Laing O'Rourke Australia Construction v H&M Engineering & Construction
[2010] NSWSC 818
At a glance
Source factsCourt
Supreme Court of NSW
Decision date
2010-07-28
Before
McDougall J, Dougall J
Source
Original judgment source is linked above.
Judgment (7 paragraphs)
Introduction: the claim and the adjudicator's reasoning 116 I have set out at [11] above the nature of the claim, and summarised the way the adjudicator dealt with it at [14] above. It is not necessary to give further details either of the claim or of the adjudicator's reasoning. The parties' submissions 117 Mr Corsaro submitted, in essence, that the adjudicator had abdicated his statutory function, and had decided the amount payable on a wholly arbitrary basis. According to Mr Corsaro, this meant that the adjudicator did not consider the claim, or deal with it in good faith, in the sense that those requirements have been discussed above. 118 Further, Mr Corsaro submitted, the adjudicator did not tell the parties that he was going to proceed in the way that he did, and offer them an opportunity to be heard on it. That, according to Mr Corsaro, amounted to a denial of natural justice. 119 Finally, Mr Corsaro submitted, by dealing with the claim in the way that he did, the referee overlooked, and did not deal with, LORAC's submissions on its individual constituents. That, he submitted, amounted to a further denial of natural justice. 120 In his submissions in reply, Mr Corsaro pointed out that, contrary to both the adjudicator's approach and the submissions for H&M, there were more reasons for LORAC's rejection of the claim (and the difference between the parties) other than that stated by the referee at para 213 ("Supervisor is included in mark up"). Mr Corsaro prepared a detailed analysis which showed that, of the 39 individual claims that were not treated as withdrawn or dealt with elsewhere by the adjudicator, eight had some other reason given for the difference between the parties. Mr Corsaro submitted that, in failing to deal with those individual grounds of dispute, the adjudicator had once again denied natural justice to LORAC, and failed to exercise his powers in good faith by giving appropriate consideration to the issues. 121 Mr Rudge submitted that the adjudicator had taken a common-sense approach to the problem, in circumstances where, as he had said, to deal with the disputes individually would have resulted in substantial cost to the parties (see para 225 of the determination). Mr Rudge submitted that this approach was justified, in particular, where there was a "common thread" between the individual claims. 122 In any event, Mr Rudge submitted, there was no material denial of natural justice. That was because, in the context of the subcontract amount and the value of payment claim 14, a difference of a little under $100,000.00, and the approach taken by the adjudicator, could not be regarded as material. Analysis 123 I do not think that the adjudicator failed to consider the payment schedule, or that he dealt with it in an unreasoned way. He took a practical approach to what he saw as being a very small part of the overall dispute. He gave reasons for his decision. Those reasons may not have involved attention to the detail of the payment claim and payment schedule, but the adjudicator explained why this was so. 124 Further, in a practical sense, it cannot be said that the result obtained by the adjudicator is capricious. It involved taking a somewhat arbitrary approach of, as he saw it, splitting the difference between the parties. 125 I accept that there may have been some denial of procedural fairness, when the adjudicator dealt with the claim in the way that he did in a manner for which neither party had contended, without giving them notice of his intention to do so. 126 If that conclusion were to have any consequence, in terms of relief, it would require consideration of the concept of materiality. In circumstances where the point is moot, I do not think that any further examination of it is necessary; on the contrary, I think that to embark upon some extended consideration of the point, by way of obiter dictum, would not be consistent with s 56 of the Civil Procedure Act 2005 (NSW). Discretion 127 There is no discretionary consideration relevant to the conclusion that I have reached in relation to claims 110, 115 and 122. Nor is there any point in considering, on a hypothetical basis, what might have been said in relation to the discretionary considerations relevant to claim 100, had I decided that there was a material denial of natural justice. Conclusion and orders 128 For the reasons that I have given, I conclude that the adjudicator denied natural justice in a material way to LORAC, and failed to perform his statutory obligations in good faith in the requisite sense, in relation to claims 110, 115 and 122. As I have indicated at [115] above, it follows from those conclusions that LORAC is entitled to relief of the kind sought and the return of the money that it has paid into Court. 129 The parties did not address on costs. However, I see no reasons why costs should not follow the event in the circumstances of this case. I shall reserve liberty to apply in respect of costs, in case either active party has a different view. 130 I make the following declaration and orders: