In determining whether the Contractor is or will be delayed in reaching Practical Completion regard shall not be had to:
- whether the Contractor can reach Practical Completion by the Date for Practical Completion without an extension of time;
- whether the Contractor can, by committing extra resources or incurring extra expenditure, make up the time lost.
If the Contractor desires an extension of time for Practical Completion, the Contractor shall within 28 days after a delay occurs give the Superintendent a written claim setting out the facts on which the claim is based.
With the claim, or as soon as practical after giving the claim, the Contractor shall give the Superintendent written notice of the number of days extension claimed.
If the Contractor is entitled to an extension of time for Practical Completion the Superintendent shall, within 28 days after receipt of the notice of the number of days extension claimed, grant a reasonable extension of time. If within the 28 days the Superintendent does not grant the full extension of time claimed, the Superintendent shall before the expiration of the 28 days give the Contractor notice in writing of the reason.
Notwithstanding that the Contractor is not entitled to an extension of time the Superintendent may at any time before the issue of the Final Payment Certificate by notice in writing to the Contractor extend the time for Practical Completion for any reason.
A delay by the Principal or the failure of the Superintendent to grant a reasonable extension of time or to grant an extension of time within 28 days shall not cause the Date for Practical Completion to be set at large but nothing in this paragraph shall prejudice any right of the Contractor to damages.
35.6 Liquidated Damages for Delay in Reaching Practical Completion.
If the Contractor fails to reach Practical Completion by the Date for Practical Completion, the Contractor shall be indebted to the Principal for liquidated damages at the rate stated in the Annexure for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is terminated under Clause 44, whichever first occurs.
...