Did the adjudicator determine Olympia's payment claim?
11It is convenient to deal first with the question whether the adjudicator determined Olympia's payment claim. However, before dealing with that issue, I should mention one preliminary matter. There was a suggestion in Knight Lawyers' letter dated 17 February 2011 that Hansen Yuncken could not raise with the adjudicator the jurisdictional issue because that issue was not raised by its payment schedule. That submission was not seriously pursued at the hearing. In any event, in my opinion, it has no substance. Section 20(2B) of the SOP Act provides:
The respondent cannot include in the adjudication response any reasons for withholding payment unless those reasons have already been included in the payment schedule provided to the claimant.
That section prevented Hansen Yuncken from raising in its adjudication response a reason for not making a payment that was not raised in its payment schedule. It did not prevent it from raising grounds on which it was asserted that the adjudicator did not have jurisdiction to make a determination.
12In relation to the question whether the adjudicator determined Olympia's claim, Olympia puts its case in two ways. First, it says that the adjudicator did not have power to determine his own jurisdiction. Second, Olympia submitted that, on its face, the decision of the adjudicator was not a determination of its claim. Rather, the adjudicator reached a conclusion that he did not "have jurisdiction to determine the adjudication application" and that the "adjudication application is invalid". These decisions, whatever they were, were not a determination of the claim. That conclusion, according to Olympia, was supported by the fact that the adjudicator reached his decision before Hansen Yuncken served its adjudication response and before the time for it to do so had expired. That was despite the fact that s 21(1) of the SOP Act provides:
An adjudicator is not to determine an adjudication application until after the end of the period within which the respondent may lodge an adjudication response.
13Hansen Yuncken, on the other hand submitted that the letter dated 22 February 2011 from ASC communicating the adjudicator's decision satisfied the requirements of s 22 of the SOP Act. That section relevantly provides:
(1) An adjudicator is to determine:
(a) the amount of the progress payment (if any) to be paid by the respondent to the claimant (the adjudicated amount ), and
(b) the date on which such amount became or becomes payable, and
(c) the rate of interest payable on any such amount.
(2) In determining an adjudication application, the adjudicator is to consider the following matters only:
(a) the provisions of this Act;
(b) the provisions of the construction contract from which the application arose,
(c) the payment claim to which the application relates, together with all submissions (including relevant documentation) that have been duly made by the claimant in support of the claim,
(d) the payment schedule (if any) to which the application relates, together with all submissions (including relevant documentation) that have been duly made by the respondent in support of the schedule,
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates.
(3) The adjudicator's determination must be in writing and must include:
(a) the reasons for the determination, and
(b) the basis on which any amount or date has been decided, if, before the making of the determination, either the claimant or the respondent requests the adjudicator to include those matters in the determination.
In Hansen Yuncken's submission, the determination of the adjudicator in substance was that the amount of the payment claim was nil because the payment claim was not validly made under the SOP Act and that determination was within the scope of the adjudicator's function. Hansen Yuncken claimed that that conclusion was supported by the decision of the Queensland Supreme Court in John Holland Pty Ltd v Schneider Electric Buildings Australia Pty Ltd [2010] QSC 159. In that case, an adjudicator had concluded that he did not have jurisdiction to determine a claim because only one reference date was available to the claimant and the claimant had previously served a claim in respect of that reference date. Section 17(5) of the Queensland Act, like s 13(5) of the SOP Act, provides that a claimant cannot serve more than one payment claim in relation to each reference date. Applegarth J held that the adjudicator's decision was a decision that fell within s 26 of the Queensland Act (which is in substantially the same terms as s 22 of the SOP Act). Consequently, the claimant was bound by the adjudicator's decision on that point and it could not therefore serve a further claim. Hansen Yuncken also claimed that its submission was supported by the decision of the Court of Appeal in Downer Construction (Australia) Pty Ltd v Energy Australia (2007) 69 NSWLR 72.
14I do not accept Hansen Yuncken's submissions. In my opinion, the adjudicator's decision was not a determination of the type contemplated by s 22 of the SOP Act. Rather, it was a decision whether the SOP Act applied to the claim made by Olympia having regard to where the relevant construction work was carried out. The adjudicator had to make a decision about that question because it was an essential precondition to the exercise of the powers granted to him by the Act. But is does not follow that, in making that decision, he was exercising a power to make a determination of the type required by s 22. As Spigelman CJ explained in Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 272 ALR 750 at [36]:
The issue to be determined is whether the adjudicator had jurisdiction to determine an "application" which had been made without compliance with the mandatory (in a negative sense) terminology of s 17(2) [which relevantly states in para (a) that an adjudication application cannot be made unless the claimant has notified the respondent within 20 business days immediately following the due date for payment of the claimant's intention to apply for adjudication of its claim]. The issue is not, contrary to some of the submissions made, whether the adjudicator had jurisdiction to determine that s 17(2)(a) had been complied with. That section is not addressed to the adjudicator and is not a matter which he is directed to "determine" within s 22(1) of the Act. It may be that it is a matter which he must "consider" as one of the "provisions of the Act" within s 22(2)(a). However, that section confers no power to determine the issue.
