[2025] VCAT 9
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-01-02
Original judgment source is linked above.
DOMESTIC BUILDING: Applicant owners, entered into a major domestic building contract with the respondent builder for the construction of three two-storey townhouses in August 2018; occupancy permit issued 9 September 2020; builder submitted final claim but owners contended works had not been completed and refused to pay final claim; contract terminated on 31 March 2021 by owners under the terms of the contract, alternatively at common law; owners claimed damages for rectification of defective work and completion of contract works, liquidated damages, damages for rectification of damage to works caused by vandalism, and for cost of second site survey; owners' claim considered and allowed in part; counterclaim for payment of final claim dismissed.
Troise v Blue Key Properties Pty Ltd (Building and Property) [2025] VCAT 9
(a) the builder had not completed the contractual scope of works by 9 September 2020;
(b) the purported occupancy permit issued by the RBS on 9 September 2020 was not a valid occupancy permit;
(c) Special Condition 6 of the contract is unenforceable;
(d) the owners did not have to pay the final claim within 14 days of the issue of the occupancy permit;
(e) the builders notice of completion dated 9 September 2020 was not a valid notice of completion the purposes of clause 36 of the contract; and
(f) the owners validly terminated the contract on 30 April 2021.
Mr Nicholas Phillpott of Counsel, instructed by Mr Daniel Oldham, solicitor, on all days of the hearing save for the morning of the final day when he was temporarily replaced by Ms E King.
Mr Dominic Cafari instructed by Mr Jeremy Johnson, solicitor
Owners obtain engineering drawings for the project from Beattie Consultant Engineers.[6]
Owners pay builder a part-payment deposit in the amount of $2,000.[8]
Builder commences demolition works at the Property.[10]
PM Kennedy prepares a Plan of Survey for the Property.[11]
Building permit for the project is issued.[12]
Builder sends the Owners a "Welcome Letter".[13]
Talcon Consulting Engineers prepares new engineering drawings.[14]
RBS approves a variation to the Building Permit for, inter alia, the new engineering drawings.
Building Inspection Record for the bored piers - approved.[15]
Meeting between the parties to discuss windows.[16]
Building Inspection Record for the ground floor frame issued - not approved.[17]
Second Building Inspection Record for the ground floor frame issued - not approved.[18]
Third Building Inspection Record for the ground floor frame issued - not approved.[19]
Written Direction to Fix issued by the RBS to the builder.[20]
Second Written Direction to Fix issued by the RBS to the Builder.[21]
Fourth Building Inspection Record for the ground floor frame issued - not approved.[22]
Fifth Building Inspection Record for the ground floor frame issued - approved.[23]
Boundary pegs at the Property removed.[24]
The Owners engaged PM Kennedy to carry out a re-establishment survey.[25]
First Building Inspection Report for the final inspection issued - not approved.[26]
Third Written Direction to Fix issued by the RBS to the builder.[27]
Builder issues invoice for $81,200.00 to the owners for the completion stage.[29]
Owners inspect the property with Mr Mammone.[30]
Owners obtain 3 reports from Inspect Direct Pty Ltd (Mr Mammone's company).[31]
Owners provide the builder with the reports from Inspect Direct Pty Ltd.[32]
Owners file an application with the DBDRV.[33]
Building Order for Minor Work issued to the owners.[34]
DBDRV issues a Certificate of Conciliation - Dispute Not Suitable.[35]
Owners serve a Notice of Intention to Terminate.[36]
Builder responds to the Notice of Intention to Terminate.[37]
Owners respond to the builder's response letter.[38]
Builder further responds to the owners' letter.[39]
Owners serve a Notice of Termination.[40]
The rule of the common law is, that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.[42]
The legality of termination of the contract by the owners
When the Builder considers that the Building Works have reached Completion the Builder is to give to the Owner:
Notwithstanding any other provision of this Contract, the Builder must not demand Final Payment until after the Builder has given to the Owner...a copy of the occupancy permit.
Occupancy is subject to the following conditions-
All appliances and services to be fitted off and commissioned prior to occupation.
'Completion' means that the Building Works to be carried out under the Contract have been completed in accordance with the Plans and Specifications set out in the Contract.
The Owner shall have 14 days to make the final payment after the certificate of Occupancy has been issued from the authority.
In respect of the case of a major domestic building contract that is not listed in the Table in s 40 ( 2) a builder must not demand or receive any amount or instalment that is not directly related to the progress of the building work being carried out under the contract.
