CITATION : Brodyn Pty Limited t/as Time Cost and Quality (ACN 001 998 830) v Philip Davenport & Ors [2003] NSWSC 1019 HEARING DATE(S) : 27/10/03 JUDGMENT DATE : 6 November 2003
JURISDICTION: Common Law Division Administrative Law List JUDGMENT OF : Einstein J DECISION : Proceedings to be dismissed.
CATCHWORDS : Building and construction - progress payments claimed under the Building and Construction Industry Security of Payment Act 1999 - determination made by adjudicator - Administrative law - whether, and if so to what extent, judicial review of adjudications made pursuant to the Building and Construction Industry Security of Payment Act 1999 is available - scope of relief available in the nature of a writ of certiorari - grounds upon which judicial review is available Building and Construction Industry Security of Payment Act 1999 (NSW) LEGISLATION CITED : Home Building Act, 1989 (NSW) Supreme Court Act 1970 (NSW) Abacus Funds Management Ltd v Davenport [2003] NSWSC 935 Deputy Commissioner of Taxation v Richard Walter Pty Ltd (1995) 183 CLR 168 Emag Constructions Pty Limited v Highrise Concrete Contractors (Aust) Pty Limited [2003] NSWSC 903 Musico v Davenport [2003] NSWSC 977 Paynter Dixon Constructions Pty Limited v JF & CG Tilston Pty Limited [2003] NSWSC 869 CASES CITED : Plaintiff S157/2002 v Commonwealth (2003) 77 ALJR 454 Public Service Board of NSW v Osmond (1986) 159 CLR 656 R v Hickman; Ex parte Fox and Clinton (1945) 70 CLR 598 R v Northumberland Compensation Appeal Tribunal; Ex parte Shaw [1952] 1 KB 338 R v Tennant; Ex parte Woods [1962] Qd R 241 Walter Construction Group Limited v CPL (Surry Hills) Pty Ltd [2003] NSWSC 266 Vroon BV v Foster's Brewing Group Ltd [1994] 2 VR 32 Brodyn Pty Limited t/as Time Cost and Quality (ACN 001 998 830) (Plaintiff) PARTIES : Philip Davenport (First Defendant) Mediate Today Pty Limited (Second Defendant) Linisil Australia Pty Ltd. (Third Defendant) FILE NUMBER(S) : SC 30078/03 COUNSEL : Mr T Davie (Plaintiff) Mr F Hicks (Third Defendant) SOLICITORS : Schrader & Associates (Plaintiff) LAC Lawyers (Third Defendant)
IN THE SUPREME COURT OF NEW SOUTH WALES EQUITY DIVISION
30078/03 Brodyn Pty Limited t/as Time Cost and Quality (ACN 001 998 830) v Philip Davenport & Ors JUDGMENT The Proceedings 1 The plaintiff, Brodyn Pty Ltd, seeks relief under section 69 of the Supreme Court Act 1970 (NSW) in the nature of certiorari quashing an adjudication determination made by the first defendant pursuant to the provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) ["the Act"]. Further, claims to injunctive relief are sought including:
"2. An order that the Third Defendant, its servants or agents, be restrained from requesting the Second Defendant, being the authorised nominating authority within the meaning of those words contained in s 24 of the Building and Construction Industry Security of Payment Act 1999 (the Act), to provide an adjudication certificate under s 24 of the Act;
"1. In or about February 2002, the Third Defendant, Linisil Pty Limited ( " Linisil " ) was invited to submit a tender for certain plumbing and hydraulics works (the " Works " ) as a subcontractor to the Plaintiff, Brodyn Pty Limited, trading as "Time Cost & Quality" ( " Brodyn " ).
b. the scheduled completion date for the Works was noted as "TBA". 5. Linisil was engaged to perform the works on the basis of its tender and the discussions at the meeting on 13 February 2002.
