© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2024] NSWCATCD 19
NCAT Consumer and Commercial
2023-10-30
Original judgment source is linked above.
REASONS FOR DECISION
Background
Treated Pine Retaining Wall Prepare for treated H4 sleeper retaining wall. Clear away soil and debris from existing concrete swale drain. Install blue metal and geo-fabric to existing concrete drain to continue flow of water. Fix treated sleepers to existing fence with bugle screws, to retain new premium garden soil mix. Construct sleeper retaining wall approximately 10 m in length and 800 mm in height, using 200x 75 H4 treated sleepers, post to be set every 1.2 m in concrete. Back of retaining wall to be lined with geo-fabric drainage material added. Supply and plan a selection of Giant Strelitzia's and Colocasia (Giant elephant ears).
Besser Block Retaining Wall Excavate out by hand for new Besser block retaining wall (wall to retain large giant strelitzer) and proposed steps. Dug out soil to go in behind treated pine retaining wall. Pour concrete footings for wall, stater bars to be used. Build and construct besser wall approximately 1 m in height and 4 m in length. Back of wall to be water proofed, drainage material to be added with Ag-pipe. Construct besser block steps.
Landscaping/Pavers Pull up existing pavers, break up paving and add in behind wall for additional drainage. Excavate out by hand for new paving heights and levels. Soil to go in behind treated pine wall. River sand to be supplied, brought in screeded to the required heights and levels. Lay new paver (supplied by client) approximately 35m sq. Pave bond to be swept through paver joints.
Applicants
Respondent
CAUSES OF ACTION OF THE APPLICANTS
DOCUMENTARY EVIDENCE OF THE APPLICANTS
Photographic Evidence
Landscaping Plans
Extracts from Websites
Extract of the Respondent's NSW Fair Trading Licence
Document Entitled 'Summary of Incomplete Parts and Cost to Complete With Alternative Companies'
The Terms of the Contract Between the Parties And When the Contract Was Formed
Was It A Term of the Contract That the Height of the Retailing Walls Be Less Than 600mm?
Did The Respondent Breach The Statutory Warranties in s 18B of the HB Act In Respect of the Work Performed?
Incomplete Work and Termination of the Contract
Did the Respondent Repudiate the Contract and Did the Applicants Accept the Repudiation?
Is the Applicant Entitled to Damages for the Increased Costs of Completing Incomplete Work?
Has the Respondent Repudiated the Contract By Performing Unlicensed and Uninsured Work?
Australian Consumer Law Causes of Action of the Applicants
The 'Costs' of Mr Pickett In Attempting to "Resolve the Issue"
Damages for Distress And Inconvenience
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 13 August 2024
Pickett
Savage
[2017] QCAT 228
[2022] VSCA 48
(1955) 94 CLR 216
(1954) 90 CLR 613
(1994) 179 CLR 403
(2004) 218 CLR 471
(2004) 219 CLR 165
(1988) 18 NSWLR 540
(2016) 260 CLR 1
(1964) 112 CLR 597
(2011) 297 ALR 56
(1938) 60 CLR 336
(1976) 136 CLR 444
(2007) 233 CLR 115
(1989) 168 CLR 385
(1982) 149 CLR 537
(1991) 174 CLR 64
(2000) 54 NSWLR 536
(2003) 77 ALJR 768
(1989) 89 ALR 275
[2004] HCA 52
[1938] HCA 34