(1) For the purposes of section 40(4) of the Act, when parties to a major domestic building contract agree that section 40(2) and (3) of the Act do not apply to that contract, the manner of agreement is to include in the major domestic building contract -
(a) a warning in the form of Form 1 in Schedule 1, which is signed by the building owner before the building owner signs the major domestic building contract; and
(b) a clause in the form of Form 2 in Schedule 1, which is signed by the building owner and the builder before they sign the major domestic building contract.
WARNING TO OWNER - CHANGE OF LEGAL RIGHTS
Under section 40 of the Domestic Building Contracts Act 1995 (the Act ) a builder cannot, under a major domestic building contract, charge more than a fixed percentage of the total contract price at the completion of each stage of building a home.
The Act also allows the parties to a major domestic building contract to agree in writing to change the stages and the percentage of the contract price to be paid at the completion of each stage.
Summary in relation to the issue of legality of the termination of the contract
Liability of the builder for damage to the works caused by vandals
The builder must maintain the insurance from the date the Owner gives the Builder Possession of the Land under clause 25 to the earlier of:
DAMAGES FOR COST OF RECTIFYING CAUSED BY VANDALS
Assessment of damages in respect of Vandal damage
Consideration of the Icon quotation of 5 April 2022
But if the rectification work has been carried out and the actual cost is known, that provides sound evidence of the reasonable cost and should ordinarily provide the basis for damages.
supply and install damaged garage door and two internal doors:
remove and replace all damaged plaster in unit ready for paint:
supply new plaster/vinyl doors to all wardrobes (vandal damage):
replace benchtop in ensuite and re-tile splashback (vandal damage)
I allow $40,199.50 rounded up to $40,200 to the owners in respect of vandal damage.
Period in which the works were to be completed
As the building period is noted as meaning the total of the days of actual building work and the estimate for delays, the building period is established to be 340 days.
Establishing the date when agreed damages began to run
If the Building Works have not reached Completion by the end of the Building Period the Owner is entitled to agreed damages in the sum set out in Item 9 of Schedule 1 for each week after the end of the Building Period to and including the earlier of:
10.0 Commencement must occur within 21 Days after the Builder receives:
(a) the final claim had been issued on 9 September 2020;
(b) payment of the final invoice is required within 14 days of the issue of the certificate of occupancy under Special Condition 6;
(c) if the final claim had been paid on time the owners would have received the keys; and
(d) accordingly the owners are deemed to have taken position on 23 September 2020.
Unit 1- $20,055.60 being $360 a week for the period 1 May 2021- 25 May 2022 (55.71 weeks)
Unit 2- $22,474.80 being $360 per week for the period 1 May 2021 -11 July 2022 (52.43 weeks);
Unit 3- $26,125.20, being $360 per week for the period 1 May 202-20 September 2022 (72.57 weeks).
There were a number of defective works that began [to] emerge which Luciano and I discovered following the post inspection reports. These defects became apparent after the units at the Premises became tenanted. Luciano and I reached out to P. Di Natale Real Estate to have these defects rectified by their assigned contractors.
Repair to leaking laundry sink in unit 2 in January 2023
Unrectified defects in unit 1 costed by Mr Osborne in his report dated 17 July 2023
Unrectified defects in unit 2 costed by Mr Osborne in his report dated 17 July 2023
Unrectified defects in unit 3 costed by Mr Osborne in his report dated #17 July 2023
Cost of rectifying defective plumbing works identified by Mr Quick and accepted by Mr Osborne.
Addition of margin to the allowance for rectification plumbing work by Icon
Claims made by the owners for rectification of the balcony and consequential water damage
Addition of margin to the allowance for rectification of the balcony and consequential damage
Summary of awards in relation to rectify the defects
Supply and install air-conditioning units in unit 1 and 2.
Supply and install kitchen appliances in units 1 and 2
Extra sectional door handsets and servicing of garage doors
Supply and install an air-conditioning unit in unit 3
Supply and install kitchen appliances in unit 3
Supply water tank pumps with mains change over
Replace top downpipe offset in units 2 and 3 and install flashing in units 1 and 3
Summary of completion items on which margin and GST is to be allowed
Supply and install air-conditioning units in unit 1 and 2: $6,300
Supply and install kitchen appliances in units 1 and 2: $4,760
Supply and install an air-conditioning unit in unit: $3,400
Supply and install kitchen appliances in unit 3: $2,380
Supply water tank pumps with mains change over: $800
Extra sectional door handsets and servicing of garage doors: $1,166
Replace top downpipe offset and install flashing: $1,127
[2] These costs were costs assessed by Mr Schmiedel in his expert report dated 24 August 2021, TB 458 at 460.
[4] Mr Schmiedel's report of 24 August 2021, [15], TB 459.
Troise
Blue Key Properties Pty Ltd