© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2005] NSWCA 49
Court of Appeal (NSW)
2005-03-03
Handley JA, Santow JA
Original judgment source is linked above.
Falgat Constructions Pty Ltd v Equity Australia Corporation Pty Ltd [2005] NSWCA 49 CITATION: This decision has been amended. Please see the end of the judgment for a list of the amendments.
JUDGMENT OF: Handley JA at 1; Santow JA at 33; Pearlman AJA at 34
DECISION: 1. Leave to appeal granted subject to the notice of appeal being filed within 14 days if not already filed.; 2. Appeal allowed.; 3. The injunction granted by Naughton DCJ on 26 November 2004 is dissolved.; 4. The notice of motion of 12 November 2004 is dismissed with costs.; 5. The opponent is to pay the claimant's costs of the proceedings in this Court and is to have a certificate under the Suitors' Fund if qualified.
CATCHWORDS: BUILDING AND ENGINEERING CONTRACTS - effect of statutory remedies under Building and Construction Industry Security of Payment Act 1999 - BUILDING AND CONSTRUCTION INDUSTRY - Statutory remedies of builder - whether concurrent pursuit of statutory and common law remedies permissible - INJUNCTIONS - anti-suit - whether concurrent pursuit of statutory and common law remedies permissible under statute - whether vexatious or oppressive - D
LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999
CASES CITED: Toubia v Schwenke (2002) 54 NSWLR 46
Falgat Constructions Pty Ltd (Claimant) PARTIES: Equity Australia Corporation Pty Ltd (Opponent)
J J Graves SC/F Clark (Claimant) COUNSEL: G Sirtes (Opponent)
Julie A Orsini (Claimant) SOLICITORS: Stephen Wawn & Associates (Opponent)
IN THE SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL CA 41052/04
HANDLEY JA SANTOW JA PEARLMAN AJA
3 MARCH 2005 FALGAT CONSTRUCTIONS PTY LTD v EQUITY AUSTRALIA CORPORATION PTY LTD CATCHWORDS
BUILDING AND ENGINEERING CONTRACTS - effect of statutory remedies under Building and Construction Industry Security of Payment Act 1999 BUILDING AND CONSTRUCTION INDUSTRY - statutory remedies of builder - whether concurrent pursuit of statutory and common law remedies permissible
INJUNCTIONS - anti-suit - whether concurrent pursuit of statutory and common law remedies permissible under statute - whether vexatious or oppressive FACTS
The builder sued the proprietor in the District Court for debt and damages under a contract for the construction of a residential building. The action was stayed pending provision of security of costs. The builder then commenced proceedings under the Building and Construction Industry Security of Payment Act 1999 (the Act). A District Court judge granted an anti-suit injunction under s 46 of the District Court Act restraining the builder from pursuing its remedies under the Act. The builder applied for leave to appeal. HELD: (1) Under the Act the statutory rights are only adjudicated on an interim basis and as such they supplement the rights of the parties under the general law. Consecutive proceedings under the Act and the general law are clearly permissible. In this case the concurrent statutory claim was not vexatious and oppressive. (2) The Act contemplates that a court will be free to undertake a final adjudication. Proceedings under the Act may interfere with court proceedings if they are commenced or carried on close to trial, but this was not the position in the present case. (3) There was no case for election; and the builder was entitled to pursue concurrently its statutory and common law remedies. (4) There is no express provision in the Act that requires statutory proceedings to be completed before court proceedings are commenced, and the general provisions of the Act do not have this effect. ORDERS
IN THE SUPREME COURT OF NEW SOUTH WALES COURT OF APPEAL CA 41052/04
HANDLEY JA SANTOW JA PEARLMAN AJA
3 MARCH 2005 FALGAT CONSTRUCTIONS PTY LTD v EQUITY AUSTRALIA CORPORATION PTY LTD Judgment 1 HANDLEY JA: The Court has before it a summons for leave to appeal from a decision of Naughton DCJ on 26 November 2004. The Judge granted an anti-suit injunction under s 46 of the District Court Act 1973 restraining Falgat Constructions Pty Ltd, a builder, from pursuing its statutory remedies under the Building and Construction Industry Security of Payment Act 1999 (the Act). The builder was the plaintiff in District Court proceedings commenced by it on 8 April 2004 claiming $414,935.69 from the defendant proprietor arising from the construction of residential buildings at 23-25 Chesterfield Parade, Bronte. 2 On 2 July 2004 Hughes DCJ ordered the plaintiff to provide $50,000 security for the costs of the District Court proceedings which he stayed until the security was provided. The plaintiff did not provide such security but filed a summons for leave to appeal. This summons was listed for hearing before this Court today, but the Registry was notified that the claimant would not be proceeding and this morning the Court made an order dismissing it with costs. 3 On 13 October the plaintiff builder initiated proceedings under the Act by serving a payment claim under s 13(1) seeking payment of $232,114.30. This represented a little over half of the plaintiff's claim in the District Court proceedings. 4 The parties have taken the necessary steps to prosecute or defend this claim up to the s 19 stage. The nominating authority has referred the builder's adjudication application to an adjudicator who has not yet accepted the appointment. It was common ground that the statutory proceedings remain on foot and could be validly continued should this Court dissolve the injunction granted by the primary judge. 5 The injunction was granted in proceedings commenced by notice of motion dated 12 November, which was heard on 25 and 26 November. On 26 November Naughton DCJ ordered; "That the plaintiff be, and is hereby restrained from proceeding further with its current statutory adjudication application under [the Act] pending the final determination of the within District Court proceeding or until further order of this Court or the Supreme Court". 6 On 30 November the plaintiff filed a summons for leave to appeal. Proceedings have been expedited and the parties have been fully heard so that should leave be granted the Court is in a position to finally dispose of these proceedings. 7 The primary judge held the District Court had power under s 46 of its Act to grant the anti-suit injunction and there were four grounds for the grant of such an injunction. These were:
09/03/2005 - "Pearlman AJ" should be "Pearlman AJA" - Paragraph(s) 34
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Falgat Constructions Pty Ltd
Equity Australia Corporation Pty Ltd
(2002) 54 NSWLR 46