b. liquidated damages would be applied in the event that Linisil did not achieve substantial completion by a certain date; and/or
c. Brodyn had assessed the sum of $1,927 per day as the liquidated and ascertained damages for the subcontract works in the event that substantial completion was not achieved by a certain date by reference to any items or considerations. 8. As at the commencement of the Works, and to the date that Linisil sought payment on its first Progress Claim, being 26 June 2002, the Subcontract comprised the following documents: a. General Conditions of Subcontract SC.JCC-D 1994 (as amended) (the " General Conditions " );
b. A document entitled "Hydraulic Services Performance Specification" dated 13 August 2001 (the " Specification " );
c. A document entitled "Hydraulic Scope of Work: - Revision A: 25/02/02 For Construction" which identified the scope of the Works, the Specification and a number of plans/drawings (the " Scope of Works document " );
d. Four Appendices, being: i. Appendix A - "Subcontractor Order"; ii. Appendix B - "Hydraulics"; iii. Appendix C - "Quality Assurance/Safety"; iv. Appendix D - "Subcontractor Employee Details" (the "Appendices") 9. On or about 26 June 2002, Bill Reid attended the head office of Brodyn to collect payment in respect of Linisil Progress Claim No.1. On this occasion, Anthony Trinh said that, in order for Linisil to be paid, Bill Reid had to sign a document entitled "Subcontract Information".
No date for substantial completion for the whole of the Works was nominated.
The Progress Claims and the performance of the Works
Progress Claim Amount claimed for the Works performed (not including retention) Response and amount paid for the Works performed (Amount is sum paid or stated not including retention monies) No.1 Remittance Advice (21 June 2002). $56, 921.15 2 June 2002 $53,926.00 actually paid. Remittance Advice (26 July 2002). No.2 $81,499.55 (includes work claimed for in Progress Claim 1) Payment Schedule (26 July 2002). 26 June 2002 $14,850.00 actually paid. Remittance Advice (6 September 2002). No.3 $45,745.00 (includes work claimed for in Progress Claims 1 & 2, less payment for Progress Claim 1) Credit Request Form (22 August 2002). 30 July 2003 $13,262 actually paid. Remittance Advice (16 Sep 2002).
No.4 $77,855.98 Payment Schedule (13 Sep 2002). (includes work claimed for in Progress Claims 1, 2 & 3, less payment for Progress Claims 1 & 2). 30 August 2003 Credit Request Form (16 September 2002).
$45,633.50 actually paid Remittance Advice (17 October 2002). No.5 $82,232.48 (includes work claimed for in Progress Claim 1, 2, 3 & 4, less payment for Progress Claims 1, 2 & 3) Credit Request Form (16 October 2002). 24 Sept 2003 $14,388 actually paid. Remittance Advice (16 September 2002).
No.6 $45,310.88 Payment Schedule (13 September 2002). (includes work claimed for in Progress Claims 1, 2, 3, 4 & 5, less payments for Progress Claims 1, 2, 3 & 4). 27 October 2003 Credit Request Form (16 September 2002).
$6,000 actually paid. Payment Schedule (28 November 2002). No.7 $58,070.88 (includes work claimed for in Progress Claims 1, 2, 3, 4, 5 & 6, less payments for Progress Claims 1,2, 3, 4 & 5) Credit Request Form (7 January 2003). 27 November 2003 $25,808.40 actually paid. No.8 $106,755.98 Payment Schedule (10 March 2003) (includes work claimed for in Progress Claims 1, 2, 3, 4, 5, 6 & 7, less payments for Progress Claims 1,2, 3, 4, 5, 6 & 7) 16 Feb 2003 Asserted that Linisil owed Brodyn $46,911.08. No.9 $107,360.98 Payment Schedule (1 May 2003) (includes work claimed for in Progress Claims 1, 2, 3, 4, 5, 6, 7 and 8, less payments for Progress Claims 1,2, 3, 4, 5, 6 & 7) 28 April 2003 Responded dealing with variations. Nil allowed or paid for Progress Claim No.9.
Progress Claim No.9 was made under the Building and Construction Security of Payment Act (NSW) 1999 (the "Act" ).
Following the response of Brodyn dated 1 May 2003, Linisil made an application for adjudication on 14 May 2003.
The matter was referred to adjudication by Philip Davenport (the First Defendant) by Adjudicate Today (a division of Mediate Today Pty Limited, the Second Defendant), being an Authorised Nominating Authority under the Act.
Linisil served written submissions with its application for Adjudication.
Brodyn served its response in respect of the Adjudication on 21 May 2003.
