TURNER CORPORATION LTD v CO-ORDINATED INDUSTRIES PTY LTD
MEAGHER, SHELLER and POWELL JJA 30 May 1995, 24 July 1995 [1995] NSWCA 476
CONTRACT - COMPLETION CLAUSE EXTENSION OF TIME FOR COMPLETION OF CONTRACT - COSTS FACTS: On 1 November 1988 Turner Corporation Ltd (the contractor) and Co-ordinated Industries Pty Ltd (the principal) entered into a written contract for the erection and completion of a hotel development. Group Architects Pty Ltd was the 'superintendent' under the contract. The contract provided that the time for practical completion was 20 February 1990.