[2020] NSWCA 118
Court of Appeal (NSW)
2020-06-16
Bell P, Macfarlan JA, Leeming JA, Stevenson J
Original judgment source is linked above.
con Australia Pty Ltd (Respondent) Representation: Counsel: M Christie SC, D Hume (Applicants) I Roberts SC, D Byrne (Respondent)
Solicitors: Dentons Australia (Applicants) Piper Alderman (Respondent) File Number(s): 2020/163263 Publication restriction: Nil Decision under appeal Court or tribunal: Supreme Court of New South Wales Jurisdiction: Equity Division - Technology and Construction List Citation: [2020] NSWSC 659 Date of Decision: 29 May 2020 Before: Stevenson J File Number(s): 2019/165506; 2019/205661
[Note: The Uniform Civil Procedure Rules 2005 provide (Rule 36.11) that unless the Court otherwise orders, a judgment or order is taken to be entered when it is recorded in the Court's computerised court record system. Setting aside and variation of judgments or orders is dealt with by Rules 36.15, 36.16, 36.17 and 36.18. Parties should in particular note the time limit of fourteen days in Rule 36.16.]
[This headnote is not to be read as part of the judgment] TFM Epping Land Pty Ltd and Katoomba Residence Investment Pty Ltd (the Developers) are judgment debtors of Decon Australia Pty Ltd (the Builder). The judgment debt is founded on the service of a payment claim by the Builder under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act) and the Developers' failure to serve a payment schedule in response. The judgment debt was entered as long ago as 11 October 2019. Following an unsuccessful appeal against the judgment, the Developers sought a stay of its execution. The Developers sought the stay on the basis that they are unable to pay the judgment debt, are insolvent if the judgment is not stayed and have a cross-claim in an amount exceeding the judgment debt. The primary judge refused the application for a stay of execution. The Developers sought leave to appeal, the application for which was heard concurrently with the appeal. The issues before the Court were:
Judgment
Procedural background
The Construction List proceeding
The SOP proceeding
The cross-claim is filed in the Construction List proceeding
The Act
The reasons of the primary judge
The dispositive "anterior matters"
Further consideration of serious question and balance of convenience
The Developers' submissions in support of leave and on the appeal
Consideration
Grosvenor has nothing to do with the Developers' application
The effect of s 32 of the Act
When may a stay of execution may be ordered on the application of the judgment debtor?
The practical effect of failing to obtain a stay of execution
The significance of delay
Conclusion
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 19 June 2020
TFM Epping Land Pty Ltd
Decon Australia Pty Ltd
(2004) 61 NSWLR 421
(2005) 62 NSWLR 385
(2018) 98 NSWLR 712
(1936) 55 CLR 499
(2002) 55 NSWLR 737
(2019) 99 NSWLR 317
(2019) 100 NSWLR 133
(2013) 82 NSWLR 268
(2002) 54 NSWLR 46
[1936] HCA 40