© 2026 Zoe. All rights reserved.
Zoe is a legal information platform. Always consult the Federal Register of Legislation for authoritative text.
[2024] NSWCATCD 39
NCAT Consumer and Commercial
2023-11-01
Original judgment source is linked above.
INTRODUCTION
JURISDICTION
ISSUES FOR DETERMINATION
PROOF
THE CONTRACT AND HOME BUILDING ACT 1989
ARE THE OWNERS ENTITLED TO REIMBURSEMENT OF PAID INVOICE #10418 FOR EXTRA WORKS VARIATION IN THE SUM OF $14,500.00? ('VARIATION CLAIM')
Quantum meruit
Conclusion
Should the $14,500.00 paid by the owners be refunded?
IS THE BUILDER ENTITLED TO PAYMENT OF INVOICE #10327 FOR A PRICE RISE IN THE SUM OF $13,000.00?
ARE THE OWNERS ENTITLED TO COMPENSATION FOR DELAY TO THE BUILDING WORKS IN THE SUM OF $40,800.00? ('DELAY CLAIM')
CONCLUSION
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales. Registrar DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 20 December 2024
(1938) 60 CLR 336
(2012) 246 CLR 498
(1906) 4 CLR 347
(1990) 20 NSWLR 251
(1991) 174 CLR 64
(2000) 54 NSWLR 536
(2003) 77 ALJR 768
(1989) 89 ALR 275
[2012] HCA 7