[2019] WASC 140
Supreme Court of WA
2019-12-04
Allanson J
Original judgment source is linked above.
CITATION : AGC INDUSTRIES PTY LTD -v- KARARA MINING LTD [2019] WASC 140
HEARD : 27 & 28 FEBRUARY, 1 - 3, 7 - 10, 13 - 17 MARCH, 21 APRIL, 22 & 23 JUNE 2017
Contract - Where plaintiff contracted with defendant to carry out construction project at mine operated by defendant - Where parties entered Early Works Contract and Main Works Contract - Where plaintiff provided workforce and was reimbursed direct costs and corporate overhead and profit (COP) - Where rate of COP in Main Works Contract varied if plaintiff achieved completion of part of works by specified milestone dates
Misleading or deceptive conduct - Whether defendant engaged in misleading or deceptive conduct in pre-contractual representations - Proof of oral representations - Whether representations were made as to future matters - Where plaintiff alleged it would have negotiated alternative contract but for representations - Whether plaintiff has proved loss
Contract - 'Prevention principle' - Where plaintiff alleged defendant caused delay which prevented it from meeting the contractual milestones and earning a higher rate of COP - Whether prevention principle may found cause of action for damages for lost opportunity to earn higher rate of COP
Contract - Implied duty of cooperation - Where plaintiff alleged defendant caused delay which prevented it meeting milestone dates and earning increased rate of COP - Content of implied duty to cooperate - Whether plaintiff proved defendant's conduct caused it to miss milestone dates - Whether defendant liable for breach of contract for conduct causing delay
Contract - Operation and construction of exclusion clause - Where contract excludes liability for consequential loss - Whether defendant liable for damages for loss of opportunity to earn higher rate of COP
Contract - Where contract provided for plaintiff to carry out works as directed by defendant - Where defendant allocated work to another contractor - Whether plaintiff had fixed scope of work - Whether defendant in breach for removing work from scope of work for reallocation to another contractor - Whether plaintiff has proved loss - Whether liability excluded as liability for consequential loss
Contract - Where parties agreed the contract could only be varied in writing - Whether contract varied by payment of allowance outside terms of contract - Whether defendant estopped from denying variation
Contract - Where defendant made monthly progress payments - Where payments on account - Where defendant disputed liability to pay allowance - Whether defendant entitled to deduct amounts paid as allowance from subsequent payment claim as a correction of error in earlier payment or to set off disputed amount
Contract - Whether defendant liable for costs incurred by plaintiff in refinancing due to delayed payment - Whether consequential loss - Whether interest prescribed in contract the sole remedy
Contract - Time bar - Whether defendant can rely on contractual time bar in defence of claims not included in final payment claim
Competition and Consumer Act 2010 (Cth), s 82 , s 87
Trade Practices Act 1974 (Cth), s 52
Adnunat Pty Ltd v ITW Construction Systems Australia Pty Ltd [2009] FCA 499
Alpha Wealth Financial Services Pty Ltd v Frankland River Olive Co Ltd [2008] WASCA 119
Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540
Australis Media Holdings Pty Ltd v Telstra Corporation Ltd (1988) 18 NSWLR 540
Badenach v Calvert [2016] HCA 18; (2016) 257 CLR 440
Biggin and Co Ltd v Permanite Ltd (1951) 1 KB 422
BP Refinery (Westernport) Pty Limited v Shire of Hastings (1994) 180 CLR 266
Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153
Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd [2001] FCA 1833; (2001) 117 FCR 424
Briginshaw v Briginshaw [1938] HCA 34; (1938) 60 CLR 336
Butcher v Lachlan Elder Realty Pty Ltd [2004] HCA 60; (2004) 218 CLR 592
Cahill v Kiversun Pty Ltd; Molonglo Group (Aust) Pty Ltd v Cahill & Anor [2017] VSC 64
Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304
Carr v JA Berriman Pty Ltd [1953] HCA 31; (1953) 89 CLR 327
Cenric Group v TWT Property Group [2018] NSWSC 1570
Codelfa Construction Pty Ltd v State Rail Authority of NSW [1982] HCA 24; (1982) 149 CLR 337
Cohen & Co v Ockerby & Co Ltd [1917] HCA 58; (1917) 24 CLR 288
Commissioner for Main Roads v Reed‑Stewart Pty Ltd [1974] HCA 53; (1974) 131 CLR 378
Commonwealth Bank of Australia v Barker [2014] HCA 32; (2014) 253 CLR 169
Crown Melbourne Ltd v Cosmopolitan Hotel (Vic) Pty Ltd [2016] HCA 26; (2016) 260 CLR 1
Darlington Futures Ltd v Delco Australia Pty Ltd [1986] HCA 82; (1986) 161 CLR 500
Di Giovanni v Dark Horse Developments Pty Ltd [2014] WASCA 188
Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640
Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd [1988] 14 NSWLR 523
Environmental Systems Pty Ltd v Peerless Holdings Pty Ltd [2008] VSCA 26; (2008) 19 VR 358
Fazio v Fazio [2012] WASCA 72
Fitzgerald v Masters [1956] HCA 53; (1956) 95 CLR 420
Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407; (2009) 76 NSWLR 603
Fubilan Catering Services Ltd v Compass Group (Aus) Pty Ltd [2007] FCA 1205
GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd [2003] FCA 50; (2003) 128 FCR 1
Gestmin SGPS SA v Credit Suisse (UK) Ltd [2013] EWHC 3560
H & E Van der Sterren v Cibernetics (Holdings) Pty Ltd (1970) 44 ALJR 157
Helton v Allen [1940] HCA 20; (1940) 63 CLR 691
Hera Project Pty Ltd v Bisognin (No 3) [2017] VSC 268
Horsell International Pty Ltd v Divetwo Pty Ltd [2013] NSWCA 368
James Hardie Industries NV v Australian Securities and Investments Commission [2010] NSWCA 332
James Point Pty Ltd v The Minister for Transport [No 3] [2018] WASC 277
John Grant & Sons Ltd v The Trocadero Building Investment Company Limited [1938] HCA 20; (1938) 60 CLR 1
John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451
Jones v Dunkel [1959] HCA 8; (1959) 101 CLR 298
Kordan Pty Limited v Federal Commissioner of Taxation [2000] FCA 1807; 46 ATR 191
Laidlaw v Hiller Hewitt Elsley Pty Ltd [2009] NSWCA 44
Lemon v Mead [2017] WASCA 215
Lighting By Design (Aust) Pty Ltd v Cannington Nominees Pty Ltd [2008] WASCA 23; (2008) 35 WAR 520
Marks v GIO Australia Holdings Ltd [1998] HCA 69; (1998) 196 CLR 494
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104
National Westminster Finance New Zealand Ltd v National Bank of New Zealand Ltd [1996] 1 NZLR 548
Nissho Iwai Australia Ltd v Malaysian International Shipping Corporation, Berhad [1989] HCA 32; (1989) 167 CLR 219
Parlux SpA v M & U Imports Pty Ltd; M & U Imports Pty Ltd v Gava International Freight SpA [2008] VSCA 161; (2008) 21 VR 170
Peter Turnbull & Co Pty Ltd v Mundus Trading Co (Australasia) Pty Ltd [1954] HCA 25; (1954) 90 CLR 235
Port Jackson Stevedoring Pty Ltd v Salmond & Spraggon (Aus) Pty Ltd [1980] UKPCHCA 1; (1980) 144 CLR 300
Probuild Constructions (Aus) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151
RJ Baker Nominees Pty Ltd v Parsons Management Group Pty Ltd [2010] WASCA 128
Robinson v Harman [1848] EngR 135; (1848) 1 Ex 850, 855; [1848] EngR 135; 154 ER 363
Secured Income Real Estate (Aus) Ltd v St Martins Investments Pty Ltd [1979] HCA 51; (1979) 144 CLR 596
Segelov v Ernst & Young Services Pty Ltd [2015] NSWCA 156
Sellars v Adelaide Petroleum NL (1994) 179 CLR 332
Servcorp WA Pty Ltd v Perron Investments Pty Ltd [2016] WASCA 79; (2016) 50 WAR 226
Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2] [2012] WASCA 53; (2012) 287 ALR 360
State of New South Wales v Deren [1999] NSWCA 22
Sze Hai Tong Bank Ltd v Rambler Cycle Co Ltd (1959) AC 576
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272
Taylor v Ellis [1956] VicLawRp 72; [1956] VLR 457
The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64
Watson v Foxman (1995) 49 NSWLR 315
Westgyp Pty Ltd v Northline Ceilings Pty Ltd [2018] WASC 244
(1) Karara engaged in misleading and deceptive conduct by representations it made in the negotiation of the Main Works Contract.
(2) AGC lost the opportunity to earn a higher rate of Corporate Overhead and Profit (COP) as a result of Karara directing Variations to the Main Works Contract which prevented AGC from meeting milestones pursuant to an incentive scheme in the Contract. AGC pleaded eight separate matters:
(3) AGC lost the opportunity to earn COP on Work within its contracted Scope of Work that Karara reassigned to Ausco.
(4) Karara was liable to reimburse an allowance (the SPEC allowance) paid to AGC's leading hands at Karara's request and COP on the SPEC allowance. This claim is made under both the Early Works Contract and the Main Works Contract.
(5) AGC incurred additional finance costs due to late payment by Karara.
(2) if they were made, were the representations misleading or deceptive;
(5) are the claims under the Australian Consumer Law subject to the contractual time bar pleaded by Karara.
(1) do the terms relied on by AGC arise on the proper construction of the Main Works Contract, or as terms to be implied in fact or in law;
(3) would AGC have achieved practical completion by 1 September 2012 (or any of the later milestone dates, and which of them) but for the Variations directed by Karara; and
(4) are AGC's claims defeated, in whole or in part, by the contractual exclusion of liability for consequential loss.
The claim for loss of COP on work allocated to Ausco
(1) AGC contended that, on the proper construction of the Main Works Contract as a whole, or by terms implied as a matter of business efficacy, AGC was obliged to carry out a fixed Scope of Works valued at about $176,789,041.00;[3]
(2) Karara contended that AGC was only obliged to perform such work and so much of the Scope of Work in sch 1 to the Main Works Contract as it was directed to do by Karara.
(1) what was the direction that Karara gave to AGC regarding the SPEC allowance;
(2) was it a term of the Early Works Contract or the Main Works Contract that Karara would reimburse AGC for the payment of the allowance;
(3) did Karara and AGC make a collateral agreement that AGC would reimburse the SPEC allowance and COP on the allowance;
(4) is Karara estopped from denying it was obliged to reimburse AGC for the SPEC allowance; and
(5) was Karara entitled to deduct or set off payments it had made in reimbursing the SPEC allowance against amounts otherwise due to AGC.
(1) on the proper construction of the Main Works Contract, do the claims for additional finance come within the exclusion of liability for consequential loss;
(2) on the proper construction of the Main Works Contract, is interest the sole remedy for late payment;
(3) has AGC proved the breaches of contract alleged; and
(4) are the losses claimed too remote to be recovered as damages for breach of contract.
(1) do the provisions governing the making of a final payment claim, and purporting to exclude claims not included in the final payment claim, apply to one or more of the claims;
(2) do the provisions for makings claims, other than a variation claim or payment claim, in the course of the Contract exclude claims that were notified in accordance with that clause;
(3) is Karara entitled to insist on its strict contractual position;
(4) has there been an abandonment by the parties of the Contract; and
(5) is Karara estopped from asserting its contractual rights.
