The reference date issue
18Clause 5.1 of the Agreement provided: -
" ... [the plaintiffs] shall pay [Halo] a project management fee ("the Fee") calculated in accordance with Item 6 of the Schedule."
19Clause 5.2 of the Agreement provided: -
"The Fee shall be payable by [the plaintiffs] to [Halo] as provided for in accordance with Item 7 of the Schedule hereto."
20Item 7 of the Schedule to the Agreement provided: -
"Tax invoices issued by [Halo] on or before the 7th day of each month must be paid by [the plaintiffs] by the 21st day of each month (or the next business day should the 21st not be a business day).
21Section 8 of the Act provides that: -
(1) On and from each reference date under a construction contract, a person:
(a) who has undertaken to carry out construction work under the contract... is entitled to a progress payment.
(2) In this section, reference date, in relation to a construction contract, means:
(a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be made in relation to work carried out or undertaken to be carried out... under the contract...". (emphasis added)
22It was common ground that, by reason of these matters, the "reference date" for the purposes of the Agreement was the seventh day of each month.
23Between 9 November 2012 and 3 December 2012, Halo issued 10 payment claims on 10 different dates. All of those payment claims purported to have been made under the Act. Each of the payment claims was in respect of work said to have been done in 10 separate months, namely February to November 2012 inclusive.
24Section 8(1) of the Act provides that "on and from" each reference date a person who has undertaken to carry out construction work under a contract is entitled to a progress payment. I read s 8(1) to mean that the progress payment to which the person who has undertaken construction work under the contract is entitled is one in respect of all of the construction work done at that reference date.
25Section 13(1) of the Act provides that a person who is or claims to be entitled to a progress payment may serve "a" payment claim on the person liable to make the payment.
26Section 13(5) of the Act provides that a claimant cannot serve more than one payment claim "in respect of" each reference date. I read the words "in respect of" in s 13(5) to mean "on and from" (consistently with the wording of s 8(1)) so that the effect of the sub-section is that a claimant may only serve one payment claim "on and from" each reference date.
27That reading of s 13(5) is consistent with the stated object of the Act as set out in s 3: -
"(1) The object of this Act is to ensure that any person who undertakes to carry out construction work... under a construction contract is entitled to receive, and is able to recover, progress payments in relation to the carrying out of that work...
(2) The means by which this Act ensures that a person is entitled to receive a progress payment is by granting a statutory entitlement to such a payment regardless of whether the relevant construction contract makes provision for progress payments." (emphasis added)
28Further, each of s 17(1), s 17(3)(f), s 22(2)(c), and s 22(2)(d) of the Act, contemplate that only one payment claim at a time can be submitted to adjudication. Thus, s 17(1) provides that a claimant may apply for adjudication of "a" payment claim. Section 17(3)(f) provides that an adjudication application must identify "the" payment claim to which it relates. Section 22(2)(c) and (d) oblige the adjudicator to consider only (amongst other things) "the" payment claim and payment schedule to which the application relates.
29Mr Goldstein submitted, and I accept, that these provisions make clear it was not possible for a party in Halo's position to "bank" reference dates and serve multiple payment claims following one reference date for work done in previous months.
30In that regard Mr Goldstein referred to the observations of McDougall J in Rail Corporation of NSW v Nebax Constructions [2012] NSWSC 6 at [43] and [44] as follows: -
"Nonetheless, it seems to me, when one considers the structure of the Act as a whole, it is reasonably clear that there should be one only application for adjudication of any one payment claim. Section 8(1) gives the right to a progress payment. Section 13 of the Act gives to a person claiming an entitlement to a progress claim the right to serve a payment claim. Section 14 provides for a response, through a payment schedule. Section 17 provides for 'adjudication of a payment claim' where, among other things, a payment schedule is provided under which the scheduled amount is less than the claimed amount.
...
It seems to me that, because s 13(5) prevents... the service of more than one payment claim per reference date per construction contract, and because the right to adjudication 'of a payment claim' is clearly referable to a payment claim that complies with the various requirements of s 13, there can only be one adjudication application for any particular payment claim for any particular contract." (emphasis added)
31McDougall J's reference to s 13(5) preventing service of more than one payment claim "per" reference date is, in my opinion, consistent with my conclusion at [26].
32At one stage in his submissions Mr Bland, who appeared for Halo, accepted that it was not possible for a party in Halo's position to "bank" reference dates. Later in his submissions, Mr Bland resiled from that concession but did not offer any positive submission refuting those made by Mr Goldstein.
33Rather, Mr Bland submitted that the 10 payment claims served by Halo between 9 November 2012 and 3 December 2012 should be seen as one payment claim, made progressively and by 10 instalments, over that period. Mr Bland submitted: -
"We can serve all of our invoices together as one continuous facsimile or we can serve them on consecutive days or we can serve them as they are prepared and put."
34Mr Bland submitted that it followed that Halo had not acted inconsistently with s 13(5) of the Act as it had served but one payment claim in respect of the relevant reference date, 7 November 2012.
35I do not accept that submission.
36Although each of the 10 payment claims were comprised by two separate invoices (and thus might each be considered one payment claim, rather than two; see for example Rail Corporation of NSW v Nebax Constructions at [31] per McDougall J and Alan Conolly & Co v Commercial Indemnity [2005] NSWSC 339 at [16], [20] and [23] per Macready M), the 10 payment claims made between 7 November 2012 and 3 December 2012 appear to be separate payment claims. They were made on different dates, each for a different month and called for payment on different dates. They are not expressed to be 10 individual components of one overarching claim. Further, in its adjudication application, Halo described the last four payment claims (being the Payment Claims which it referred to adjudication) as each being separate payment claims.
37My conclusion is that by reason of s 13(5), Halo was only entitled to serve one payment claim "in respect of" (that is, on and from) the reference date of 7 November 2012. That one claim was the first that it served, on 9 November 2012 (in respect of the work done in February 2012). That payment claim was paid. It was not possible for Halo to serve any further payment claims "in respect of" the reference date of 7 November 2012. Therefore, the purported payment claims of 26 November 2012, 28 November 2012, 30 November 2012 and 3 December 2012, being those referred to the Adjudicator, were not "payment claims" within the meaning of the Act.
38Accordingly, the Adjudicator had no jurisdiction to deal with the matter and the Determination is void.