Invalidity: s 34
42 Section 34 of the Act provides as follows:
"34 No contracting out
(1) The provisions of this Act have effect despite any provision to the contrary in any contract.
(2) A provision of any agreement (whether in writing or not):
(a) under which the operation of this Act is, or is purported to be, excluded, modified or restricted (or that has the effect of excluding, modifying or restricting the operation of this Act), or
(b) that may reasonably be construed as an attempt to deter a person from taking action under this Act,
is void."
The parties' submissions
43 John Holland's submissions on this point were based on the proposition that cl 5.7 should be "properly construed as permitting security to be retained for the purpose of securing the repayment of adjudication monies" (written submissions dated 4 August 2006, para 62). If cl 5.7 were to be so construed, then, John Holland submitted, "it necessarily undermines the scheme of adjudication that is established by the Act. It would permit a principal which has suffered an adverse adjudication determination to reverse the result of that determination without pursuing the procedure envisaged by the Act, namely, commencing proceedings in which an order for restitution of adjudication monies may be made under s 32(3)(b) of the Act. Instead, a principal could have recourse to security … . It could, as in the present case, refuse to reduce the amount of security - notwithstanding that the Contractor's obligations of performance under the Contract have been discharged and Practical Completion has been achieved … " (ibid, para 64).
44 In supplementary written submissions dated 10 August 2006, John Holland extended its attack to cls 42.7 and 46. The basis was that if cl 42.7.2 permitted the superintendent to determine and certify an amount owing that was inconsistent with the results of adjudication determinations then it was void; and so were cls 42.7.4 and 46, which in substance would permit the RTA to give effect to any such determination of the superintendent. On this basis, John Holland submitted, the superintendent could issue a "negative certificate" pursuant to cl 42.7.4 "which negates prior adjudication determinations" and which would "set at naught the entitlement to progress payments that the Act provides and protects …" (citing Abacus Funds Management v Davenport [2003] NSWSC 1027 at paras [35] to [37]).
45 The RTA's primary position was that the s 34 point did not arise because the discretion under cl 5.7 was not qualified in any relevant way (in particular, by cl 5.1). I have dealt with that submission already (see para [24] above).
46 Alternatively, the RTA submitted, John Holland's s 34 submissions fell down at every step. The security was not to be characterized in the narrow way that was the foundational assumption of John Holland's submissions. John Holland's obligations under the contract had not been discharged. The security was not a precondition of payment with no other function (contrast Brewarrina Shire Council v Beckhaus Civil Pty Ltd [2005] NSWCA 248 at para [219]). The rights given by the Act were interim rights, which might be reversed after a final determination in some appropriate forum, and it was not inconsistent with any provision of the Act or, more generally, its "purpose", to require a contractor to provide security pending such a final determination.
The contractual scheme
47 Clause 42.7 provides in essence for what in ACA Developments Pty Ltd v Sullivan (2005) 21 BCL 71 at 76 [16], although speaking of s 32(3), I described as "a final 'accounting' ". The process for which the clause provides takes place after the expiry of the defects liability period, which in turn is 12 months after the achievement of practical completion. The only construction work for which John Holland had any entitlement to be paid would have been performed prior to practical completion (on the basis that, as the term was defined in the contract, practical completion could not be achieved until the works were completed "except for minor omissions and minor defects". The only construction work that would be performed thereafter would be defects rectification, for which John Holland had no entitlement to be paid.) Thus, the cl 42.7 procedure would necessarily commence at a time when a payment claim could no longer be served (s 13.4(b)). In other words, by the time the machinery of cl 42.7 comes to be engaged, the regime for progress payments for which the Act (read in conjunction with the contract) provides has come to an end.
Analysis
48 I do not think that anything in cls 5.7, 42.7 or 46 (considered separately or together) excludes, modifies or restricts the operation of the Act. Plainly, cl 5.7 by itself does not do so.
49 It is correct to say that cl 42.7 requires a final reconciliation of the amount owing by one party to the other under the contract. It is equally correct to say that this final reconciliation may reach a conclusion inconsistent with that reached by one or more adjudicators in respect of payment claims made in respect of work performed under the contract. But it does not follow that the operation of the Act is thereby excluded, modified or restricted.
50 As I have already said, the Act (at least implicitly) recognises that adjudicators may err. That is why an adjudicator's determination is not finally conclusive of rights and liabilities under the contract. (I recognise that, absent reviewable error, such a determination may be regarded as conclusive of an entitlement to the amount of a progress payment; but that is a different matter.)
51 In a practical sense, a final determination of a balance owing under a construction contract may "undo" the effect of a prior determination by an adjudicator of the amount of a progress payment. But that is because the final determination - however it is made - establishes, on a final basis, the amount owing by one party to the other. If the final determination is made by a court, or arbitral or other tribunal, of competent jurisdiction then it establishes finally and conclusively (of course, subject to any appeal that may lie) the relevant rights of the parties to the contract.
