[2025] VSC 774
General information, not legal advice.
Supreme Court of Victoria
2025-12-11
Matthews J
Original judgment source is linked above.
(a) council has a recognised legal right, being the right to be provided with the executed PCG. This is a contractual right in respect of which ADCO Group is in breach;
(b) damages are an inadequate remedy; and
(c) there is no equitable reason to refuse the injunction sought, since it is just that a mandatory injunction be ordered. I have rejected ADCO Group's submissions that it has already done all things within its power to provide the executed PCG and that it would be impossible for ADCO Group to perform.
(a) ADCO Group is in breach of clause 5.6 and Item 14A of the Construction Contract; and
(b) ADCO Group is required to provide to Council the executed PCG.
(a) the declaratory relief 'must be directed to the determination of legal controversies and not to answering abstract or hypothetical questions';
(b) the plaintiff or applicant must have a 'real interest' in seeking the relief;
(c) there must be a 'proper contradictor' in the sense of a person who has 'a true interest to oppose the declaration sought'. In appropriate cases, this requirement may be fulfilled notwithstanding the declarations are sought by consent; and
(d) declaratory relief may not [be] appropriate where the 'declaration will produce no foreseeable consequences for the parties'.
H Issue 4: Did ADCO Constructions enter into a contract or a collateral contract with Council to deliver an executed PCG to Council or to ADCO Group for provision to Council?
(a) the relevant legal principles in respect of contract formation;
(b) whether certain individuals (namely Mr McBurnie and/or Mr McLean) and/or ADCO Group had authority (actual or ostensible) or agency to enter into a contract with Council on behalf of ADCO Constructions;
(c) whether the conduct and circumstances relied on by Council give rise to the formation of the alleged contract between ADCO Constructions and Council. In this regard, Council principally relies on:
- the Tender Submission;
- the Departures Table;
- the Letters of Intent;
- the McLean 11 March Email;
- the McBurnie Email;
- the 23 March 2021 site meeting; and
- the Construction Contract;
(d) whether there was consideration given for the alleged contract;
(e) whether there was an intention to create legal relations between Council and ADCO Constructions;
(f) whether any collateral contract is void due to clause 7(b) of the Formal Instrument of Agreement of the Construction Contract; and
(g) whether the alleged contract is unenforceable due to s 126 of the Instruments Act.
It is not the subjective beliefs or understandings of the parties about their rights and liabilities that govern their contractual relations. What matters is what each party by words and conduct would have led a reasonable person in the position of the other party to believe. References to the common intention of the parties to a contract are to be understood as referring to what a reasonable person would understand by the language in which the parties have expressed their agreement. The meaning of the terms of a contractual document is to be determined by what a reasonable person would have understood them to mean. That, normally, requires consideration not only of the text, but also of the surrounding circumstances known to the parties, and the purpose and object of the transaction.
In any determination as to whether a binding contract exists, it is the objective intent of the parties, as revealed in the factual context, that is the paramount consideration. The fact of agreement and its content is to be determined by the communications between the parties considered objectively. It is also legitimate to consider the factual context in which the communications took place. Regard may also be had to communications between the parties subsequent to the date of the alleged contract, at least to the extent to which those communications may inform the meaning of the language used by the parties in earlier exchanges between them which evidenced the fact of agreement and its content and defined the commercial context.
[109] In order to establish a collateral contract in respect of a statement of fact, three circumstances are usually present:
(a) an intention by the maker of the statement that the statement be relied on;
(b) reliance by the party alleging the existence of the contract. There is a presumption of reliance where the maker of the statement intended the statement to be relied on and a contract was entered into; and
(c) an intention on the part of the maker of the statement to guarantee its truth or falsity_._
[110] The third circumstance is essential and must be proved or inferred.
...
[112] It is not possible to infer a collateral contract for which the consideration is the entry into the principal contract, if it is agreed prior to the making of the statement subsequently relied upon as a collateral contract, since the consideration in such a case would be past consideration.
...
H.2 Who had authority or agency on behalf of ADCO Constructions to enter into the contract?
Actual authority is established on the basis of a consensual legal relationship between principal and agent, under which the agent is conferred with authority to act on behalf of the principal. Consent may be express, or implied when it is inferred from the conduct of the principal and agent and the circumstances of the case. The scope of authority is to be determined by the ordinary principles of construction of contracts, and by reference to any proper implication from the course of business between the principal and its agent.
...
Apparent authority, on the other hand, is not based on a consensual relationship between principal and agent. Instead, apparent authority arises when there is an appearance or representation of authority to a third party, created by the principal in respect of her or his agent. Succinctly expressed in the context of contractual relations:
... "apparent" or "ostensible" authority ... is a legal relationship between the principal and the contractor created by a representation, made by the principal to the contractor, intended to be and in fact acted upon by the contractor, that the agent has authority to enter on behalf of the principal into a contract of a kind within the scope of the "apparent" authority, so as to render the principal liable to perform any obligations imposed upon him by such contract. To the relationship so created the agent is a stranger. [She or he] need not be (although [she or he] generally is) aware of the existence of the representation ... The representation, when acted upon by the contractor by entering into a contract with the agent, operates as an estoppel, preventing the principal from asserting that [she or he] is not bound by the contract.
Although this original expression of apparent authority was confined to an agent's authority to enter into contracts, the underlying principles are relevant, and have been applied, to any conduct that an agent purports to perform on behalf of her or his principal.
The scope of apparent authority therefore fundamentally relies on the representation made by the principal to a third party. Crucially, the representation must be made by the principal or a person to whom the principal has conferred actual authority. Without more, a mere representation by a person purporting to act as an agent as to that person's own authority to act on behalf of a principal is insufficient to establish apparent authority. For apparent authority to exist, the representation itself may be made through words or conduct, expressly or impliedly, or by acquiescence; and it is sufficient that the agent is placed in a position by the principal to allow her or him to give the appearance of authority. However, the scope of apparent authority is at all times limited by the third party's knowledge of limitations imposed on the agent's authority. If the third party knows that the agent is acting in violation of her or his actual authority, apparent authority cannot be established.
For completeness, additional observations may be made in relation to attribution of conduct to a corporation: (1) generally, the principles of attribution are subject to a corporation's constitution, which may define or determine the authority that can be conferred on an agent; and (2) actual authority is conferred by the corporation's constitution or some antecedent act such as a resolution, or by those who have authority and are permitted to delegate this authority.
Actual and apparent authority are not mutually exclusive; it is often the case they will coincide, but they can exist independently and the scope of authority of each may differ. Further, as between 2 corporations within a corporate group, the question of any relationship of principal and agent must be approached applying the relevant principles as the corporations are separate legal entities despite the connection to the same group.
(a) at item 1 of the Departures Table, ADCO responded: 'Item 14A- please insert "ADCO Constructions Pty Ltd"';
(b) further to (a) above, the reference to the specific ADCO Constructions Pty Ltd entity, suggests that the references to 'ADCO' are in fact references to both ADCO Constructions and ADCO Group;
(c) that position is also supported by the references in ADCO's responses to 'We' (see for example, ADCO's Response of 20.10.20 on item 2 of the Departures Table);
(d) it is further supported by a further reference to ADCO's '50 years of experience' (see ADCO's Response at item 6 of the Departures Table), which Mr McBurnie confirmed during his evidence incorporated the experience of ADCO Constructions.
(a) at all material times prior to the execution of the Construction Contract, ADCO Constructions represented to Council that ADCO Group had the legal right and entitlement to obtain a PCG from ADCO Constructions and provide it to Council;
(b) ADCO Constructions had the authority to make such a representation; and
(c) Council reasonably relied on that representation.
(a) the identification of ADCO Constructions as ADCO Group's parent company in the Tender Submission and the remaining contents of that document;
(b) ADCO Constructions' correspondence during the negotiation of the Construction Contract;
(c) ADCO Constructions' agreement to the Departures Table;
(d) the undertakings given at the site meeting on 23 March 2021 as recorded in the relevant site meeting minutes; and
(e) Mr McLean's and Mr McBurnie's involvement in the negotiation of the Construction Contract.
(a) Tender Submission - the mere fact that ADCO Constructions was the parent company, together with the other content of the Tender Submission, does not give rise to any relevant representation. There is no evidence that Council relied on the Tender Submission in forming the view that ADCO Group could enter into a contract on behalf of ADCO Constructions. Mr Ridley's and Mr Freer's clear evidence was they understood that the Tender Submission was from ADCO Group. Further, it is to be observed that the Tender Submission deleted the requirement for a PCG. Given this, the Tender Submission could not give rise to the requisite representation.
(b) Alleged correspondence from ADCO Constructions - correspondence from Mr McLean variously referred to ADCO Group and ADCO Constructions, sometimes within the same letter. While it may be less than orderly to send letters in this way, it does not bear upon the issues in this proceeding. The letters were concerned with the tender clarifications relating to pricing and clearly concerned ADCO Group's Tender Submission. On any view, they do not give rise to the relevant representation. Further, there is no evidence that Council relied on these letters in forming the view that ADCO Group could enter into a contract on behalf of ADCO Constructions. Indeed, there is no evidence to support a finding that Council relied on the company names used in these letters. As to the correspondence concerning Mr McBurnie, the submissions set out at paragraph 324 applies here as well.
(c) ADCO Constructions' agreement to the Departures Table - while ADCO Constructions does not accept that it approved the Departures Table, even if it did that does not give rise to a representation made by ADCO Constructions to Council. Council had no knowledge of whether ADCO Constructions had or had not approved the Departures Table. Mr Ridley gave evidence that he had assumed, based on prior dealings, that ADCO Constructions would provide the PCG.
(d) 23 March 2021 site meeting - the site meeting concerned the conduct of the Project, which was being undertaken by ADCO Group. The relevant minutes concern the obligation under clause 24.1A of the draft construction contract. Properly understood, the statements made in that meeting were made by ADCO Group and not ADCO Constructions. There was no representation made by ADCO Constructions. Mr Ryan gave evidence that he was representing ADCO Group in the meeting. Further, there was no evidence that Council relied on the statements made in this meeting in forming the view that ADCO Group could enter into a contract on behalf of ADCO Constructions. Council called no evidence from any Council representative that attended the meeting, despite such persons being plainly available. The failure to call Mr Filosa, Ms White and Ms Ho was not explained, and the Court may infer that their evidence would not have assisted Council.
(e) Mr McLean's and Mr McBurnie's involvement in the negotiation - it is not apparent how the involvement of Mr McLean or Mr McBurnie in the contract negotiations could give rise to a relevant representation, particularly in light of Council's case as to their actual or apparent authority. ADCO Constructions otherwise refers to and relies on the submissions above at paragraphs 324 to 326 above.
H.5 Conduct and circumstances relied on by Council to give rise to the formation of the alleged contract between ADCO Constructions and Council
(a) the Departures Table;
(b) the Site Meeting Minutes dated 23 March 2021;
(c) the McBurnie Email; and
(d) clause 5.6 and item 14A and Annexure Part D of the executed Construction Contract.
Q: All right. It's not said on behalf of the parent, which is the entity to sign the parent company guarantee?---
A: It - it's not possible to isolate the two different companies in a response such as this. This is a statement by ADCO Group knowing that the PCG will be acceptable to ADCO, but it is not willing to proffer it without the other matters being um resolved.
Q: I understand that, but in order to get to that point you have to know that the parent thinks the PCG is acceptable and will be provided, correct?---
A: Well they'd already reviewed the PCG and in the form um that it was being provided it would've been acceptable to ADCO Constructions.
Q: All right, well and you're a director of ADCO Constructions?---
A: I am.
Q: Yes. So you're in a sense advising that it is acceptable, by looking at it as a lawyer acting for ADCO Constructions, and as a director you've formed the view that it would be acceptable, correct?---
A: Yes.
Q: You understand, don't you, that whether or not ADCO Constructions had agreed to provide a PCG in other projects doesn't mean that it had or had not agreed to provide one here?---
A: No, I thought they'd agreed on the basis of the departures table.
ADCO Constructions Pty Ltd will be providing a guarantee.
Q: So apart from those three, all the other contractual documents are now finalised to your satisfaction?---
A: Yes, the documents as drafted are agreed.
Q: Yes. And you sign off on that, "Cameron McBurnie, chief commercial operator, ADCO Constructions"?---
A: Yes.
