[30] Ibid. at [84].
[31] All the figures exclude GST.
[32] (2001) NSWLR 705.
[33] (1990) 24 FCR 313.
[34] Makita at 729; Arnotts at 349.
[35] See Appendix D of the Judgment.
[36] Clause 35.6
[37] Clause 35.5.
[38] Plaintiff's closing submission dated 30 October 2003.
[39] See, for example, Allcard v Skinner (1887) 36 Ch D 145; Union Bank of Australia Ltd v Whitelaw [1906] VicLawRp 119; [1906] VLR 711; Commonwealth Bank of Australia Ltd v Amadio [1983] HCA 14; (1983) 151 CLR 447; Peter Birks and Chin Nyuk, 'On the Nature of Undue Influence' in Jack Beatson and Daniel Friedmann (eds), Good Faith and Fault in Contract Law (1995) 57; N C Seddon and M P Ellinghaus, Cheshire and Fifoot's Law of Contract (8th ed, 2002) Ch 14.
[40] [1969] 2 NSWR 530.
[41] [1988] 13 NSWLR 661.
[42] Ibid at 672.
[43] Ibid.
[44] Citing Spotts v. Baltimore & Ohio Railroad Co. 102 F (2d) 160,162 (1939).
[45] [1989] 1 ACSCR 93.
[46] Ibid. at 110.
[47] See Hudson's Building and Engineering Contracts in Australia: including the duties and liabilities of architects, engineers and surveyors (11th ed., 1995) at 821; also, Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd [2003] FCA 174 at [89].
[48] Ibid. at 822.
[49] Citing Lord Esher MR in McDonald v Mayor of Workington (1983) 9 TLR 230.
[50] Ibid.
[51] Eg. See John Holland Construction and Engineering Pty Ltd v Majorca Projects Pty Ltd [1996] 13 BCL 235; Hickman v Roberts [1913] AC 229; Multiplex Constructions v SOR Pty Ltd [2001] 17 BCL 174; Baulderstone Hornibook Pty Ltd v Qantas Airways Ltd [2003] FCA 174.
[52] Page v Landaff and Dinas Powis Rural Council [1901], Hudson, Building Contracts (4th ed) , vol. 2, p.316.
[53] Hickman v. Roberts, Ibid. at 233.
[54] Ibid.
[55] Ibid.
[56] Ibid. at 239.
[57] Ibid. at 240.
[58] Ibid. at 233, 238.
[59] Ibid. 238.
[60] Ibid. at 233.
[61] Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd; Ibid. at [97].
[62] Hickman v. Roberts, Ibid at 236.
[63] (2002) 18 BCL 322.
[64] Ibid. at [50].
[65] In their final submissions dated 30 October 2003, Kane said that "the plaintiff accepts that EOT 4 was submitted for 32 days and a contingency of 15 days and does not seek to assert that the claim was submitted for 47 days... However, Tivendale asserts that in reality the Plaintiff was delayed 47 days by the structural steel". I note that in the plaintiff's consolidated particulars dated 9 November 2001, the plaintiff stated that its request for EOT 4 - as made in writing and dated 8 October 1999 - requested a total of 32 days for his EOT, with no mention of the 15 day "contingency" later inserted by Tivendale. Given the plaintiff's vacillation on the point, I have taken their submission to mean that they claimed 32 days and not 47 days overall for EOT 4.
[66] Note that when added up, the various delays claimed for each component of EOT 4 exceed the total claim for 32 days. Whether the breakdown figures given in the plaintiff's submissions were incorrect or whether Kane claimed a lesser amount overall as a result of concurrent delays (or for other reasons), it is unclear.
[67] (2002) 18 BCL 15.
[68] (1992) 58 BLR 1.
[69] Ibid.
[70] McAlpine Humberoak Ltd v McDermott International Inc, Commentary 58 BLR 5.
[71] Ibid.
[72] Ibid.
[73] McAlpine Humberoak Ltd v McDermott International Inc (1990) 51 BLR 34.
[74] (1992) 58 BLR 1, 17.
[75] Woolf and Russell LJJ.
[76] (1992) 58 BLR 1, 28.
