[2003] NSWSC 1070
defendant. Application for interlocutory injunction and declarations dismissed; plaintiffs to pay defendant's costs of the interlocutory application; matter adjourned to directions list (para 41).
The plaintiffs sought to stop Tolco enforcing an adjudicator's payment determination made under the Security of Payment Act, arguing jurisdictional error and denial of natural justice. The adjudicator accepted a critical timesheet showing work on 10 September 2002 and treated the claim as a valid progress claim. Bergin J found no arguable jurisdictional error or denial of natural justice sufficient to justify interlocutory relief, emphasising the interim, speedy nature of the statutory scheme (s 32). The injunction was refused and costs were ordered against the plaintiffs (paras 21, 34, 40-41).
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
1,852 words · generated 15/07/2026
This was an interlocutory attack on an adjudicator's determination made under the Building and Construction Industry Security of Payment Act 1999 (NSW) (the Act). The plaintiffs (Pasquale Lucchitti trading as Palluc Enterprises and others) contracted with Tolco Pty Ltd for a steel roof structure (quote dated 14 March 2002) and a dispute arose about variations and additional work. Tolco served a progress claim dated 9 September 2003. The plaintiffs served a payment schedule on 29 September 2003 disputing the claim and raising issues about the Act's applicability and timeliness (paras 12–16). Tolco sought adjudication; an adjudicator (John L O'Brien) was appointed and delivered a determination on 31 October 2003 finding Tolco entitled to progress payment, relying in part on a "critical document", a weekly timesheet (Exhibit E143) showing activity on 10 September 2002 (paras 21, 23).
2 cited instruments linked from this judgment.
The plaintiffs filed a summons on 5 November 2003 seeking declarations that the adjudication determination and the adjudicator's appointment were null and void, and an interlocutory injunction restraining Tolco from taking steps to enforce the adjudication or issuing an adjudication certificate (paras 1–3). The matter was heard urgently on 7 November 2003 before Bergin J (paras 1, 3). The judge dismissed the application for interlocutory relief and ordered the plaintiffs to pay the defendant's costs; the matter was adjourned to the directions list (para 41).
Three principal legal strands underpinned Bergin J's reasoning.
Factual and procedural assessment of the adjudicator's conduct. The adjudicator accepted the timesheet (E143) as showing activity on 10 September 2002 and concluded that the claimant had a valid progress claim (paras 21, 23). The plaintiffs argued the adjudicator committed jurisdictional error by saying he could not have regard to paras 1 and 2 of the adjudication response (which raised the lump sum agreement and a dispute as to quantification) yet effectively ignoring material aspects of the respondent's case (paras 24–26). Bergin J examined the determination and concluded the adjudicator, despite his stated limitation, had in substance considered the lump sum/variation issues and had sought to value the claim using the best evidence before him (paras 27–35). In short, the court concluded there was no clear jurisdictional error on the facts: the adjudicator had struggled with poor documentation but endeavoured to perform his duties under the Act (paras 33–35).
Statutory context and limits on review. Bergin J emphasised the interim and speedy character of the Security of Payment scheme. He cited (and relied on) recent authorities to the effect that adjudication is an interim process designed to produce speedy payments and that judicial intervention is constrained (paras 39–40). The judge specifically invoked s 32 of the Act, noting it 'looms large' when considering interlocutory restraint (para 40). This statutory context weighs heavily against granting interlocutory relief which would subvert the scheme's object.
Discretion and balance of convenience. Even if arguable errors were identified, the court had to exercise discretion and assess whether there was a serious issue to be tried and whether the balance of convenience favoured granting an injunction. Bergin J was not persuaded a serious issue to be tried existed on the plaintiffs' grounds (paras 35, 38), and the balance of convenience, taking into account the Act's policy and the monetary quantum (circa $30,000), favoured refusal (para 40). The judge also considered that such a dispute could be litigated in the Local Court (para 40).
For those reasons the injunction was refused and costs ordered against the plaintiffs (para 41).
Before this decision: a growing line of decisions in the NSW Supreme Court (including Musico v Davenport [2003] NSWSC 977, Paynter Dixon [2003] NSWSC 869, and Brodyn Pty Ltd v Davenport [2003] NSWSC 1019) was shaping the understanding of judicial intervention in adjudications under the Act. Those authorities emphasised the interim nature of adjudication and the narrow basis on which courts should intervene at interlocutory stages.