Q: Yes. And - - -?---
A: ADCO Constructions as you'll note is just a - it's not a business name - ah a company name, it's just the global handle that we use for our company.
Q: Well, it's not signed off under the name of ADCO Group through [sic] is it, because you were looking at this in your role as head legal officer for all the group - - -?---
A: Agreed, as corporate counsel, yes.
(a) the alleged promised timing for provision of the PCG is inconsistent with the contract asserted by Council. The site meeting minutes record the date for provision as being 26 March 2021, which is before the Construction Contract was signed or the Notice to Proceed was issued. The contract alleged by the Council is one that required provision of the PCG within five business days after the issue of the Notice to Proceed, being the timing stipulated in the Construction Contract which Council also alleges constitutes the alleged contract; and
(b) subsequent to both that site meeting and the alleged timing for provision of the PCG stated in the minutes (being 26 March 2021), the requirement to provide the PCG was the subject of further communications.
H.5.7 Entry into the Construction Contract
(a) clause 5.6 and Item 14A of the Construction Contract, which contain the requirement for a PCG executed by ADCO Constructions; and
(b) the fact that the Construction Contract was executed by Mr McBurnie and Mr Conroy on or about 31 March 2021. Mr Conroy was a Company Secretary of ADCO Group and of ADCO Constructions at this time. Mr McBurnie was a director of both ADCO Constructions and ADCO Group. At no stage did Mr McBurnie raise any concerns as to the ability of ADCO Constructions or ADCO Group to provide Council with the PCG.
[3] The existence of matters of importance in which the parties have not reached consensus in their informal agreement will render it the less likely that they intended immediately to be bound before the execution of a formal document. Even where the parties have agreed on the "major matters", their subsequent conduct may indicate that they did not intend to be bound until the other issues between them were resolved in a formal document.
[4] In order to determine in what areas the parties were, and were not, in agreement, and what matters they considered necessary in order for an agreement to exist, it is legitimate to examine their subsequent conduct. Where correspondence between the parties after an informal agreement refers to important terms and conditions not mentioned during that informal discussion, it may more readily be inferred that the earlier discussion was simply a preliminary negotiation and not a binding agreement.
[5] Depending on the size, importance and complexity of the subject matter, the less formal the initial agreement, the less likely it will be that it was intended to be legally binding and enforceable. Thus, an oral discussion which contemplates a subsequent formal written agreement is less likely to have been intended to have been immediately binding.
[6] It is necessary in every case to consider the nature and importance of the transaction which the parties contemplate. Where the agreement concerns a large sum, or concerns a significant transaction, it is less likely to have been intended to be presently binding.
...
[8] Where a binding agreement is said to have been formed as a result of correspondence, it is necessary to look at that correspondence as a whole. It is wrong to isolate any part of the correspondence from the rest in order to prove or disprove the existence of a binding agreement. The same approach should be taken to the analysis of words and phrases within the correspondence. Reference to an "agreement" having been reached does not necessarily prove the existence of a presently binding contract. Conversely, references to a "proposed" agreement, and similar expressions, will not necessarily mean that no agreement presently exists. It is a question of how the words are to be interpreted in their context, and in the light of the correspondence, viewed as a whole.
(a) at Recital A - 'The Principal has entered into the Contract with [ADCO Group] for the performance of the works'. This reflects the parties' intention that the Construction Contract was to be agreed and executed before ADCO Constructions provided any deed of guarantee. This intention runs counter to Council's case in this proceeding;
(b) at Recital B - 'In consideration of [Council] entering into the Contract with [ADCO Group] at the request of [ADCO Constructions] (which request is testified by execution of this Deed), [ADCO Constructions] agrees to provide the guarantees, agreement and undertakings contained in the Deed'.
H.8 Is any collateral contract void due to clause 7(b) of the Formal Instrument of Agreement of the Construction Contract?
The [Construction] Contract... supersedes and cancels any contract, deed, arrangement, related condition, collateral arrangement, condition, warranty, indemnity or representation imposed, given or made by a party (or an agent of a party) prior to the execution date.
H.9 Does the alleged contract with ADCO Constructions satisfy the Instruments Act?
An action must not be brought to charge a person upon a special promise to answer for the debt, default or miscarriage of another person or upon a contract for the sale or other disposition of an interest in land unless the agreement on which the action is brought, or a memorandum or note of the agreement, is in writing signed by the person to be charged or by a person lawfully authorised in writing by that person to sign such an agreement, memorandum or note.
However, the meaning of the requirement of signature in s 4 must be understood in the context of the particular manner in which the Statute of Frauds was historically interpreted. Many of the cases which followed the enactment of the Statute of Frauds developed a contorted interpretation of its words. Doctrines, such as part performance, were developed to avoid the literal application of the statute where the case did not fall within the mischief which the statute aimed to prevent.
The formal requirement in s 4 of the Statute of Frauds that a written memorandum or note be "signed by the party to be charged therewith" has been interpreted in a line of cases consistent with the approach of letting out of the statute cases which might have fallen within its terms. Those cases gave the word "signed" a meaning "very different from its normal meaning", sometimes recognising as a signature "nothing which could ordinarily be called a signature". The same broad approach was taken where qualifications were imposed upon a signature.
It has, therefore, been the law since 1807 that s 4 of the Statute of Frauds can be satisfied by a letter which refers to a written, although unsigned, agreement. The boundaries of this doctrine have varied but a situation such as the 30 October 2006 letter from the second defendant, which expressly referred to the Lease, has always fallen within the doctrine. The 30 October 2006 letter was signed by the second defendant and her signature was unqualified.
...where the alleged breach of the collateral contract is no more than the failure by a party to sign the memorandum necessary to make the contract of sale enforceable given the provisions of the Statute of Frauds, there will be no enforceable breach of the collateral contract; to hold otherwise would simply negate the operation of the Statute.