52 In the present case, the contract authorises the superintendent (in the first instance) to make a final determination of the balance due by one party to the other in respect of work under the contract. There is no reason why a final determination by the superintendent could not "undo" the effect of a prior determination by an adjudicator, in just the same way as a final determination by a court or arbitral or other tribunal might do so. Of course, the contract provides for a process of review of determinations by the superintendent (cl 45); there is no equivalent review process for the decisions of courts or arbitral or other tribunals (and such rights of appeal as there may be are not to be equated to the kinds of review for which cl 45 provides). But this relates to the finality of the superintendent's determination. It says nothing as to the subject matter of that determination, or as to its effects on prior determinations by adjudicators.
53 Mr Collins submitted that the superintendent could not revisit the proper amounts of progress payments when he performed his function under cl 42.7 and issued a final payment schedule. The submission was that the superintendent was, in respect of progress payments, "functus officio".
54 The parties entrusted a number of functions to the superintendent. One was the valuation and certification of progress claims (cl 42.1.2). Another was the issue of a final payment schedule (cl 42.7.1). Of course, there were many others; and not all connected with payment obligations.
55 A payment schedule issued by the superintendent in response to a monthly payment claim must identify the payment claim to which it relates, must be based on the superintendent's determination of the contract value of work carried out, and must give reasons if the amount certified is less than the amount claimed (cl 42.1.2).
56 A final payment schedule under cl 42.7 is required to set out the superintendent's determination of the amount finally due by one party to the other in connection with the work under the contract. In substance, what is required is a valuation of all work performed under the contract for which John Holland is entitled to be paid, and all other claims in connection with the work under the contract for which John Holland is entitled to be paid, and a comparison of the total of those amounts with the total amount actually paid and any amounts that under the contract John Holland is liable to pay to the RTA. I do not think that there is anything in this scheme which puts it outside the superintendent's power to reassess the value of work that has been valued by an adjudicator, even though the adjudicator's value may differ from that assigned by the superintendent in the latter's payment schedule under cl 42.1.2.
57 If Mr Collins' submission were correct, the superintendent would be bound to accept every valuation of work by an adjudicator, even though there might be a palpable or manifest, but not reviewable (in the Brodyn sense) error: for example, an application of the wrong rate for an item of work, an accidental duplication or double counting for a particular item of work, or a simple arithmetical error. Mr Collins did not shrink from embracing this consequence. He submitted that it was up to the party dissatisfied to take the dispute to the next stage of dispute resolution.
58 It is a little difficult to understand why the parties should have intended such a cumbersome procedure to be followed in the case of palpable or manifest error. If it be accepted that errors of the kind described in the previous paragraph might be cured, or corrected, on a final determination of the balance due under the contract (and Mr Collins did not submit to the contrary), there is no commercial utility in preventing the superintendent from doing this; in requiring him to rubber stamp the previous mistakes and send them on to the cl 45 processes. On the contrary, it seems to me, there is much utility (bearing in mind the availability of the cl 45 review process) in permitting the superintendent to attempt this task. For example, the commonsense and correctness of the superintendent's determination may be so clear that the party adversely affected by it will not trouble to take the next step.
59 Thus, I think, the construction for which Mr Collins contends lacks commercial utility; indeed, I think, it would lead to commercial inutility. I do not think that such an intention should be imputed to the parties unless their language permits of no other view; in my opinion, it does not.
60 Further, if Mr Collins' submission were correct, it would not be open to the superintendent to correct an obvious error that he himself had made in valuing a progress claim, in circumstances where John Holland had gratefully accepted the consequent payment. It is very difficult to see why this should be so.
61 In this context, what I have said in para [59], based on considerations of commercial utility and inutility, is equally applicable.
62 Once it is accepted, as I think it must be, that the interim determination of rights under the Act (either alone or in conjunction with the contract) and the final determination of rights under the contract are separate and distinct, I think it must follow that no one - superintendent or other - performing the latter function can be bound by a determination reached in performing the former function. The processes are separate and distinct; and they remain so even though the same person is (at least "at first instance") involved in both of them. The performance of one function does not render that person functus officio in respect of the second.
63 In short, I do not think that a final determination of rights (including as to what is payable by one party to the other under the contract) has anything to do with the operation of the Act, in circumstances where that determination of necessity takes place after the rights given by the Act cease to be available (see para [47] above). It follows, in my view, that nothing done as part of or in the course of such a final determination of rights can exclude, modify or restrict the operation of the Act.
64 Equally, I think, there can be no purported, or effect of, exclusion, modification or restriction of operation.
65 That leaves for consideration s 34(2)(b). If the submission is to be made good in respect of that paragraph, it must necessarily mean that a contractor in John Holland's position might be deterred from taking action under the Act (ie, claiming a progress payment) by the prospect of being required to repay it, and of having its security retained until such repayment was made. The obvious answer to that is that John Holland was not. It entered into this contract, and made progress claims, knowing that at least one half of its security must be held (and, perhaps, the whole might be held) until the issue of a final payment schedule and the satisfaction of obligations certified by it. Although there was some suggestion in the correspondence of a pattern of dealings, or expectations, as to return of part of the security following practical completion, John Holland did not rest its case, under s 34, on any such conduct or expectation.
Conclusion
66 I do not think that any or all of cls 5.7, 42.7 or 46 (considered separately or together) are rendered void by operation of s 34(2) of the Act.
Conclusion and orders
67 John Holland's attacks on the RTA's decision not to release any part of the security fail. I make the following orders: