[2011] HCA 38
High Court of Australia
2011-10-05
Tamberlin AJ, Kiefel JJ, McDougall J, French CJ, Bell JJ
Original judgment source is linked above.
Shoalhaven City Council v Firedam Civil Engineering Pty Limited
On appeal from the Supreme Court of New South Wales
D F Jackson QC with J A Steele for the appellant (instructed by TressCox Lawyers)
Notice: This copy of the Court's Reasons for Judgment is subject to formal revision prior to publication in the Commonwealth Law Reports.
Shoalhaven City Council v Firedam Civil Engineering Pty Limited
Contract - Construction - Dispute resolution clause - Parties to contract agreed to expert determination of claims for damages for breach of contract - Expert contractually obliged to give reasons - Whether inconsistency in expert's reasons - Whether court has power to review expert's determination made under contract.
Words and phrases - "expert determination", "inconsistency", "issue", "valid and sufficient reasons".
Commercial Arbitration Act 1984 (NSW), ss 24, 28, 33, 44.
. Pursuant to cl 41 where Firedam encountered site conditions materially adverse in comparison to those which it should reasonably have foreseen at the date of the Contract. To obtain an extension of time under cl 41, Firedam would have to give Shoalhaven the notice required by that clause. Any extension of time would be granted pursuant to cl 54[3].
. Pursuant to cl 52 where Shoalhaven instructed Firedam to undertake a variation of the works. The parties were required to endeavour to agree in writing on the value of the variation and its effect on time. Absent agreement, the matter could be referred to the issues resolution process under the Contract[4].
. Pursuant to cl 54 where a delay to completion occurred or was anticipated. Firedam was entitled to an extension of time subject to conditions set out in cl 54.1 including:
".1 a Variation, other than one for which, under clauses 41.6, 42.4 and 44.3, there is no payment for delays; or
.2 a breach of the Contract by the Principal which causes delay, disruption or interference to the Contractor carrying out the Works."
"The Principal may in its absolute discretion for the benefit of the Principal extend the time for Completion at any time and for any reason, whether or not the Contractor has Claimed an extension of time. The Contractor is not entitled to an extension of time for Completion under this clause 54.6 unless the Principal exercises its discretion to extend the time for Completion."
As appears later in these reasons, Shoalhaven's entitlement to compensation for delays caused by Firedam was calculated by the Expert by reference to a completion date extended under cl 54.6 in order to exclude delays attributable to Shoalhaven.
.2 must make its determination on the basis of the submissions of the parties, including documents and witness statements, and the Expert's own expertise; and
.3 must issue a certificate in a form the Expert considers appropriate, stating the Expert's determination and giving reasons, within 16 weeks, or as otherwise agreed by the parties, after the date of the letter of engagement of the Expert referred to in clause 75.2 of the General Conditions of Contract."
The terms "Expert", "Expert Determination" and "Issue" were all defined in the General Conditions by reference to their usage in cll 73 and 75. Specifically, the term "Expert Determination" was defined as:
"The process of determination of an Issue by an Expert, under clause 75 and the procedure in Schedule 6 (Expert Determination Procedure)."
This claim for a variation related to additional under-boring of sheds, gardens, trees and driveways that Firedam said it could not have been aware of at the time of its tender. Firedam claimed compensation based on 659.5 metres of under-boring and an extension of time of 33 days.
This claim related to additional costs said to have been incurred by Firedam "as a consequence of encountering extremely hard rock". Firedam claimed an extension of time of 22 days in relation to this variation.
This claim related to a realignment of the transfer main pipeline. Firedam claimed an extension of time of 90 days in relation to this variation.
Part of the claim to variation 10(a), which was defined by reference to the length of the additional under-boring works, was granted. Out of a total length of 659.5 metres claimed, the Expert determined that Firedam was entitled to compensation for 28 metres characterised as variation. He also found Firedam entitled to compensation for 138 metres attributable to breaches by Shoalhaven. The sum was 166 metres. Firedam had not substantiated its claim for delay in relation to the under-boring. The Expert therefore declined to make a determination of an extension of time. The Expert also found that Firedam had encountered materially adverse site conditions within the meaning of cl 41.2 of the General Conditions but held that its rights to an extension of time on that account had been extinguished because of its failure to give the written notice required by cl 41.