This judgment sits with that line. Bergin J cited Musico for the proposition that such applications are discretionary and that the Security of Payment scheme is interim (para 39). He referred to his own (and Einstein J's) prior judgments emphasising the same policy (para 40). The practical effect is to reinforce a high threshold for interlocutory relief against adjudicators' determinations: courts should be slow to restrain enforcement unless a clear jurisdictional defect or denial of natural justice plainly emerges and a serious issue to be tried exists.
After this judgment: the decision consolidates the approach that (1) poor presentation of materials does not of itself establish jurisdictional error if an adjudicator nonetheless engages with the substance; (2) acceptance of a party's documentary evidence (such as the timesheet here) will not attract interlocutory relief where the evidence was before the adjudicator and not contested in that forum; and (3) the statutory aim of speedy interim decisions (s 32) is a weighty consideration against injunctive relief.
Readers should note this judgment is one piece in a developing jurisprudence of the time. Bergin J expressly situates his decision among contemporaneous authorities (paras 39–40).
Para 21 (adjudicator's acceptance of timesheet): Quote: "I have been obliged to accept that the weekly time sheet... shows some activity... on 10 September 2002 so that the claim appears to have been served on the last possible date." Plain English: The adjudicator relied on a weekly timesheet that showed work actually took place on 10 September 2002. That made the claimant's progress claim timely, it was served at the last possible date allowed.
Para 24 (the adjudicator's stated exclusion of paras 1 and 2): Quote: "I can not have regard to paragraphs 1 and 2 as these reasons are not included in the payment schedule." Plain English: The adjudicator said he could not consider certain arguments because those arguments had not been raised earlier in the strict statutory payment schedule, and the Act restricts what a respondent may raise in adjudication unless it was in the payment schedule.
Para 34 (judge's overall assessment of adjudicator's engagement): Quote: "In my view the adjudicator clearly strived to do his duty... he had regard to the Act as required by s 22; that he had regard to the contract... the payment claim... the payment schedule... and... the submissions." Plain English: The judge concluded that, despite messy documents, the adjudicator tried to do the job required by the statute and considered the available evidence and arguments before making his decision.
Para 40 (statutory policy emphasised): Quote: "The intention is to effect a speedy payment of contractors. It does not affect the parties' rights and importantly s 32 in my view looms large in deciding this case." Plain English: The Security of Payment Act is designed to get money moving quickly, it's an interim mechanism and does not finally resolve all disputes. Section 32 (which preserves parties' broader rights) is an important reason for refusing to block enforcement at an interlocutory stage.
Para 41 (disposition): Quote: "I refuse the application for injunctive relief." Plain English: The court denied the plaintiffs' request to stop Tolco enforcing the adjudication.
This decision is directly engaged where:
Practically, a litigant seeking to overturn or restrain enforcement of an adjudicator’s determination should ensure (a) a clear jurisdictional error or breach of natural justice is demonstrated on the face of the adjudicator's decision, or (b) that the balance of convenience compellingly favours intervention despite the Act's interim policy.
This judgment expressly relies on contemporaneous authorities (Musico, Paynter Dixon, Brodyn) to support non-interventionist principles (paras 39–40). The judgment itself is consistent with a body of early Security of Payment jurisprudence emphasising the interim nature of adjudication and the limited role of courts at interlocutory stages.
This judgment does not record later appellate treatment of itself, nor does it assert any broad innovate rule beyond applying established principles to the facts. Practitioners should therefore treat it as a fact-specific reinforcement of the prevailing approach: interlocutory relief against adjudication determinations is exceptional and will be refused where the adjudicator has engaged with the materials and no plain jurisdictional defect is shown (paras 34, 38–41). For authoritative, up-to-date treatment, further research would be required to locate subsequent appellate authority engaging this judgment.
The boundary between a mere error of law made by an adjudicator and a jurisdictional error that justifies judicial intervention remains fact-sensitive. Bergin J treated the adjudicator's mischaracterisation (saying he would not have regard to paras 1 and 2 but nevertheless dealing with the subject-matter) as non-jurisdictional on these facts (para 34). Different factual postures may produce different outcomes.
