67 It is true that the strictly correct approach is to view the work done overall and in total to assess its reasonableness: see Riverside Motors Pty Ltd v Abrahams [1945] VLR 45 at 55 and Pavey & Matthews (at 263). However, in that exercise, apart from considering the views expressed by the expert witnesses, my view is that it is perfectly proper and open to take into account also the views of Mr Zeater. It is all the more so where he is a licensed builder. Each invoice should be separately so reviewed in terms of the price (inclusive of GST) indicated.
68 Invoice No 464 of 4 July 2007 dealt with the demolition of part of the old brick factory in the agreed contract amount of $33,000.00. Mr Worthington accepted this as the original tender price, Mr Capladi made no comment on it and neither did Mr Zeater or Mr Rahme. It was paid. I accept it as a fair and reasonable amount.
69 Invoice No 465 of 10 July 2007 in the amount of $5,599.50 related to the hire and use of a saw cutter during the demolition phase. Mr Zeater conceded an amount of $4992.00 and the disputed amount was $607.50. This represented a variation to the demolition contract to meet what Mr Rahme said was a concealed concrete beam not ascertainable at the time of the original site inspection and in respect of which the contract price excluded "latent conditions." Mr Zeater's position was that it was up to Rahme Civil what means and equipment it used to perform the demolition work and, in any case, the beam was not concealed. Mr Worthington considered the cost to hire the saw cutter was reasonable. Mr Capladi considered Mr Rahme should have made a full and thorough inspection prior to submitting the quotation. I am not satisfied Rahme Civil has made out a case for the extra cost of the saw cutter over the original tender price. Thus, the amount owing on this invoice becomes $4,992.00.
70 Invoice No 477 of 12 July 2007 in the amount of $5,373.50 concerned the cleaning and sorting of asbestos mixed with bricks and concrete buried under a concrete slab which was found only during demolition. Mr Zeater conceded an amount of $3,817.00 on this invoice but disputed $1,556.50. Again, Mr Rahma, relied on the "latent conditions" exclusion. It is to be noted that the original contract price excluded "any surface or buried demolition material…removal of contaminated materials" but included "asbestos removal." Mr Worthington considered the cost reasonable by reference to the quantity as to labour and truck hire rates whereas Mr Capaldi assessed an amount at less than half of that claimed. I accept the need for an extra cost as the offending material was buried. Mr Worthington made his assessment by express reference to photographs of the material but Mr Capaldi merely expressed a view without reasoning Mr Worthington's approach. I prefer Mr Worthington's assessment and will therefore allow the full amount of $5,373.50 for this item.
71 Invoice No 491 of 30 July 2007 was in the amount of $577.50 in relation to the use of an excavator. Mr Zeater accepted the correctness of the invoice. Mr Worthington said the amount was reasonable; Mr Capaldi made no comment. I will accept the claimed amount as reasonable.
72 Invoice No 501 of 27 August 2007, as referred to earlier, dealt with the cost of demolishing and removing part of the front facade after the truck incident at the direction of Mr Zeater in the amount of $9,594.20. As it happened, the invoiced amount was substantially less than that calculated by Mr Capaldi of $12,018.00 who said Mr Worthington did not allow for safety on the site as to the use of "tiger tails" on electrical wires, scaffolding, providing pedestrian access and the use of a crane for the temporary support. I will, therefore, allow the invoiced amount of $9,594 as reasonable consistent with Mr Worthington's approach.
73 Invoice No 506 of 5 September 2007 in the amount of $701.25 in relation to the use of an excavator. Mr Zeater did not dispute the correctness of this claimed amount. Mr Worthington said it was reasonable and Mr Capaldi made no comment. I will allow it.
74 Invoice No 520 of 7 September 2007 in the amount of $99,255.20 was in relation to excavation work and removal of waste material and debris. Of the claim, $93,700.00 has been paid by Zeater & Sons and the balance of $5,555.20 is disputed. The dispute arose due to differences in what Mr Rahme and Mr Zeater said they agreed as to a reduction in the rates for the removal of material from the site. Mr Rahme said, as confirmed in an email to Zeater & Sons of 27 July 2007, that the rate would be $55.00 per cubic metre whereas Mr Zeater said it would be $35.00 per cubic metre for certain types of waste and $45.00 per cubic metre for others; there was also disagreement as to the amount of waste actually removed. Regardless of any such agreement, Mr Worthington considered the rate charged by Rahme Civil for the volume of waste involved was reasonable according to industry standard charges. Mr Capaldi made no comment. Given the reasonableness of the rate according to Mr Worthington, I accept the amount claimed on the invoice so that $5,555.20 remains due.
75 Invoice No 532 of 26 September 2007 in the amount of $4,868.80 in relation to the cost of trucks to remove the debris was accepted by Mr Zeater as correct. Mr Worthington considered it to be fair and reasonable. I will allow it.
76 In the result, the amounts I accept as reasonable for the eight invoices on a quantum meruit basis are
as follows -
Date Invoice No Amount
$
4.7.07 464 33,000.00
10.7.07 465 4,992.00
12.7.07 477 5,373.50
30.7.07 491 577.50
27.8.07 501 9,594.20
5.9.07 506 701.25
7.9.07 520 99,255.20
26.9.07 532 4,868.80
Total: $158,362.45