Liquidated damages
193 The Council appeals against the refusal by the Master to allow its application to amend its claim so that it incorporates a claim for liquidated damages.
194 By cl 35.6 of the General Conditions, the Council is entitled to liquidated damages "for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is terminated under cl 44, whichever first occurs". Thus, the first step in ascertaining whether a claim for liquidated damages is capable of being maintained is to determine the dates for practical completion and termination.
195 I have noted that Mr Christie accepted that the dates for practical completion should be assumed as having been extended to about March 2002. This is not a matter on which any concession was forthcoming from Beckhaus and the Master made no finding on this issue.
196 I have previously expressed the opinion that the date on which the Contract was terminated by agreement could be no later than the date on which the trial commenced, namely, 15 March 2004.
197 On the assumption that the date for practical completion was March 2002, the period over which a claim for liquidated damages, potentially, might be made is about two years.
198 In refusing the Council's application to amend, the Master was materially influenced by the fact that Beckhaus suspended work under the Contract in terms of the Act.
199 On 22 May 2002 Beckhaus served upon the Council a notice of intention to suspend work in terms of s 15(2)(b) of the Act. The Council failed to pay the monies claimed by progress claim No 7 and on 27 May 2002 Beckhaus suspended work under the Contract in terms of s 27(1) of the Act. In consequence, Beckhaus submitted that it was entitled to rely on s 27(3) of the Act which has the effect that Beckhaus is not liable to the Council for any loss or damage suffered by it following a lawful suspension of work under the Act. The Master upheld these contentions.
200 The Council submitted that the Master should have held that progress claim No 7 was subject to a condition precedent that had not been fulfilled, namely, the requirement under cl 42.1 of the General Conditions that Beckhaus should support its progress claims with such information as the superintendent might reasonably require.
201 The Council contended that a letter of 2 April 2002, written by the superintendent to Beckhaus, set out information that Beckhaus should have provided to satisfy the condition precedent.
202 The letter of 2 April 2002 referred to outstanding test certificates for compaction (under cl 8.9.3 of the technical specifications) and stated "the test certificates received are insufficient in number". The letter requested Beckhaus "to provide all remaining test certificates for compaction of embankment and pavement material". The Council submitted, further, that an affidavit dated 19 March 2004 by Mr Corven, the superintendent, assisted in providing Beckhaus with particulars of the information required to comply with the condition precedent.
203 Master Macready, in dealing with the condition precedent argument, did not address the request in the letter of 2 April 2002 and the affidavit evidence of the superintendent to which I have referred. The Council rested its case on this aspect of the appeal on his omission to deal with these matters.
204 The letter of 2 April 2002 referred to test certificates that had been issued and also to certificates that were never issued and did not exist. The issued certificates were supplied to the Council by 8 June 2002.
205 The Council submitted that Beckhaus should have advised the superintendent that the tests relating to non-existent certificates had not been undertaken and, hence, no certificates were issued in respect thereof.
206 The non-existent certificates were not referred to in the Council's pleadings or identified at the trial in any way save for the Council producing the letter from the superintendent of 2 April 2002 and relying on his affidavit dated 19 March 2004.
207 On 1 June 2004, during argument before the Master (after the close of evidence), the Master said to Mr Christie that he wished to identify "precisely what it is said you say the request was for the information [the subject of the condition precedent]". The Master observed that the submissions made on the Council's part did not "make it clear precisely what it is you say is the information".
208 A week thereafter, on 8 June 2004, Mr Christie handed to Master Macready a document that he said responded to the questions the Master had asked about the identity of the information that, according to the Council, had not been provided to the superintendent. The document in question referred, amongst other things, to the superintendent's request of 2 April 2002 to provide all remaining test certificates for compaction of the embankment and pavement material as well as to the statement in the letter of that date that the test certificates provided were insufficient in number. The document handed to the Master did not squarely assert that information about the non-existent certificates should have been supplied to the superintendent so as to comply with the condition precedent.
209 In my opinion, the Council did not in adequately clear terms inform Beckhaus and the Master that its argument that the condition precedent had not been fulfilled was based, in part, on the failure to advise that certain the tests had not been performed. It is plain that Master Macready did not understand that the Council put its case in this way. Although he dealt fully with the Council's arguments as to other information that the Council contended had not been supplied to it, he did not deal with the non-existent certificates. In my opinion, the Master was entirely justified in assuming that the matters with which he did deal constituted all the matters relied on by the Council on this issue. In my view, it is now too late for the Council to advance this contention. Beckhaus has not had a proper opportunity of dealing with the point - had it known, for example, that this case was being made against it, it might have sought to cross-examine the superintendent as to whether he knew in any event that the tests had not been carried out, or to lead evidence which went to the issue.
210 Accordingly, in my opinion, Master Macready correctly held that, as at 27 May 2002, the condition precedent had been met and Beckhaus was entitled to suspend work.