The treatment of evidentiary materials that are first produced late in the adjudication process (for example, the 'critical' timesheet) remains delicate. Here the plaintiffs had not objected to that document before the adjudicator and the judge noted statutory constraints (para 33). A deliberate withholding or concealment of decisive documentary material may raise stronger grounds for relief, but Bergin J's judgment does not fully map out that boundary.
The interplay between s 20(2)(b) (limits on what a respondent can include in an adjudication response) and the respondent's broader rights in subsequent litigation remains unresolved at a general level. Bergin J accepted the adjudicator's literal approach to s 20(2)(b) but also found that, in substance, the adjudicator addressed the lump sum/variation dispute (paras 24, 27–34). How different formulations of payment schedules and responses will be treated in future cases may require appellate clarification.
The practical threshold for what amounts to a 'serious issue to be tried' in this context is influenced by the Act's policy, s 32 and the amounts at stake. Bergin J suggested modest claims are better litigated in lower forums (para 40). How courts will weigh public interest in preserving the statutory scheme against extraordinary cases of injustice is not exhaustively settled.
In sum, Pasquale Lucchitti v Tolco reinforces a restrained supervisory approach to adjudication under the NSW Security of Payment regime. It underscores that poor drafting, procedural clumsiness or an adverse outcome in adjudication will not automatically attract interlocutory relief; claimants must show clear jurisdictional error, denial of natural justice, or other compelling grounds to displace the statutory policy favouring speedy interim determinations (paras 33–41).
CITATION : Pasquale Lucchitti Trading as Palluc Enterprises and Ors v Tolco Pty Limited and Anor [2003] NSWSC 1070 HEARING DATE(S) : 7 November 2003 JUDGMENT DATE : 7 November 2003
JURISDICTION: Equity Division Technology and Construction List JUDGMENT OF : Bergin J DECISION : Application dismissed.
CATCHWORDS : [INJUNCTIONS] - Whether the First Defendant should be restrained from taking any steps in relation to an adjudication determined by the Second Defendant in respect of a dispute between itself and the Plaintiffs - Whether adjudicator exceeded his jurisdiction in determining the dispute under the Building and Construction Industry Security of Payment Act 1999 (NSW) LEGISLATION CITED : Building and Construction Industry Security of Payment Act 1999 (NSW) Supreme Court Act 1970 (NSW) Brodyn Pty Limited Trading as Time Cost and quality (ACN 001 998 830) v Philip Davenport and Ors [2003] NSWSC 1019 CASES CITED : Musico v Davenport [2003] NSWSC 977 Paynter Dixon Constructions Pty Limited v JF & CG Tilston Pty Limited and Anor [2003] NSWSC 869 Pasquale Lucchitti Trading as Palluc Enterprises (First Plaintiff) Ben Lucchitti Trading as Palluc Enterprises (Second Plaintiff) Paul Lucchitti Trading as Palluc Enterprises (Third Plaintiff) Sam Lucchitti Trading as Palluc Enterprises (Fourth Plaintiff) PARTIES : Irene Mavis Lucchitti Trading as Palluc Enterprises (Fifth Plaintiff) Umberto Pallone Trading as Palluc Enterprises (Sixth Plaintiff) Flora Pallone Trading as Palluc Enterprises (Seventh Plaintiff) David Alfred Pallone Trading as Palluc Enterprises (Eighth Plaintiff) Tolco Pty Limited (First Defendant) John O'Brien (Second Defendant) FILE NUMBER(S) : SC 55046/03 COUNSEL : DS Weinberger (Plaintiffs) WG Muddle (First Defendant) Robert Webley & Associates (Plaintiffs) SOLICITORS : Deacons (First Defendant) John O'Brien (In Person)
55046/03 PASQUALE LUCCHITTI TRADING AS PALLUC ENTERPRISES & ORS V TOLCO PTY LIMITED & ANOR JUDGMENT 1 This is yet another application in respect of an adjudication under the Building and Construction Industry Security of Payment Act 1999. The plaintiffs filed a Summons on 5 November 2003 seeking a declaration that the adjudication determination made by the second defendant, John L O'Brien, on 31 October 2003, is null and void. 2 The plaintiffs seek an order that the first defendant, Tolco Pty Ltd, be permanently restrained from taking any steps in relation to the adjudication determination and also seek a declaration that the appointment of John L O'Brien, the second defendant, is null and void. Finally, an order is sought under s 69 of the Supreme Court Act quashing the adjudication determination of the second defendant. 3 This matter came into the list urgently for the hearing of a notice of motion that seeks an order that until further order the first defendant be restrained from taking any steps to enforce the adjudication made on 31 October and that it also be restrained from issuing an adjudication certificate under the Act. 4 In support of the notice of motion the plaintiffs rely upon the affidavit of Robert George Webley, who is the solicitor for the plaintiffs. That evidence discloses that the plaintiffs obtained a quotation from the first defendant, to whom I shall refer as the defendant, to carry out roofing work at a partly completed home unit building that the plaintiffs had purchased at 8-10 Kembla Street, Wollongong. That quotation is in evidence in exhibit E1. It is in the following terms: "Dear Pasquale, we acknowledge receipt of above mentioned enquiry and thank you for the invitation.