(1) Mr Stuart Maxwell Kenny, its then CEO, Executive Chair and Managing Director;[4]
(2) Mr George Alistair Stuart Arndt, its Project Controls Manager;[5]
(3) Mr Gerard Patrick Hutchinson, its Group Manager Corporate, Development;[6]
(4) Ms Christine Ann Deering, its Cost Administrator;[7] and
(5) Ms Elaine Catherine Buchanan, its Employee Relations Manager for the Project.[8]
(1) Mr Richard Thomas Bourne, its Project Director;[9]
(2) Mr David Arthur Geddes, its Contracts and Commercial Manager;[10]
(3) Mr Andrew Donovan Lindsay, its Manager Commercial Operations;[11]
(4) Mr Dennis James Gangell, its Senior Planner;[12]
(5) Ms Melissa Irene Kuipers, its Site Senior Cost Controller;[13] and
(6) Mr Steve Thistlethwaite, its Senior Project Superintendent for the Project.[14]
The rule in Jones v Dunkel is no more than a statement of common sense. It is regularly referred to but often mistakenly applied. It is regularly formulated in two different, albeit related ways. One formulation, derived from the judgment of Dixon J at 304-5 is that where a party having the onus adduces evidence in support of his or her case which gives rise to a positive inference which is more probable than another inference which is also open, that more probable inference if left unexplained will be accepted. It is important to note that his Honour, referring to an unreported judgment of the High Court in Bradshaw v McEwans Pty Ltd (27 April 1951), firmly rejected the rule that failure to give evidence permits an inference to be drawn where the state of evidence is such that there are 'competing inferences of equal degree of probability' so that the choice between them is a mere matter of conjecture. The other formulation, derived from the judgment of Kitto J at 308 is that where there is an inference favourable to a plaintiff and the defendant chooses to call no evidence to rebut it, it can be concluded that that evidence would not have assisted the case of the defendant and an inference favourable to the plaintiff, for which there are grounds in the evidence, might then be more confidently drawn. Both formulations are to be found linked in the judgment of Menzies J at 312 where his Honour, explaining what a proper direction to the jury in that case would make clear:
(i) that the absence of the defendant ... as a witness cannot be used to make up any deficiency of evidence;
(ii) that evidence which might have been contradicted by the defendant can be accepted the more readily if the defendant fails to give evidence;
(iii) that where an inference is open from facts proved by direct evidence and the question is whether it should be drawn, the circumstance that the defendant disputing it might have proved the contrary had he chosen to give evidence is properly to be taken into account as a circumstance in favour of drawing the inference.[19]
(a) For AGC, Mr Nicol and Ms Tibbets were part of the team. Neither was called as a witness.
(b) For Karara, Mr Geddes was responsible for formulating and negotiating contracts, and overseeing a team of 25 to 30 people working under him with respect to details of the Scope of Work.[31]
There is a view that in the trial of a commercial case the best approach in such circumstances is to place little, if any, reliance on witnesses' recollections of what was said in meetings and conversations. I acknowledge the doubt that necessarily attends the recollection of conversations many years in the past. But it does not follow that the correct starting point is to simply place little reliance on oral recollection. Rather, I should assess that evidence in light of its inherent probabilities in the context of the objectively established facts.[67]
At the start of the meeting, Mr Murdoch said to me words to the effect that 'we'll get this sorted in 10 minutes, here's what I'm proposing.' Murdoch said to me words to the effect that:
(a) KML was willing to agree to a base profit rate for AGC of 11% of the costs of the works, with a structure for an incremental increase of 4% on the total cost of the works if particular conditions were met;
(b) under this proposal, there would be no 'downside' for AGC ...;
(c) KML would reinstate the scope of works which KML had previously indicated it was going to remove from AGC. That scope of work was valued at between $43 to $50 million ...;
(d) with the reinstated scope of works, the total cost of the remaining structural, mechanical and piping works to be carried out by AGC was approximately $200 million ...;
(e) with the additional 4%, and the reinstatement of $43 to $50 million of works, AGC stood to earn an additional $8 to $10 million ...;
(f) the additional 4% would be payable to AGC if it completed the 'dirty concentrate works' by particular milestones which would be set by me and him ...;
(g) key KML staff responsible for managing performance of the works were already incentivised and that that would be 'insurance for the project' ...;
(h) we would set four dates as the milestones for the completion of the dirty concentrate works as follows:
Mr Murdoch and I did not discuss the dates which we would set as the milestones for completing the dirty concentrate works. I said to Mr Murdoch words to the effect that AGC was willing to agree to the proposed structure. Mr Murdoch said words to the effect that he would arrange for our agreement to be reduced to writing.[71]
No risk/no exposure to LD's, No exposure to productivity issues, No exposure to workmanship rework costs.
Reinstatement of full remaining scope, est $43m-$50m.
I am not sure what the awarded value will be but based upon available bonus pool the contract value must be in the order of $200m.
Milestone bonus payments of 4% to take total mark up to 15%.
These will be applied to construction schedule activities, 4 off separable portions, 1% extra mark up to each of the targets.
Senior Karara staff have bonus payments tied to the same milestones.
Steve believes there will be an additional $8m-$10m available for AGC to earn.
Action is currently with Steve to arrange for written confirmation of this agreement.
It is intended to begin from Feb onwards.[73]
I'm going to characterise it ... in another way to say that he had said to me, 'the upside to AGC is in the order of 8 to 10 million'.[84]
It was a ... contract that we were entering into, had an expectation that with the management team and the processes there, the right amount of labour that would be required to execute the work, there would be an earning ability of about 200 million.[88]
The scope of work was - had been evaluated and assessed by AGC and then there was this apparent scope of work that was - was going to be removed. I don't think anybody had truly costed the scope that was going to be removed, but - and this is why there was a little bit of flexibility there. But in the end, the agreement was that we expected that the overall value of the work that was going to be undertaken by AGC was around about 200 million. [89]
It's generally what would have been said to me. Not specifically. I can't - I didn't relay it or record it word for word.[92]
I can see that. That's correct. But it doesn't remove the fact that he represented to me that they were incentivised on ‑ I'm going to now say on a similar basis but if they weren't incentivised with similar dates or the same dates there would be a conflict.[95]
In the interests of making Friday's meeting a 'hand shake' there are two outstanding issues that need to be agreed your end so in advance would be great. We have rejected your commercial guys counter as this isn't what we agreed.
(a) I should not worry about AGC failing to achieve the first milestone because AGC was currently erecting approximately 350 tonnes of steel per week. Mr Murdoch said to me words to the effect that the 'target' for AGC was 230 tonnes of steel per week, and that for AGC to 'get in front' it would need to erect 250 tonnes of steel per week ...;
(b) there was accommodation for AGC's personnel currently available on site, and there would be additional beds available after April 2012 ...;
(c) there was 'acceleration built into the mobilisation plan' and 'float in the program' ...; and
(d) in April and May, the weather would be improving.[117]
[Acceleration] is built into [mobilisation] plan.
Now, you don't actually remember him saying that: You shouldn't worry about AGC failing to achieve the first milestone because AGC was currently erecting 350 tonnes of steel per week.
You don't actually remember him saying that, do you?---Not word for word, but I - - -
Well, not even remotely, do you?---No, that's not correct. My notes reflect that.[129]
So the point that you're making here is this, isn't it? That the real understanding you had at the time was that Mr Murdoch was telling you that he was going to improve project management?---The real understanding was that Mr Murdoch was aware of the ‑ the site conditions, he was aware of the schedule, and that he would do what was necessary to ensure that barriers were removed so that we could get on and achieve the productivity and the progress required to ensure that we made the milestones.
And how do you say that he represented that to you?---Because - - -
What did he say that led you to that understanding?---Because there was float built into the schedule, the beds were going to be made available ... at the accommodation village, that the supervision ... the key personnel from KML were incentivised. So not one thing ... - but a number of factors led me to believe that KML had ... the project targets ... as not only a target, but something that they were managing too. They had the levers that could control the progress and the productivity.[131]
... I understood him to mean that there would be no impediment to AGC mobilising sufficient personnel to site to achieve practical completion of the dirty concentrate works.
Got that from a combination of what he said about accommodation and the fact that there was float in the program?---That's correct.
Or just the accommodation?---No. The acceleration in the program and the accommodation led me to believe that we needed additional resources - that there would be - sorry, there would be additional resources called upon and that there was sufficient accommodation for those resources to be accommodated.[133]
I can confirm that the Scope of Works that has been incorporated in the conformed contract does include all of the works that were removed from AGC's scope of works except for process plant areas contracted out to another contractor.[138]
Please proceed with conforming the contract, incorporating Schedule 2J as was attached to this email and including all of the works that were removed from AGC's scope of works except for process plant areas contracted out to another contractor.[139]
The question whether conduct is misleading or deceptive or is likely to mislead or deceive is a question of fact. In determining whether a contravention of s 52 has occurred, the task of the court is to examine the relevant course of conduct as a whole. It is determined by reference to the alleged conduct in the light of the relevant surrounding facts and circumstances. It is an objective question that the court must determine for itself. It invites error to look at isolated parts of the corporation's conduct. The effect of any relevant statements or actions or any silence or inaction occurring in the context of a single course of conduct must be deduced from the whole course of conduct. Thus, where the alleged contravention of s 52 relates primarily to a document, the effect of the document must be examined in the context of the evidence as a whole. The court is not confined to examining the document in isolation. It must have regard to all the conduct of the corporation in relation to the document including the preparation and distribution of the document and any statement, action, silence or inaction in connection with the document.[149]
to convey to KML, AGC's actual progress of the SMP works against its planned progress and to forecast progress going forward to completion ...
