© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2018] NSWCA 276
Court of Appeal (NSW)
2018-10-17
Basten JA, Leeming JA, White JA, McDougall J
Original judgment source is linked above.
Background circumstances
Statutory scheme
Legal issues
Impugned reasoning of adjudicator
Grounds of appeal
Conclusion
Endnotes
Goodwin Street Developments Pty Ltd
DSD Builders Pty Ltd
Richard Green Construction Lawyers (Appellant) CCS Legal Pty Ltd (First Respondent) File Number(s): 2018/253475 Decision under appeal Court or tribunal: Supreme Court Jurisdiction: Equity Division Citation: [2018] NSWSC 1229 Date of Decision: 6 August 2018 Before: McDougall J File Number(s): 2018/193623
headnote [This headnote is not to be read as part of the judgment] Goodwin Street Developments Pty Ltd ("the owner") and DSD Builders Pty Ltd ("the builder") were parties to a construction contract. On 19 March 2018, the owner purported to terminate the contract. On 30 April 2018 the builder served a payment claim on the owner in the amount of $727,256. On 14 May 2018 the owner served a payment schedule in response of $0, stating that the builder owed it a substantial sum for rectification of defective works and damage, and replacement of stolen items. The builder applied for adjudication of the payment claim. The adjudicator provided her determination on 15 June 2018, awarding the builder an amount of $265,510. The owner commenced proceedings in the Equity Division seeking to have the determination quashed; the primary judge dismissed the proceedings. Section 10 of the Building and Construction Industry Security of Payment Act 1999 (NSW) relevantly provides: 10 Valuation of construction work and related goods and services (1) Construction work carried out or undertaken to be carried out under a construction contract is to be valued: … (b) if the contract makes no express provision with respect to the matter, having regard to: … (iv) if any of the work is defective, the estimated cost of rectifying the defect. The key issue on appeal was whether the adjudicator's determination was invalid for want of good faith. Lack of good faith was said to be established by the adjudicator's failure to apply s 10(1)(b) when valuing the construction work the subject of the payment claim. The Court (Basten JA, Leeming and White JJA agreeing) dismissed the appeal and held:
[2015] VSC 631
(2004) 61 NSWLR 421
(2008) 237 CLR 146
(2015) 230 FCR 385
(1986) 162 CLR 24
(2010) 243 CLR 164
(2016) 95 NSWLR 157
(1981) 151 CLR 170
(2004) 61 NSWLR 521
(2001) 51 NSWLR 589
(1979) 180 CLR 322
(1997) 42 NSWLR 70
(1979) 180 CLR 323
(2016) 95 NSWLR 147
(2002) 209 CLR 597
(1998) 196 CLR 329
(1997) 188 CLR 501
(2000) 204 CLR 82
(2004) 221 CLR 30
(2007) 232 CLR 189
(2001) 206 CLR 323
(2003) 77 ALJR 1088
[2001] HCA 30
[2002] HCA 11