© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2017] NSWCA 53
Court of Appeal (NSW)
2017-03-03
Beazley ACJ, Basten JA, Leeming JA
Original judgment source is linked above.
men of the City of London v Cox (1867) LR 2 HL 239 The Mayor and Aldermen of the City of London v London Joint Stock Bank (1881) 6 App Cas 393 Thomas A Edison Ltd v Bullock (1913) 15 CLR 679 Town & Country Sport Resorts (Holdings) Pty Ltd v Partnership Pacific Ltd (1988) 20 FCR 540 Walter Rau Neusser Oel Fett AG v Cross Pacific Trading Ltd [2005] FCA 955 Young v Cooke [2017] NSWCA 33 Texts Cited: A G Saddington, "Orders of Court and Garnishee Process" (1948) 21 Australian Law Journal 346
Chitty's Archbold's Practice of the Court of Queen's Bench (London, H Sweet, 1862) Vol 1
R Walker, The Practice of the Supreme Court of New South Wales at Common Law (4th ed 1958)
R Therry, Reminiscences of Thirty Years' Residence in New South Wales and Victoria (Royal Australian Historical Society, Sydney University Press (1863, facsimile edition 1974) Category: Principal judgment Parties: Fitz Jersey Pty Ltd (Applicant) Atlas Construction Group Pty Ltd (Respondent) Representation: Counsel: Mr M Christie SC/Mr B Kremer (Applicant) Mr I Roberts SC/Ms J Wright (Respondent)
Solicitors: Gillis Delaney Lawyers (Applicant) Bradbury Legal (Respondent) File Number(s): 2017/41629 Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Equity Division Citation: [2017] NSWSC 72 Date of Decision: 06 February 2017 Before: McDougall J File Number(s): 2017/15773
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
headnote [This headnote is not to be read as part of the judgment] In December 2010 the applicant, Fitz Jersey Pty Ltd ("the developer"), engaged the respondent, Atlas Construction Group Pty Ltd ("the builder"), to design and construct a major development project at Mascot in Sydney. On 15 November 2016, the builder served a final payment claim on the developer pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW) ("Security of Payment Act") for an amount in excess of $10.5 million plus interest. On 29 November 2016, the developer served a payment schedule asserting that no money was owing to the builder. An adjudicator determined that the payment claim was payable in full. As the developer did not make payment within the five business days specified under the Act, the builder obtained an adjudication certificate, which it filed in the Supreme Court. The result was a judgment debt, on the basis of which the builder then obtained a garnishee order. On 27 January 2017, the garnishee order was served on the developer's bank, which duly paid the amount owing from the developer's account. Prior to the adjudication certificate being filed, the developer had commenced proceedings under s 69 of the Supreme Court Act 1970 (NSW) challenging the validity of the adjudication determination. The developer did not, however, seek interlocutory relief, or an undertaking from the builder not to take steps to enforce the determination. On learning of the payment from its bank account, it sought orders that the garnishee order be set aside and the money repaid. That application was dismissed by McDougall J in the Equity Division. The questions before this Court were whether: (1) the builder was required to notify the developer that an order for judgment debt had been obtained before taking steps to enforce it; (2) in applying ex parte for a garnishee order with respect to the judgment debt, the builder was required to notify the court that the developer had commenced proceedings to review the underlying adjudication determination; and (3) the primary judge erred in refusing to set aside the garnishee order and order repayment of the amount paid by the garnishee. The Court (Beazley ACJ, Basten JA and Leeming JA), granting leave to appeal but dismissing the appeal, held: In relation to question (1):
Judgment
Statutory scheme
Chronology of relevant events
Reasoning of primary judge
Duty to give notice of registration of certificate - (grounds 2(d), (e))
Duty of candour on ex parte application (grounds 2(a)-(c))
(1) alleged error
(2) legal principles
(3) application of principles
Approach to discretionary relief (ground 1)
Conclusion
Obligation to notify the developer that a certificate had been filed?
Obligation to inform Court of commencement of proceedings?
Endnotes
Amendments 23 March 2017 - [11] Changed "filed" to "serve" in last line. [74] Changed "here" to "there" in last sentence. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 23 March 2017
Fitz Jersey Pty Ltd
Atlas Construction Group Pty Ltd
[2008] QCA 397
[1912] HCA 72
(2009) 239 CLR 346
(2010) 78 NSWLR 393
(2002) 213 CLR 543
(1993) 32 NSWLR 662
(1936) 55 CLR 499
(2009) 240 CLR 319
(2007) 69 NSWLR 577
(1913) 15 CLR 679
(1988) 20 FCR 540
(2016) 90 ALJR 370
(2005) 223 CLR 1
(1912) 15 CLR 679
[2002] HCA 49