The data for update the schedule was based on status weekly updates from AGC's Construction Supervisors was reported to my planning team.[157]
The Weekly Progress Reports were provided to AGC's head office.[158]
The Contract constitutes the entire, final and concluded agreement between the Parties. It supersedes any previous arrangements, correspondence, tenders, representations, proposals, understandings and communications, whether oral or in writing including the Early Works Contract.[164]
(a) KML was willing to agree to a cost reimbursable contract with AGC on the basis that:
(i) AGC was entitled to be reimbursed its direct costs;
(ii) KML would pay AGC a margin on its direct costs, being AGC's corporate overhead and profit;
(iii) the margin would be equal to 15% of AGC's direct costs;
(iv) the margin was subject to AGC completing the Dirty Concentrate Works by milestone dates that had yet to be agreed;
(v) there would be a series of consecutive milestone dates agreed for the completion of the Dirty Concentrate Works and if a milestone date was not achieved, the margin would be reduced by about 1%, to a minimum of 11%;
(vi) the margin would apply to the whole of the works, being the remaining structural, mechanical and piping works performed by AGC, and not just the Dirty Concentrate Works;
(b) the cost to undertake the SMP works necessary for the construction and installation of KML's ore processing plant (the Plant) was to be approximately $200 million;
(c) the SMP works to construct the Plant would include works valued at approximately $43 to $50 million, which KML had earlier indicated would be performed by a different contractor;
(d) on the basis of the 15% margin to be paid on AGC completing the Dirty Concentrate Works by the first milestone date, AGC would have the opportunity to earn an additional $8 to $10 million margin on the $200 million worth of SMP works to be completed;
(e) there was no 'down side' to AGC, as KML would not delay AGC's performance of the SMP works and AGC would not be exposed to liquidated damages, productivity issues, or workmanship rework costs; and
(f) KML would not do anything to prevent AGC from completing the Dirty Concentrate Works by the first milestone;
(g) AGC could be assured that KML would not do anything to prevent AGC from completing the Dirty Concentrate Works by the first milestone as the key KML staff responsible for managing performance of the works were already incentivised to manage performance of the works and they would have their bonuses tied to the same milestones, once KML and AGC agreed the milestone dates for completion of the Dirty Concentrate Works, which would be AGC's 'insurance for the project'.[166]
(i) the scope of work included SMP works valued at approximately $200 million, including works that KML had removed for later reallocation ... valued at approximately $43 to $50 million, which KML had earlier indicated would be performed by a different contractor;
(ii) the 15% margin would apply to the whole of the SMP works if AGC completed the Dirty Concentrate Works by the first milestone and not just to the direct costs associated with the completion of the Dirty Concentrate Works; and
(iii) KML would not do anything to prevent AGC from completing the Dirty Concentrate Works by the first milestone.[167]
(a) AGC was currently erecting approximately 350 tonnes of steel per week, and that the 'target' for AGC was 230 tonnes of steel per week, and that for AGC to 'get in front' it would need to erect 250 tonnes of steel per week;
(b) there was accommodation for AGC's personnel currently available on site, and there would be additional beds available after April 2012; and
(c) there was 'acceleration built into the mobilisation plan' and 'float in the program'. [168]
(i) it had sufficient steel on site to enable AGC to erect 250 tonnes of steel per week, and thereby achieve practical completion of the Dirty Concentrate Works earlier than the first milestone;
(ii) accommodation would not be an impediment to AGC mobilising sufficient personnel to site to achieve practical completion of the Dirty Concentrate Works by the first milestone;
(iii) the availability of accommodation for AGC personnel was going to improve in April 2012;
(iv) there would be no impediment to AGC mobilising sufficient personnel to site to achieve practical completion of the Dirty Concentrate Works by the first milestone.[169]
(a) KML engaged Ausco Engineering Pty Ltd to carry out SMP works valued at approximately $62 million, which were SMP works contained in the scope of work of the Main Works Contract;
(b) KML asserted that the 15% margin that would apply to AGC's completion of the works, or such other margin as was determined by reason of AGC's completion of the Dirty Concentrate Works, only applied to works undertaken during the Interim Period (as defined in the Main Works Contract) and not to all works undertaken pursuant to the Main Works Contract;
(c) KML prevented AGC from completing the Dirty Concentrate Works by the first milestone;
(d) KML did not have sufficient steel on site to enable AGC to erect 250 tonnes of steel per week;
(e) KML did not have sufficient accommodation to enable AGC to mobilise sufficient personnel to site to achieve practical completion of the Dirty Concentrate Works by the first milestone;
(f) KML did not ensure that the availability of accommodation for AGC personnel improved in April 2012; and
(g) KML did not permit AGC to mobilise sufficient personnel to site to achieve practical completion of the Dirty Concentrate Works by the first milestone.[170]
(2) alternatively, a cost reimbursable contract with the COP component fixed at a higher rate;
(3) alternatively, a cost reimbursable contract with a different milestone regime;
(4) alternatively, a cost reimbursable contract with the COP fixed at a higher rate, and which applied to the whole of the SMP works;
(5) alternatively, a cost reimbursable contract with the COP fixed at a flat rate of 13.5%;
(6) alternatively, a contract under which it had more control over the amount of labour on site, its prioritisation, and the amount of non-Dirty Concentrate Works that it was required to complete and therefore, the opportunity to complete the Dirty Concentrate Works by one of the milestone dates.[182]
Because, based on my conversation with Mr Murdoch, I thought that AGC had good prospects of achieving practical completion of the dirty concentrate works by the first milestone, and even better prospects of achieving practical completion of the dirty concentrate works by each of the subsequent milestones, I agreed to the milestone dates and percentages which Mr Murdoch proposed at our meeting on 2 March 2012.[184]
relatively straightforward bargain ... for AGC to perform a fixed scope of SMP work ... For that work, it was to be compensated in the order of $176 million, made up of reimbursement of its direct costs and a margin calculated as a percentage of the direct costs. The margin was to be 15%, reducing to 11% if milestones for the practical completion of the dirty concentrate works were not achieved.[196]
(i) AGC did not have and was not obliged to perform any fixed scope of work under the Contract and was only obliged to perform such Work and so much of the scope of work in Schedule 1 as it was directed to do by Karara's Representative; and
(ii) upon being directed to perform Work or part of The Works, AGC was required to perform that Work in accordance with the Contract. [197]
1.3. Annexures to the Formal Instrument of Agreement;
1.5. Schedules 1-12 to the Agreement;[198] and
shall perform the Contractor's Responsibilities in accordance with the Directions of the Company's Representative as required by the Company to enable the Company to achieve Practical Completion of The Works:
(a) On or before by an agreed Date of Practical Completion; and
(b) In accordance with an approved Program including Key Dates.[207]
The Works means the whole of the Work to be carried out and completed in accordance with the Contract, as Directed by the Company's Representative including Variations provided for by the Contract;
Work means any work or activity to be undertaken by the Contractor in accordance with the Contract, as directed by the Company's Representative, in order to perform the WUC including the provision of materials or goods, installation or erection of goods or equipment, that shall form part of The Works;
WUC (from 'Work under the Contract') means the work which the Contractor is or may be required to carry out and complete under the Contract, as directed by the Company's Representative, and includes Variations, remedial work, Construction Plant and Temporary Works.
The intent of this section is to provide the Contractor with a general outline of the extent of the WUC [the work which the Contractor is or may be required to carry out and complete under the Contract, as directed by the Company's Representative, and includes Variations, remedial work, Construction Plant and Temporary Works]. The Contractor shall examine all of the Contract documents including all drawings, specifications exhibits, and other referenced documents to determine the full extent of the WUC.
The Contractor shall supply the Contractor's Representative, Key Personnel and Workforce to complete the Work directed to be completed by the Company's Representative as set out in the Scope of Work... The Scope of Work excludes those works the Contractor has already completed under an agreement between the Company and the Contractor dated 31 March 2011.[213]
The Scope of Work (SOW) consists of the supply of all management, supervision, labour, materials, equipment, Construction Plant, scaffolding, tools, consumables, temporary Works and transportation necessary to install the Structural, Mechanical and Piping Work associated with the Project.
Unless otherwise stated in this SOW, the Contractor shall be responsible for the performance of the whole of The Works including such Work as may be required, but not specifically described herein, in order to achieve Practical Completion in accordance with the requirements of the Contract.[214]
The services to be provided by the Contractor shall include, but not be limited to
[this is followed by a series of dot points which include]
(i) Supply of design, engineering, materials and equipment required to complete the Scope of Work including:
(B) Design Documents and Drawings (including structural steel and piping); and
(C) Company-Supplied Items (including mechanical equipment, prefabricated structural steel, loose mechanical items and materials in prefabricated state for receipt, handling, assembly, installation and hook‑up by Contractor);
The Contractor shall be generally responsible for provision of:
(i) the Contractor's Representative, Key Personnel and the Contractor's Workforce, in accordance with the Contract, as directed by the Company's Representative, to undertake the installation, assembly, construction, testing and commissioning of the Works (hereinafter described collectively as Personnel);
(ii) Construction Plant (including consumables, cranes, vehicles, scaffolding and temporary construction materials), in accordance with the Contract, as directed by the Company's Representative, to undertake the installation, assembly, construction, testing and commissioning of the Works;
(iii) Contractors Insurances in accordance with the Contract;
(v) Contractor-Supplied Documents in accordance with the Contract, as directed by the Company's Representative;
(vi) Contractor-Supplied Items in accordance with the Contract, as directed by the Company's Representative; and
(vii) Quality assurance, industrial relations, occupational health & safety, environmental protection and HSEC in accordance with the Contract, with respect to:
(A) the activities of the Contractor's Representative, Key Personnel and the Contractor's Workforce, in accordance with the Contract, as directed by the Company's Representative; and
(B) Contractors Construction Plant, in accordance with the Contract, as directed by the Company's Representative
(C) Any other obligation, duty, responsibility or requirement which the Contractor is required to fulfil or perform in accordance with the Contract.[218]
in accordance with the Contract as directed by the Company's Representative to:
(ii) For a Defects Liability Period after Acceptance.
shall be responsible for the provision of the required number of suitably experienced, skilled, qualified and trained labour personnel and supervision for the completion of WUC, as Directed by the Company's Representative, in accordance with the Contract (the Workforce).
Subject to any Direction of the Company's Representative as to the required number of the Contractor's Workforce from time to time, the Contractor shall not reduce or depart or deviate from the Workforce Requirements without the prior consent or Direction of the Company's Representative. If requested by the Contractor's Representative, the Company acknowledges that such consent or Direction may be given or refused at the absolute discretion of the Company's representative.
(b) Corporate Overhead and Profit paid to Contractor.[227]
a variation to the WUC by anyone or more of the following:
(c) a change the levels, lines, positions or dimensions;
(f) a Direction to demolish or remove material or Work no longer required by the Company;
(g) an increase, decrease or reduction of the Workforce or the Workforce Requirements or any part;
The Company's Representative may Direct the Contractor, by Direction to the Contractor's Representative, to increase or reduce the number or composition of the Contractor's Workforce, or otherwise change the Workforce Requirements, at any time and from time to time. Any such Direction to:
any claim for payment of money (including damages) or for an increase in the Contract Sum:
(a) under, arising out of, or in any way in connection with, the Contract, including any Direction of the Company's Representative;
(b) arising out of, or in any way in connection with, WUC, Work or The Works; or
(2) in tort for negligence or otherwise, including negligent misrepresentations; or
After the date of Milestone 5 (1 October 2012) for the remaining period of the Contract (irrespective of the Date of Practical Completion of the Dirty Concentrate Works) the factor for Corporate Overhead and Profit shall be eleven (11) per cent.
Milestone 2: later than 1 August 2012 but not later than 15 August 2012
Milestone 3: later than 15 August 2012 but not later than 29 August 2012
Milestone 4: later than 29 August 2012 but not later than 12 September 2012
Milestone 5: later than 12 September 2012 but not later than 1 October 2012
(2) where AGC had been requested to suspend the carrying out of its responsibilities by the Company's Representative pursuant to GC 38 and the suspension was the sole cause of the delayed achievement of the date of Practical Completion of the Dirty Concentrate Works.[250]
(a) KML directed AGC to reduce the number or composition of AGC's Workforce, or otherwise change the Workforce Requirements;
(b) KML directed AGC to undertake additional non-scope work contained in over 1,800 Work Packs and other variation directions given by KML;
(c) KML delivered Company-Supplied steel, mechanical equipment and piping later than planned;
(d) KML provided Work Method Statements (WMS) to AGC later than planned;
(e) KML directed AGC to integrate AUSCO's workforce into AGC's Blue Collar workforce;
(f) KML directed AGC to undertake works other than the Dirty Concentrate Works;
(h) KML directed changes to the Program.[251]
(a) Karara was not liable on any basis for late or delayed provision of any Company-Supplied Items or documents;[255]
(b) AGC was solely responsible for delay in provision of Contractor‑Supplied Items;[256]
(c) AGC was required to give written notice of anything that would probably cause delay to WUC; [257]
(d) Karara might direct AGC to suspend carrying out the whole of or any part of its Responsibilities;[258]
(e) if AGC or Karara delayed in conducting an inspection or a test, the other might conduct the inspection or test;[259]
(f) it was a substantial breach for AGC to fail to proceed with due expedition and without delay;[260]
(g) Karara's representative might adjust the Milestone Dates in sch 2J for delay by Force Majeure Event, or where AGC was requested to suspend carrying out this responsibility. The Force Majeure Event or the suspension (and no other event) had to be the cause of delayed achievement of the date for Practical Completion of the Dirty Concentrate Works.[261]
If any changes to the schedule are deemed as being required by myself, I discuss this with AGC staff, who, if in agreement will either make the logic change, or request myself to do it. [265]
With reference to Special Conditions of Contract, Clause 2.3 Program, 'the Company shall be responsible for the Program ...' Contractor requests a copy of the Program from which WUC is scheduled from 1 February 2012.
