[2022] NSWCATCD 10
NCAT Consumer and Commercial
2021-03-31
Original judgment source is linked above.
Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 22 Rekrut and Scott v Champion Homes Sales Pty Ltd [2017] NSWCATAP 187 Repfix Industries Pty Ltd v FBD Group [2020] NSWDC 514 Rice v JR and SD Farmer t/as Urban Bespoke Homes [2020] NSWCATAP 208; Robinson v Hindmarsh Construction Australia Pty Ltd [2021] NSWCATAP 51 Roude v Helwani [2020] NSWCA 310 Rudas and Andrassy v Eid [2021] NSWCATAP 4 Ruxley Electronics and Construction Ltd v Forsyth [1996] AC 344 Sabouni v Revelop Building and Developments Pty Ltd [2021] NSWSC Suecha Pty Ltd v VSD Glass & Timber Pty Ltd [2020] NSWCATAP 170 Tabcorp Holdings Pty Ltd v Bowen Investments Pty Ltd [2009] HCA 8 [17]; (2009) 236 CLR 272 Thurston v Goway Travel Pty Limited [2020] NSWCATAP 140 Walker Group Constructions Pty Ltd v Tzaneros Investments Pty Ltd [2017] NSWCA 27 Woodward v Warwick Green Building Pty Ltd [2021] NSWCATAP 210 Texts Cited: Nil Category: Principal judgment Parties: Matter HB 20/32292: SDL Project Solutions Pty Ltd (Applicant) James Kim (Respondent)
Matter HB 20/42551: James Jong In Kim (Applicant) SDL Project Solutions Pty Ltd (Respondent) Representation: Counsel: M Maconachie (James Kim) D O'Connor (SDL Project Solutions Pty Ltd)
Solicitors: Fox & Staniland Lawyers (James Kim) Adams & Partners Lawyers (SDL Project Solutions Pty Ltd) File Number(s): HB 20/32292; HB 20/42551 Publication restriction: Nil
REASONS FOR DECISION
Relevant Contractual Provisions
Performance of Works by the Builder and Disputation between the Parties
BUILDER'S POINTS OF CLAIM
HOMEOWNER'S POINTS OF CLAIM
DOCUMENTARY EVIDENCE OF THE PARTIES
Homeowner
Builder
Both Parties
Which Party Lawfully Terminated the Contract?
Did the Homeowner Refuse to Pay Valid Variations and Tell the Builder In Substance The Contract Was At An End At The Meeting on 9 September 2019?
Did The Homeowner Engage Other Contractors to Perform Work In The Period Between 9 September 2019 and 25 November 2019?
Credit of Witnesses
Did the Homeowner Comply With Clause 27 of the Contract Before Referring the Matter to NSW Fair Trading?
Did The Homeowner Provide The Builder With Tipping Receipts Regarding the Disposal of Soil/Spoil?
Did the Homeowner Disclose to the Builder He Was Only the Co-Owner of the Land?
Homeowner's Conduct In Not Paying The Driveway Variation
Did the Homeowner (and/or Ms Choi) Engage and Direct Contractors to Perform Works?
Did the Homeowner Engage Contractors to Perform Works To the Property Between 25 November 2019 and 2 March 2020
Conclusion-The Issue of Repudiation
Did the Homeowner Lawfully Terminate the Contract?
The Homeowner's Claims For Damages In Respect of Defective and Incomplete Work.
Defective Work
Item 1-Masonry
Item 2-Ceiling Height of First Level of Unit A
Item 3-Kitchen Overhead Cupboard Unsightly Overlapping Window Glazing
Item 4-Balconies in Unit A and Unit B
Item 5-Height of Balcony Balustrade in Unit A
Item 6-Unit A-Overcut Tiles Below Bathroom Taps Unit A
Item 7-Architraves
Item 8-Bath in Unit B
Item 9-Vanity in Unit B
Item 10-Sewer Gully
Contingencies; Site Establishment; Builder's Margin
Second Joint Expert Scott Schedule-Stormwater Dish Drain; Stormwater Pit; and Water Tanks
Item 1-Concrete Stormwater Dish Drains Unit A
Item 2-Unit A Stormwater Pit
Item 3-Signage on On-Site Detention Tanks
Summary-Cost of Rectifying Defective Work
Section 48MA of the HB Act
The Homeowner's Damages Claim For Incomplete Work
Homeowner's Claim For Rent Expenses Incurred
Homeowner's Claim for Credit for Provisional Sum Items
Brickwork
Joinery
Fixtures and Fittings
Appliances
Tile Supply
Floor Finishes
Lighting Supply
Landscaping
Conclusion-Adjustments for Provisional Sums
Homeowner's Claim for 'Failure to Give Credit for Preliminaries'
Homeowner's Claim For Provision of Certifications By Tradespersons To Obtain an Occupation Certificate
The Builder's Claim For Quantum Meruit
The Issue of Costs
Summary of Findings
ORDERS 1. In Matter HB 20/42551 SDL Project Solutions Pty Ltd is to pay James Jong In Kim the sum of $112,853.21 within 28 days of the date of this decision. 2. In Matter HB 20/32292, the application is dismissed. 3. The homeowner is to file and serve all costs submissions and documents by 14 days from the date of this decision. 4. The builder is to file and serve all costs submissions and documents by 28 days from the date of this decision. 5. The homeowner is to file and serve all costs submissions in reply by 35 days from the date of this decision. 6. The costs submissions are to include reference to whether or not the parties seek a further oral hearing on the issue of costs. The Tribunal may determine it appropriate to decide the issue of costs without further oral hearing pursuant to s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW). 7. The costs documents and submissions are to be filed in hard copy with the Tribunal. 8. Both parties have leave to apply in writing to vary or extend the timetable for costs submissions and documents.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 14 March 2022
(2014) 253 CLR 560
(1954) 90 CLR 613
(1991) 174 CLR 64
(1982) 148 CLR 658
(1992) 175 CLR 353
(1987) 162 CLR 22
(2009) 236 CLR 272
(1976) 136 CLR 444
(2007) 233 CLR 115
(1989) 168 CLR 385
(1982) 149 CLR 537
(2000) 54 NSWLR 536
(2003) 77 ALJR 768
(1989) 89 ALR 275
[2009] HCA 8