Decision
47 The referee was entitled to accept evidence from senior management of Abigroup that, if they had known of the project management agreement, they would have sought one or more of three specified changes, and that failing Peninsula's agreement to one or more of these matters, they would not have recommended that Abigroup enter into the building contract and it would not have done so; and the primary judge was correct to accept this finding.
48 However, the referee's finding that not to disclose the existence of this "agency agreement" was "misleading and deceptive, though not necessarily intentionally" is in a different position. It can be said that this is also a question of fact, even if it amounts to a finding that the conduct in question falls within s.52 of the Trade Practices Act: cf. Ambulance Service of NSW v. Daniel [2000] NSWCA 116 at [47]-[52] and cases there cited. However, this finding was plainly based on a view as to the true legal effect of the project management agreement. With reference to this agreement, the referee said this:
Whatever the actual effect might be, I would be in no doubt that a further obligation to be Peninsula's agent in all matters in relation to the design and construction of the project would tilt the balance to some extent in Peninsula's favour.
49 The primary judge took a similar view, to the effect that the project management agreement meant that East Asia was Peninsula's agent in all matters in relation to the design and construction of the project.
50 The authorities referred to by Mr. Douglas and Mr. Walker are not altogether clear as to whether a person in the position of a superintendent of a building contract is the owner's agent in exercising all the functions of the superintendent. However, in my opinion the better view (supported by Perini, Dixon, Egan and London Borough of Merton, and not refuted by Sutcliffe) is that the superintendent is the owner's agent in all matters only in a very loose sense, and that, when exercising certifying functions in respect of which the superintendent must act honestly and impartially, the superintendent is not acting as the owner's agent, in the strict legal sense. In my opinion, this is confirmed by the consideration that the issue of a certificate by the superintendent does not bind the owner to any extent beyond what is prescribed by the building contract itself, so that the owner can challenge such certificates. If the superintendent was acting as the owner's agent in the strict sense, the issue of the certificate would be an act done by the owner through its agent, which the owner could not then challenge.
51 In my opinion, it is an erroneous construction of the project management agreement to treat it as requiring East Asia to act as Peninsula's agent, in the strict sense, in all matters in relation to the design and construction of the project, including in relation to the certification function under the building contract. The project management agreement authorises East Asia to act as Peninsula's agent, but it requires East Asia to act in a professional manner in various functions, including the function of administering the building contract and in the certification role under that contract (clauses 2.5 and 5.1.16). To the extent that this requirement is inconsistent with East Asia acting as Peninsula's agent, in the strict sense, it prohibits East Asia from doing so. There is nothing in the authorisation of East Asia to act as agent which affects this prohibition.
52 There is some force in Mr. Walker's submission that this is just one judge's view, contrary to the view taken by the only commercial people to have given an opinion on the matter, including the referee, as well as that of the primary judge; and that even if my view were correct as a matter of fine legal interpretation, what was important was the effect of this undisclosed agreement on commercial people.
53 However, I do not think this submission should prevail.
54 In my opinion, for conduct to be misleading or deceptive, it must be such as is apt to mislead or deceive in some non-trivial respect; so that to make out a case under s.52, Abigroup needed to show that the non-disclosure of the project management agreement was apt to do just that. It was clear from the building contract itself that the Superintendent was to be engaged and paid by Peninsula, and was to act in some respects as Peninsula's agent; and the question was whether the undisclosed agency agreement relevantly changed this position. If my construction of the project management agreement is correct, the respect in which non-disclosure was apt to mislead or deceive could only be that there was an undisclosed agreement the true effect of which had no relevant impact on East Asia's exercise of its role as Superintendent, but which could be read by commercial people as having such impact.
55 No such case was suggested on the pleading. Furthermore, suppose that Peninsula had expressly represented to Abigroup that its agreement with East Asia required East Asia to perform various services in connection with the project for Peninsula for reward, including supervision of the building contract, but did not impinge on East Asia's obligation to act honestly and impartially in the discharge of its functions as superintendent. Accepting as I do that this is the true effect of the agreement, I do not believe that such an express representation could possibly be misleading or deceptive, even if commercial people might wrongly come to a different view. The present situation, where no express representation was made, is in my opinion a fortiori. Accordingly, in my opinion the referee's finding as to misleading conduct is vitiated by an error of law, and should be set aside.