Mediate Today informed the parties that Philip Davenport had made his Adjudication by fax dated 26 May 2003. By that fax, Adjudicate Today stated that: a. the adjudication of Philip Davenport included a determination that Brodyn pay 100% of the fees and expenses of the adjudicator;
b. the fees and expenses of the adjudicator were $7,260; and
c. pursuant to subsection 29(5)(a) of the Act, the decision was withheld the fees and expenses of the adjudicator had been paid by Brodyn or any other party. 20. Brodyn, without knowing the substance of the determination, failed or refused to pay the fees and expenses of the adjudicator as determined. In this way, Brodyn prevented Linisil from having the benefit of the adjudication for approximately three months.
21 On 28 August 2003, Linisil paid the fees and expenses of the adjudicator as quantified in order to obtain the adjudication.
"21 Section 30(1) of the Act is not a privative clause. It does not seek to exclude judicial review. It is not of the nature of such provisions as were considered in R v Hickman; Ex parte Fox and Clinton (1945) 70 CLR 598 and does not fall within the principles discussed in Deputy Commissioner of Taxation v Richard Walter Pty Ltd (1995) 183 CLR 168 and more recently in Plaintiff S157/2002 v Commonwealth (2003) 77 ALJR 454. Indeed, the current provision is less restrictive than it was in the original legislation which provided that no action lay against an adjudicator or any other person with respect to anything done or omitted to be done by the adjudicator in good faith in the exercise of the adjudicator's functions under the Act.
22 I do not construe the present legislation as seeking to exclude review by the courts of adjudicators' determinations by way of orders in the nature of prerogative writs…
33 Nonetheless, that certiorari lies to quash a decision for error of law on the face of the record is clearly established ( R v Northumberland Compensation Appeal Tribunal; Ex parte Shaw [1952] 1 KB 338). In R v Tennant; Ex parte Woods [1962] Qd R 241 a Full Court of the Supreme Court of Queensland sought to exclude from the ambit of the writ trivial errors of law by limiting them to those that were fundamental or vital so as to make the impugned decision unwarrantable. That approach was criticised in Aronson and Dyer, Judicial Review of Administrative Action, Law Book Company, Sydney, 2000, at 178-179 on the basis that it equates patent error of the law with jurisdictional error.
34 In light of this controversy, I am not prepared on this interlocutory application to find that the plaintiff has such slim prospects of success that the balance of convenience favours a dismissal of the notice of motion.
35 It will be for the plaintiff to establish what the record is. Reasons for a decision do not, of themselves, constitute part of the record but may be incorporated by reference ( Public Service Board of NSW v Osmond (1986) 159 CLR 656 at 667, 671, 675, 678). I assume for present purposes that the record includes the first defendant's adjudication determination and the contract…
39 Notwithstanding my reluctance to do so in light of the legislative intention demonstrable in the Act, I am of the view that the plaintiff's second challenge raises an arguable case that there is error of law on the face of the record that may give rise to an order in the nature of certiorari quashing the determination. I am of the view that the status quo with respect to that issue should be preserved pending its determination. I reject the plaintiff's first challenge and decline to grant interlocutory relief in respect of it. I decline to make any order against the third defendant. No such order is necessary to protect the plaintiff pending determination of its summons." [2003] NSWSC 935 10 Section 25(4)(a)(iii) of the Act is extremely important in terms of any decision as to the extent to which judicial review of such adjudications is in principle available. As McDougall J has pointed out in Musico, this subsection prevents a respondent seeking to set aside a judgment based on an adjudication certificate, from challenging the adjudicator's determination. As McDougall J has indicated:
"55 That must mean that in any such proceedings, the judgment cannot be set aside upon the basis that the adjudicator (for example) erred in law in some step of his or her reasoning. It would be quite inconsistent with the legislative intention that is evident in s 25(4) to permit a challenge to be raised, by way of relief in the nature of prerogative relief, upon the ground of error of law. The legislature could hardly be taken to have intended that, having forbidden entry by the front door, it was nonetheless happy for access to be obtained from the rear." [2003] NSWSC 977 11 A further matter of particular significance is to be found in the fact that Part 2 of the Act in providing for the entitlement to progress payments specifically provides that there are two alternative routes to determining the amount of a progress payment to which a person is entitled in respect of a construction contract. Section 9 provides that the relevant amount is to be:
"(a) the amount calculated in accordance with the terms of the contract; or (b) if the contract makes no express provision with respect to the matter , the amount calculated on the basis of the value of construction work carried out or undertaken to be carried out by the person (or of related goods and services supplied or undertaken to be supplied by the person) under the contract." 12 Section 10 which then provides in subsection (1) for the manner in which construction work carried out or undertaken to be carried out under a construction contract is to be valued, provides for that valuation to be in accordance with the terms of the contract or, if the contract makes no express provision with respect to the matter, for the valuation to have regard to a range of matters including the contract price for the work, and in the case of defective work, the estimated cost of rectifying the defects. A similar approach is taken in subsection (2) to the method by which related goods and services supplied or undertaken to be supplied under a construction contract are to be valued. 13 In short, even where no express contractual provision is made with respect to the amount of a progress payment to which a person is entitled in respect of a construction contract or where no express provision is made with respect to the valuation of construction work carried out under a construction contract, the adjudicator has a judgmental role in determining those matters. And the adjudicator exercises that role by reference to the integers stipulated for by the Act. 14 What the legislature has effectively achieved is a fast track interim progress payment adjudication vehicle. That vehicle must necessarily give rise to many adjudication determinations which will simply be incorrect. That is because the adjudicator in some instances cannot possibly, in the time available and in which the determination is to be brought down, give the type of care and attention to the dispute capable of being provided upon a full curial hearing. It is also because of the constraints imposed upon the adjudicator by section 21, and in particular by section 21(4A) denying the parties any legal representation at any conference which may be called. But primarily it is because the nature and range of issues legitimate to be raised, particularly in the case of large construction contracts, are such that it often could simply never be expected that the adjudicator would produce the correct decision. What the legislature has provided for is no more or no less than an interim quick solution to progress payment disputes which solution critically does not determine the parties rights inter se. Those rights may be determined by curial proceedings, the Court then having available to it the usual range of relief, most importantly including the right to a proprietor to claw back progress payments which it had been forced to make through the adjudication determination procedures. That clawback route expressly includes the making of restitution orders. 15 During the taking of submissions from the parties, Mr Davie, counsel for the plaintiff, addressed at length on the proposition that the adjudicator is a tribunal obliged to act judicially, making the following points: · that the adjudicator once appointed exercises power conferred on him or her by statute; · that the adjudicator has the statutory power to provide a determination which expressly confers rights upon the claimant, including the right to payment, carrying with it the right to suspend work in circumstances which might otherwise constitute a breach of contract; and · that the adjudicator in carrying out the determination is required to decide questions which confer and proclaim a legal right, namely the determination that a progress payment is payable. 16 In many circumstances a statutory provision providing a tribunal with such powers would inexorably result in the decisions of the tribunal being open to judicial review and in particular review in the nature of a writ of certiorari provided for in section 69 (3) of the Supreme Court Act. That subsection reads:
"It is declared that the jurisdiction of the Court to grant any relief or remedy in the nature of a writ of certiorari includes jurisdiction to quash the ultimate determination of a court or tribunal in any proceedings if that determination has been made on the basis of an error of law that appears on the face of the record of the proceedings." 17 The critical parameter of present significance in terms of the consideration of the extent to which an adjudication determination is amenable to judicial review is the fact that the determination does not finally determine the parties rights even where following the issue of an adjudication certificate, the determination in due course becomes enforceable as a judgment for a debt. All that such a judgment achieves and amounts to is an obligation for the judgment debtor to make a particular payment to the judgment creditor. That payment is regarded as a progress payment mandated by the Act when it has been regularly engaged and when each of the steps provided for have been carried out to the letter. 