H.10.1 Whether Mr McBurnie, Mr McLean and/or ADCO Group had authority to enter into a contract with Council on behalf of ADCO Constructions
H.10.1.1 Actual authority of Mr McBurnie and/or Mr McLean
(a) I do not see how it can seriously be suggested that Mr McBurnie's role as legal adviser to companies in the ADCO corporate group, including ADCO Group and ADCO Constructions, can be said to be an office carrying with it the authority to enter into contracts on behalf of the corporate entity to which Mr McBurnie was providing advice. To the extent that Mr McBurnie's role as legal adviser is relied upon by Council as conferring actual authority on him by ADCO Constructions to do so, I reject it;
(b) Similarly, Mr McBurnie's role as Chief Commercial Officer of ADCO Constructions is not an office that carries with it the cloak of actual authority to enter into contracts on behalf of ADCO Constructions. The title suggests a senior role, but nothing more;
(c) Where Mr McBurnie was but one of a number of directors of ADCO Constructions, for him to have actual authority to enter into contracts on behalf of ADCO Constructions Council would need to establish that ADCO Constructions had conferred such authority on a single director. I accept ADCO Constructions' submission that in a company with several directors, a director acting individually has no usual authority to bind a company. Such a proposition is well-established and recognised law. As is pointed out in Ford, Austin & Ramsay's Principles of Corporations Law, in such a company a director's normal power is to bind the company only by joining with other directors in a collective resolution of the board of directors. If a single director is to have power to bind the company as a single director, then they must have that power delegated to them by the appropriate organ.[125] Here, there is no evidence that ADCO Constructions had conferred such power on a single director; and
(d) ADCO Constructions relies heavily on its constitution in respect of Mr McBurnie's alleged actual authority, pointing out the requirements under its constitution as to how it may execute documents. Under its constitution, execution without using a seal requires signing by either two directors, or one director and company secretary, or one director and another person appointed by the directors for that purpose. The constitution goes no further than how a document may be executed. It assists ADCO Constructions' position but it is not determinative of it. I accept Council's point that there is no evidence of it having been made aware of ADCO Constructions' constitution at the time of negotiations, but such provisions of ADCO Constructions' constitution are standard and one would expect that Council would have known or assumed this to be the case insofar as execution of documents was concerned. In any event, the manner of execution of documents required by ADCO Constructions' constitution is not a complete answer in and of itself to the question of Mr McBurnie's actual authority to make a binding promise on behalf of ADCO Constructions by virtue of his position as a director of that company.
(a) He was not a director of ADCO Constructions (or of ADCO Group, for that matter). He was an employee of ADCO Constructions. The evidence does not establish whether, at the time of negotiations, Council knew which ADCO entity was his employer;
(b) His position title was described as State Pre-Construction Manager. Council has not established that such a position constitutes an office which bears an implied grant of power to bind ADCO Constructions to a contract;
(c) ADCO Constructions' submissions on Mr McLean's alleged actual authority, set out at paragraphs 317 and 318 above, are compelling and I accept them. I cannot put the argument any better. I will add this: leaving aside for one moment which ADCO entity applies, at best, Mr McLean had actual authority to negotiate with Council, but he did not have actual authority to bind the company to a contract to provide the PCG; and
(d) This is so, notwithstanding Council's submission that the defendants' failure to call Mr McLean as a witness fortifies the basis for finding that Mr McLean had actual authority to agree to provide the PCG on behalf of ADCO Constructions. The rest of the evidence as to Mr McLean not having actual authority to bind ADCO Constructions is compelling, and I decline to draw the inference urged upon me by Council.
(a) Mr McLean's email signature at times contained his title as Pre-Construction Manager and the organisation as 'ADCO Constructions (Vic) Pty Ltd';
(b) Mr McLean's email signature used in his email dated 1 October 2020 attaching ADCO's response to Council's iteration of the Departures Table, in which the response for Item 10 stated 'Accepted provided agreement can be reached on other key areas of the contract', was in the same form as in sub-paragraph (a) above;
(c) Mr McLean's email signature used in his emails of 11 March 2021 contained his title as Pre-Construction Manager and the organisation as 'ADCO Constructions';
(d) Mr Adaikalavan's email signature contained his title as Victorian State Manager and the organisation as 'ADCO Constructions'. This was the case for his email to Mr Haughton dated 2 October 2020 with the subject line 'Change of Name/ADCO Trading Entities', advising of the name change of ADCO Constructions (Vic) Pty Ltd to ADCO Group Pty Ltd;
(e) Mr Ryan's email signature used in an email of 22 March 2021, which attached the 22 March Register, contains his title as Project Manager and the organisation as 'ADCO Constructions (Vic) Pty Ltd'. I note that by this time, this was no longer the name of that entity - it had changed to ADCO Group Pty Ltd; and
(f) Mr McBurnie's email signature in the McBurnie Email contained his title as Chief Commercial Officer and the organisation as 'ADCO Constructions'.
(a) A letter from Mr McLean to Ms Maitland dated 28 August 2020 is on ADCO Constructions (Vic) Pty Ltd letterhead on the first page; the 'ADCO' logo is on each subsequent page of the letter, and the letter is signed by Mr McLean, Pre-Construction Manager, 'ADCO Constructions Pty Ltd';
(b) A letter from Mr McLean to Mr Haughton dated 28 September 2020 has the same features as described in sub-paragraph (a) above; and
(c) A letter from Mr McLean to Mr Haughton dated 6 October 2020 has the ADCO logo on each page and is signed by Mr McLean, Pre-Construction Manager, 'ADCO Constructions Pty Ltd'.
(a) Council's letter dated 17 September 2020 advising that ADCO's tender had been accepted was addressed to Mr Adaikalavan of 'ADCO Constructions Pty Ltd'. This letter referred to 'your submission' and the tendered pricing, in circumstances where the cover letter for the Tender Submission was signed by Mr Adaikalavan of 'ADCO Constructions (Vic) Pty Ltd'; and
(b) Contrastingly, Council's letters dated 22 December 2020, 29 January 2021, 2 and 17 March 2021, being each of the Letters of Intent, are addressed to Mr Adaikalavan of 'ADCO Group Pty Ltd' and refer in the body of the letters to 'ADCO Group Pty Ltd'.
(a) where 'ADCO', or the ADCO logo only, or 'ADCO Constructions' is concerned, one has to look beyond the label given to what is actually occurring within each of the documents, along with their context, to make any determination about which entity is actually being referred to, if indeed there is an intention to refer to a specific entity;
(b) 'ADCO' does not necessarily mean a specific entity;
(c) 'ADCO Constructions' does not necessarily mean 'ADCO Constructions Pty Ltd'; and
(d) the description of the organisation in an email signature is not necessarily indicative of a specific entity.