15The decision of the Court of Appeal in Downer Construction (Australia) Pty Ltd v Energy Australia [2007] NSWCA 49 ; (2007) 69 NSWLR 72 is not inconsistent with the point made by Spigelman CJ. Before dealing with that decision, it is important to put it in context. In Brodyn Pty Limited v Davenport [2004] NSWCA 394; (2004) 61 NSWLR 421, the Court of Appeal held that relief in the nature of certiorari was not available to quash a determination of an adjudicator on the grounds of jurisdictional error. In reaching that conclusion, the court thought that a legislative intention to minimise court involvement in the operation of the SOP Act could be discerned from the terms of the statute. However, the Court of Appeal thought that there were a number of essential preconditions to an adjudication determination which, if they did not exist in a particular case, meant that the determination was void. Those preconditions included:
1 The existence of a construction contract between the claimant and the respondent, to which the Act applies (s 7 and s 8).
2 The service by the claimant on the respondent of a payment claim (s 13).
3 The making of an adjudication application by the claimant to an authorised nominating authority (s 17).
4 The reference of the application to an eligible adjudicator, who accepts the application (s 18 and s 19).
5 The determination by the adjudicator of this application (s 19(2) and s 21(5)), by determining the amount of the progress payment, the date on which it becomes or became due and the rate of interest payable (s 22(1)) and the issue of a determination in writing (s 22(3)(a)). ([2004] NSWCA 394; (2004) 61 NSWLR 421 at [53] per Hodgson JA.)
16Brodyn was overruled by the Court of Appeal in Chase Oyster Bar Pty Ltd v Hamo Industries Pty Ltd [2010] NSWCA 190; (2010) 272 ALR 750. In that case, the Court of Appeal held, following the decision of the High Court in Kirk v Industrial Relations Commission (NSW) [2010] HCA 1; 239 CLR 531, that the court did have power to grant relief in the nature of certiorari against an adjudicator for jurisdictional error. Clearly, Downer Construction (Australia) Pty Ltd v Energy Australia [2007] NSWCA 49 ; (2007) 69 NSWLR 72 was decided before Chase Oyster Bar and it must be read in that light.
17In Downer Construction, the contract was for the construction of a tunnel to carry electrical cables. A clause in the contract entitled the contractor, Downer, to be paid extra costs if it encountered a "Latent Condition" during tunnelling operations. Downer made a claim under that clause following water ingress into the tunnel. The claim was expressed in different terms in the adjudication application. However, the adjudicator concluded that the claim and the application raised substantially the same issues. Energy Australia took issue with that conclusion and submitted that, since the adjudication application was sufficiently different from the payment claim, the application was not for adjudication of the claim or the adjudicator's determination of the application was not a determination of the claim. On that question, Giles JA (with whom Santow JA and Tobias JA agreed) said (at [87]):
In my opinion, determination of the parameters of the payment claim is a matter for the adjudicator, and a reasonable but erroneous decision by the adjudicator does not invalidate the determination. In the present case, in determining the amount of the progress payment (if any) to be made it was for the adjudicator to decide whether the water ingress fell within latent conditions for the purposes of the contract, and the parameters of the payment claim in that respect. He did so. As to both, it could not be said that the adjudicator's decision was without foundation, and if the adjudicator addressed the matters and came to his decisions, even if other decisions could have been come to, he did what the Act required - he determined the adjudicated amount.
What is clear from this passage is that the court took the view that the question whether the claim and application raised the same issue was one of the matters that the adjudicator was required to decide in order to reach a determination under s 22. It was not an issue that went to his jurisdiction either in the narrow sense considered in Brodyn or the broader sense considered in Chase Oyster Bar . The position in the present case is quite different since, even on the narrow approach adopted in Brodyn , the question whether there was a construction contract to which the Act applies - that is, a construction contract which did not involve construction work carried out outside New South Wales or related goods and services supplied in respect of construction work of that type - is a question that goes to whether the adjudicator can exercise jurisdiction. It is not a question the determination of which forms part of the exercise of that jurisdiction.
18I accept that it is difficult to reconcile the conclusions of the previous paragraph with statements made by Applegarth J in John Holland . However, the decision in that case did not turn on whether the original adjudicator's decision was a decision under s 26 of the Queensland Act. Rather, it turned on the extent to which a decision of an adjudicator was binding in a later adjudication. The resolution of that issue did not depend simply on characterising the decision in relation to the earlier adjudication application as falling within s 26 of the Queensland Act. It also turned on principles of issue estoppel and abuse of process. In any event, John Holland was decided before Chase Oyster Bar . In my opinion, the point made by Spigelman CJ in the latter case is correct and I should follow it.
19In my opinion, the conclusion that the adjudicator did not make a determination under s 22 of the SOP Act is supported by what the adjudicator actually did. He was asked to make a decision on the question of jurisdiction before he accepted his nomination. Faced with that request, he accepted his nomination but, on the same day, caused ASC to write to the parties to say that he accepted that he did not have jurisdiction. He did not wait for an adjudication response as he was required to do before making a determination under s 22. Nor does it appear that he examined the payment claim or the payment schedule in arriving at his decision. Rather, what he relied on was the fact that the construction site was located outside New South Wales. It seems clear from those facts that the adjudicator - correctly, in my view - was not purporting to make a determination under s 22.