Firedam was entitled to additional costs incurred by reason of encountering extremely hard rock and to an extension of time of at least 22 days. The Expert rejected Shoalhaven's submission that Firedam had failed to comply with contractual procedures conditioning its entitlement to the extension of time. However, Firedam was not awarded delay costs under cl 55 as none had been "expressly claimed".
No amount was awarded for variation 62. Firedam had not demonstrated its actual costs of the realigned line, nor provided a calculation of the reasonable allowance for the under-boring in the original location. The claimed extension of 90 days was refused as Firedam had "not provided any reasoned support" for it.
. There was no inconsistency between the reasons of the Expert for rejecting Firedam's claim for an extension of time pursuant to variation 10(a) and his reasons for allowing an extension of time of nine days in the exercise of the discretion conferred on Shoalhaven by cl 54.6. The Expert was dealing with different claims, based on different criteria and calling for different findings[20].
. The Expert had used Shoalhaven's power to extend time under cl 54.6 in order to arrive at a reasonable and fair means by which general damages, the subject of Shoalhaven's cross-claim, could be calculated[21].
. The Expert determined the nine day extension so that there would be a benchmark against which Shoalhaven's claim could be assessed[22].
. By parity of reasoning Firedam's submissions in relation to variation 62 were rejected. In light of the rejection of its claims in relation to variations 10(a) and 62, it did not press its claims in relation to variation 12[23].
. The Expert Determination in relation to variation 10(a), that a delay of nine days should be attributed to Shoalhaven, was inconsistent with his finding, in relation to that variation, that Firedam had not discharged its onus of showing that delay for a defined period had occurred and that the additional work required caused delay in reaching completion[24].
. The Expert Determination in relation to variation 62, granting an extension of 89 days pursuant to cl 54.6, reflected a finding of fact inconsistent with the Expert's conclusion in dealing with Firedam's claims[25].
. It could be assumed, without deciding, that the Expert had the power to grant an extension of time under cl 54.6 - that proposition was not in issue[26].
. The Expert's extension of time under cl 54.6 was granted because of a variation or breach of contract by Shoalhaven, which would have attracted the application of cl 55.1. Yet he awarded no delay costs under cl 55.1 to Firedam[27].
. The Expert did not tell Firedam why it was not entitled to delay costs and thus "failed to give proper reasons for his decision"[28]. The Determination did not answer the contractual description[29].
"when there is an unexplained discrepancy in his conclusions concerning some of those issues, he has not provided reasons for his determination as a whole."
The discrepancy identified by Campbell JA was the Expert's determination that nine days of delay were attributable to Shoalhaven with no explanation of the Expert's failure to allow that nine days as an extension of time when assessing variation 10(a). The Expert had failed to fulfil his obligation of "giving reasons" because the reader of his reasons was left wondering about what construction he had put on cl 54.6[31].
"The evident advantage of an expert determination of a contractual dispute is that it is expeditious and economical. The second attribute is a consequence of the first: expert determinations are, at least in theory, expeditious because they are informal and because the expert applies his own store of knowledge, his expertise, to his observations of facts, which are of a kind with which he is familiar."[36]
It appears to have been an unstated premise in the proceedings leading to this appeal that the contractually binding effect of the Determination between the parties was conditional upon the giving of reasons as required in cl 4 of Sched 6 to the General Conditions. In this case it was held by the Court of Appeal that the reasons for the Determination disclosed an inconsistency and did not account for it. The question whether there was an unexplained inconsistency is a threshold question. If answered in the negative, the further question whether the reasons were, on that account, insufficient to support a binding Determination will not arise.
.2 must make its determination on the basis of the submissions of the parties, including documents and witness statements, and the Expert's own expertise; and
.3 must issue a certificate in a form the Expert considers appropriate, stating the Expert's determination and giving reasons, within 16 weeks, or as otherwise agreed by the parties, after the date of the letter of engagement of the Expert referred to in clause 75.2 of the [General Conditions].
