[2025] VCAT 269
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-04-04
Original judgment source is linked above.
For the reasons given orally at the hearing, the Tribunal orders:
'[p]ay the [joined party] the sum of $5,678.57 for a claim or entitlement arising under the domestic building contract dated 31 January 2022 ... by no later than 20 September 2024.'
(1) A person who is required to comply with a dispute resolution order may apply to VCAT for review of the decision to issue or amend the dispute resolution order.
(2) An application under subsection (1) must be made within 20 business days after the later of -
(a) the day on which the applicant was given a copy of the dispute resolution order or the amendment to the dispute resolution order (as the case requires); or
(b) if under the VCAT Act the applicant requests a statement of reasons, the day on which the applicant receives that statement of reasons or the applicant is informed under section 46(5) of that Act that a statement of reasons will not be given.
(3) An application under subsection (1) must be made on the ground that -
(a) the description in the dispute resolution order of the domestic building work that is defective or incomplete is incorrect; or
(b) the period specified in the dispute resolution order for carrying out the rectification or completion work is not reasonable; or
(c) a requirement in the dispute resolution order to take a specific action or to refrain from taking action is not necessary or is not reasonable.
(4) In determining an application for review of a dispute resolution order, VCAT may also make any order it considers fair in relation to the domestic building contract to which the dispute relates.
(5) Without limiting subsection (4), VCAT may do one or more of the following -
(a) vary any term of the domestic building contract (including the completion date, the contract price, a provisional sum or the amount to be paid for a prime cost item);
(b) declare that a term of the domestic building contract is, or is not, void under section 132;
(c) declare void any unjust term of the domestic building contract, or otherwise vary the domestic building contract to avoid injustice.
(1) In exercising its review jurisdiction in respect of a decision, the Tribunal -
(a) has all the functions of the decision-maker; and
(b) has any other functions conferred on the Tribunal by or under the enabling enactment; and
(c) has any functions conferred on the Tribunal by or under this Act, the regulations and the rules
(2) In determining a proceeding for review of a decision the Tribunal may, by order -
(a) affirm the decision under review; or
(b) vary the decision under review; or
(c) set aside the decision under review and make another decision in substitution for it; or
(d) set aside the decision under review and remit the matter for re-consideration by the decision-maker in accordance with any directions or recommendations of the Tribunal.
(3) Subject to subsection (4), a decision of a decision-maker as affirmed or varied by the Tribunal, or a decision made by the Tribunal in substitution for the decision of a decision-maker -
(a) is deemed to be a decision of that decision-maker; and
(b) subject to any contrary order by the Tribunal, has, or is deemed to have had, effect from the time at which the decision under review has or had effect.
An Order for Agreed Damages was issued to Sherridon Pty Ltd by the DBDRV to pay the Building Owner $5,785.71.00, however the days submitted by the owners were incorrect. As per the HIA Schedule 4 Special Conditions, Item 11 Building Period commences upon base stage being completed which was dated 09.09.2022. Notice of Completion and Occupancy Permit was issued to the client 09.10.2023. Building Period as per the HIA Contract is 280 Days, As construction overlapped the Christmas Period all clients were advised of the mandatory Christmas shutdown period of 15 Business Days. Based on our calculations the client is owed $3,571.43.[2]
Clause 10: The building period is 280 days, which includes actual building work and the estimates for delays ['the Building Period**']**.
Schedule 3: The following are the progress stages of work:
For the purposes of this contract the building period under Schedule 1 Clause 1constitutes [sic] and commences upon the builder completing the base stage' ['SC 11'].
Agreed damages for late completion of the Building Works:
the building Works are complete in accordance with the Contract Documents.
Is SC 11 an unjust term of the building contract?
(1) a builder must not enter into a major domestic building contract unless the contract -
(g) states the date when the work is to start, or how that date is to be determined; and
(h) if the date is not yet known, states that the builder will do everything that is reasonably possible for the builder to do to ensure that the work will start as soon as possible; and
(i) states the date when the work will be finished, or if the starting date is not yet known, the number of days that will be required to finish the work once it is started (emphasis added).
When did the builder achieve practical completion of the building works?
When work is to be considered to have been completed
A builder must not demand final payment under a major domestic building contract until -
(a) the work carried out under the contract has been completed in
accordance with the plans and specifications set out in the contract; and
(b) the building owner is given either -
(i) a copy of the occupancy permit under the Building Act 1993 , if the building permit for the work carried out under the contract requires the issue of an occupancy permit; or
(ii) in any other case, a copy of the certificate of final inspection.
[2] Endorsed on application form filed by the builder.
[4] [2025] VCAT 9. See also Cardona v Brown [2010] VSC 368; Sumic v Muzaferovic (Domestic Building) [2013] VCAT 1862; Alpha Developers and Promoters Pty ltd v Advance Building & Engineering Pty Ltd [2015] VCAT 317; Dawn v Carlisle Homes Pty Ltd [2025] VSCA 58.
Sherridon Pty Ltd
Chief Dispute Resolution Officer, Domestic Building Dispute Resolution Victoria
Troise v Blue Key Properties Pty Ltd (Building and Property) [2025] VCAT 9 considered. See also Cardona v Brown [2010] VSC 368; Sumic v Muzaferovic (Domestic Building) [2013] VCAT 1862; Alpha Developers and Promoters Pty ltd v Advance Building & Engineering Pty Ltd [2015] VCAT 317; Dawn v Carlisle Homes Pty Ltd [2025] VSCA 58.
(1991) 172 CLR 84