...it [is] certainly important as to who goes... to sign the contract at the end of the day, but my experience as a construction lawyer is that when there's a group of companies they share their experience and information, and often I'm talking to officers of that contractor who... sit in different arms.
H.10.1.2 Apparent authority of Mr McBurnie, Mr McLean and ADCO Group
(a) ADCO Constructions being identified as the parent company in the Tender Submission, and other references to ADCO Constructions or the corporate group, or features of them, throughout the document do not connote that ADCO Group has apparent authority to contract on behalf of ADCO Constructions;
(b) Further, given that it was ADCO Group's Tender Submission, not ADCO Constructions' document, any representations made in it were made by ADCO Group, not ADCO Constructions. Representations made by the agent do not constitute representations by the principal, and for apparent authority, it is the representation by the principal that the agent has authority which is key. As stated in Cargill (No 28), 'apparent authority arises when there is an appearance or representation of authority to a third party, created by the principal in respect of his or her agent';[126]
(c) I accept ADCO Constructions' submissions in respect of Council's reliance on the Tender Submission (see paragraph 330(a) above);
(d) Correspondence which Council contends as coming from ADCO Constructions does not clearly do so at all. As I have demonstrated at paragraphs 453 to 458 above, and as I have concluded at paragraph 462 above, nothing can be confidently inferred as to whether such correspondence actually emanated from ADCO Constructions or ADCO Group. Rather, each document needs to be looked at as a whole and in its factual context. This is better done in section H.10.2 below, but as will be seen, I do not accept that this was correspondence on behalf of ADCO Constructions;
(e) I accept ADCO Constructions' submissions in respect of Council's reliance on correspondence allegedly from ADCO Constructions (see paragraph 330(b)) above;
(f) I do not accept, for the reasons that will be set out at section H.10.2.2 below, that Mr McLean's email of 1 October 2020 and the attached iteration of the Departures Table is to be construed as ADCO Constructions agreeing to the Departures Table. Even if it had, given Mr McBurnie's evidence that he assumed that Mr Harding had approved the response in the Departures Table for Item 10, Council had no knowledge of that at the relevant time. I do not see how this Departures Table is to be construed as a representation of apparent authority;
(g) Council's submission is that the defendants' failure to call Mr Harding as a witness means that I should draw an inference adverse to ADCO Constructions in respect of Mr McBurnie's evidence described in the preceding sub-paragraph. I take Mr McBurnie's evidence for what it was, that it was his assumption. Council does not explain how Mr McBurnie's evidence on this could give rise to an adverse inference as to the failure to call Mr Harding. Nonetheless, even if Mr Harding did do what Mr McBurnie says he did, and that is approve the response given in the 1 October iteration of the Departures Table, that goes no further than making it an approved response. It would not be, for all the other reasons I have stated when considering the Departures Table (in this and other sections of the judgment), a promise to provide the PCG;
(h) I do not accept Council's characterisation of the 23 March 2021 site meeting as ADCO Constructions giving undertakings that were recorded in the site meeting minutes. First, there is no basis for construing them as undertakings, regardless of who they are said to be from. I think 'undertakings' puts it too highly. Second, and more importantly, I do not accept that the ADCO personnel present at the site meeting, being Mr Ryan, Mr Waters and Mr Nicholls, were there to represent ADCO Constructions. Rather, I find that they were present to represent ADCO Group. Mr Ryan's and Mr Waters' employment contracts were in evidence. Mr Ryan was employed by ADCO Constructions. On the other hand, Mr Waters' letter of employment, dated 15 September 2020, was on ADCO Constructions (Vic) Pty Ltd letterhead. He was being employed in the Melbourne office as Senior Contracts Administrator, the body of the letter refers to 'ADCO', and the letter is signed by Mr Adaikalavan for 'ADCO Constructions Pty Ltd'. There is no evidence to suggest that Council had any knowledge of which ADCO entity employed Mr Ryan, Mr Waters and Mr Nicholls. I infer from all of the evidence that irrespective of which ADCO entity employed these men (or any of the other ADCO people involved in these events, for that matter), they worked on various projects for different entities in the ADCO corporate group. I do not accept that site meeting minutes recording them as being from 'ADCO Constructions', which the evidence establishes were prepared by either Council or Turner & Townsend, means that they should be taken as representing the parent company at the site meetings. I accept ADCO Constructions' submissions on this reliance on the 23 March 2021 site meeting as set out at paragraph 330(d) above; and
(i) Mr McLean's and Mr McBurnie's involvement in the negotiations do not, for reasons already outlined above, carry representations as to their apparent authority.
H.10.2 Whether the conduct and circumstances relied on by Council give rise to the formation of the alleged contract between ADCO Constructions and Council
(a) Council equivocates on whether the PCG was to be provided by ADCO Constructions to it, or to ADCO Group for it to pass on to Council; and
(b) Council does not clearly state by when the PCG was to be provided under the alleged contract by ADCO Constructions (to it or to ADCO Group to pass on). Different positions were adopted by Council. Was it 26 March 2021, as per the 23 March 2021 site meeting, or within five business days after issuing the Notice to Proceed, or some other date?
(a) First, the Tender Submission is ADCO Group's document, not ADCO Constructions' document. It is therefore not conduct which can be sheeted home to ADCO Constructions. I have already rejected the notion that in making the Tender Submission, ADCO Group was acting as ADCO Constructions' agent (see paragraphs 483(b) and (c) above). I do not accept that references throughout the document to 'ADCO' incorporate ADCO Constructions as well as ADCO Group or are references to ADCO Constructions. It was either a reference to the party submitting the tender, being ADCO Group, or to the ADCO corporate group as a whole. Nor do I accept that the reference to 'ADCO Constructions' in the insurance information provided with the Tender Submission was to be taken as meaning the second defendant: in this regard, I agree with ADCO Constructions' submission at paragraph 353 above.
(b) Second and perhaps most importantly, in no way could the content of the Tender Submission be read as containing a representation or a promise that an executed PCG would be provided. Rather, the content of the Tender Submission is to the contrary: when listing requested departures from the Tender Contract, the response was that the requirement for a related party guarantee was to be deleted. Thus, there was no representation or promise to provide a PCG. The stated position was the complete opposite of that.
