© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2024] NSWCA 63
Court of Appeal (NSW)
2024-03-12
Payne JA, Adamson JA
Original judgment source is linked above.
Introduction
Summary of background matters
The primary judgment summarised
The primary issues in this Court
Consideration and determination
(a) Leave to appeal
(b) The policy of the SOP Act
(c) Ground 1
(d) Ground 2
(e) Ground 3
(f) Re-exercise of discretion
Conclusion
Amendments 10 April 2024 - Applicant's representation updated. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 10 April 2024
McDonald
MAK Constructions and Building Services Pty Ltd
HEADNOTE [This headnote is not to be read as part of the judgment] In early 2022, the parties entered into a contract for residential building work (the Contract). The building work had progressed significantly by the time that the contract was terminated by the home owner (the owner) for breach. Around that time, the builder made a payment claim under ss 8, 9 and 13 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOP Act). The following day, the owner served in response a payment schedule pursuant to s 14 of the SOP Act. On 19 December 2022, and several weeks after the builder had made an application for adjudication of the disputed payment claim under s 17 of the SOP Act, the owner commenced proceedings against the builder in the NSW Civil and Administrative Tribunal (NCAT) for recovery of alleged rectification costs and costs to complete. Damages are claimed in the amount of $528,112.00. These proceedings were transferred to the District Court of NSW by consent in February 2023 (the District Court Proceedings). On 27 January 2023, the builder obtained an adjudication certificate under s 22 of the SOP Act in the amount of $246,493.20. The adjudication certificate was filed in the District Court as a judgment for debt in the amount of $246,695.20 pursuant to s 25 of the SOP Act. The only action taken by the builder around this time to enforce the judgment debt was to obtain various garnishee orders against Ms McDonald. The only amount recovered by the builder has been by way of a garnishee order on Macquarie Bank Ltd in the amount of $200.19. On 17 April 2023, the builder filed a notice of motion in the District Court Proceedings, seeking a stay of those proceedings until such time as the owner paid the judgment debt and the costs ordered on 8 March 2023 (in respect of the owner's withdrawn notice of motion to stay the judgment debt or alternatively, its enforcement). On 21 July 2023, the primary judge, Olsson SC DCJ, granted the stay. It was not until 6 months after the primary judge granted the stay that the builder took further steps to enforce the judgment debt by filing in the District Court on 29 January 2024 a notice of motion seeking a writ for the levy of property. The parties were agreed that this Court may determine for itself the merits of the builder's motion filed on 17 April 2023, rather than remit the matter to the District Court. On appeal, the principal issues were: (i) Whether leave to appeal should be granted. (ii) Whether s 32 of the SOP Act preserves the rights of parties to a construction contract to bring a claim for damages arising under the contract in circumstances where a stay of the proceedings is sought pending payment of a judgment debt obtained pursuant to s 25 of that Act. (iii) Whether the primary judge erred in exercising the discretion to stay the owner's proceedings. (iv) Whether this Court should exercise the discretion to stay the owner's proceedings. (v) Whether the primary judge failed to afford the owner procedural fairness with respect to her finding that the amended statement of claim was effectively a cross-claim and nullified the benefit provided by the SOP Act. The Court (Griffiths AJA, Payne and Adamson JJA agreeing) held, granting leave to appeal and allowing the appeal, with costs: As to issue (i) (1) Leave to appeal should be granted. The applicant (the owner) raises an issue of public importance and general application with reference to the need to reconcile the underlying policy of the legislative scheme to enable a builder to receive progress payments promptly, while preserving the common law rights of both parties in respect of the construction contract as provided for in s 32 of the SOP Act: at [35]. As to issue (ii) (2) The primary judge misconstrued s 32(3) of the SOP Act insofar as her Honour concluded that this provision endorsed a right to bring a claim at common law only after the judgment debt is satisfied. There is nothing in the legislative scheme to support such a qualification: at [49]. (3) The owner's right to bring a claim for damages arising under the Contract is expressly preserved by s 32(2) of the SOP Act: at [45]. The terms of s 32 are clear and state unequivocally that nothing in Pt 3 of the SOP Act affects any rights of a party to a construction contract and that nothing done under or for the purposes of Pt 3 affects any civil proceedings arising under a construction contract: at [50]. Samadi Developments Pty Ltd v SX Projects Pty Ltd [2015] NSWSC 1576 at [6]-[7] and Grant Constructions Pty Ltd v Claron Constructions Pty Limited [2006] NSWSC 369 at [11]-[13] approved. (4) Such a construction does not prevent the ordinary operation of the legislative scheme: at [57]. The circumstances of this case differ to cases in which an owner or developer seeks a stay of proceedings brought by a builder to enforce a judgment debt under the SOP Act: at [40]. Here, there is and was nothing stopping the builder from seeking to enforce the judgment debt: at [58]. TFM Epping Land Pty Ltd v Decon Australia Pty Ltd [2020] NSWCA 118 distinguished. As to issue (iii) (5) The primary judge's exercise of discretion to stay the proceedings miscarried as a result of her misconstruction and misapplication of s 32 of the SOP Act, as explained above, and for four other reasons: at [59]-[60]. First, her Honour failed to consider and assess the strength of the owner's case: at [60]. Secondly, her Honour erred in characterising the amended statement of claim as though it were a cross-claim: at [61]. Thirdly, her Honour erred in describing the amended statement of claim as effectively being a cross-claim, which is prohibited by s 15(4)(b)(i), in circumstances where s 15 had no application to this case: at [62]. Fourthly, the builder failed to take prompt and meaningful steps to enforce the judgment debt and offered no explanation for the 6 month delay in obtaining the writ for the levy of property, which sits very uncomfortably with the legislative policy of the SOP Act: at [63]-[64]. As to issue (iv) (6) The Court declined to stay the owner's proceedings: at [68]. First, a stay would be inconsistent with the rights preserved by s 32 of the SOP Act: at [69]. Secondly, the builder's failure to take prompt and meaningful steps to enforce the judgment debt weighs heavily against a stay being granted: at [70]. Thirdly, the financial hardship of the respective parties (depending on whether or not a stay is granted) was considered to be a neutral factor as each party would suffer some degree of hardship if unsuccessful: at [71]. Fourthly, there is no basis to find that the case is hopeless or lacking in reasonable prospects: at [72]. As to issue (v) (7) The primary judge's error in characterising the amended statement of claim as effectively being a cross-claim was substantive, not procedural: at [65].
[2008] QCA 397
(1994) 49 FCR 576
(2006) 228 CLR 152
(2019) 99 NSWLR 317
(2018) 264 CLR 1
[2006] HCA 63