55037/2009 FIREDAM CIVIL ENGINEERING PTY LIMITED v
SHOALHAVEN CITY COUNCIL
JUDGMENT
1 HIS HONOUR: This is an application by the plaintiff ("Firedam") for declarations that an Expert Determination arising from a dispute with the defendant ("Shoalhaven") is not binding on it and that, on the proper construction of the contract between the parties, Firedam is entitled to commence legal proceedings against Shoalhaven.
2 The issue, briefly stated, is whether the declarations should be made.
How the issue arises?
3 Firedam as contractor and Shoalhaven as principal on 18 October 2005 entered into a contract in respect of the design and construction of a wastewater collection and transportation system for the Conjola Regional Sewage Scheme.
4 Disputes arose under the contract relating to variation claims by Firedam and consequential extension of time claims. Under the contract, disputes and issues arising must be referred for Expert Determination and there is a threshold amount which, if awarded, permits the parties to proceed to litigation. That amount is $500,000. In the present case, the amount of the determination by the Expert against Shoalhaven was marginally below this, being about $497,142.55.
5 The contract provides that unless a party has a right to commence litigation the parties must treat each determination of the Expert as final and binding and give effect to it (Clause 75.7). Under Clause 75.6, where the determination is under $500,000 then litigation can only be commenced within 56 days after receiving the Determination. In this case, the last date on which Firedam could commence legal proceedings was 12 May 2009. Assuming that Firedam had a contractual entitlement to bring the legal proceedings it is said that it is out of time because the proceedings were commenced on 15 May 2009.
6 The Expert engaged was Mr Neil Turner ("the Expert") who was appointed by letter on or about October 2008. The purpose of such a provision is to achieve certainty and finality and to avoid the time, expense and uncertainty of resorting to litigation. For this reason in recent years there has been a trend against setting aside expert determinations except in limited circumstances. This "hardening" of the courts' attitude to reviewing determinations was referred to by the New South Wales Court of Appeal in Holt v Cox (1997) 23 ACSR 590 at 596.
7 Six unresolved issues were referred for determination relating to claims by Firedam for variations and consequential extensions of time. The three presently relevant issues are Variation 10a for additional under-boring work, Variation 12 for rock blasting and Variation 62 for a transfer main re-alignment. Shoalhaven has made a cross-claim seeking damages for delayed completion.
8 Under Schedule 6 to the contract, a procedure is prescribed for the Expert which details the matter that must be determined and the role of the Expert. Those provisions are as follows:
" Questions to be determined by the Expert
The Expert must determine for each Issue the following questions (to the extent that they are applicable to the Issue ):
Is there an event , act or omission, which gives the claimant a right to compensation, or otherwise assists in resolving the Issue if no compensation is claimed:
under the Contract
for damages for breach of the Contract, or
otherwise in law?
If so:
what is the event , act or omission?
on what date did the event, act or omission occur?
what is the legal right which gives rise to the liability to compensation or resolution otherwise of the Issue ?
is that right extinguished, barred or reduced by any provision of the Contract, estoppel, waiver, accord and satisfaction, set-off, cross-claim, or other legal right?
In the light of the answers to clauses 1.1.1 and 1.1.2 of this Expert Determination Procedure:
what compensation, if any, is payable from one party to the other and when did it become payable?
applying the rate of interest specified in the Contract, what interest, if any, is payable when the Expert determines that compensation?
if compensation is not claimed, what otherwise is the resolution of the Issue ?
The Expert must determine for each Issue any other questions identified or required by the parties, having regard to the nature of the Issue ." (Emphasis added)
9 The role of the Expert is prescribed by the procedure as follows:
" Role of Expert
The Expert:
acts as an Expert and not as an arbitrator;
must make its determination on the basis of the submissions of the parties, including documents and witness statements, and the Expert's own expertise; and
must issue a certificate in a form the Expert considers appropriate, stating the Expert's determination and giving reasons, within 16 weeks, or as otherwise agreed by the parties, after the date of the letter of engagement of the Expert referred to in clause 75.2 of the General Conditions of Contract."
10 This procedure is important because the basic submission for Firedam is that the Expert's determination in the present case is not in accordance with the terms of the contract with the consequence that there has been no expert determination and therefore there is no bar to the commencement of legal proceedings by Firedam. It is alleged Mr Turner did not use his own expertise in relation to the grant of an extension of time in respect of the variations which he found and also because he did not address the question of compensation arising from a finding that the act of Shoalhaven caused part of the delay to completion. Firedam alleges that there were inconsistent findings made by Mr Turner in relation to extensions of time and that no reasons were given to explain the inconsistencies.
11 For the purpose of deciding the issues raised before me, it is convenient to deal with the application by Firedam for an extension of time in relation to Variation 10a and the counter-claim by Shoalhaven for damages due to delayed completion. The reasoning of Mr Turner on these two questions in relation to Variation 10a also crystallised the substance of the case brought by Firedam in respect of Variation 62 and it is common ground that if adverse findings are made with respect to Variations 10a and 62 then Variation 12 is not pressed.