.2 If a certificate issued by the Expert contains a clerical mistake, an error arising from an accidental slip or omission, a material miscalculation of figures, a mistake in the description of any person, matter or thing, or a defect of form, then the Expert must correct the certificate."
"An award, subject to the Arbitration Act and to any contrary criterion in the arbitration agreement, is final and binding on the parties to the agreement (s 28). The award may order specific performance of a contract if the Supreme Court would have power to decree specific performance (s 24). By leave of the Supreme Court, judgment may be entered in terms of an award and an award may be enforced in the same manner as a curial judgment or order to the same effect (s 33). The Supreme Court is empowered by s 44 to remove an arbitrator who has misconducted the proceedings or who is incompetent or unsuitable to deal with the particular dispute.
These statutory provisions indicate that the making of an award in arbitration proceedings is more than the performance of private contractual arrangements between the parties which yields an outcome which rests purely in contract. They also suggest the importance which the provision of reasons by arbitrators has for the operation of the statutory regime. That statutory regime involves the exercise of public authority, whether by force of the statute itself or by enlistment of the jurisdiction of the Supreme Court. It also ... displays a legislative concern that the jurisdiction of the courts to develop commercial law not be restricted by the complete insulation of private commercial arbitration."
".1 [Firedam] will be entitled as an adjustment to the Contract Price to its direct, reasonable additional costs (including costs of delay or disruption), necessarily and unavoidably incurred by [Firedam] in dealing with materially adverse Site Conditions, from the date of provision to [Shoalhaven] of the written notice required by clause 41.2, having taken all reasonable steps to minimise the costs in dealing with materially adverse Site Conditions; and
.2 [Firedam] may also be entitled to an extension of time for Completion under clause 54 for delays caused by the materially adverse Site Conditions occurring from the date of provision to [Shoalhaven] of the written notice required by clause 41.2."
"as a reasonable entitlement to [an extension of time] and in order to disentangle [Shoalhaven] caused causes of delay from other causes, so that [Shoalhaven] can have a determinate date from which general damages may be determined."
The date of completion so fixed by the Expert was 15 November 2007. Completion in fact had been achieved on 30 May 2008, and this was not denied by Firedam. The Expert went on to determine the cross‑claim on the footing that the breach by Firedam in failing to achieve due completion extended from 15 November 2007 to 30 May 2008.
"[Shoalhaven] may in its absolute discretion for the benefit of [Shoalhaven] extend the time for Completion at any time and for any reason, whether or not [Firedam] has Claimed an extension of time. [Firedam] is not entitled to an extension of time for Completion under this clause 54.6 unless [Shoalhaven] exercises its discretion to extend the time for Completion."
"They are distinct claims based on different criteria and they call for different findings. [The Expert], in dealing with the cross‑claim by Shoalhaven, on a proper interpretation of his reasons, was referring to the power to extend time under Clause 54.6 in order to arrive at a reasonable and fair means by which general damages, the subject of Shoalhaven's cross‑claim, could be calculated."
Kanivah Holdings Pty Ltd v Holdsworth Properties Pty Ltd (2002) 11 BPR 20,201 at 20,208-20,209 [61]. ↑
Bremer Handelsgesellschaft mbH v Westzucker GmbH (No 2) [1981] 2 Lloyd's Rep 130 at 132-133; Halifax Life Ltd v The Equitable Life Assurance Society [2007] 1 Lloyd's Rep 528 at 542 [85]. ↑
Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314 at 331-337 per McHugh JA; Holt v Cox (1997) 23 ACSR 590 at 596-597; AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd (2006) Aust Contract Reports ¶90‑241 at 89,425-89,426 [51]-[54]. ↑
Firedam Civil Engineering Pty Ltd v Shoalhaven City Council [2010] NSWCA 59. ↑
cf Capricorn Inks Pty Ltd v Lawter International (Australasia) Pty Ltd [1989] 1 Qd R 8 at 39‑40. ↑
cf Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314; Holt v Cox (1997) 23 ACSR 590; Kanivah Holdings Pty Ltd v Holdsworth Properties Pty Ltd (2002) 11 BPR 20,201. ↑
Shoalhaven City Council
Firedam Civil Engineering Pty Limited
(2005) 31 WAR 187
(1985) 1 NSWLR 314