Contractor seeks Company's planned activities to meet Milestone Dates for Completion. Pursuant to Clause 36.1.2, the Contractor also requests any written confirmation of any directives issued by the Company that represent a departure from the original WUC Program date 1 February 2012 as Contractor is obligated to provide written notice to the Company if the Contractor is unable to reasonably comply with any such directives.[266]
The exclusion of consequential loss: Main Works Contract GC 28.2
In no event will the Company be liable for the Contractor's Consequential Loss arising out of or in connection with the Contract.
loss or damage arising out of or in connection with the Contract including:
The terms of exception clauses must sometimes be read down if they cannot be applied literally without creating an absurdity or defeating the main object of the contract ... But such a modification by implication of the language which the parties have used in an exception clause is not to be made unless it is necessary to give effect to what the parties must be understood to have intended. [275]
48.1.2 The Company's Representative, before the Date of Practical Completion, may Direct a Variation.
48.1.4 The Contractor shall always be bound to execute a Variation.
48.1.5 The cost of the Variation shall be reimbursed to the Contractor in accordance with the Pricing Schedule.
(a) neither party would prevent the other from performing or enjoying the benefit of the Main Works Contract;
(b) Karara would do all such things as were necessary on its part to enable AGC to obtain the benefit of the Main Works Contract;
(c) Karara would act reasonably, having regard to AGC's interests under the Main Works Contract.[284]
36.1.1 The Contractor shall not and shall ensure that the Contractor's Personnel shall not, in the performance of the Contractor's Responsibilities, without reasonable cause, depart from the Program.
36.1.2 The Company's Representative may Direct in what order and at what time the various stages or portions of the Contractor's Responsibilities shall be carried out. If the Contractor can reasonably comply with the Direction, the Contractor shall ensure that the Contractor's Personnel do so. If the Contractor cannot reasonably comply, the Contractor's Representative shall give the Company's Representative written notice of the reasons.
36.1.3 If compliance with any such Directions under this clause, except those pursuant to the Contractor's default, causes the Contractor to incur more or less cost than otherwise would have been incurred had the Contractor not been given the Direction, the difference shall be assessed by the Company's Representative and reimbursed in accordance with the Contract.
where KML's representative directed a Variation which prevented AGC from completing the Dirty Concentrate Works by the first milestone date, alternatively, the second milestone date, alternatively, the third milestone date, alternatively, the fourth milestone date, alternatively, fifth milestone date, KML was obliged to reimburse AGC for the Corporate Overhead and Profit it would have been entitled to in accordance with the Main Works Contract but for the Variation.[296]
(2) it must be necessary to give business efficacy to the Contract, so that it will not be implied if the Contract is effective without it;
(3) it must be so obvious that 'it goes without saying';
(5) it must not contradict any express term of the Contract.[298]
Implication of a term in fact in a contract, by reference to what is necessary to give it business efficacy, was described in Codelfa Construction Pty Ltd v State Rail Authority of NSW as raising issues 'as to the meaning and effect of the contract'. Implication is not 'an orthodox exercise in the interpretation of the language of a contract, that is, assigning a meaning to a particular provision.' It is nevertheless an 'exercise in interpretation, though not an orthodox instance.' The implication of terms in fact was also characterised in Attorney General of Belize v Belize Telecom Ltd as an exercise in construction. Lord Hoffmann, delivering the judgment of the Privy Council, said:
'it is not enough for a court to consider that the implied term expresses what it would have been reasonable for the parties to agree to. It must be satisfied that it is what the contract actually means.'
The distinction thus drawn is appropriate even though the scope of the constructional approach adopted by Lord Hoffmann has been debated.[299]
care must be exercised in identifying both the content and operation of an implied obligation to co‑operate lest it be at odds with the terms upon which the parties have expressly agreed.[302]
(a) neither party would prevent the other from performing or enjoying the benefit of the Main Works Contract;
(b) Karara would do all such things as were necessary on its part to enable AGC to obtain the benefit of the Main Works Contract;
(c) Karara would act reasonably, having regard to AGC's interests under the Main Works Contract.[303]
(1) there were no observations of direct impact on the work due to the delivery of Work Method Statements;[309]
(2) there was no observed direct impact on productivity from the integration of the Ausco workforce into the AGC workforce.[310]
(a) by 11 August 2012, as contained in the 'Original Baseline Program';
(b) by 12 September 2012, as contained in the revised baseline program, 'RBL ‑ 22 Jan';
(c) by 31 August 2012, as contained in the revised baseline program, 'RBL 6 May',
taking into account 11 specified events and matters.
(1) most of the delay events were running in parallel;
(2) five of the six notices that lasted more than nine months were for delayed delivery of Company‑Supplied material.[314]
Equally, we have construction programs that deal with a critical path of works that involves delivery of equipment and construction of the works that ultimately leads to forecast dates for completion. The two things don't marry. And I've no real way of assessing whether one or the other was driving the progress of the project at any given time.[328]
Changing workforce requirements by directing AGC to limit the number of blue collar employees on site
(i) On 30 March 2012, KML's Mr Stark informed AGC's Ms Buchanan, that KML had placed a hold on all recruitment for the project.
(ii) On 3 April 2012, KML's Mr Stark informed AGC's Ms Buchanan, that KML had placed a hold on recruitment of 63 blue collar employees.
(vii) On 20 May 2012, KML's Mr Bourne directed AGC's Mr Vorster to maintain a Blue Collar labour work force of between 500 and 515 workers.
(viii) On 22 May 2012, KML's Mr Bourne wrote to AGC's Mr Vorster and re-stated the direction that AGC was to maintain a Blue Collar labour work force of between 500 and 515 workers.
(ix) On 23 July 2012, KML's Mr Bourne wrote to AGC's Mr Vorster stating that AGC was to maintain a Blue Collar labour work force of between 500 and 515 workers and otherwise, cease all further personnel mobilisations to Site.
(x) On 23 July 2012, KML's Mr Bourne wrote to AGC's Mr Vorster stating that AGC subsequent personnel mobilisations shall be directed as required.[330]
Were the directions by Karara Variations of the Contract
shall be responsible for the provision of the required number of suitably experienced, skilled, qualified and trained labour personnel and supervision for the completion of WUC, as Directed by the Company's Representative, in accordance with the Contract (the Workforce).
(1) GC 11.1.2 provides that the 'the required number of labour personnel and supervision, and their skills, qualifications and other requirements' be set out in sch 4 (Workforce Requirements).
(2) AGC was required to maintain its Workforce at the required number 'without reduction and otherwise in accordance with the Workforce Requirements, from the Commencement Date until the Date of Practical Completion.'[339]
Subject to any Direction of the Company's Representative as to the required number of the Contractor's Workforce from time to time, the Contractor shall not reduce or depart or deviate from the Workforce Requirements without the prior consent or Direction of the Company's Representative. If requested by the Contractor's Representative, the Company acknowledges that such consent or Direction may be given or refused at the absolute discretion of the Company's Representative.
(5) By GC 52.2.2, failure by AGC to employ, engage or retain the Contractor's Workforce in accordance with the Workforce Requirements was a substantial breach.
Would AGC have met the milestone dates but for the directions
As per discussions and agreement today between AGC/KML the following group of people are only approved to start.
This would thereby finalise AGC total workforce on site. (Capped)
As from Week Starting Monday 14/05/2012 any attrition from project can be replaced. (1 for 1)[354]
Access to the area. Whether there are construction methodologies that need to be determined first. It depends on the complexity of the works. Certain works may require a high degree of planning and that revolves around more than just construction itself, but health and safety, depending on the materials that you're using. It also depends on the type of materials that has been brought in, to what extent are they ready to be sold or do additional preparations need to be done on site?[358]
Scope of Work' means construction and installation of all structural, mechanical and piping works for the Project's process plant as further described by the Scope of Work.[371]
(1) Karara would be generally responsible for the supply of design, engineering, materials and equipment required to complete the Scope of Work;
(2) AGC would be generally responsible for the provision of Personnel and Construction Plant to undertake the installation, assembly, construction, testing and commissioning of the Works, 'in accordance with the Contract, as directed by the Company's Representative'.
(ii) transport to the workshop that is to be provided by the Company;
(v) procure the services of Company's Representative for inspection and sign off of all repairs;
(vi) load and transport the repaired steel members back to the designated laydown area;
(viii) the Work carried out by the Contractor in paragraphs (i) to (vii) inclusive is required (applicable to each work pack issued) to be coded separately under a specific code to enable the Company to monitor the amount of this Work for back charge purposes by the Company.
The Contractor shall perform the Work in accordance with the sections 3.6.2 and 3.6.3 of the Scope of Work.
(1) A contiguous column or piece of steel might not yet have arrived on site. Karara would often direct AGC to re-fabricate that particular piece of steel.
(2) AGC might identify steel with some sort of deformity, for example from damage in transit. The steel might need to be reworked before it could be installed.
(3) Steel might not match Karara's drawings, requiring re-fabrication to correct the error.
(4) Steel members might be out of alignment resulting in erected steel framework not being square.[375]
AGC was reimbursed for its Direct Costs, including the cost of performing the Work Packs as part of the normal monthly payment process. AGC was not required to make a variation claim before performing Work Packs or other variation work.[378]
We have not got a schedule that anyone can work to, and the current schedule is an out of date record of what has been constructed. Construction are installing steel and equipment as it becomes available and as such are jumping about the site. This makes timely procurement of items impossible, and everything is just classed as critical. However, with the manpower available, engineering and procuring everything at once is not possible leading to problems with 'late supply' when construction suddenly move to a new item.[384]
Were the Work Packs variations or within the Scope of Works
(1) It is a fair inference that where a Work Pack recorded that the time was to be back charged to the supplier, AnSteel, the work related to rectification of defective steel. Rework of steel considered by Karara to be defective was within scope.[390]
(2) There were 47 Work Packs recorded as needing to be back charged to AGC. It is a fair inference that these Work Packs were for defective work that AGC was to rectify at its own cost, and were not a Variation.[391]
(3) Work Packs were issued for other matters, including unloading steel and modifications to unloaded steel; at least arguably, that work was within the Contractor's Responsibilities. AGC did not establish that it was not.
Did the additional Work Packs delay Practical Completion of the Dirty Concentrate Works
Late delivery of company-supplied steel, mechanical equipment and piping
(iv) On 10 April 2012, ... in relation to the delayed delivery to Site of distributors 1314-DI-068 and 1318-DI-069.
(v) On 24 April 2012, ...in relation to delays affecting: Area 1304 HP ‑ waiting for plate work for feeder: Area 1313 ‑ waiting for steel; Area 1317 ‑ waiting for missing tailing tank steel; Area 1320 ‑ steel work missing in relation not CV 009, 010 and 012 steel, expansion joints and valves for piping.
(vi) On 7 June 2012, ... in relation to delayed delivery of the Conveyor Jackdown Idlers.
(vii) On 25 July 2012, ... in relation to delayed delivery of a Tail Pulley Frame Trolleys for Conveyors CV 020, 021, 022 and 041.
(viii) On 6 August 2012, AGC's ... in relation to delayed delivery of the Metal Detectors for 1304 Belt Feeders and 1302 CV 11.
(ix) On 10 September 2012, ... in relation to delayed delivery of the hand rails.
(x) On 10 September 2012, AGC's ... in relation to delayed delivery of particular equipment, including sump pumps and other pumps, a conveyor transfer chute and other chutes amongst others.
(xi) On 24 September 2012, ...in relation to delayed delivery of equipment for the 1301CVR, 1302CVR, 1304CVR, 1306PG, 1319TDS, 1321PW, 1322PS, and 1323R.
Did late delivery delay practical completion of the Dirty Concentrate Works
The Company-Supplied Items are supplied to assist the Contractor in the performance of the Contractor's Responsibilities in accordance with the Contract. The Company, at its expense, shall use reasonable endeavours to Deliver the Company-Supplied Items to the Site in accordance with the Program but shall not be obliged to do so by the time or times stated in the Program nor shall the Company be liable to the Contractor on any basis for late or delayed provision of any Company-Supplied Items at any time or from time to time.
(1) Karara pleaded that, by GC 12.1.6 it was not liable to AGC on any basis for late or delayed provision of any information, material, documents and instructions, including Work Method Statements;[425]
(2) Karara denied that any failure to approve and return Work Method Statements constituted a Variation or Variation Order within the meaning of GC 48.1.2;[426]
(3) Karara pleaded that irrespective of the matters alleged, AGC would not have achieved the Milestone Dates.[427]
The Contractor shall observe the access and programming constraints and shall obtain the approval of the Company for the programming and work methods including Temporary Works, hard barricades and other protective measures.
