issued a payment schedule indicating that no amount would be paid, as there was no valid reference date which permitted a payment claim to be made in November. The contractor obtained an adjudication that it was entitled to payment. The Council then sought relief in the Equity Division. Ball J declared that, there being no reference date in November 2016, the payment claim was invalid, and quashed the determination of the adjudicator. The contractor appealed to this Court. The question on appeal was: Did practical completion of the work occur, as the Council alleged, on 16 September 2016, with the result that the relevant payment reference date was 28 September 2016; or did practical completion occur, as the contractor submitted, on the date on which the certificate of practical completion was issued, namely 25 November 2016, with the result that the relevant reference date was 28 November 2016? The Court (Beazley ACJ, Basten JA and Meagher JA) allowed the appeal and held:
Judgment
(a) factual background
(b) the statutory scheme
(c) contractual provisions
(a) the issues
(b) construing the contract
(c) conclusions as to date of practical completion
(d) validity of certificate
Practical completion - factual determination
Conclusions
Endnotes
Abergeldie Contractors Pty Ltd
Fairfield City Council
[1999] HCA 21
[2008] QCA 397
(1976) 135 CLR 110
(2010) 78 NSWLR 393
(2014) 251 CLR 640
(1999) 197 CLR 611
(1938) 59 CLR 369
(2009) 1 Qd R 390
(1944) 69 CLR 407