Friday 9 November 2007
DOWNER ENGINEERING POWER PTY LIMITED v P & H MINEPRO AUSTRALASIA PTY LIMITED
JUDGMENT
1 GILES JA: I agree with Hoeben J.
2 BASTEN JA: The resolution of this appeal turns largely upon the construction of clause 5 of the sale of business agreement entered into between the parties on 11 October 2002. (Clause 5 is set out in full by Hoeben J at [24] below). As the submissions demonstrated there were a number of levels of particularity at which the dispute could be considered and there were a number of separate entry points through different provisions contained in clause 5 of the agreement. However, the first question should be whether any, and if so which, of these disputes are properly to be resolved by the Court.
3 The parties provided in the agreement (clause 7) that the valuation of "work in progress" should take place after "Completion", which was to occur at 12 noon on 11 October 2002. The relevant adjustments following completion which did not constitute part of the agreement entered into, involved three figures. The first, which concerned "cash on hand" was unlikely to involve any dispute. The second was identified as "deferred tax asset" which was defined as a percentage of employee entitlements. Those entitlements were also to be taken into account as an element of "accepted liabilities" which may have involved elements subject to disputation. The third item concerned "work in progress" which became the subject of the present dispute.
4 The basis of calculation of figures to be included in the completion statement was identified in clause 5.3, as was the time by which the completion statement was to be delivered by the seller (the Appellant) to the buyer (the Respondent).
5 Clause 5 allowed for disagreements between the parties as to the figures to be inserted in column 2 of the completion statement and made provision in clause 4.4 for their resolution. The clear effect of clause 5.4 was that the figures to be included in column 2 were to be "final and binding on the parties". That result was to occur by one of three methods. First, the parties were required to use all reasonable endeavours to reach agreement on the figures and, if they were agreed, the agreed figures would be final and binding: paragraphs (a) and (b). If the parties did not agree, the figures contained in column 2 of the completion statement could nevertheless become final and binding as the result of the occurrence of one of two events, which were intended to cover the field of possibilities. Which event operated depended upon whether one of the parties referred the matters in dispute to a valuer for determination pursuant to clause 5.5, within a specified period. If the dispute were referred to a valuer within that period, the valuer's written determination was to be final and binding on the parties: clause 5.5(d). If the dispute were not referred to a valuer, by the end of the specified period, the values contained in the draft completion statement supplied by the seller were to be final and binding on the parties: clause 5.4(d).
6 In the present case, there was no agreement and there was no referral to a valuer pursuant to clause 5.4(c), by either party. Accordingly, pursuant to clause 5.4(d), the figures contained in the draft statement provided by the Appellant were described as "final and binding on the parties".
7 On this reasoning, the Appellant would have made out its contractual entitlement and would succeed on the appeal. The Respondent sought to avoid this conclusion by contending that the document provided to it by the Appellant on 8 November 2002 was not a "completion statement" for the purposes of clause 5.3 and accordingly the provisions of clause 5.4 were not engaged.
8 The statement was said not to comply with the requirements of clause 5.3 because it failed to include in column 2 the figure for work in progress identified in the inventory of work agreed upon at the conclusion of the stocktake, pursuant to clause 5.2(b). The Appellant replied that it was entitled to include amounts additional to the valuation which had been included in the inventory of work because the inventory was based upon a physical verification of the work done and did not take account of items which could properly be included by application of the factors set out in clause 5.3(b).
9 It may thus be seen that the dispute was one concerning the proper construction of clause 5 of the agreement. The relevant question was thus reduced to whether a dispute as to the construction and operation of clause 5 itself constituted a matter which the agreement contemplated would be referred to the valuer. If referral of a dispute involving such an issue were covered by the agreement, the Respondent could not escape the operation of clause 5.4(d). The answer to that question turned upon the construction of clause 5.4(c) which it is convenient to set out:
"If either party does not agree, within the period referred to in clause 5.4(a), that the column 2 of Completion Statement has been prepared on the basis provided for in this agreement, the Buyer or Seller (as the case may be) may, at any time within 10 Business Days after the end of that period, refer the matters in dispute to the Valuer for determination in accordance with clause 5.5."
10 Leaving to one side for present purposes the reference to clause 5.5, it is clear that matters in dispute which may be referred must involve the question whether column 2 "has been prepared on the basis provided for in this agreement". It is clear that the phrase "Completion Statement" is the document prepared by the seller under clause 5.3: it is defined in these terms in clause 1. (In clause 5.4(d), it is referred to as "the draft Completion Statement", but nothing turns on this variation in terminology.) No doubt there are various reasons why the completion statement prepared by the seller may not have been prepared "on the basis provided for in this Agreement" but in the absence of some clear indication to the contrary, it is impossible to read this language as excluding a requirement that the valuer form a view as to the construction of relevant elements in the agreement, in order to determine the dispute as to its operation. The present dispute falls precisely within the objective meaning of that phrase: it is a dispute as to whether the agreement required the seller to insert the figure agreed upon as part of the inventory of work in progress under clause 5.2(b) or whether it was entitled to include additional amounts in its calculations. That dispute, which occupied a number of hours in this Court, could have been described with complete accuracy as a dispute as to whether column 2 of the completion statement had been prepared on the basis provided for in the agreement.