Tolco wishes to advise our price for the fabrication, erection and completion of steel roof structure at Kembla Street Wollongong is $39,160".
There is then a particularisation of the price which allows for certain matters, including materials, fabrication, site, supply of roll beams, et cetera. That document also states that the prices are subject to GST and that "any savings made in the above areas will be passed on to the client". 5 The evidence states that the solicitor, Mr Webley, was informed by one of the plaintiffs, Pasquale Lucchitti, and that he verily believed that the quotation was accepted on or about 14 March 2002 and that the defendant commenced work shortly after. Mr Webley claims that in early November 2002 he was approached by Pasquale, who instructed him that he had just received a bundle of invoices in a plain manilla envelope. Those invoices are in evidence as exhibit E2 through to E35. Examples of those invoices show that the first defendant was claiming that work was done on site at Kembla Street to install a new roof from dates in June, July and August. It is also apparent there were invoices up to about 5 September 2002. 6 Correspondence ensued between the plaintiffs and the defendant and on 16 December 2002 a letter was sent to the plaintiffs as a result of correspondence that disputed the claim made for the payment for works allegedly done in addition to those which were in fact contained in the letter or quotation of 14 March 2002. In that letter the defendant claimed that Tolco had tendered on a particular scope of works relating to the steel roof structure which had been detailed in the 14 March 2002 quote. The letter goes on to claim that following acceptance of the quote certain works were additional to the tender, including detailed drawings which were not in the original offer, in the amount of $7,546, a survey, amounting to $577.50 and modifications to beams, which were in fact delivered by the plaintiffs, amounting to $270. 7 The letter states further that the site works, which were not in the 14 March document, included such things as modification to trusses, window headers, vertical columns and modifications to a lift well, supply of fabrication items and scaffolding, totalling $30,956.30. There is then a reference to the original quote, which was the 14 March document, in the amount of $39,160, less the crane supplied by the plaintiffs, less blast and paint, totalling works completed for an amount of $64,556.30. 8 In a letter, which was not objected to, but has a heading "Without Prejudice", the plaintiffs wrote to Tolco in terms including: "I spoke with you originally and inspected the site with you. The inspection was of a partially completed roof structure. Our agreement was a total price to complete the works. The price was all inclusive and there was no discussion about drawings or surveys. All of that work was included in our original discussion and quote. There was no mention of any additional drawings or surveys." 9 There was also reference in that letter to initial discussions that the defendant could use anything that was on site, or rip it out and start again, whatever the plaintiffs wanted. It was claimed that was the basis of the defendant's tender, or quote, and that the defendant was always entitled to modify or use whatever the defendant obtained or whatever the plaintiffs had. Specific reference was made to the item in the 16 December letter to the modification to the lift well. It was stated that: "The item which you say was modification to lift well is actually part of the roof structure which was in the original discussion and tender." and: "I accept items 2, 3 and 4, namely all of the window headers are properly extras."