18 So read, none of the propositions put forward by Mr Davie is conclusive as to the extent to which, if at all, judicial review of the adjudicator's determination is available. And in determining the limited extent to which the procedures under the Act are open to judicial review, it is necessary to take into account the central mischief sought to be remedied as exposed by the second reading speech. Justice McDougall has relevantly set out that reading speech in Musico (see [2003] NSWSC 977 at [20]). It makes it very plain that the legislation was aimed at permitting contractors and subcontractors to obtain a prompt interim progress payment on account, pending final determination of all disputes. Were the Court to now hold that disappointed respondents may, following an adjudication determination, invoke general review by the courts of those determinations by way of orders in the nature of prerogative writs, the way would be open for a wholesale undermining of the mischief sought to be dealt with by the Act. 19 This then provides the essential reason as to why upon the proper construction of the Act the following conclusions may be drawn: · that apart from any privative effect the Act might have, relief under section 69 of the Supreme Court Act would in principle lie against an adjudicator appointed under section 19 of the Act; · that the determination of an adjudicator made pursuant to section 22 of the Act is in principle susceptible to judicial review; · that judicial review of adjudication determinations made under the Act may be undertaken on jurisdictional grounds (at least in the sense that involves refusing to exercise, or acting in excess of, jurisdiction); · that judicial review of adjudication determinations made under the Act may be undertaken for denial of natural justice or for fraud; and · that relief in the nature of certiorari will not lie to quash the determination of an adjudicator on the basis of non-jurisdictional error of law on the face of the record [because the legislative scheme set out in section 25 (4) is inconsistent with the availability of this ground of review]. 20 This conclusion generally follows the reasons for judgment given by McDougall J in Musico (see [2003] NSWSC 977 at [42]-[60]). Were any grounds of review made out? 21 The particular alleged shortcomings in the determination upon which the plaintiff has sought to rely were put as follows:
"1. The last paragraph of the second page of the reasons for determination says: The major item which the Respondent seeks to deduct from progress payments is an amount of $69,372.00 for liquidated damages. The Respondent says that the Contract provides for liquidated damages for delay. Item M1 of the Appendix to the Contract provides for liquidated damages of $1,927.00 per day. Clause 10.15 provides that if the Claimant fails to bring the Sub-Contract Works to Substantial Completion by the Date for Substantial Completion the Claimant may be liable to pay liquidated damages. The Date for Substantial Completion' is defined in clause 1.02.10 as the date stated in item B10 of the Appendix. In item B10 there are 10 dates shown for 10 different portions of the building. There is no single 'Date for Substantial Completion'. Consequently, there can be no breach under clause 10.15 and no liquidated damages. 2. It is submitted that the conclusion that there 'can be no breach under clause 10.15 and no liquidated damages' does not follow from the premise that 'there is no single 'Date for Substantial Completion'.
Ss 9(a) and 22(2) and (3) of the Building and Construction Industry Security of Payment Act ( the Act)
(b) that party can recover the GST it will have to pay if it has entered into a contractual relationship with the party to whom the supply is made enabling it to do so;
(c) if there is no such contractual arrangement then there is no right to pass on the GST. 13. In this particular case the claimant would have to pay GST on amounts paid to it for variations.
There is no indication that there was any agreement enabling the claimant to pass on the amount it would have to pay to respondent.
The implied agreement identified by the adjudicator appears to be based on nothing more than the absence of an express agreement. This, it is submitted, constitutes an error of law.
In the next paragraph the adjudicator says: Clause 10.02.04 provides [of the Contract] says that the Respondent must pay to the Claimant an amount equal to the Respondent's valuation less, among other things, Progress claims and the value of work must not include • Variations not agreed in writing • Any claims for recompense over the contract sum unless agreed in writing
He then goes on to assess the value of a number of variations which were not agreed in writing and/or claims for recompense over the contract sum not agreed in writing.
It is submitted that the task of the adjudicator in this case was to determine the amount of the claimant's payment claim that was payable to it pursuant to the terms of the contract.
In doing so the adjudicator determined the amount of the progress payment to be made by the respondent to the claimant. 20. The clear and express words of the contract were that progress claims must not include variations and other claims not agreed in writing.
Short minutes of order 25 Short minutes should be brought in. Costs may be argued.
I certify that paragraphs 1 - 25 are a true copy of the reasons for judgment herein of the Hon. Justice Einstein given on 6 November 2003
Susan Piggott
Associate
6 November 2003
Last Modified: 11/10/2003 DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Brodyn Pty Limited t/as Time Cost and Quality (ACN 001 998 830)
Philip Davenport & Ors
(1995) 183 CLR 168
(2003) 77 ALJR 454
(1986) 159 CLR 656
(1945) 70 CLR 598