[77] Ibid. at 22.
[78] (1902) 86 LT 764.
[79] Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970) 1 BLR 114; The Cape Hatteras [1982] 1 Lloyd's Rep 518; and SMK Cabinets v Hili Modern Electrics Pty Ltd [1984] VicRp 31; [1984] VR 391.
[80] (1992) 58 BLR 1.
[81] (1992) 58 BLR 1, 22.
[82] Ibid. at 35.
[83] Ibid. The court also stated that despite this detail (or perhaps indeed because of it) the pleadings of the plaintiff failed to properly identify cause and effect. With this in mind, Lloyd L.J. made the following comment: "The very fact that the total entitlement claimed by [McAlpine] ... came to [sterling]1m more than their actual costs should surely have put the judge and his assessors on inquiry."
[84] The principles are broadly discussed in Keith Pickavance, Delay and Disruption in Construction Contracts (1st ed,1997) 486.
[85] Fletcher Construction Australia Ltd v Lines MacFarlane & Marshall Pty Ltd (No. 2) [2002] VSCA 189.
[86] For example, breakdowns of claims regarding masonry was given on 20 August 1999; regarding hydraulics and other items on 14 August 2000 and trade finishes on 21 August 2000.
[87] Information was requested regarding hydraulics, Alucobond and resilient finishes on 8 August 2000 and provided on 14 August 2000. There was a further request regarding tiles on 21 August 2000 and it was provided on the same day.
[88] See, eg, Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) 14 BCL 215, per Rolfe J; Daysea Pty Ltd v Watpac Pty Ltd [2001] QCA 49 at 18-22, per Williams JA.
[89] See, eg, Minson Nacap Pty Ltd v Aquatec-Maxcon Pty Ltd (2001) 17 BCL 269 at [19]-[20] per Byrne J. See generally Adrian Baron, 'Progress claims, payment certificates and legal stability' (2003) 19 Building and Construction Law 271.
[90] Brewarrina Shire Council v Beckhaus Civil Pty Ltd (2003) 19 BCL 177.
[91] Brewarrina Shire Council v Beckhaus Civil Pty Ltd (2003) 19 BCL 177 at [91], citing Federated Seaman's Union of Australasia v Commonwealth Steamship Owners' Association [1922] HCA 7; (1922) 30 CLR 144.
[92] [2004] VSCA 18; (2004) 8 VR 16.
[93] [2001] QCA 49.
[94] See, eg, Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) 14 BCL 215.
[95] The existence of such a condition precedent was considered by the NSW Court of Appeal in Brewarrina Shire Council v Beckhaus Civil Pty Ltd (2003) 19 BCL 177 and has been approved by the Victorian Court of Appeal in Aquatec-Maxcon Pty Ltd v Minson-Nacap Pty Ltd [2004] VSCA 18; (2004) 8 VR 16; notwithstanding the significant academic discussion that has ensued: see, eg, Adrian Baron, 'Progress claims, payment certificates and legal stability' (2003) 19 Building and Construction Law 271.
[96] [2004] VSCA 18; (2004) 8 VR 16.
[97] See for instance Byrne J's analysis in Zauner Construction Pty Ltd v No 2 Pitt Street Pty Ltd (2001) 17 BCL 357 and the view of the Queensland Court of Appeal in Daysea Pty Ltd v Watpac Pty Ltd [2001] QCA 49.
[98] Aquatec-Maxcon Pty Ltd v Minson-Nacap Pty Ltd [2004] VSCA 18; (2004) 8 VR 16 at [12]- [13].
[99] Ibid. at [26].
[100] Ibid. at [24].
[101] (2001) 17 BCL 357.
[102] [2001] QCA 49.
[103] Blue Chip Pty Ltd v. Concrete Constructions Group Pty Ltd (1966) 13 B.C.L. 31; Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) BCL 215.
[104] The unauthorised deduction of liquidated damages point in this case is to be distinguished from the liquidated damages argument raised by the defendant contractor in State of Tasmania v Leighton Contractors [2004] TASSC 132. In that case, Cox CJ determined that the liquidated damages clause of the contract was not a genuine pre-estimate of the principal's (i.e. the State government's) damages. Rather, the sums deducted were "extravagant and exorbitant" and amounted to a penalty. The State was therefore ordered to pay back in full the amount of $1,832,000 deducted as liquidated damages.