10 Clearly the plaintiffs accepted that there were additional matters known as, in this letter "extras". The letter continued: "I felt that the extra items (window headers) were offset by the supply of the 250 universal beams and the other input that I provided and that overall that my offer of 11 November 2002 was fair." 11 On 6 May 2003 the plaintiffs' solicitors advised the defendant that notwithstanding the various attempts to arrange meetings, the plaintiffs had heard nothing from the defendant and therefore enclosed a cheque, not for $39,160 but for $35,750, made up as the amount of the offer, plus GST. On receipt of that letter the defendant acknowledged receipt of the cheque and credited it to the plaintiffs' outstanding account and once again requested payment of $31,726. 12 On 9 September 2003 the defendant served a progress claim number two for a total amount, including GST, of $35,327.93. Attached to that claim was a schedule detailing what is referred to firstly as the contract and then further variations. In addition, the payment claim was attached with a statement as required by the Act that it was a payment claim under the Building and Construction Industry Security of Payment Act 1999. 13 The plaintiffs served a payment schedule in response to the defendant's payment claim on 29 September 2003. It stated: "Payment schedule, reference: Progress claim number 2 dated 9 September 2003. Scheduled amounts: Nil. Reasons, disputed claim as set out in our letters dated 29 September 2003 and 10 September 2003 and Palluc letter dated 20 November 2002, further copies enclosed."
14 The letter of 29 September 2003 was a letter in which the solicitors for the plaintiffs disputed the plaintiffs' liability to pay the amount due. It was stated that the amount concerned was not a progress claim and that prior to the December 2002 amendments was not subject to the legislation. It was claimed it was a final payment sought after completion of the work. Amongst other things it raised questions about whether the claim had been made within 12 months as required by the Act, and whether the defendant was entitled to seek adjudication, suggesting that it was not. It stated: "As advised previously this is not a question of progress payments. Our client disputes the entitlement to the remainder claimed and has now gone ahead to pay the full amount of what it considers was due. In those circumstances it is not able to put forward a payment schedule, the full amount is in dispute as is the fact of whether it is within the legislation."
There was then an invitation to withdraw the defendant's claim. 15 Exhibit E149 is a letter dated 10 September 2003 stating that the defendant had already been advised that the remainder of the claim was disputed and that the plaintiffs had paid the undisputed part of the invoice but the remainder was in dispute. It states, "it has been explained on numerous occasions" but did not descend into any further detail. 16 The third letter referred to in the payment schedule at Exhibit 40 was a letter from the plaintiffs to Tolco. It stated:
"Just to clarify one issue, I note that no invoices were submitted under the Security of Payment Act 1999, nor do I concede that it applies. I note that even if that legislation did apply the payment schedule I would be submitting would be full payment of the actual contract sum within seven days. This was $25,760 plus GST adjustment for the two items not ultimately carried out. This is in line with the quote you gave me before the work started." 17 The defendant made application under the Act for the appointment of an adjudicator. The adjudicator was appointed and submissions were made. 18 The respondent's adjudication response, which appears at Exhibit E198, was one and a half pages in length. Paragraphs 1 and 2 of that response stated: "1. The parties entered into a lump sum agreement on 14 March 2002. Annexed and marked A is a copy of the agreement. It is not in dispute that there were some deletions from the scope of the works. There is dispute as to its quantification. 2. It was a term of the agreement that the contract price would be paid upon completion."
19 These two paragraphs appeared under the heading "background". There is then a reference in the response that on 9 September 2003 the defendant had served what it described as a progress claim purportedly pursuant to the Act. After recounting the history of the application for adjudication, and the fact that the defendant lodged the adjudication application on 14 October and that the adjudicator had been appointed, the response deals with submissions in relation to the Act. 20 The adjudicator received documentation from both sides. It is apparent that his position was about as uncomfortable as mine is in respect of the way in which documentation has been presented. It is obvious that he did not receive a great deal of help with the documents. He said: "The respondent (that is the plaintiffs in these proceedings) contends that the claim is out of time saying that it was served more than twelve months after completion of the work under the contract. I have had much difficulty in dealing with this issue on the materials provided to me by the claimant which have been most unhelpful."
21 What had happened was that the defendant had served a document additional to the ones that I have referred to, which has been referred to in submissions before me as the "critical document", which is found at Exhibit E143. Although there is no evidence showing that the plaintiff did not receive this document until the adjudication process, such a claim was made before me. That document refers to work at the site on 10 September. The adjudicator said: "I have been obliged to accept that the weekly time sheet (that is the critical document to which I have just referred as E143) provided by the claimant for the week ending 15 September 2002 shows some activity on the job, identified as job number 2178 on this sheet and on the earlier dated daily hourly hire sheets by one D Zaffanato - who had been previously employed on the job as evidenced by the daily hourly hire sheets - on 10 September 2002 so that the claim appears to have been served on the last possible date."
22 That was the adjudicator's finding in respect of the submission put in para 3 of the response. The adjudicator then dealt with the payment schedule, the notice of intention to lodge the adjudication application and finally came to the adjudication response. The adjudicator said that under s 20 (2)(b) of the Act the respondent, that is the plaintiffs in these proceedings, could not include in the adjudication response: "Any reasons for withholding payment unless those reasons have already been included in the payment schedule provided to the claimant." 23 The adjudicator then determined that the claim was a valid claim as defined by the Act and, inter alia, that there was work done on the job on 10 September 2002 and that the claimant was entitled to make a progress claim under the Act and to seek adjudication. He also determined that the letter of 20 November 2002 from the respondent to the claimant and the letter of 10 September from the solicitors did not add anything to the respondent's case. 24 The controversial section of the determination is the following: "As to the matters raised in the adjudication response, I find as follows:
I can not have regard to paragraphs 1 and 2 as these reasons are not included in the payment schedule."
25 Mr Weinberger, counsel for the plaintiffs in these proceedings, submits that is a jurisdictional error committed by the adjudicator. He submitted that the correspondence to which I have referred, which was attached to the payment schedule and forming part of it, clearly raised the matters referred to in paras 1 and 2. That is, that the lump sum agreement was relied upon and that there was dispute as to its quantification. 26 Mr Muddle, counsel for the defendant, submitted that one has to be careful in reviewing that correspondence because what is being put in the correspondence was not dealing with the question that was really raised before the adjudicator and that is the variation claim to the contract. What was put simply at the bottom of the 29 September letter was a disputation of entitlement to the remainder claimed, that is the variations, and nothing further. Mr Muddle submitted that no claim was made in that letter, simply a bald assertion that there was a disputation about the remainder claimed. 27 It is a little curious that the adjudicator found himself in the circumstances where he said he could not have regard to those submissions because in para 2.9 he said this: "It is clear that during the course of construction there occurred changes to the work and that there arose a dispute over the additional work and cost."
28 That is clearly a recitation of part of what the plaintiffs were claiming in para 1 of the response which the adjudicator said that he would not have regard to. The adjudicator then went on: "This is evidenced in the first instance by a letter produced by the claimant addressed to the respondent dated 16 December 2002 in which the claimant asserts that it had completed work to the value of $64 odd thousand. Bearing in mind that this letter was composed long after the work was completed I take that amount to be the correct total, although it is not mirrored in the claim. The difference is not explained. Obviously the respondent disagreed with the claimant on the amount payable and refused to pay the amount claimed. It appears that the respondent instead paid three amounts to the claimant as evidenced by the card transactions document provided by the claimant."
