[2023] NSWCATCD 155
NCAT Consumer and Commercial
2023-08-25
Original judgment source is linked above.
Outline
Jurisdiction
History of the proceedings
Hearing
Relevant law
Owners' evidence
Builder's evidence
Owners' submissions
Builder's submissions
Submissions in reply
Consideration - application of the owners
Claim 1
Claim 2
Claim 3
Claim 4
Claim 5
Claim 6
Claim 7
Claim 8
Claim 9
Claim 10
Claim 11
Claim 12
Claim 13
Claim 14
Claim 15
Summary
Consideration - cross-application, ie application of the builder
Component 1
Component 2
Component 3
Component 4
Components 5 and 6
Component 7
Component 8
Summary
Conclusion
Costs
Orders
In HB 23/18492: 1. The applicants are to pay the respondent $52,325.71 on or before 10 October 2023. 2. Within 24 hours of that amount being paid, the respondent is to provide the owners with unrestricted access and possession of their property, including but not limited to the provision of all keys. 3. No order as to costs.
In HB 23/30249: 1. The application is dismissed. 2. No order as to costs.
Appendix A Chronology Date Description Reference 17 Dec 20 Contract signed - contract price $555.489.96 A7, B2/29 23 Jun 21 Building work commenced B2/1 05 Jul 21 Owners paid $3,179.98 Not disputed 07 Jul 21 Owners paid $2,309.98 E1 19 Jul 21 Owners paid $157,690.02 E2 29 Jul 21 The owners vacated the site and began renting A5 20 Aug 21 Builder issued invoice #29 for $232,309.98 A140-144 26 Aug 21 Owners paid $160,000.00 E2 09 Mar 22 Owners paid $160,000.01 E3 15 Mar 22 Owners paid $47,009.68 for PC and PS items E3 16 May 22 Builder issued invoice #68 for $11,173.34 A145-146 26 May 22 Owners paid $11,173.34, a total paid of $541,363.01 E3 13 Jul 22 Owners provided builder a copy of their tile order A74-76 25 Jul 22 Owners advised builder as to their carpet order A100 08 Aug 22 The parties met on site A46 25 Aug 22 Builder sent email, giving notice of suspension of work, based on unpaid invoice #70 B3/181 29 Aug 22 Builder's letter said additional cost to complete of $215,000, that $165,277.94 had to be paid before work recommences, as set out in invoice #78 A47-49 01 Sep 22 Owner's email disputed validity of invoice #70 B4/1 08 Sep 22 Owners sent letter to builder, alleging breaches of the HBA and disputing the builder's right to suspend work D8 20 Oct 22 Owners' letter said variations need to be signed and agreed before work is undertaken A53 24 Oct 22 Builder's letter said "Final increase $150,000" A51 31 Oct 22 Builder sent payment schedule for that amount A52 01 Nov 22 Owners signed schedule (the agreement) A52 23 Nov 22 Owners paid $25,000 E4 27 Jan 23 Owners advised builder carpet ready for installation A103 10 Feb 23 Owners paid $40,000 E5 19 Feb 23 Builder issued variations #1, #2, and #3 and email A56-58, 63 19 Feb 23 Builder told owners not to give notice to estate agent A139 24 Feb 23 Emails exchanged re variation A59-62 24 Feb 23 Builder issued invoice #137 for $2,520.00 A89
Date Description Reference 01 Mar 23 Emails exchanged in relation to carpet A105 08 Mar 23 M Babekuhl signed stat. dec. re plumbing work A92 08 Mar 23 Builder issued invoice #150 for $7,618.71 A54 08-21 Mar Emails exchanged re walk through A65-71,98-99 9 Mar 23 Owners paid $935 to their building inspector A97 14 Mar 23 Builder issued invoice #151 for $1,795.20 A64 22 Mar 23 Builder's email said work completed, attached photos A81-86 22 Mar 23 First of emails, up to 20 Apr 23, re completion A126-135 26 Mar 23 Builder issued variations #4, #5, #6 and #7 A73, 77-79 27 Mar 23 Builder issued invoice #155 for $17,308.42 A72 27 Mar 23 Owners disputed variations #4-7 and invoice #151 A80 05 Apr 23 Emails re plumber not signing compliance document A90 05 Apr 23 Occupation certificate issued to owners A108 05 Apr 23 Owners raised lack of gas compliance certificate A123 05 Apr 23 Builder issued invoice #160 for $64,999.99 A87 05 Apr 23 Builder issued invoice #160 for $49,999.99 A119 10 Apr 23 First of nine recent receipts re 03 Apr 23 - 05 Jun 23 A109-117 11 Apr 23 The owners paid $35,000, giving total of $641,363.01 A5 13 Apr 23 Owners sought final inspection before paying invoice A120 20 Apr 23 Owners lodged an application with the Tribunal 26 Apr 23 Builder issued invoice #168 for $24,441.00 A88 02 May 23 Gas compliance certificate provided A124 31 May 23 Builder alleged unauthorised site access by owners A138 06 Jun 23 Builder purports to cancel agreement A136 09 Jun 23 First directions hearing conducted by the Tribunal 16 Jun 23 Notice of hearing issued for the application 02 Jul 23 Builder lodged a cross-application with the Tribunal 06 Jul 23 Notice of hearing issued for the cross-application 15 Jul 23 Builder's letter to owners said it would be seeking all costs associated with the building work B5/83 15 Jul 23 Builder issued invoice #179 for $623,996.75 B2/137-142 21 Jul 23 Second directions hearing conducted by the Tribunal
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 23 July 2024
[1998] HCA 11
[2003] HCA 22
[1990] HCA 59