Introduction 1 The plaintiff ("Abacus") engaged the second defendant ("Renascent") to carry out refurbishment of Abacus' premises at 109 Pitt Street, Sydney. On 25 August 2003, Renascent served on Abacus a payment claim made pursuant to s 13 of the Building & Construction Industry Security of Payment Act 1999 ("the Act"). The claim was in the sum of $1,750,844.48. 2 On 9 September 2003, Abacus served on Renascent a payment schedule under s 13 of the Act. That payment schedule was accompanied by a progress certificate of Morgan Moore & Associates Pty Ltd, the "architect" under the contract. The progress certificate was in the amount of $372,038.32 and it was that amount that Abacus, in its payment schedule, said that it proposed to pay. It is accepted that the amount of $372,038.32 has been paid to or for the benefit of Renascent (in the latter case, by payment to a subcontractor of Renascent, who had obtained and served on Abacus a debt certificate under the Contractors Debts Act 1997). 3 Renascent was dissatisfied with Abacus' response to the payment claim, and accordingly applied to the third defendant ("Adjudicate Today"), an authorised nominating authority under the Act, for the appointment of an adjudicator. Adjudicate Today referred the application to the first defendant ("Mr Davenport") under s 19(1) of the Act. Mr Davenport accepted the application and accordingly, by s 19(2), "is taken to have been appointed to determine the application". 4 Thereafter, Abacus lodged with Mr Davenport an adjudication response under s 20 of the Act. The Determination 5 Mr Davenport made a determination in writing on 3 October 2003. Adjudicate Today provided that determination to the parties on 9 October 2003. Mr Davenport determined that Renascent was entitled to a progress payment of $819,796.32, made up as follows:
Admitted amount (i.e., the amount set out in Abacus' payment schedule) $372,038.32 Variations $ 49,687.00 On-site costs $313,081.00 Backcharges $ 84,990.00
6 The first of these amounts is self-explanatory. The second relates to a number of variations that had been claimed by Renascent that the architect, in its progress certificate, noted had not been resolved and that would be certified once resolved. 7 The third item relates to delay costs claimed by Renascent. That claim comprised an amount for on-site overheads and an amount for off-site overheads. Mr Davenport allowed the former, but not the latter. 8 The fourth matter relates to backcharges that Abacus had deducted. Mr Davenport found that the deduction was unjustified, and accordingly included it in the calculation of the progress payment. The issues for determination 9 Abacus sought relief in the nature of certiorari to quash Mr Davenport's determination. It relied on five asserted errors of law that, it said, were apparent "on the face of the record". However, whilst my judgment was reserved, the parties resolved their differences in relation to variations: the error alleged by para 1(a) of the summons. That means that paras 2(a) and 6 were not pressed. 10 Renascent submitted that, on the proper construction of the Act, relief in the nature of certiorari was not available. 11 The issues for decision were therefore:
(1) Discharge order 1 made by Gzell J on 23 October 2003.
(3) Order the plaintiff to pay the second defendant's costs.
(4) Reserve liberty to apply. 58 The liberty to apply is reserved against the unlikely event that either Mr Davenport or Adjudicate Today seeks any relief, or in case Renascent wishes to claim against the usual undertaking as to damages given by Abacus as the price for obtaining interlocutory relief. ******
Last Modified: 11/14/2003 DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated.
Abacus
Davenport & Ors
CITATION : Abacus v Davenport & Ors [2003] NSWSC 1027 HEARING DATE(S) : 28 October 2003 JUDGMENT DATE : 14 November 2003