Goodwin Street Developments Pty Ltd v DSD Builders Pty Ltd
[2018] NSWCA 276
At a glance
Source factsCourt
Court of Appeal (NSW)
Decision date
2018-10-17
Before
Basten JA, Leeming JA, White JA, McDougall J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Background circumstances
- On 2 March 2018 the owner issued the builder with a notice to remedy defaults, pursuant to clause Q1.1 of the contract. On the basis that the defaults had not been remedied, and the builder had failed to show within 10 working days reasonable cause why they could not be remedied, the owner issued a notice pursuant to clause Q1.2 on 19 March 2018 terminating the contract.
- On 30 April 2018 the builder served a payment claim on the owner with a reference date of 15 March 2018, in the amount of $727,256. On 14 May 2018 the owner provided a payment schedule in response, denying liability for the amount claimed and stating that the builder owed it a substantial sum, with the result that the schedule amount was $0.
- On 28 May 2018 the builder applied for adjudication of the payment claim pursuant to s 17 of the Security of Payment Act. The owner failed to lodge an adjudication response within the time fixed by s 20, with the result that the adjudicator was required not to consider the response: s 21(2). The information provided by the owner was therefore limited to the payment schedule dated 14 May 2018, to which were attached certificates of the contract administrator setting out an assessment of the cost of completing the works, and setting out amounts payable to the owner, which included an amount for the "rectification of defective & incomplete works" ($280,000) and an amount for "rectification of damage/replacement of stolen items" ($551,382). These sums were broken up into their constituent elements.
- On 15 June 2018 the adjudicator provided her determination awarding the builder an amount of $265,510. The reasons provided by the adjudicator ran to some 22 pages. In substance, issue was taken with 10 paragraphs (one page) under the heading "The respondent's off-setting claims". It will be convenient to set out so much as is necessary from that part of the adjudication determination when considering the substance of the challenge raised by the owner.