...the system I use, is that I highlight in yellow outstanding matters still to be negotiated between the parties. When I circulated the [Departures Table after the meeting on 5 October 2020], clause 5 was not highlighted in yellow as an outstanding item and it is recorded that agreement had been reached. In circumstances where Boroondara was requiring ADCO Group and ADCO Constructions to provide the PCG, it was my understanding from ADCO's response that ADCO Group and ADCO Constructions had agreed to provide Boroondara the PCG.
H.10.3 Whether there was consideration given for the alleged contract with ADCO Constructions
H.10.4 Whether there was an intention to create legal relations between Council and ADCO Constructions
(a) the nature of the parties was such that if there was to be a legally binding arrangement between them, one would expect it to be in writing and properly executed;
(b) the subject matter of the alleged contract was sufficiently significant that one would expect the arrangement to be in writing and properly executed;
(c) to the extent there were any negotiations between Council and ADCO Constructions, these were for the Construction Contract to which ADCO Constructions was not a party;
(d) the point made by ADCO Constructions at paragraph 406 is compelling. That the Construction Contract contained a form of the PCG that was later to be executed evinces an intention that ADCO Constructions and Council did not intend to contract until the PCG was signed in writing by both parties;
(e) as already indicated, there is no sufficiently clear and unequivocally promissory conduct by ADCO Constructions;
(f) to the extent that a number of items of correspondence are said to lead to the alleged contract, examination of that correspondence as a whole does not evidence the existence of a presently binding contract;
(g) also, as already indicated, the alleged contract is insufficiently certain, which weighs against a finding that the parties intended to be legally bound; and
(h) the point made by ADCO Constructions at paragraph 410 is also particularly salient. The extent which Council went to in order to ensure that the Construction Contract would be legally binding by going into great detail as to the manner of its execution by ADCO Group is in stark contrast to the proposition that Council and ADCO Constructions intended to be legally bound by an arrangement that was not clearly expressed in writing or executed in an appropriate manner.
H.10.5 Whether any collateral contract is void due to clause 7(b) of the Formal Instrument of Agreement of the Construction Contract
H.10.6 Whether the alleged contract with ADCO Constructions satisfies s 126 of the Instruments Act
H.11 Conclusion as to whether ADCO Constructions made a binding contractual promise to Council to provide the PCG
(a) Mr McBurnie and/or Mr McLean did not have actual or ostensible authority to enter into a contract with Council on behalf of ADCO Constructions;
(b) ADCO Group did not have ostensible authority to enter into a contract with Council on behalf of ADCO Constructions;
(c) the conduct and circumstances relied upon by Council do not give rise to the formation of the alleged contract between Council and ADCO Constructions. Fundamentally, the conduct and circumstances relied upon do not possess the requisite promissory character, and even if they did, it was not conduct on behalf of ADCO Constructions;
(d) if I had found in favour of Council in respect of the alleged contract with ADCO Constructions, I would have accepted that there was consideration for that contract - the consideration being Council's entry into the Construction Contract with ADCO Group;
(e) there was no intention to create legal relations between Council and ADCO Constructions, other than upon execution of the PCG;
(f) the alleged collateral contract is not void due to clause 7(b) of the Formal Instrument of Agreement of the Construction Contract; and
(g) the alleged contract is not unenforceable due to s 126 of the Instruments Act.
I Issue 5: Has Council waived its right to be provided the PCG under the alleged contract with ADCO Constructions?
(a) I have not accepted that Council waived its rights as against ADCO Group. Accordingly, ADCO Constructions' reliance on the same conduct and arguments relied on by ADCO Group fails for the same reasons; and
(b) There was no separate conduct or arguments relied on by ADCO Constructions to found its contentions regarding waiver or abandonment, and so there is no separate basis for finding in favour of ADCO Constructions on this issue.
J Issue 6: What is the appropriate relief to be granted to Council in respect of ADCO Constructions' failure to provide the PCG?
(a) on 2 October 2024 (in Council's letter of that date), the fact that a PCG had not been provided; and
(b) on 30 January 2025 (in the statement of claim), that the Council considered there was a contract between it and ADCO Constructions by which ADCO Constructions had promised to provide the Deed of Guarantee.
(a) Issue 1: The proper interpretation of clause 5.6 and Item 14A of the Construction Contract is that ADCO Group must provide a PCG executed by ADCO Constructions to Council. That is a standalone obligation that is not conditional on it being provided within five business days of the Notice to Proceed being issued, and it is not only a precondition to ADCO Group being able to submit a payment claim, access the site to conduct the works, or be paid the Advance Payment Amount.
(b) That being the case, and there being no contest that ADCO Group has not provided the executed PCG to Council, ADCO Group is in breach of the obligation to provide the executed PCG.
(c) Issue 2: Council has not waived its right against ADCO Group to be provided the executed PCG.
(d) Issue 3: It is appropriate to grant a mandatory injunction in favour of Council that ADCO Group do all things within its power to provide Council with a PCG executed by ADCO Constructions. It is not appropriate to make the declarations sought by Council.
(e) Issue 4: ADCO Constructions did not make a binding contractual promise to deliver the executed PCG to Council or to ADCO Group for provision to Council. It did not enter into a contract or a collateral contract with Council to provide an executed PCG.
(f) Issue 5: the issue of whether Council waived its right as against ADCO Constructions to be provided the executed PCG does not arise, as it has no such right as against ADCO Constructions. If it were necessary to determine the issue, I would find that Council had not waived any rights against ADCO Constructions.
(g) Issue 6: the question of relief in favour of Council as against ADCO Constructions does not arise. Had I found that Council had a contractual right as against ADCO Constructions for the executed PCG, I would have found it appropriate to make the mandatory injunction sought by Council against ADCO Constructions.
(a) a proposed form of order, if that is agreed; or
(b) if there is not agreement on the proposed form of order, each party's preferred form of order.
[1] Prior to 6 October 2020, ADCO Group was named ADCO Constructions (Vic) Pty Ltd, after which it underwent a change of name.
[2] Capitalised terms in this judgment have the same meaning as contained in the Construction Contract, unless otherwise stated.
[3] Guaranteed Obligations means all of the obligations, responsibilities and liabilities of ADCO Group arising out of or in connection with the Construction Contract.