(i) as to the scope of the Work to be performed by AGC;
and that it did so acting reasonably.[437]
(i) permit Karara's contractors at any time to have access to the Site for any purpose [GC 32.2.1];
(ii) ensure that its personnel permitted persons engaged by Karara to carry out work on the Site other than WUC and to cooperate with them [GC 32.2.2]; and
(iii) ensure that its personal cooperated with other contractors to ensure the coordination of the work of the other contractors with the performance of AGC's responsibilities [GC 32.2.3].[438]
(1) Ausco to provide additional resources for installation of Piping and other trades as deemed necessary to ensure DC.
(2) KML Supervision to actively manage new work teams.
(3) Ausco to provide additional Supervision to assist KML as applicable.
(4) KML to immediately review performance of AGC Supervision and remove non-performers.
(5) Remove from AGC package areas 1314/1318/1321/1320 piping scope and re-place with Ausco under direction from KML.
(6) Ausco to immediately supply additional resources as recently requested.[439]
Did the directions of May and 9 August 2012 delay practical completion of the Dirty Concentrate Works
The direction to undertake Works other than the Dirty Concentrate Works
The Contractor itself prior to and during the alleged Delay period has not performed its obligations in accordance with the Contract particular to failures in efficient recruitment activities, maintaining the required workforce numbers as directed by the Company and has recorded a number of negative disciplinary events related to 'no shows' and positive 'alcohol and drug' test results which has caused Delay to WUC due to increased workforce demobilisations, disruptions and the like.[461]
Did the direction prevent AGC meeting the Milestone Dates
Other directed changes/ Directed changes to the Program
The Company's Representative may direct the Contractor or the Contractor's Personnel to suspend the carrying out of the whole or part of the Contractor's Responsibilities for such time as the Company's Representative thinks fit.
Loss of Corporate Overhead and Profit in relation to work performed by Ausco
(1) Karara breached the requirement to reimburse AGC the cost of the Variations in accordance with the Pricing Schedule; [479]
(2) Karara breached its obligation to reimburse AGC for the COP pursuant to the Loss of Opportunity term;[480] and
(3) by progressively decreasing the works AGC was required to perform and giving parts of the works to Ausco, Karara breached the Cooperation Terms.[481]
where KML's representative directed AGC to reduce the number or composition of AGC's Workforce, or otherwise change the Workforce Requirements, at any time from time to time, KML was required to pay AGC the forgone Corporate Overhead and Profit of the Variation at the rate of 15%.[483]
(1) AGC did not have, and was not obliged to perform, any fixed scope of work under the Contract and was only obliged to perform such Work and so much of the scope of work in Schedule 1 as it was directed to do by Karara's Representative;
(2) Karara, in its absolute discretion, could terminate the Contract, in whole or in part, for its convenience;
(3) alternatively, Karara, acting reasonably, could terminate the Main Works Contract in whole or in part for its convenience.[485]
(1) the exclusion of Consequential Loss in GC 28.2;
(2) the limited circumstances in which AGC was entitled to any adjustment to the milestone dates;
(3) that COP was only payable on Direct Costs actually incurred; and
(4) Karara was entitled, acting reasonably, to direct a Variation to reduce the number or composition of AGC's Workforce or otherwise change the Workforce Requirements or Scope of Works.[486]
KML advises that certain elements of conveyor installation will be removed from Construction scope.
(2) Installation of conveyors 1319 CV-023; 024; 041; 042; 043 to battery limit of building 1318 South.
(3) Installation of conveyors 1315 CV -022; 021; 1314 CV-020 to battery limit of building 1314 West.
AGC will still require to provide tooling/material handling/materials as per current arrangements with KML etc to support conveyor installation labour.
Schedule management will be maintained through AGC planner and scheduler.
The works removed as listed above will be under the control of KML ...
These works will be commencing in approximately 2 to 3 weeks by other resources under KML direction and control.[492]
We are considering mobilising extra persons from Ausco, and if it happens you will be notified but please note if there are additional Ausco personnel brought to site, this number will be deducted from the AGC forecast, so the overall forecast SMP number will remain the same. I suggest that Ausco will have a presence here up until at least September or longer. [500]
Pursuant to Clause 6 the Company gives notice to the following:
Pursuant to Clause 11 Contractor's Workforce Subclause 11.1.1 '... The Contractor shall be responsible for the provision of the required number of suitably experienced, qualified and trained labour personnel and supervision for the completion of WUC ...' the Company advise that the Contractor, to date, has been unable to meet its obligations under the Contract particular to the provision of suitably experienced, qualified and trained labour personnel (the Workforce).
Pursuant to Subclause 11.2.1 '... The Company's Representative may direct the Contractor, by Direction to the Contractor's Representative, to increase or reduce the number or composition of the Contractor's Workforce, or otherwise change the Workforce Requirements, at any time and from time to time ...' therefore as a result of the Contractor being unable to meet its obligation under the Contract, the Company instructs the Contractor to integrate the labour personnel of Ausco Engineering into the Contractor's current Workforce.[505]
48.1.2. The Company's Representative, before the Date of Practical Completion, may Direct a Variation.
Pursuant to GC 1, Variation is defined to include a Variation to the WUC by 'an increase, decrease or omission of any part'; 'a Direction to not carry out Work'; and 'an increase, decrease or reduction of the Workforce or the Workforce Requirements or any part'.
11.2.1 The Company's Representative may Direct the Contractor, by Direction to the Contractor's Representative, to increase or reduce the number or composition of the Contractor's Workforce, or otherwise change the Workforce Requirements, at any time and from time to time. Any such Direction to:
Clause 1 is part of a printed form, and the powers conferred upon the architect extend to the giving of directions on a great variety of matters in addition to the 'omission of any work'. The clause is a common and useful clause, the obvious purpose of which ‑ so far as it is relevant to the present case ‑ is to enable the architect to direct additions to, or substitutions in, or omissions from, the building as planned, which may turn out, in his opinion, to be desirable in the course of the performance of the contract. The words quoted from it would authorize the architect (doubtless within certain limits which were discussed in R v Peto) to direct that particular items of work included in the plans and specifications shall not be carried out. But they do not, in my opinion, authorize him to say that particular items so included shall be carried out not by the builder with whom the contract is made but by some other builder or contractor. The words used do not, in their natural meaning, extend so far, and a power in the architect to hand over at will any part of the contract to another contractor would be a most unreasonable power, which very clear words would be required to confer.[516]
The Contractor... is entitled to perform all the contract work, so that a provision giving the Employer or their Architect a power to make omissions only contemplates genuine omissions, that is, work which it is intended should not be carried out at all. The Employer will generally not be entitled to use the power to omit work from the contract works in order to give it to another Contractor to do, or to do the work themselves ....[517]
(1) The defined terms 'Work' and 'WUC', in the Main Works Contract distinguished between the work AGC was directed by Karara to perform, and the Scope of Works. Karara submitted, in effect, that the Scope of Work specified the work that AGC was to perform, if so directed, and how it was to be performed.[518]
(2) SC 2.1 and SC 2.4 specified the general responsibilities of Karara and AGC. SC 2.1(b) stated the Contractor's Responsibility to provide personnel and plant, 'as directed by the Company's Representative, to undertake the installation, assembly, construction, testing and commissioning of the Works'. Karara submitted that AGC's obligations were confined to performing the work it was directed to perform by Karara's representative.[519]
Subject to the performance by the Contractor of its obligations under the Contract, the Company shall reimburse the Contractor for Direct Costs and Corporate Overhead and Profit in accordance with the Contract including the Pricing Schedule.
(a) preparation of a detailed cost estimate for the balance of The Works;
(b) preparation of the program for the balance of The Works; and
(c) preparation of Resources Plan for the balance of The Works.[523]
'Contract' means a contract for supply, construction and installation of all structural, mechanical and piping works for the ore processing plant for the project
'Scope of Work' means construction and installation of all structural, mechanical and piping works for the Project's process plant as further described by the Scope of Work.[525]
(1) an email of 2 March 2012, from Mr Stark (Karara) to Mr Andrews (AGC), in which Mr Stark advised that 'certain elements of conveyor installation will be removed from Construction scope';[528]
(2) the email of Mr Gangell (Karara) to Mr Thistlethwaite (Karara) and Mr Stark of 25 March 2012, regarding 'Ausco responsibilities';[529]
(3) an email of 10 May 2012 from Mr Thistlethwaite to Mr Andrews, advising that 19 more Ausco people would be arriving for the piping crews and that Karara would require them to complete an AGC induction;[530]
(4) an email chain between Mr Stark and Mr Klynsoon (AGC) and Mr Campbell (AGC) and others in which Mr Stark advised AGC of additional work scope that had been identified and removed from the AGC scope.[531]
(1) the exclusion of consequential loss would result in the contract being illusory only;
(2) the definition of consequential loss should be understood as limited to excluding liability only for indirect losses that were not within the reasonable contemplation of the parties;
(3) the losses show from Karara's breach of the Main Works Contract;
(4) GC 28.2 should be limited to acts which do not involve intentional, wilful or deliberate conduct;[533] and
(5) GC 28.2 is ambiguous, and should be construed contra proferentum.
(1) $123,590.71 plus GST for SPEC Allowance under the Early Works Contract; and
(2) $1,817,437.09 plus GST for SPEC Allowance under the Main Works Contract.[558]
(1) The matters contained in statement of claim pars [113] ‑ [116] gave rise to an estoppel in law and equity.[559] In its written submissions, AGC claimed this as both a conventional estoppel and an estoppel by representation or conduct.
(2) Karara's actions in querying the entitlement to the SPEC allowance, but continuing to reimburse AGC until August 2013 gave rise to an estoppel in law and equity.[560]
(3) Karara is estopped by conventional estoppel, from resiling from the common assumption that Ms Kuipers (Karara) exercised the powers and functions of the Company Representative under the Main Works Contract and was authorised to approve AGC's Direct Costs.[561]
The Pricing Schedule shall require the Contractor to submit monthly progress Claims on a cash flow neutral basis for:
(a) Reimbursement of approved Direct Costs subject to verification and audit...
The Contractor shall make its claims for payment on the basis of actual hours worked and wages paid to Direct Labour is verified by payroll records and in accordance with the applicable provisions of the Site Labour Agreement.
Reimbursement for overtime worked by Direct Labour outside normal working hours without prior written approval by Company except in emergency circumstances which will be subject however to subsequent written approval by Company following justification by Contractor.
Contractor will not be reimbursed for direct labour which are not the subject of an approved Resources Plan pursuant to Schedule 3C, or not otherwise approved by KML in writing in accordance with Schedule 2B, will not be included in Direct Costs...
If the leading hands work the 8 hours they get 9 hours if they work 9 hours they get 10 hours so on and so on 1 extra hour on what they work. If they only work 7.5 they only get 8.5 please pass this on to the leading hands. Nothing is for free.[579]
The Leading hands must start early with the supervisors and finish with the supervisors, when the supervisors are on site they must also share the paperwork and the daily safety audits with the supervisors. When the supervisor is on R&R they will have step into the supervisor role and run the crew as the supervisor. This is the role that is on offer. The extra hour is for time worked and extra responsibility required.[580]
(1) AGC was to be reimbursed for actual net costs incurred for payment of Direct Labour;
(2) the rates of pay for Direct Labour were required to be on the basis of the specified industrial agreements;
(3) overtime worked by Direct Labour without prior written approval was excluded and not to be subject to reimbursement;
(4) Direct Labour not otherwise approved by Karara in writing would not be reimbursed and not included for the purposes of the mark‑up for COP;
(5) working hours for Direct Labour were to be in accordance with the Site Labour Agreement.
(1) The parties have proceeded on the basis of an underlying assumption of fact, law, or both, of sufficient certainty to be enforceable (the assumption).
