[This headnote is not to be read as part of the Judgment]
The appellant, Probuild Constructions (Aust) Pty Ltd (Probuild), was the head contractor for the renovation of the Tank Stream Hotel in Hunter Street, Sydney. On 19 May 2014 it subcontracted with the first respondent, DDI Group Pty Ltd (DDI), to carry out works related to the renovation (Subcontract). The Date for Practical Completion of the works was 5 January 2015. As events turned out, the Date of Practical Completion was 28 May 2015, 144 days later.
Clause 41 of the Subcontract provided a mechanism by which DDI could seek an extension of time in the event it envisaged a delay in carrying out the works, including delay caused by a variation to the Subcontract works. Clause 41.9 conferred on Probuild a discretionary power to extend time, notwithstanding that DDI was not entitled to or had not claimed an extension of time.
DDI sought, pursuant to the process for which the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOP Act) provides, to recover monies it said were due under the Subcontract. In the course of the SOP Act process, a number of documents were exchanged in which, as was accepted, both parties referred incorrectly to clauses of the Subcontract. DDI lodged a Payment Claim pursuant to s 13 of the SOP Act for an amount of $2,175,267 (including GST). A large component of the Payment Claim was in respect of variations DDI said Probuild directed it to undertake after the Date for Practical Completion.
Probuild provided a Payment Schedule pursuant to s 14 of the SOP Act in which it said, relevantly, that DDI's claim should be reduced to nil by reason of a set-off for liquidated damages in the amount of $2,328,998 calculated by reference to the 144 days between the Date for Practical Completion and the Date of Practical Completion. The liquidated damages claim was based on DDI's failure to complete the work by the Date for Practical Completion. Probuild asserted that DDI had not been granted nor was entitled to an extension of time.
DDI made an application for adjudication of its Payment Claim pursuant to s 17 of the SOP Act. In its supporting documents, DDI gave notice that its adjudication documents should be treated as both a Notice of Delay, pursuant to cl 41.5 of the Subcontract, and an extension of time claim, pursuant to cl 41.8 of the Subcontract. Clause 41.8 was not a mechanism for extending time. DDI argued this was intended to be a reference to cl 41.9. In other documents, DDI asserted it was Probuild that instructed it to depart from the Subcontract construction program and that Probuild was clearly aware of the delays by reason of the revised construction programs it issued. It denied Probuild's liquidated damages claim was reasonable and asserted it was an invention of convenience.
In its adjudication response, Probuild reiterated that DDI had no entitlement to any extension to the Date for Practical Completion.
The second respondent, Ian Hillman, was appointed as the adjudicator pursuant to s 19 of the SOP Act. He rejected Probuild's claim for liquidated damages. He noted that, based on DDI's submissions, there were contract variations being directed by Probuild and submitted for approval by DDI as late as 9 June 2015. He concluded that it appeared "totally inconsistent and unreasonable" for Probuild to be directing DDI to perform significant additional work under the Subcontract after the original Date for Practical Completion and then making a claim for liquidated damages against DDI for following Probuild's express directions. He held that, while there may have been DDI caused delays, he was not satisfied that Probuild was entitled to a liquidated damages claim for the total 144 days.
Probuild commenced proceedings in the Supreme Court by way of summons seeking an order in the nature of certiorari quashing the adjudicator's purported determination. Probuild's essential complaint was that the determination was infected by a denial of procedural fairness (natural justice). It contended that the adjudicator rejected its liquidated damages claim on bases which neither party had notified to the other or contended for, and which the adjudicator had not notified the parties. Probuild also asserted that, had the adjudicator intended to so act, he should have invited the parties to make further submissions, as he was empowered to do under s 21(4) of the SOP Act.
The primary judge dismissed Probuild's summons. His Honour held there had been no denial of procedural fairness and that the adjudicator had "dealt with Probuild's argument as made". On appeal, Probuild contended that in so holding, the primary judge erred. Probuild argued that underpinning the adjudicator's rejection of its liquidated damages claim was the application of the prevention principle. Probuild reiterated the submission made at first instance that as the adjudicator had not notified either party of his intention to apply that principle, there had been a breach of the fundamental requirement of natural justice of the right to a hearing.
DDI submitted that when regard was had to the totality of material before the adjudicator and the submissions made by the parties, the adjudicator had afforded Probuild procedural fairness and the primary judge did not err in so finding.
The principal issue on appeal was whether the adjudicator applied the prevention principle and, if so, whether in doing so he had denied Probuild procedural fairness.
Held, dismissing the appeal per McColl JA (Beazley ACJ and Macfarlan JA agreeing):
The essence of the prevention principle is that a party cannot insist on the performance of a contractual obligation by the other party if it itself is the cause of the other party's non-performance: [114].
Spiers Earthworks Pty Ltd v Landtec Projects Corp Pty Ltd (No 2) (2012) 287 ALR 360; (2012) 28 BCL 282; [2012] WASCA 53 applied.
The prevention principle applies to delays in practical completion caused by variations resulting from the act or default of the principal. In the context of delaying variations, whether ordered before or after the due date for completion, the prevention principle is grounded upon considerations of fairness and reasonableness: [115].
SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VR 391; Turner Corp Pty Ltd (recv & mgr apptd) v Austotel Pty Ltd (1997) 13 BCL 378; Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No 2) [2007] EWHC 447; [2007] BLR 195 referred to.
The operation of the prevention principle can be modified or excluded by extension of time provisions, such as cll 41.5 - 41.6 of the Subcontract. This is, in essence, because if a party fails to exercise a contractual right which would have negated the effect of the preventing conduct, the preventing conduct can no longer be said to be the cause of the delay: [118].
Turner Corp Pty Ltd (recv & mgr apptd) v Austotel Pty Ltd (1997) 13 BCL 378 applied.
Turner Corporation Ltd (in liq) v Co-ordinated Industries Pty Ltd (1994) 11 BCL 202; Turner Corporation Ltd (in prov liq) v Co-ordinated Industries Pty Ltd (1995) 12 BCL 33; Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd [1970] 1 BLR 111 referred to.
Probuild was obliged to exercise the discretionary extension of time power conferred by cl 41.9 honestly and fairly having regard to the underlying rationale of the prevention principle: [128].
Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211; (2002) 18 BCL 322; 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491 referred to.
The application of the prevention principle was squarely in issue in the adjudication process having regard to the documents which were before the adjudicator. Probuild's submissions reflected a recognition that by virtue of the fact it sought to claim liquidated damages in respect of the period after the Date for Practical Completion during which it had directed DDI to undertake variations, such directions were capable of being regarded as acts of prevention invoking the prevention principle which would, or could, disentitle it to its liquidated damages claim. In that context, Probuild sought to avoid the operation of the prevention principle by submitting, in effect, that it was DDI's failure to seek an extension of time which prevented performance of the contractual obligations within time: [132], [134].
In its adjudication documents, DDI had asserted that Probuild had engaged in what might prima facie be regarded as acts of prevention, all of which caused DDI to be delayed: [134].
In those circumstances, it was open to the adjudicator to find Probuild had failed to establish its liquidated damages claim. Probuild was not denied procedural fairness: [144].