[4] Clause 7(b) of the Formal Instrument of Agreement (part of the Construction Contract) contained a term that the Construction Contract supersedes and cancels any contract, deed, arrangement, related condition, collateral arrangement, condition, warranty, indemnity or representation imposed, given or made by a party (or an agent of a party) prior to the execution date.
[5] [1959] HCA 8; (1959) 101 CLR 298 (Jones v Dunkel) per Kitto J (at 308) and Menzies J (at 312).
[7] [2011] HCA 11; (2011) 243 CLR 361 (Kuhl).
[8] Ibid, [64] (Heydon, Crennan & Bell JJ).
[9] Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104 (Mount Bruce Mining), 116 [46].
[14] Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 (Electricity Generation Corporation v Woodside Energy), 656-7 [35] (the plurality).
[15] See Electricity Generation Corporation v Woodside Energy, [35] (this passage also notes the other matters to be given consideration, such as the commercial purpose of the contract).
[18] Craine, 326 (citations omitted).
[25] Craine, 335 (citations omitted).
[26] (1990) 170 CLR 394, 423 (Verwayen).
[27] See for example, Elderslie Property Investments No 2 Pty Ltd v Dunn [2007] QSC 372, [59].
[29] [1997] 1 VR 127, 141.
[31] (2019) 59 VR 305; [2019] VSC 756, [61].
[32] Chamberlain v R (No 2) [1984] HCA 7; (1984) 153 CLR 521, 531.
[33] Moore v National Mutual Life Association of Australasia Ltd [2011] NSWSC 416.
[34] [2001] NSWCA 20; (2001) 187 ALR 380, [50].
[35] Verwayen, 398; Tool Metal Manufacturing Co Ltd v Tungston Electric Co Ltd [1955] UKHL 5; [1955] 1 WLR 761.
[36] Ajayi (t/as Colony Carrier Co) v RT Briscoe (Nigeria) Ltd [1964] 1 WLR 1326, 1330.
[37] Mathews Capital Partners Pty Ltd v Coal of Queensland Holdings Ltd [2012] NSWSC 462, [39].
[39] Civil Mining & Construction Pty Ltd v Wiggins Island Coal Export Terminal Pty Ltd, [2017] QSC 85, [799]. See also Canberra Advance Bank Ltd v Benny (1991) 115 ALR 207, 220.
[40] Rilgar Nominees Pty Ltd v BHA Holdings Pty Ltd [2014] VSC 632, [71].
[41] Tenth Vandy Pty Ltd v Natwest Markets Australia Pty Ltd [2010] VSC 2, [17]; Jagatramka v Wollongong Coal Ltd [2021] NSWCA 61 (Jagatramka), [49].
[43] East Rockingham RRF Project Co Pty Ltd as Trustee for the East Rockingham RRF Project Trust v Acciona Construction Australia Pty Ltd [2024] FCA 759, [151] (East Rockingham).
[44] East Rockingham, [160]-[163].
[45] Relying on Redland Bricks Ltd v Morris [1969] 2 All ER 576 (Redland Bricks), 579, 581.
[46] East Rockingham, [171]-[173].
[48] East Rockingham, [167]-[173].
[50] JD Heydon, MJ Leeming and PG Turner, Meagher, Gummow & Lehane's Equity: Doctrines & Remedies (LexisNexis, 5th ed, 2014), [20-030] citing Fothergill v Rowland (1873) LR 18 Eq 132, 140. This part of Meagher, Gummow & Lehane was cited with approval in 85 Princess Pty Ltd v Fleming [2025] NSWSC 407, [145].
[52] JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [2019] WASC 177, [143]-[157]; JKC Australia LNG Pty Ltd v CH2M Hill Companies Ltd [2020] WASCA 112 (JKC Australia (Appeal)), [143]-[144]; [169]-[170].
[53] See, for example JKC Australia (Appeal), [174].
[55] Ewing International, [352] (emphasis added).
[56] Optus Networks Pty Ltd v City of Boroondara [1997] 2 VR 318, 336-337.
[58] ADCO Group says that Council makes a vague submission that both ADCO Group and Council have a right to obtain the PCG from ADCO Constructions, but what this right is and how it arises and becomes legally enforceable is never explained by Council. The Court ought not to order a mandatory injunction that requires a party to embark on uncertain and disputed litigation to seek to enforce some alleged right: Wroth v Tyler [1973] 1 All ER 897 and Costigan v Hastler (1804) 2 Sch & Lef 160. Plainly, this proposition is of even stronger force when the alleged right has not actually been identified or properly articulated, or that prosecution of that alleged right would lead to an inability to comply with the mandatory injunction sought, as is the case here.
[59] [2024] VSCA 86 (Parwan Investments).
[62] JD Heydon, MJ Leeming and PG Turner, Meagher, Gummow & Lehane's Equity: Doctrines & Remedies (LexisNexis, 5th ed, 2014) [20-005], [20-140] cited with approval by the Court of Appeal in Parwan Investments.
[63] The parties differ on whether Redland Bricks stands for the proposition that damages may be an inadequate remedy where it is too difficult to calculate the damage suffered or likely to be suffered.
[65] Ibid, 22 (emphasis added in original).
[66] [2016] VSC 42 (Mecon), [22].
[72] Uranium Equities Ltd v Fewster [2008] WASCA 33, [224].
[73] John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451,[93].
[74] This is the term alleged in respect of the collateral contract and the independent contract. See further amended statement of claim, [14] and [15A].
[75] This is the term alleged only in respect of the independent contract. See further amended statement of claim, [15A].
[76] [2001] FCA 279; (2001) 187 ALR 302, 330, [109]-[112] (SVI Systems) (citations omitted).
[77] Ford, Austin & Ramsay's Principles of Corporations Law, [13.020].
[78] [2022] VSC 13 (Cargill (No 28)).
[79] Ibid, [3088]-[3092] (citations omitted) (emphasis added).
[80] Ford, Austin & Ramsay's Principles of Corporations Law, [13.030.6]; Hely-Hutchinson v Brayhead Ltd [1967] 3 All ER 98 (Brayhead), 102.
[81] Ford, Austin & Ramsay's Principles of Corporations Law, [13.030.3]; Brayhead 102.
