[This headnote is not to be read as part of the judgment]
The appellant (the lessee) was the lessee under a lease with the first respondent (the lessor) for the development and operation of a vineyard. Clause 4.26(b) of the lease made provision for circumstances where the productivity of the premises was affected by a natural disaster. The clause had two limbs. The first involved consideration of whether production had been reduced by more than 50% of average production capacity, as defined in the lease. The second involved consideration of whether production capacity had been so reduced. If these limbs were satisfied, cll 4.26(h) to (j) applied. If the lessor and lessee could not agree on certain matters regarding circumstances where productivity was affected by a natural disaster, either party could refer the matter to an expert under cl 4.26(d). Under cl 4.26(f), the expert could issue a final determination as to the calculation of the reduction of production or production capacity, whether the reduction was due to a natural disaster and the remedial work necessary to restore production capacity.
In October 2013, a severe frost occurred in the area in which the vineyard was situated, causing a substantial diminution in the production of grapes for the 2014 vintage year. As a consequence, the lessee invoked cl 4.26, asserting that the volume of grapes capable of being produced in the vineyard had been reduced by more than 50% of average production capacity. In June 2014, the issue was referred to the expert, the second respondent, under cl 4.26(d).
In October 2014, the expert issued a determination that although a natural disaster had occurred, any resulting reduction of production or production capacity was less than 50% of average production capacity. The expert determination was made on the basis that, as to the first limb of cl 4.26(b), 2014 production had to be compared with average production capacity. In relation to the second limb, the expert compared prefrost production capacity for 2014 with average production capacity.
The lessee brought proceedings in the Supreme Court seeking to have the expert determination set aside and declarations as to the correct construction of cll 4.26(b) and (f). The primary judge dismissed the summons on the basis that the expert determination was not reviewable and the expert's determination was correct, although he reached his conclusion in a different fashion to the expert. The lessee appealed against both of these conclusions.
The Court held (Bathurst CJ, Beazley P and McColl JA agreeing), allowing the appeal and remitting the matter to the expert for determination in accordance with the Court's reasons:
Issue 1: The correct construction of cll 4.26(b) and (f)
1. On the basis of the words used by the parties, considered in the context of the lease as a whole, and the purpose and object of cl 4.26, as it appeared from the lease, if reduction of production capacity was in issue, cl 4.26 required a comparison of pre-disaster production capacity for that year. If the difference exceeded 50% of average production capacity, then cll 4.26(h) to (j) applied. Thus, the expert and primary judge were in error in their construction of cl 4.26: [88], [90] (Bathurst CJ); [92] (Beazley P); [93] (McColl JA).
Issue 2: Was the expert's determination reviewable
1. Whether the expert's determination was reviewable depended on whether the determination was made in accordance with the contract, i.e., whether or not the expert carried out the task which he or she was contractually required to undertake. If the expert in fact carried out that task, the fact that he or she made errors or took irrelevant matters into account would not render the determination challengeable. If the expert did not perform the task, but rather performed some different task, or carried out the task in a way not within the contractual contemplation of the parties, objectively ascertained, then the determination would be liable to be set aside: [74]-[75] (Bathurst CJ); [92] (Beazley P); [93] (McColl JA).
Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314; AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd [2006] VSCA 173; Holt v Cox (1997) 23 ACSR 590; Shoalhaven City Council v Firedam Civil Engineering Pty Ltd [2011] HCA 38; 244 CLR 305
1. Questions of mixed fact and law and pure questions of law can be left for the determination of an expert. While it is a matter of contractual construction in each case, parties are more likely to have left to an expert matters involving discretion or opinion, rather than matters of objective fact: [76] (Bathurst CJ); [92] (Beazley P); [93] (McColl JA).
Downer Engineering Power Pty Ltd v P & H Minepro Australasia Pty Ltd [2007] NSWCA 318; AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd [2006] VSCA 173; WMC Resources Ltd v Leighton Contractors Pty Ltd [1999] WASCA 10; 20 WAR 489
1. The fact that an expert determination is said to be final and binding makes little difference to whether the determination is reviewable. To the extent that the decision is made in accordance with the terms of the contract, it will be final and binding. To the extent that it is not, it will be subject to review: [85] (Bathurst CJ); [92] (Beazley P); [93] (McColl JA).
AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd [2006] VSCA 173
1. In making an assessment under cl 4.26(f), the expert was required to determine the manner in which the formula in cl 4.26(f) operated. However, the contract did not reveal an intention that the parties would be bound if the expert misapplied this formula. Thus, the decision-making authority of the expert did not extend to determining the construction in the formula so as to leave his or her decision on this issue unreviewable. The fact that the decision was said to be final and binding did not compel a contrary conclusion. Therefore, the primary judge erred in concluding that the expert's determination on the construction of the formula was incapable of review: [80]-[83], [85], [87] (Bathurst CJ); [92] (Beazley P); [93] (McColl JA).
Mercury Communications Ltd v Director General of Telecommunications [1994] CLC 1125; Mercury Communications Ltd v Director-General of Telecommunications (1996) 1 WLR 48