(2) Each party has, to the knowledge of the other, expressly or by implication accepted the assumption as being true for the purposes of the transaction.
(3) Such acceptance was intended to affect their legal relations in the sense that it was intended to govern the legal position between them.
(4) The proponent was entitled to act and has, as the other party knew or intended, acted in reliance upon the assumption being regarded as true and binding.
(5) The proponent would suffer detriment if the other party were allowed to resile or depart from the assumption.
(6) In all the circumstances it would be unconscionable to allow the other party to resile or depart from the assumption.
... to the extent the proponent relies upon an assumption of law or an assumption of mixed fact and law, the assumption of law must relate to private legal rights. Relevantly, for present purposes, a common assumption as to 'private legal rights' includes a common assumption as to the effect of contracts or agreements.[601]
(1) Payment was upon the general principle that AGC was able to maintain a neutral financial cash flow position;[603]
(2) AGC was to submit a payment claim detailing the amount of Direct Costs claimed, the COP claimed, and cumulative totals;[604]
(3) AGC was to submit a Cost Reconciliation Statement to Karara's Representative, to include all supporting documentation evidencing Direct Costs and other amounts claim during the previous month;[605]
(4) within a prescribed time, Karara's Representative was to provide a Progress Certificate evidencing the amount to be invoiced by AGC with respect to the relevant payment claim;[606]
(5) provision was then made for the submission of invoices and payment 'on a correctly rendered invoice, in accordance with the relevant Progress Certificate', and less 'any deductions the Company is entitled to make pursuant to any other clause under the Contract';[607]
(6) payment, other than Final Payment, was on account only;[608]
(7) Karara's Representative might, before issue of the Final Payment Certificate, by a further certificate correct any error which has been discovered in a previous certificate.[609]
47.5.1 The Company may deduct from moneys due to the Contractor any money due or which may become due from the Contractor to the Company under the Contract or otherwise and if those moneys are insufficient, the Company may have recourse to Security under the Contract.
47.5.2 The Company's entitlement to set off or deduct will not be affected by:
[Claim] includes any claim for payment of money (including damages) or for an increase in the Contract Sum:
(a) under, arising out of, or in any way in connection with, the Contract, including any Direction of the Company's Representative;
(b) arising out of, or in any way in connection with, WUC, Work or The Works; or
(2) in tort for negligence or otherwise, including negligent misrepresentations; or
Progress certificates are for the benefit of the builders to enable them to obtain payments on account during the progress of the works. And clauses 39 and 34 taken together make it clear that an obligation is imposed upon the defendant to pay the amount of the certificate when granted. The amount constitutes a debt due to the plaintiff. Unless the contract so provides progress certificates are not conclusive and payments made under them are 'provisional and subject to adjustment or to readjustment at the end of the contract,' and also, I think, in cases of error or mistake before its end.[613]
(1) under GC 24.1.3 for costs incurred by the Company for the protection of people and property;
(2) under GC 25.1.1 for urgent action by the Company to protect WUC;
(3) under GC 35.1.4 for work not carried out in accordance with a direction;
(4) under GC 40.3.3 for rectification of defective works;
(5) under GC 41.7.1 costs in connection with inspection or testing.
(a) (GC 47.1.2 (as varied)) ‑ Cost Forecast) at the commencement of each calendar month, KML was to provide AGC with a forecast of AGC's Direct Costs and Corporate Overhead and Profit for that calendar month (Cost Forecast). The cost forecasts were those which were claimable by AGC as set out in Schedules 2A through to 2J of the Main Works Contract. If AGC agreed with KML's Cost Forecast, AGC was to confirm the relevant forecast;
(b) (GC 47.1.5 (as varied)) if AGC did not agree with KML's Cost Forecast, AGC was to provide KML with a forecast cost which more accurately reflected the likely Cost Forecast and where it did:
(i) within three (3) business days, KML's representative shall review the Cost Forecast and request any additional information from AGC;
(ii) if requested, AGC shall provide any additional information within three (3) business days and by no later than the sixth (6th) calendar day of the month;
(c) (GC 47.1 (as varied)) If requested, AGC shall provide to KML's representative within three (3) business days any additional information with respect to any matters affecting KML's ability to issue the Progress Certificate (as defined in GC 47.1.7 (as varied) and the contract) and this process shall conclude by no later than the eleventh (11th) calendar day of the month;
(d) (GC 47.1, 47.1.9(b) and SC 3 (as varied ‑ Advance Payment Security)) AGC shall obtain a bank guarantee in the form of the unconditional banker's undertaking as set out in Appendix F for the amount of the Cost Forecast by no later than the fourteenth (14th) calendar day of the month (Advance Payment Security);
(e) (GC 47.1.6 (as varied)) For all weeks ending on Sunday in the month, on or before the following Thursday, AGC was to submit to KML's representative a cost statement for the week (Weekly Cost Reconciliation Statement) containing:
(i) all supporting documentation evidencing the Direct Costs (stipulated as reimbursable to AGC in the pricing Schedules 2A to 2I) incurred by AGC during the previous week, including purchase orders, invoices and remittance advices;
(ii) approved Contractor‑Supplied Items (as defined in the Contract) AGC had paid for, whether the items were onsite, or held in storage elsewhere;
(iii) any other relevant documentation reasonably requested by KML's representative;
(f) (GC 47.1.7 (as varied)) On the fourteenth (14th) calendar day of the month, KML's representative shall provide AGC with a Progress Certificate evidencing the amount to be invoiced by AGC with respect to the Cost forecast, adjusted for over or under payments of AGC's actual costs in the previous month as calculated by the weekly Cost Reconciliation Statements;
(g) (GC 47.1.9 and SC 3 (as varied)) Not later than the fifteenth (15th) calendar day of the month, AGC shall submit to KML's representative:
(i) an invoice for payment in the amount certified in the Progress Certificate; and
(ii) the Advance Payment Security in exchange for the return by KML's representative to AGC of the previous months' Advance Payment Security;
(h) (GC 47.1.10) KML shall pay the invoice within two (2) business days of receipt, less:
(i) any amounts paid directly by KML to a Subcontractor;
(ii) any deductions KML is entitled to make pursuant to any other clause under the Main Works Contract.
(1) AGC's letter to Karara, dated 10 April 2012;[616]
(2) Karara's letter to AGC, dated 15 April 2012;[617]
(3) AGC's letter to Karara, dated 24 April 2012;[618]
(4) Karara's letter to AGC, dated 25 April 2012.[619]
The Company has investigated current practices and confirms its agreement to adopt the principles of the revised payment process contained within B2362_CST004_Ltr 003_Payment Process Flow Chart pdf.
Please submit a letter requesting the Company's Approval, outlining the Contractors proposal in detail. [623]
Pursuant to C 47 Payment the Company herein approves the Contractors request to revise the monthly payment process generally in accord with the Contractors B2362_CST004_Ltr 003_Payment Process Flow Chart pdf.
The Company will endeavour to process the Contractors Payment Claims in accord with Contract requirements; however the Company rejects the Contractors request 'to issue a variation to align relevant Contract Clauses ...'[625]
Except as provided at Law or in equity or elsewhere in the Contract, none of the terms of the Contract shall be varied, waived, discharged or released, except with the prior written consent of the Parties.
(1) AGC was to submit a Payment Claim on the first of each month detailing its forecast Direct Costs and amount for COP for that calendar month.
(2) Within 7 business days of receipt, Karara's Representative was to review the Payment Claim and request any additional information required; AGC was to provide any additional information so requested within 5 Business Days.
(3) On the seventh of each month AGC was to submit to Karara's Representative a Cost Reconciliation Statement for the previous month, including all supporting documentation and confirmation of the total amount of Security provided by the AGC as at the date of the Cost Reconciliation Statement.
(4) On the fourteenth of the month, Karara's Representative was to provide AGC's Representative with a Progress Certificate evidencing the amount to be invoiced by AGC.
(5) If AGC failed to submit a Payment Claim for any given month Karara's Representative would issue a Progress Certificate evidencing its opinion of moneys due to AGC for the month.
(6) On the fifteenth of the month, the AGC was to submit to Karara's Representative:
(7) Payment on a correctly rendered invoice, in accordance with the relevant Progress Certificate, was to be made by the Company within two Business Days of receipt of a correctly rendered.
Both building contracts provided for what was, by any measure, a very high interest rate (19.94% per annum) for late payment under the building contracts. The obvious inference is that the agreed interest rate was to recompense the appellant for not having the use of the moneys due and payable under the building contract. Even if, which has not been established, that rate did not protect the appellant against all relevant loss, it would not be in the reasonable contemplation of the parties that he would be entitled to top it up with a Hungerfords claim.[638]
(a) a statutory declaration certifying payment of workers, subcontractors and contractors; and
(b) a written Final Payment Claim endorsed 'Final Payment Claim'.[639]
a Payment Claim together with all other Claims whatsoever in connection with the subject matter of the Contract including all Claims which the Contractor considers exist under or arising out of any alleged breach of the Contract whether or not such Claims had been made at any time previously.[640]
For AGC, the following held the specified positions at the time of the events relevant to this decision:
(8) Dave Gilbert - Executive General Manager, Operations.
(9) Gerard Hutchinson - Group Manager Corporate Development.
(12) Hugh Nicol - Group Manager - Commercial Services.
(15) Lisa Tibbits - Senior Contracts Specialist and Risk Co‑ordinator.
For Karara, the following held the specified positions at the time of the events relevant to this decision:
(3) David Geddes - Contracts and Commercial Manager.
(5) Melissa Irene Kuipers - Site Senior Cost Controller.
(6) Andrew Donovan Lindsay - Manager General Operations.
(12) Steve Thistlethwaite - Senior Project Superintendent.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
CITATION : AGC INDUSTRIES PTY LTD -v- KARARA MINING LTD [2019] WASC 140 (S)
Costs - Where defendant seeks costs without regard to the limit on daily and hourly rates for named practitioners - Where orders relate to unusually difficult, complex and important construction dispute - Whether fairly arguable that costs allowed in determination are inadequate
Legal Profession (Supreme Court) (Contentious Business) Determination 2012 (WA)
Legal Profession (Supreme Court) (Contentious Business) Determination 2014 (WA)
Legal Profession (Supreme Court) (Contentious Business) Determination 2016 (WA)
Legal Profession Act 2008 (WA), s 276, s 277, s 280
Buitendag v Ravensthorpe Nickel Operations Pty Ltd [2014] WASCA 29 (S)
Crawley Investments Pty Ltd v Elman [2014] WASC 233 (S)
Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd [2011] WASC 268 (S2)
Flotilla Nominees Pty Ltd v Western Australian Land Authority [2003] WASC 122 (S); (2003) 28 WAR 95
Red Hill Iron Pty Ltd v API Management Pty Ltd [2012] WASC 323 (S)
Sino Iron Pty Ltd v Mineralogy Pty Ltd [No 2] [2017] WASCA 76 (S)
The Pilbara Infrastructure Pty Ltd v Brockman Iron Pty Ltd [No 2] [2014] WASC 345 (S)
(a) without regard to the limits on the daily and hourly rates in Table A of the relevant Legal Profession (Supreme Court) (Contentious Business) Determination for:
(ii) Counsel (Anthony Bereyne and Darren Pratt); and
(iii) Senior Practitioners (Anthony Bereyne and Darren Pratt);
(b) without regard to the limits (whether as to the maximum allowances for time, number of and experience of legal practitioners or total costs) imposed by Table B of the relevant Legal Profession (Supreme Court) (Contentious Business) Determination in relation to the Scale Items for:
(ii) giving discovery of documents (scale item 7(b));
(iii) inspection of discovered documents (scale item 8);
(vi) Senior Counsel fee on brief (scale item 20(b)).