211 The Master held that, as a consequence of the delay caused by the suspension, the superintendent should have exercised the discretion available to him under cl 35.5 of the General Conditions to extend the time for practical completion notwithstanding that Beckhaus had not applied for such an extension of time. I agree with the Master's view on this issue (cf Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd (2002) 18 BCL 322 at 343 [78] - 343 [81]). Mr Christie, in his oral submissions, did not contend that the Master had erred in this respect. He said that he "would not cavil" with the proposition that the superintendent, acting fairly, would have given an extension to the date for practical completion corresponding to the suspension period.
212 The Council contended that Master Macready should have held that on 18 November 2002 it paid progress claim No 7 and, accordingly, on that date the suspension of work under the Act ceased.
213 Sections 27(1) and (2) of the Act provide:
"(1) A claimant may suspend the carrying out of construction work … under a construction contract if at least 2 business days have passed since the claimant has caused notice of intention to do so to be given to the respondent under s 15, 16 or 25.
(2) The right conferred by sub-section (1) exists only for so long as the respondent fails to comply with the requirements referred to in s 15(1), 16(1) or 25(1), as the case may be."
214 Of "the requirements referred to in s 15(1), 16(1) or 25(1)", those in s 15(1)(b) are presently relevant. Those requirements comprise the obligation of a "respondent" to "pay the whole or any part of the claimed amount on or before the due date for the progress payment to which the payment claim relates".
215 The payment made by the Council to Beckhaus on 18 November 2002 was subject to the condition that it be secured by a bank guarantee provided at the instance of Beckhaus. Mr Christie accepted that, without the bank guarantee, the Council would not have paid the amount of progress claim No 7.
216 By reason of the requirement to provide a bank guarantee, Beckhaus did not have access to the funds represented by the payment for use in its day to day operations.
217 Master Macready held that a payment that was conditional on the provision of a bank guarantee did not remove the suspension under s 27 of the Act. In coming to this conclusion he relied on "the imperative of giving effect to the purpose of the statutory right of suspension". He said:
"[T]he remedy provided by s 27 of the Act is capable of achieving its full intended function only if the payment which terminates the claimant's right of suspension can be applied to defray expenses and liabilities incurred in carrying out the work to which the progress payment relates."
218 I agree with the view so expressed. In Brodyn Pty Ltd v Davenport (2004) 61 NSWLR 421 Hodgson JA (with whom Mason P and Giles JA agreed) said:
"The Act discloses a legislative intention to give an entitlement to progress payments, and to provide a mechanism to ensure that disputes concerning the amount of such payments are resolved with the minimum of delay. The payments themselves are only payments on account of a liability that will be finally determined otherwise: ss 3(4), 32. The procedure contemplates a minimum of opportunity for court involvement: ss 3(3), 25(4)."
219 The purpose of the Act was to ensure that contractors and sub-contractors, in the circumstances stipulated, could obtain a prompt interim progress payment on account, pending final determination of all disputes (Brodyn Pty Ltd v Davenport [2003] NSWSC 1019 per Einstein J; see also Multiplex Constructions Pty Ltd v Luikens [2003] NSWSC 1140 at [96] per Palmer J). If the requirements of the Act concerning such interim progress payments could be satisfied by payments made conditionally against the provision of bank guarantees, the purpose of the Act would be defeated. In the circumstances, I agree that the payment of 18 November 2002 did not cause the suspension to cease; the suspension continued until the Contract was terminated.
220 In the circumstances, the claim for liquidated damages is capable of running from, the latest, March 2002 (the date for practical completion accepted by the Council - but not by Beckhaus) to 27 May 2002 when Beckhaus suspended work. This is a relatively short period.
221 In refusing leave to the Council to amend so as to claim liquidated damages, the Master, amongst other things, balanced the cost and inconvenience of the further hearing that would be required to establish the date for practical completion against the relatively small amount to which the Council might be entitled in respect of liquidated damages (having regard to his findings relating to the suspension of work under the Act).
222 In the light of the orders that I propose, Macready AsJ might be disposed to allow further evidence on one or more of the several issues remitted to him. I make no comment on the prospects of this occurring, this being (as I have said) a matter entirely within his discretion. The prospect, however, of further evidence being led on the other issues does, however, constitute a change of circumstances relative to the Master's decision not to allow the claim for liquidated damages.
223 In my opinion, fairness requires the Master's decision to refuse to allow the claim for liquidated damages to be set aside so as to allow the Council, if it wishes, to renew the application before his Honour when the matter is remitted. If Macready AsJ determines the other issues remitted to him without allowing any further evidence, I would have thought it unlikely that he would allow the claim for liquidated damages to proceed (as his reasoning, as previously expressed, would remain the same). On the other hand, were evidence to be allowed, Macready AsJ might consider that it would be fair to allow evidence to be led in support of the dates necessary to establish a right on the part of the Council to liquidated damages. For this reason I propose that orders be made setting aside the Master's decision to refuse leave to amend so as to claim liquidated damages and remitting the issue to him for decision when determining all the issues that I propose be returned to Macready AsJ for decision afresh.