[2021] NSWCA 69
Court of Appeal (NSW)
2021-03-23
Bathurst CJ, Bell P, Gleeson JA, Henry J
Original judgment source is linked above.
Solicitors: Salim Rutherford Lawyers (Appellant) HWL Ebsworth Lawyers (Respondent) File Number(s): 2020/278937 Decision under appeal Court or tribunal: Supreme Court of New South Wales Jurisdiction: Equity Division - Technology and Construction List Citation: [2020] NSWSC 1158 Date of Decision: 28 August 2020 Before: Henry J File Number(s): 2020/123334
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
HEADNOTE [This headnote is not to be read as part of the judgment] The appellant, Lahey Constructions Pty Ltd (Lahey), entered into two contracts (together, the Contracts) with the respondent, the Minister for Education for the State of New South Wales (the Department), for the performance of building and construction works upgrading Manly Vale Public School and Bardia Public School. The Contracts incorporated the New South Wales Government GC21 (Ed 2) General Conditions of Contract. The terms of the Contracts included identical provisions concerning the expert determination of issues that were unable to be resolved between the parties. Subject to certain exceptions, the determination of the expert was to be treated as final and binding. One exception was where the monetary value of the determination exceeded the threshold amount of $500,000. In such event, either party was entitled to bring litigation challenging the expert determination. In assessing whether the threshold amount had been achieved, cl 71.8.2 required that the amount of the determination be calculated without having regard to any amount that had been paid under the Building and Construction Industry Security of Payment Act 1999 (NSW) (SoP Act). The parties referred for expert determination disputes Lahey had raised under the Contracts. The Department in turn raised defences, cross-claims and set-offs, as well as its own claims. During the expert determination process, but separately to that process, Lahey served SoP Act payment claims on the Department. These payment claims included the matters that Lahey had raised for expert determination under the Contracts. Following adjudication of the payment claims under the SoP Act, the Department made payments to Lahey. The expert determined that the Department was entitled to either "set-off" or to "repayment" of the amount it had paid to Lahey pursuant to the adjudications. Lahey brought proceedings in the Technology and Construction List of the Equity Division of the Supreme Court in relation to the issues that had been referred to the expert for determination. The Department successfully sought an order for summary dismissal of the proceedings. The primary judge (Henry J) concluded that the expert determination for each of the Contracts was final and binding because on the proper construction of cl 71.8.2, the value of their disputes did not exceed the threshold amount of $500,000 for either contract. Lahey sought leave to appeal from the decision of the primary judge, asserting that the primary judge erred in her construction of the expert determination clause. Held, granting leave to appeal and allowing the appeal (per Gleeson JA; Bathurst CJ and Bell P agreeing): Applying settled principles of contractual construction, clause 71.8.2 of the Contracts required that any payment made under the SoP Act, and not only some of the payments, be disregarded when calculating the determined amount by the expert for the purposes of the jurisdictional provision. This construction was supported by the text of clause 71.8.2: [51]-[52]; and by the context, which included that payments made under the SoP Act are interim or provisional in nature, subject to the parties' rights under the construction contract: [53]-[56]. Further, the primary judge's construction would create a perverse incentive for Lahey not to resort to making progress claims under the SoP Act for fear that it would lose the possible right to litigate disputes about important matters in terms of monetary significance: [64]-[65]. Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7; Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2014] HCA 37; Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99; [1973] HCA 36; Southern Han Breakfast Point Pty Ltd (in liq) v Lewence Construction Pty Ltd (2016) 260 CLR 340; [2016] HCA 52; Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4 referred to. On the proper construction of clause 71.8.2, the threshold amount of $500,000 had been achieved and Lahey was not precluded from bringing litigation in relation to the disputes under either contract: [68]-[69].
Judgment
The Contracts
The Expert Determination
The primary judge's reasons
Grounds of appeal
Principles
Submissions
Table summarising expert determination - Bardia Public School 1 2 3 4 Claim # Details of Claim Amount paid to Lahey pursuant to Adjudication Amount determined by Expert Amount payable to DoE pursuant to Expert Determination 1 V004 - Suspension $434,027.90 $49,655.67 $384,372.23 2 V047 - Air Conditioning $1,340,542.89 $1,333,022.83 $7,520.16 3 V015 - Acceleration $2,843,888.00 $1,094,643.20 $1,749,244.80 4 V146 - Asbestos Removal Playspace CW1 Wall Stockpile $634,761.69 $699,986.31 -$65,224.62 5 V128 - Asbestos Removal Black A&B Asbestos Piles $840,320.67 $840,320.67 $0.00 6 V011 - Asbestos Soil 500t $168,648.15 $164,925.60 $3,722.55 7 V013 - Hire of Concrete Barriers $353,890.54 $331,165.75 $22,724.79 8 V051 - Existing School Sewer Diversion $36,120.22 $36,120.22 $0.00 9 V056 - Sports Field Changes $167,469.06 $164,433.06 $3,036.00 10 V062 - Structural Steel Changes $269,769.61 $157,960.20 $111,809.42 11 V073 - New fire hydrant pump room $224,036.15 $194,945.60 $29,090.55 12 V090 - Car Park Design Changes $92,031.66 $84,892.30 $7,139.36 Total $7,405,506.54 $5,152,071.41 $2,253,435.24
Reasoning
Text
Context
Purpose
The primary judge's construction should be rejected
Summary
Conclusion and Orders
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 26 April 2021
Lahey Constructions Pty Ltd
The State of New South Wales
[2009] NSWCA 272
[2015] VSCA 318
(1973) 129 CLR 99
(2010) 78 NSWLR 393
(2014) 251 CLR 640
(2015) 256 CLR 104
(2018) 264 CLR 1
(2015) 47 VR 177
(2016) 260 CLR 340
(1992) 30 NSWLR 1
(2011) 244 CLR 305