[82] Ford, Austin & Ramsay's Principles of Corporations Law, [13.070] citing Brayhead, 102; Crabtree-Vickers Pty Ltd v Australian Direct Mail Advertising & Addressing Co Pty Ltd [1975] HCA 49; (1975) 133 CLR 72.
[83] Ford, Austin & Ramsay's Principles of Corporations Law, [13.120] citing Brick and Pipe Industries Ltd v Occidental Life Nominees Pty Ltd [1992] VicRp 68; [1992] 2 VR 279; Motor Yacht Sales Australia Pty Ltd (t/as Boutique Boat Co) v Cheng [2021] NSWSC 1141, [127]-[146].
[84] Ford, Austin & Ramsay's Principles of Corporations Law (online at 8 September 2025), [13.080], citing Northside Developments Pty Ltd v Registrar-General [1990] HCA 32; (1990) 170 CLR 146,205 (among other authorities).
[85] Gino Del Pont, Law of Agency (3rd Ed. LexisNexis Butterworths 2014), 8.27.
[87] Pacific Carriers Ltd v BNP Paribas [2004] HCA 35; (2004) 208 ALR 213, 225.
[88] See Handbury v Nolan (1977) 13 ALR 339, 348-349.
[89] See JJ Savage & Sons Pty Ltd v Blakney [1970] HCA 6; (1970) 119 CLR 435.
[90] [1984] HCA 64; (1984) 156 CLR 41 (Hospital Products), 61-2.
[93] Crown Melbourne Ltd v Cosmopolitan Hotel (Vic) Pty Ltd [2016] HCA 26; (2016) 260 CLR 1, (Crown v Cosmopolitan) [22] (French CJ, Kiefel and Bell JJ).
[95] DH MB Pty Ltd v Manning Motel Pty Ltd [2014] NSWCA 396, [7]-[23]; see also Hoyts v Spencer [1919] HCA 64; (1919) 27 CLR 133.
[96] TW Timber Treatment Pty Ltd v Giddings [2022] VSCA 147, [43].
[97] Ermogenous v Greek Orthodox Community of SA Inc [2002] HCA 8; (2022) 209 CLR 95, 105 [25].
[99] Ibid, 14569-14570 (citations omitted).
[100] See, obiter in Manning Motel Pty Ltd v DH MB Pty Ltd [2013] NSWSC 1582, [23].
[102] See s 126 of the Instruments Act 1958 (Vic); Crown v Cosmopolitan, 445 [267] (Gordon J in obiter). See also Cosmopolitan Hotel (Vic) Pty Ltd v Crown Melbourne Ltd (Retail Tenancies) [2012] VCAT 225, [170]-[171].
[104] For example, see Pugwall Pty Ltd v Arthur McKenzie Investments Pty Ltd [2022] VSCA 272 (Pugwall), [43]-[70], Kyrou, Sifris and Kennedy JJA; Alonso v SRSR Investments (WA) Pty Ltd [2012] WASC 168 (Alonso), [67]-[92], per Edleman J.
[107] Delaney v Purves [1930] QWN 6.
[108] Scottish Amicable Life Assurance Society v Reg Austin Insurances Pty Ltd (1985) 9 ACLR 909.
[109] Clark Equipment Credit of Australia Ltd v Kiyose Holdings Pty Ltd (1989) 21 NSWLR 160.
[110] Elpis Maritime Co Ltd v Marti Chartering Co Inc [1992] 1 AC 21.
[114] Wright v Madden [1992] 1 Qd R 343 (Wright v Madden), 349.
[116] [2021] NSWSC 119, [125]-[127].
[117] [1992] VicRp 63; [1992] 2 VR 217, 232.
[118] Actionstrength Ltd v International Glass Engineering IN.GL.EN SpA [2003] UKHL 17; [2003] 2 AC 541, 549 [19].
[119] (2002) 68 VR 559, [54]-[55].
[125] Ford, Austin & Ramsay's Principles of Corporations Law (online at 12 November 2025), [13.080].
[128] Pugwall, [63]-[68], [70].
[129] Delaney v Purves [1930] QWN 6, 7.
[131] JD Heydon, MJ Leeming and PG Turner, Meagher, Gummow & Lehane's Equity Doctrines & Remedies (LexisNexis Butterworths, 5th ed, 2014), [20-025].
[132] Sino Iron Pty Ltd v Mineralogy Pty Ltd (No 2) [2017] WASCA 76; (2017) 55 WAR 36, [132]-[137].
Boroondara City Council
ADCO Group & Anor [2025] VSC 774
CONTRACT - Guarantee - Requirement for writing - Instruments Act 1958 (Vic), s 126 - Pugwall Pty Ltd v Arthur McKenzie Investments Pty Ltd [2022] VSCA 272, considered.
EQUITY - Mandatory injunction for performance of a contractual term - Whether damages an adequate remedy - Damages an inadequate remedy for non-provision of guarantee and for loss of an agreed risk allocation mechanism - East Rockingham RRF Project Co Pty as Trustee for the East Rockingham RRF Project Trust v Acciona Construction Australia Pty Ltd [2024] FCA 759, applied - Discretionary considerations for equitable relief - Impossibility of performance - Parwan Investments Pty Ltd v Hooper [2024] VSCA 86, considered - Held performance not impossible or inutile.
(1959) 101 CLR 298
(2011) 243 CLR 361
(2015) 256 CLR 104
(2014) 251 CLR 640
(2008) 238 CLR 570
(2022) 277 CLR 445
(1920) 28 CLR 305
(1990) 170 CLR 394
(2019) 59 VR 305
(2000) 49 NSWLR 262
(1984) 153 CLR 521
(2001) 187 ALR 380
(1991) 115 ALR 207
(2004) 219 CLR 165
(2001) 187 ALR 302
(1975) 133 CLR 72
(1990) 170 CLR 146
(2004) 208 ALR 213
(1977) 13 ALR 339
(1970) 119 CLR 435
(1984) 156 CLR 41
(2016) 260 CLR 1
(2005) 214 ALR 392
(1919) 27 CLR 133
(2022) 209 CLR 95
(1911) 12 CLR 562
(1992) 28 NSWLR 564
(1989) 21 NSWLR 160
(2002) 68 VR 559
(2017) 55 WAR 36