11 The only potential source of contrary indication was the requirement that the valuer determine the matters in dispute "in accordance with clause 5.5". The relevant part of clause 5.5 is to be found in paragraph (a), which provided:
"The party referring a matter to the Valuer for determination under clause 5.2 or clause 5.4 must instruct the Valuer to make the determination in accordance with the requirements set out in clause 5.3(b) and to complete the determination as soon as practicable."
12 Clause 5.3(b), excluding an irrelevant qualification, provided:
"The parties agree that … column 2 of the Completion Statement must be completed on a basis consistent with (in order or [of?] priority):
(1) the 30 June 2002 figures (and accompanying notes) in column 1 of the Completion Statement …;
(2) the accounting polices described in schedule 9; and
(3) the Accounting Standards."
13 Two inferences were sought to be derived from this provision by the Respondent. The first, being the more general, was that the exercise to be undertaken by the valuer was to be an accounting exercise. The second and more specific inference was that the same accounting exercise was expected to apply to the preparation of the inventory of work in progress to be agreed for the purposes of clause 5.2(b), which might itself be the matter of referral to the valuer, in a case of dispute, pursuant to clause 5.2(c) and clause 5.5.
14 It is convenient to deal with the latter (particular) argument first. That argument, whether right or wrong, involves the construction of the agreement and is another way of stating the question whether column 2 of the completion statement provided by the Appellant was in fact prepared on the basis provided for in the agreement. For present purposes it is therefore the first (general) argument which is relevant.
15 The Respondent's contention must be that the final words of clause 5.4(c) demonstrate that the parties only envisaged a dispute as to the matters of accounting arising from the application of clause 5.3(b). However, if that were the intention, the broad language contained in clause 5.4(c) as to whether column 2 had been prepared on the basis provided for in the agreement, could readily have been recast as a dispute as to whether column 2 had been prepared in accordance with clause 5.3(b) of the agreement. An alternative construction is that the final words of that paragraph, picking up par (a) from clause 5.5, were intended to ensure that the valuer was bound to apply clause 5.3(b), as were the parties to the agreement, in undertaking a relevant accounting exercise. It would not, on that approach, necessarily follow that no other disputes were expected to arise or, if they did arise, to be capable of referral to the valuer.
16 One reason for supposing that matters for referral were not restricted to accounting exercises arises from the right of the buyer who disagreed with "any part of the inventory of work in progress" to refer the matter to the valuer. The primary purpose of the stocktake (which resulted in the inventory of work in progress) was to undertake a physical verification of work in progress: there is no reason to suppose that the buyer could not dispute some element of the physical verification and refer such a matter to the valuer for determination. The language of clause 5.4 would appear to mirror the language of clause 5.2 to the extent that each appears to envisage that any sort of dispute as to the steps to be taken in preparation of the completion statement might be referred to the valuer.
17 It is well-established that the effect of a determination by a valuer depends upon the construction of the contract pursuant to which the referral takes place: see Legal & General Life of Australia Ltd v A Hudson Pty Ltd (1985) 1 NSWLR 314 (Mahoney, Priestley and McHugh JJA) followed in Holt v Cox (1997) 23 ACSR 590; 15 ACLC 645, Strang Patrick Stevedoring Pty Ltd v James Patrick & Co Pty Ltd (1993) 32 NSWLR 583 (Giles J), Goldspar Australia Pty Ltd v The Council of the City of Sydney [2001] NSWCA 246 (Giles JA, Beazley and Stein JJA agreeing) and by the Victorian Court of Appeal in AGL Victoria Pty Ltd v SPI Networks (Gas) Pty Ltd [2006] VSCA 173 (Nettle JA, Maxwell P and Bongiorno AJA agreeing) at [43]-[44] and [51]-[54]. (Nettle JA in the last case, at [52], sought to draw an analogy between a challenge to the determination of an expert appointed under a contract and judicial review of an administrative decision based on the concept of jurisdictional error. The analogy is evocative, but may need to be treated with caution: administrative action is not necessarily reviewable only for jurisdictional error; further, there may be limits as to the extent to which an administrative officer can be vested with power to determine questions of law. Different principles apply in relation to the construction of a contract between private parties.)
18 The operation of these principles may be tested in the present case by asking whether, if the particular disputes now under consideration had been referred to a valuer, his or her determination would have been binding. The indications in the contract relied upon by the Respondent do not demonstrate that it would not have been. Accordingly, a dispute of the kind now in issue was within the contemplation of the parties as one which could properly be referred to the valuer. In the absence of such a referral, the Respondent is bound by the figures contained in column 2 of the completion statement, as provided by the Appellant.