56 My approach discloses a further problem for Abigroup, which links with the next topic, namely causation of loss. The referee accepted Abigroup's evidence that, if it had known of the agreement, it would have sought one or more of three modifications to the arrangement (identified as (a), (b) and (c) in par.17 of Mr. Abbott's evidence set out above), and if Peninsula did not agree to one or more of them, would not have gone ahead at all. However, the referee did not make any finding as between these alternatives. Officers of Peninsula were called, and they did not give evidence one way or the other as to whether they would have acceded to any of the three modifications which Abigroup said it would have sought, and they were not cross-examined on this matter. In those circumstances, Mr. Walker submitted that the primary judge was correct to infer that Peninsula would not have acceded to any of the modifications and that there would have been no building contract.
57 In my opinion, although this inference was clearly available in relation to the first two of the alternatives, (a) and (b), it was not available in relation to the third, (c). If as I believe the true effect of the project management agreement was in accordance with the third modification, there is every reason to believe that Peninsula would have agreed to modification (c), to the extent of making the true position clearer. The onus was on Abigroup to prove causation, and although the evidentiary onus can shift and although I am prepared to say it did shift in relation to the first two alternatives, I do not think it shifted in relation to the third. To put this another way, I do not think that Abigroup showed any basis for drawing an inference that Peninsula and East Asia would not have agreed specifically that the arrangement between them not impinge on East Asia's obligation to exercise its functions as Superintendent honestly and impartially, when this was already the true effect of the agreement between them.
58 In my opinion, there is also a difficulty faced by Abigroup arising from the referee's failure to find that the non-disclosure was intentional. I accept Mr. Douglas' submission that, in so far as what is alleged to be misleading or deceptive conduct arises from Peninsula's refraining from disclosing the project management agreement, Abigroup needs a finding that this refraining was not inadvertent. Mr. Walker submitted that it was sufficient that Peninsula knew of the project management agreement, acted intentionally in negotiating, and did not disclose the agreement in circumstances where this was not due to mistake. However, in my opinion the requirement in s.4(2)(c) that a refraining be otherwise than inadvertent requires that there be actual advertence to the question of whether something should be done or not and the formation of an intention that it not be done. I think this is in accordance with the decision in Semrani.
59 Mr. Walker relied on the alternative submission that Peninsula's misleading and deceptive conduct was the entry into the building contract without making the disclosure, and this was a "doing" and not a mere "refraining". However, there was no finding by the referee that the positive conduct was itself misleading or deceptive, or any identification of how it was misleading and deceptive. In my opinion, if Abigroup wished to rely on the positive conduct as being misleading, it would have been necessary to allege and prove what representation was conveyed by the positive conduct. For example, Abigroup could have alleged and sought to prove that the positive conduct conveyed that, apart from the relationship between the two companies constituted by their common directors and overlapping ownership, there was nothing inhibiting East Asia from performing its duties as superintendent honestly and impartially. Abigroup gave no evidence as to what it understood to have been conveyed or represented by the positive conduct, but only gave evidence that if some disclosure had been made, it would have acted differently. That evidence, in my opinion, was appropriate to a case of "refraining", but not to a case of "doing".
60 It follows from my above reasons that in my opinion also, there was no breach by Peninsula of cl.23 by reason of the project management agreement.
61 In so far as the referee found that the Superintendent did not assess variation claims reasonably or fairly, that is not a breach of contract for which Peninsula could be liable. In so far as the referee found that Peninsula failed to ensure that the Superintendent arrived at a reasonable measure of time in respect of delays caused by Peninsula and the Superintendent, this would be a breach of cl.23 by Peninsula. However, the only damages that might flow from these matters were identified by the referee as "most likely to lie in an award of interest for the late and wrong decisions on variations". That seems to relate to the matter in respect of which there was no breach by Peninsula itself, and there does not seem to be any support in the referee's report for damages flowing from the breach by Peninsula: Peninsula's breach affected only the question of extensions of time, to which I will come.