(1) Subject to any costs agreement made in accordance with Division 6 or the corresponding provision of a corresponding law, section 306 and the Legal Aid Commission Act 1976 section 14 ‑
(b) any other aspect of the costs charged by law practices,
(2) Despite subsection (1), if a court or judicial officer is of the opinion that the amount of costs allowable in respect of a matter under a costs determination is inadequate because of the unusual difficulty, complexity or importance of the matter, the court or officer may do all or any of the following ‑
(a) order the payment of costs above those fixed by the determination;
(b) fix higher limits of costs than those fixed in the determination;
(c) remove limits on costs fixed in the determination;
(d) make any order or give any direction for the purposes of enabling costs above those in the determination to be ordered or assessed.
... there should be no expectation that, as a matter of course, rates in the costs agreement which are above scale will be ordered to be the rates to apply in taxation as between party and party. There would have to be evidence justifying the higher rate. The whole point of the existing scale is that the rates are struck by reference to what is being charged within the profession. It is true that the hourly rates can only be an average or mean of the upper rates determined in the survey, and there will be some cases where the unusual complexity or importance of the case warrants the special expertise of the practitioner involved and warrants an increase in the hourly rate. In some cases not involving unusual complexity or importance, the higher rates paid will not be recoverable. A party is always entitled to the luxury of retaining the highest paid practitioners in the conduct of their case, but they cannot always expect to recover these costs from the other party. If the hourly rates in the scale are thought by parties or practitioners to be too low for work which is not of unusual complexity or importance, then submissions should be made to the Legal Costs Committee to increase the rates in the scale.[650]
Was the matter unusually difficult, complex or important
(e) discovery was a very substantial undertaking. Jackson McDonald received approximately 220Gb of raw data from [the defendant] (potentially the equivalent of 1,000,000 documents) which was reduced to approximately 200,000 documents for analysis and processing. Ultimately, the defendant discovered in the order of 25,000 documents over the course of the matter;
(f) the trial bundle was voluminous (approximately 1600 documents plus schedules containing many more documents and comprising 34 hardcopy folders);
(g) sixteen lay witnesses provided witness statements (20 witness statements in total) and 14 of those witnesses were called to give evidence at trial;
(h) expert evidence was required by both parties and both parties experts was sourced from outside the jurisdiction ...[651]
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] In their pleadings and documents, AGC used the initials KML for the defendant. The defendant used Karara. I will refer to the defendant as Karara except where directly quoting from documents.
[3] The amount in the cash flow forecast in sch 10 of the Contract.
[18] Jones v Dunkel [1959] HCA 8; (1959) 101 CLR 298, 320 ‑ 321.
[19] Kordan Pty Limited v Federal Commissioner of Taxation [2000] FCA 1807; 46 ATR 191 [47].
[20] Defined in the Early Works Contract as the SMP Contract: Recital D(2).
[25] Early Works Contract sch 1A, cl 3.1.
[42] In each case, Karara's obligation was to use 'reasonable endeavours'.
[48] See Commercial Clarification Register, 19 December 2011 Row 34: TB 317.
[65] Watson v Foxman (1995) 49 NSWLR 315, 318 ‑ 319.
[66] Gestmin SGPS SA v Credit Suisse (UK) Ltd [2013] EWHC 3560 [20], [22].
[67] Westgyp Pty Ltd v Northline Ceilings Pty Ltd [2018] WASC 244 [53] (citations omitted).
[68] James Hardie Industries NV v Australian Securities and Investments Commission [2010] NSWCA 332 [269].
[69] Parlux SpA v M & U Imports Pty Ltd; M & U Imports Pty Ltd v Gava International Freight SpA [2008] VSCA 161; (2008) 21 VR 170 [30]; see also State of New South Wales v Deren [ 1999] NSWCA 22 [149]; Taylor v Ellis [1956] VicLawRp 72; [1956] VLR 457, 463 ‑ 465.
[100] TB 461. COP was at a rate of 6%.
[105] Exhibit 3 [58]-[60]; TB 462.
[122] ts 595, compare Exhibit 3 [69].
[144] ts 629. The COP was calculated at 15% to October 2012.
[148] Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304 [102].
[149] Butcher v Lachlan Elder Realty Pty Ltd [2004] HCA 60; (2004) 218 CLR 592 [109].
[150] Marks v GIO Australia Holdings Ltd [1998] HCA 69; (1998) 196 CLR 494 [34], [38].
[151] Briginshaw v Briginshaw [1938] HCA 34; (1938) 60 CLR 336; Helton v Allen [1940] HCA 20; (1940) 63 CLR 691, 712.
[152] John Holland Pty Ltd v Kellogg Brown & Root Pty Ltd [2015] NSWSC 451 [94].
[162] Exhibit 12A [239] - [240]; TB 1476.
[165] Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304 [130].
[172] Fubilan Catering Services Ltd v Compass Group (Aus) Pty Ltd [2007] FCA 1205 [547].
[173] Fubilan Catering Services Ltd v Compass Group (Aus) Pty Ltd [2007] FCA 1205 [547].
[174] Fubilan Catering Services Ltd v Compass Group (Aus) Pty Ltd [2007] FCA 1205 [547].
[178] Plaintiff's closing submissions [66].
[179] See, for example, TB 392 and TB 399.
[180] See Exhibit 37A [226] - [233]; Exhibit 28A [39] - [40].
[187] Badenach v Calvert [2016] HCA 18; (2016) 257 CLR 440 [38] - [41].
[188] Sellars v Adelaide Petroleum NL (1994) 179 CLR 332, 364.
[198] Including Scope of Work and Technical Specifications.
[199] Main Works Contract Formal Instrument of Agreement, cl 1.7.
[200] Main Works Contract Formal Instrument of Agreement, cl 1.8.
[201] For the use of recitals in the construction of a contract, see the discussion in Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407; (2009) 76 NSWLR 603 [379] ‑ [389].
[202] Main Works Contract Formal Instruction of Agreement, cl 2.1.
[203] Main Works Contract, GC 2.1.1 (emphasis added); 'Direction includes any written direction, approval, assessment, authorisation, certificate, decision, demand, determination, explanation, instruction, notice, order, permission, rejection, request or requirement issued by the Company's Representative to the Contractor in accordance with the Contract': GC 1.
[207] Main Works Contract SC 2.3. The Main Works Contract defined Key Dates, but often did so by reference to Sch 3, which was not used.
[212] Main Works Contract SC 2.3 (emphasis added).
[214] As noted above, Practical Completion was to be achieved by the Company, and not the Contractor.
[218] Emphasis added - The responsibilities generally described by SC 2.1 (b)(i) - (vii) are hereinafter collectively referred to as 'the Contractor's responsibilities'.
[219] The reference to sch 4 appears to be an error, the requirements for the Contractor's Workforce are in sch 9. Schedule 4 was 'Employee and Industrial Relations'.
[220] Main Works Contract, sch 9, conditions (a) and (e).
[223] Main Works Contract GC 17; 'Company - Supplied' items were defined in GC1 as materials, equipment, goods or the like to be provided by the Company to the Contract for incorporation into the Works.
[228] Main Works Contract GC 17, GC 12, Sch 9.
[231] Main Works Contract GC 48.1.1, 48.1.2.
[234] Statement of claim [41(b)], Defence [41(b)].
[235] Main Works Contract GC 49.1.1(b).
[242] Main Works Contract GC 54.1.1(b).
[245] 'Direct Labour' was defined as 'all labour provided by the Contractor for the purposes of completing the WUC to be employed at Site...including Workforce...': Main Works Contract sch 2B, cl 1.
[246] Main Works Contract sch 2J, cl 1.1.
[247] Main Works Contract sch 2J, cl 1.3.
[248] See Fitzgerald v Masters [1956] HCA 53; (1956) 95 CLR 420, 426 - 427.
[249] Main Works Contract sch 2J, cl 1.5(b), repeated in cl 1.6.
[250] Main Works Contract sch 2J, cl 11.7.
[252] Statement of claim [102], [103].
[254] Keating on Construction Contracts, (10th Ed), [8-018].
[255] Main Works Contract GC 12.16, GC 17.
[261] Main Works Contract sch 2J, 1.7.
[267] ts 1463; See Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd [No 2] [2012] WASCA 53; (2012) 287 ALR 360 [47].
[268] [2012] WASCA 53 [47]: See Secured Income Real Estate (Aus) Ltd v St Martins Investments Pty Ltd [1979] HCA 51; (1979) 144 CLR 596, 607.
[269] See Cenric Group v TWT Property Group [2018] NSWSC 1570; Hera Project Pty Ltd v Bisognin (No 3) [2017] VSC 268 [105] - [109]; Cahill v Kiversun Pty Ltd; Molonglo Group (Aust) Pty Ltd v Cahill & Anor [2017] VSC 64; Cohen & Co v Ockerby & Co Ltd [1917] HCA 58; (1917) 24 CLR 288, 297; Peter Turnbull & Co Pty Ltd v Mundus Trading Co (Australasia) Pty Ltd [1954] HCA 25; (1954) 90 CLR 235, 246 - 247.
[270] See Probuild Constructions (Aus) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151 [128]. McColl JA held that a contract principal was obliged to exercise a reserve power to grant an extension of time 'honestly and fairly having regard to the underlying rationale of the prevention principle...or, if necessary, because there is an implied duty of good faith in exercising the discretion'.
[272] Statement of claim [102], [103].
[273] Darlington Futures Ltd v Delco Australia Pty Ltd [1986] HCA 82; (1986) 161 CLR 500, 510.
[274] Port Jackson Stevedoring Pty Ltd v Salmond & Spraggon (Aus) Pty Ltd [1980] UKPCHCA 1; (1980) 144 CLR 300, 305.
[275] H & E Van der Sterren v Cibernetics (Holdings) Pty Ltd (1970) 44 ALJR 157, 158 (Barwick CJ & Kitto J agreeing) (citations omitted).
[276] Nissho Iwai Australia Ltd v Malaysian International Shipping Corporation Berhad [1989] HCA 32; (1989) 167 CLR 219, 226 - 227.
[277] Main Works Contract GC 28.1.2(c).
[281] Compare, Environmental Systems Pty Ltd v Peerless Holdings Pty Ltd [2008] VSCA 26; (2008) 19 VR 358 [93].
[282] Main Works Contract SC 2.2(a), sch 2J.
[285] Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104, 116 [46] - [51] (citations omitted); see also Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640, [35].
[286] See Horsell International Pty Ltd v Divetwo Pty Ltd [2013] NSWCA 368 [158]; Segelov v Ernst & Young Services Pty Ltd [2015] NSWCA 156 [88].
[290] Main works Contract sch 2B, cl 3.1.
[291] Main Works Contract sch 2B, cl 3.3.
[292] Main Works Contract sch 2C, cl 2.2.1.
[293] Main Works Contract sch 2D, cl 1.4.
[294] Main Works Contract sch 2D, cl 1.5.
[297] Commonwealth Bank of Australia v Barker [2014] HCA 32; (2014) 253 CLR [113] (Gageler J). See also Kiefel J [62].
[298] BP Refinery (Westernport) Pty Limited v Shire of Hastings (1994) 180 CLR 266, 282 ‑ 283.
[299] Commonwealth Bank of Australia v Barker [22] (citations omitted).
[300] Codelfa Construction Pty Ltd v State Rail Authority of NSW [1982] HCA 24; (1982) 149 CLR 337, 346.
[301] James Point Pty Ltd v The Minister for Transport [No 3] [2018] WASC 277; Australis Media Holdings Pty Ltd v Telstra Corporation Ltd (1988) 18 NSWLR 540; Servcorp WA Pty Ltd v Perron Investments Pty Ltd [2016] WASCA 79; (2016) 50 WAR 226 [83].
[302] Campbell v Backoffice Investments Pty Ltd [2009] HCA 25 (2009) 238 CLR 304 [168].
[304] See statement of claim [59], [63], [69], [73], [79], [86], [95], [101]. There is one exception [111], where AGC pleaded breach of the Cooperation Terms by progressively decreasing the works AGC was required to perform by giving parts of the Main Works to Ausco. The Ausco claim needs to be considered separately.