[105] See Commonwealth v Verwayen (1990) 170 CLR 394 at 444; Walton Stores Ltd v Maher [1988] HCA 7; (1988) 164 CLR 387.
[106] $1,216,546.
[107] $132,618.
[108] $374,618.
[109] The show cause notice was issued on 8 September 2000.
[110] $1,216,546.64
[111] $340,562
[112] Le Hy Ta recorded, for instance, that Jeffery made a request for delivery dockets on 6 September 2000, the day of the site inspection for progress certificate 15. Le Hy Ta also organised for a copy of delivery dockets to be provided to Jeffery on 14 September 2000, the same day the original payment certificate no. 15 was received from Jeffery.
[113] (1940) 3 All E.R. 60 at 71.
[114] (1884) 9 App. Cas. 434, per Lord Selbourne.
[115] Ibid.
[116] [1982] HCA 47; (1982) 149 C.L.R. 620.
[117] Per Gibbs C.J. in Ibid. at 625-6.
[118] Per Deane and Dawson J.J. in Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd [1989] HCA 23; (1988) 166 C.L.R. 623 at 658.
[119] Per Lord Mansfield in Boone v. Eyre (1777) 1 H.Bl. 273n; see also D.W. Greig & J.L.R. Davis The Law of Contract (1987) 1201-3.
[120] See Luna Park (NSW) Ltd v. Tramways Advertising Pty Ltd [1938] HCA 66; (1938) 61 C.L.R. 286 and Federal Commerce and Navigation v. Molena Alpha Inc. [1979] A.C. 757; see also Paterson, Robertson & Heffey in the Principles of Contract Law (2nd ed., 2005) at 371.
[121] Ibid. As examples of cases involving parties attempting to terminate a contract where no such right exists, see Petrie v. Dwyer [1954] HCA 75; (1954) 91 C.L.R. 99; and Ogle v. Comboyuro Investments Pty Ltd [1976] HCA 21; (1976) 136 C.L.R. 444.
[122] [1964] 2 Q.B. 699 at 734; also cited in DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 C.L.R.423 at 432.
[123] See DTR Nominees Pty Ltd v Mona Homes Pty Ltd (1978) 138 C.L.R.423; see also Paterson, Robertson & Heffey in the Principles of Contract Law (2nd ed., 2005) at 371-2.
[124] See for example DTR Nominees Pty Ltd v Mona Homes Pty Ltd [1978] HCA 12; (1978) 138 C.L.R. 423 at 431-3.
[125] Ibid.
[126] [1978] HCA 12; (1978) 138 CLR 423 at 431.
[127] [1995] UKPC 48; [1996] 1 W.L.R. 270 at 276-7.
[128] [1978] HCA 12; (1978) 138 C.L.R. 423.
[129] See McDonald v Dennys Lascelles Ltd [1933] HCA 25; (1933) 48 C.L.R. 457 at 476-477, per Dixon C.J.
[130] Foran v Wight [1989] HCA 51; [1989] 168 CLR 385, 408; Shevill v Builders Licensing Board [1982] HCA 47; [1982] 149 CLR 620, 625-6; Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd [1989] HCA 23; [1989] 166 CLR 623, 634.
[131] See also DTR Nominees Pty Ltd v Mona Homes Pty Ltd [1978] HCA 12; [1978] 138 CLR 423, 431.
[132] There was evidence that the first defendant later settled third party proceedings against the solicitor.
[133] [1906] HCA 67; (1906) 4 CLR 347.
[134] The tables were contained in the final address materials "accompanying folders of materials provided by the defendants in support of their claim".
[135] See Waltons Stores (Interstate) Ltd v. Maher [1988] HCA 7; (1988) 164 C.L.R. 387, 413.
[136] Amended reply and defence to counterclaim.
[137] Certain subcontractors were identified: Custom Chassis, Iser Kitchens, Premium Shower Screens.