29 It is clear that the adjudicator was very much alive to the issue that the plaintiffs disputed the matters claimed by the defendant, albeit that he had said that he would not have regard to paras 1 and 2. In paragraph 2.9 the adjudicator said: "The plaintiff had not taken issue with the quantum of the claim or the value of the work other than to maintain that the whole of the amount unpaid was disputed." The adjudicator also noted that nowhere did the plaintiffs identify what amount has been paid and accordingly he had had to assess the amount paid and the balance payable from the confusing material put forward by the claimant. 30 Mr Weinberger submits that the adjudicator also fell into error in failing to identify the terms of the contract and, secondly, that he failed to value the contract. In other words, he did not comply with his duty under the Act or misunderstood it to the extent that those failures were jurisdictional errors. 31 There was also a claim that there was denial of natural justice. The question before me is whether there is a serious issue to be tried in respect of these matters and Mr Muddle has submitted there is no serious issue to be tried. 32 Mr Muddle submitted that what this adjudicator did was to look at the terms of the contract to decide that there were claims made pursuant to a variation and when one looks at a document in evidence, E80, before the adjudicator there was evidence which included a claim that the plaintiff had "verbally requested" the defendant to carry out further works in relation to the structure. That was the claim that he was looking at and that was the claim that he had to decide on the documents before him. He considered those matters. He did not fail to consider them. What the plaintiffs' claim here is that he decided against them inappropriately. If that was an error it is not a jurisdictional error. 33 The portions of the determination to which I have referred in my view indicate that this adjudicator was struggling to do his duty pursuant to the Act, notwithstanding the difficulties in which he found himself. He did his best in the circumstances of the material before him and he said that he was obliged to accept that "critical" weekly time sheet. Mr Weinberger candidly conceded that no issue was taken with that time sheet before the adjudicator but submitted that was because of a prohibition upon that process pursuant to s 22(2)(c)&(d). 34 Whatever be the case in respect of that document, in my view the adjudicator clearly strived to do his duty and found, particularly in the last paragraph of 2.2, that he was obliged to accept the critical document as part of the contract and that the work was in fact done. Whether that is right or wrong is another matter but I am looking at what he purported to do and it is clear to me that he had regard to the Act as required by s 22; that he had regard to the contract that was the best evidence before him, even though the documents were unhelpful; that he had regard to the payment claim; that he had regard to the payment schedule; and that he also had regard to the submissions. Although he said that he did not have regard to paragraphs 1 and 2 of the response, I am of the view he effectively had regard to the submission put generally that this was a lump sum contract. 35 There is also a point raised by Mr Weinberger that a jurisdictional error was made in failing to value the contract. Once again the adjudicator in setting out the progress payment in sections 2.9 and 2.10 of his determination in my view did value the contract. Whether that was right, as I say, is another matter. I am not satisfied on the balance of probabilities that there is a serious issue to be tried on those matters. 36 The final matter is the question of a reference date. Under s 8 of the Act a right to a progress payment is said to arise in this way: "(1) On and from each reference date under a construction contract a person: (a) Who has undertaken to carry out construction work under the contract, or, (b) Who has undertaken to supply related goods and services under the contract is entitled to a progress payment."
37 S. 8(2) of the Act provides that a reference date in relation to a construction contract means a date determined by or in accordance with the terms of the contract and if the contract makes no express provision the last day of the named month in which the construction work was first carried out. There was a point raised by reason of the inclusion of a reference date in the progress claim. I do not regard that point as going anywhere. If the work is done pursuant to a construction contract then on and from the reference date, that being either in the contract or at the end of the month on which the work was done, the progress payment can be claimed. 38 The adjudicator considered the point raised as to whether there was a jurisdictional question, that is whether the claim was out of time. He disagreed with the submissions put by the plaintiffs. Assuming that I am wrong in respect of what I have referred to as the adjudicator's consideration of matters contained in paras 1 and 2 of the response, notwithstanding his statement that he had not had regard to them, I am not persuaded that it is a jurisdictional error. 39 But even if that is wrong it is to be remembered, in line with what McDougall J said in Musico v Davenport [2003] NSWSC 977 at par 52, that the matter is one of discretion. The application before me is for an injunction on an interlocutory basis. That too is a matter of discretion on the balance of convenience. 40 Both in my judgment in Paynter Dixon Constructions Pty Limited v JF & CG Tilston Pty Limited and Anor [2003] NSWSC 869 and in a recent judgment of Einstein J in Brodyn Pty Ltd Trading as Time Cost and Quality (ACN 001 998 830) v Philip Davenport and Ors [2003] NSWSC 1019 emphasis has been placed on the interim nature of the process under this Act. It is just that. The intention is to effect a speedy payment of contractors. It does not affect the parties' rights and importantly s 32 in my view looms large in deciding this case. Even if there had been a serious issue to be tried on a balance of convenience I would not be persuaded that I should restrain the defendant in this matter. The amount in issue between the parties ($30,000) in respect of the contractual dispute suggests that this matter should be litigated in the Local Court. 41 I refuse the application for injunctive relief. The plaintiffs are to pay the defendant's costs of the interlocutory application. This matter is adjourned to the directions list at 12 noon on 14 November 2003. *****
Last Modified: 11/25/2003 DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.