[308] Exhibit 31 [7.2.14] - [7.2.16]; Exhibit 34 [69], [3.5.2].
[309] Exhibit 32, Issue 4.4; and see Exhibit 31[8.6]. Mr Kong's delay analysis did not observe issues regarding Work Method Statements on the critical path. He did not, retrospectively, quantify any actual delay caused.
[310] Exhibit 32, Issue 4.5. And see Exhibit 31 [8.7.14], [8.7.19].
[314] Exhibit 31 [6.2.10] - [6.2.12].
[318] Exhibit 31 [7.2.14] ‑ [7.2.16].
[320] Exhibit 31 [2.4.3], [7.3.1] - [7.3.6].
[321] Exhibit 31 [2.4.4] - [2.4.5].
[323] Exhibit 31 [9.2.7] - [9.2.8].
[325] See, for example, Exhibit 31 [8.4.12], [8.4.26], [8.4.28]; [8.9.51] - [8.9.53].
[329] Statement of claim [49(a)], [56].
[332] Statement of claim [50] - [51].
[345] Exhibit 31 [2.5.5], [9.2.7], [9.2.10].
[366] Statement of claim [61], [62].
[367] Statement of claim [51], [62].
[368] Statement of claim [53], [62]
[369] Statement of claim [58], [63].
[370] AGC's closing submissions [310], [312].
[376] Exhibit 12A [225], [227] ‑ [230].
[385] Exhibit 31 [8.3.47] - [8.3.53].
[388] Exhibit 31, App 1.2 Sch 1 [24].
[390] Main Works Contract, Sch 1A, cl 2.4.1 (d)(iii).
[391] See Main Works Contract GC 40.3.2.
[395] Statement of claim [51], [67].
[396] Statement of claim [53], [67]
[397] Statement of claim [58], [69].
[398] Statement of claim [68], [69].
[408] AGC's closing submissions [334] - [335].
[409] Exhibit 31 [7.2.9], for NOD 1, 3 and 3a (a re-issue of NOD 3).
[410] Exhibit 31 [8.4.15] - [8.4.17].
[412] AGC's closing submissions [338].
[413] See Electricity Generation Corporation v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 [40] - [43].
[415] See Darlington Futures Ltd v Delco Australia Pty Ltd [1986] HCA 82; (1986) 161 CLR 500, 510.
[416] AGC's closing submissions [337].
[417] Statement of claim [70] - [73]; Main Works Contract SC 2.1(b).
[422] Statement of claim [51], [75].
[423] Statement of claim [53], [75]
[424] Statement of claim [58], [76].
[433] Statement of claim [58], [78], [79].
[434] Statement of claim [77(ii)]; TB 955.
[445] Statement of claim [82(i), (ii)].
[446] Statement of claim [82(iv)]. Main Works Contract GC 36.1.2 provided:
The Company's Representative may Direct in what order and at what time the various stages or portions of the Contractor's Responsibilities shall be carried out. If the Contractor can reasonably comply with the Direction, the Contractor shall ensure that the Contractor's Personnel do so. If the Contractor cannot reasonably comply, the Contractor's Representative shall give the Company's Representative written notice of the reasons.
[449] Statement of claim [51], [85].
[450] Statement of claim [53], [85].
[451] Statement of claim [58], [86].
[464] Exhibit 31 [8.8.26] ‑ [8.8.27].
[465] Exhibit 31 [8.8.9]. In his statement, Mr Arndt continues that Karara directed that Ausco perform the work under the supervision of AGC: see ex 12A [415].
[468] Exhibit 31 [8.8.23]. The weekly progress report for the week ended 5 August 2012 had a projected date for Practical Completion of the dirty concentrate work was 23 October 2012, after milestone 5 had passed: see TB 1500, report 33.
[472] Statement of claim [51], [94].
[473] Statement of claim [53], [94]
[474] Statement of claim [58], [95].
[475] Statement of claim [100] ‑ [101].
[479] Statement of claim [51], [110].
[480] Statement of claim [53], [110].
[481] Statement of claim [58], [111].
[482] Statement of claim [106], [111].
[485] Defence [109] and, in particular, Main works Contract GC 53.1.1.
[486] Defence [107], incorporating by reference defence [22(c)], [22(d)(ii)], [22(d)(ix)] to [22(d)(xi)], [35(g)], and [41].
[496] Main Works Contract vol 2 cl 3.3.2.
[497] Main Works Contract vol 2 cl 3.9.3.1(c).
[501] See TB 783; TB 803; TB 826; TB 827.
[515] Carr v JA Berriman Pty Ltd [1953] HCA 31; (1953) 89 CLR 327.
[516] Carr v JA Berriman Pty Ltd [1953] HCA 31; (1953) 89 CLR 327, 347 (emphasis added) (citations omitted); see also Commissioner for Main Roads v Reed‑Stewart Pty Ltd [1974] HCA 53; (1974) 131 CLR 378.
[517] Hudson's Building and Engineering Contracts (13th ed) [5-026].
[518] Karara's closing submissions [400].
[519] Karara's closing submissions [401].
[520] Lemon v Mead [2017] WASCA 215 [176]; Franklins Pty Ltd v Metcash Trading Ltd [2009] NSWCA 407; (2009) 76 NSWLR 603 [379] - [390].
[522] Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104 [50].
[523] Early Works Contract sch 1, cl 3.2.
[525] Main Works Contract SC 1.1 (emphasis added).
[527] Karara's closing submission [431(b)].
[532] AGC did not accept Karara's repudiation and terminated the Contract.
[533] Relying on Sze Hai Tong Bank Ltd v Rambler Cycle Co Ltd (1959) AC 576.
[534] Darlington Futures Ltd v Delco Australia Pty Ltd [1986] HCA 82; (1986) 161 CLR 500, 510, 511.
[535] The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64, 80 (Mason CJ and Dawson J), 99 (Brennan J), 118 (Deane J), 137 (Toohey J).
[536] AGC's closing submissions [259].
[537] Robinson v Harman [1848] EngR 135; (1848) 1 Ex 850, 855; [1848] EngR 135; 154 ER 363, 365; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272 [13].
[543] Biggin and Co Ltd v Permanite Ltd (1951) 1 KB 422, 438, cited in The Commonwealth v Amann Aviation Pty Ltd [1991] HCA 54; (1991) 174 CLR 64, 83.
[545] Statement of claim [113(i), (ii)].
[549] Statement of claim [117] ‑ [118].
[554] Defence [113(c)]; Early Works Contract GC 8.
[556] Main Works Contract GC [48.1.12], [48.1.13], [48.5].
[557] Defence [116]; Early Works Contract sch 28 cls 3.3, 3.4; Main Works Contract cls 3.3 ‑ 3.4.
[564] Early Works Contract, Annexures Item 7.
[565] Early Works Contract, Formal Instrument of Agreement cl 1.8.
[566] Early Works Contract GC 48.1.13.
[569] Early Works Contract Sch 2, cl 1.
[570] Main Works Contract, Annexures, Item 1, Item 2.
[573] Main Works Contract, Formal Instrument of Agreement, cl 1.8.
[590] TB 892, Item 10.2; TB 910, Item 10.2
[596] Early Works Contract GC 8. The same GC is present in the Main Works Contract: GC 8.
[597] See, generally, Lighting By Design (Aust) Pty Ltd v Cannington Nominees Pty Ltd [2008] WASCA 23; (2008) 35 WAR 520 [21] - [23], [89] - [90], [203] - [205]; RJ Baker Nominees Pty Ltd v Parsons Management Group Pty Ltd [2010] WASCA 128 [92] - [97]; Fazio v Fazio [2012] WASCA 72 [188]-[195].
[598] Branir Pty Ltd v Owston Nominees (No 2) Pty Ltd [2001] FCA 1833; (2001) 117 FCR 424 [369]; see also Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153 [162].
[599] Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd [1988] 14 NSWLR 523, 534 ‑ 535; Laidlaw v Hiller Hewitt Elsley Pty Ltd [2009] NSWCA 44.
[600] Main Works Contract Formal Instrument of Agreement, cl 1.8.
[601] Alpha Wealth Financial Services Pty Ltd v Frankland River Olive Co Ltd [2008] WASCA 119 [164] (Steytler P agreeing); see also Pullin JA at [27]. See also GEC Marconi Systems Pty Ltd v BHP Information Technology Pty Ltd [2003] FCA 50; (2003) 128 FCR 1 [426], adopting National Westminster Finance New Zealand Ltd v National Bank of New Zealand Ltd [1996] 1 NZLR 548, 550.
[604] Main Works Contract GC 47.1.2, GC 47.1.3.
[613] John Grant & Sons Ltd v The Trocadero Building Investment Company Limited [1938] HCA 20; (1938) 60 CLR 1, 23 (citations omitted).
[624] Exhibit 12A [465]; Exhibit 12B [3] ‑ [8]; TB 745.
[626] Adnunat Pty Ltd v ITW Construction Systems Australia Pty Ltd [2009] FCA 499 [39]; Australian Broadcasting Corporation v XIVth Commonwealth Games Ltd (1988) 18 NSWLR 540, 548 ‑ 550.
[627] Adnunat Pty Ltd v ITW Construction Systems Australia Pty Ltd [2009] FCA 499[39].
[634] Statement of claim [149] ‑ [156].
[638] Di Giovanni v Dark Horse Developments Pty Ltd [2014] WASCA 188 [45] (Newnes & Murphy JJA agreeing).
[639] Defence [157] ‑ [164], [22(d)].
[641] Main Works Contract GC 49.1.1(b).
[647] Sino Iron Pty Ltd v Mineralogy Pty Ltd [No 2] [2017] WASCA 76 (S) [11] ‑ [16].
[648] Sino Iron Pty Ltd v Mineralogy Pty Ltd [No 2] (S) [11].
[649]See, for example, Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd [2011] WASC 268 (S2) [7] (Le Miere J); Red Hill Iron Pty Ltd v API Management Pty Ltd [2012] WASC 323 (S) [30] (Beech J); The Pilbara Infrastructure Pty Ltd v Brockman Iron Pty Ltd [No 2] [2014] WASC 345 (S) [10] (Edelman J).
[650] Flotilla Nominees Pty Ltd v Western Australian Land Authority [2003] WASC 122 (S); (2003) 28 WAR 95 [22].
[651] Affidavit of Anthony David Bereyne, sworn 10 October 2019, [18](e) ‑ (h).
[653] Crawley Investments Pty Ltd v Elman [2014] WASC 233 (S) [23].
[655] Buitendag v Ravensthorpe Nickel Operations Pty Ltd [2014] WASCA 29 (S) [7].
(2001) 53 NSWLR 153
(2001) 117 FCR 424
(2004) 218 CLR 592
(1917) 24 CLR 288
(2014) 253 CLR 169
(2016) 260 CLR 1
(2009) 76 NSWLR 603
(2003) 128 FCR 1
(1970) 44 ALJR 157
(1940) 63 CLR 691
(1938) 60 CLR 1
(2008) 35 WAR 520
(1954) 90 CLR 235
(2003) 28 WAR 95
(1988) 18 NSWLR 540
(2016) 257 CLR 440
(1938) 60 CLR 336
(1982) 149 CLR 337
(1974) 131 CLR 378
(1986) 161 CLR 500
(2014) 251 CLR 640
(2008) 19 VR 358
(1956) 95 CLR 420
(2008) 21 VR 170
(2016) 50 WAR 226
(2012) 287 ALR 360
(1994) 180 CLR 266
(2009) 238 CLR 304
(1953) 89 CLR 327
(1959) 101 CLR 298
(1998) 196 CLR 494
(2015) 256 CLR 104
(1989) 167 CLR 219
(1980) 144 CLR 300
(1979) 144 CLR 596
(1994) 179 CLR 332
(2009) 236 CLR 272
(1991) 174 CLR 64
(1995) 49 NSWLR 315