[2025] VSCA 58
General information, not legal advice.
Court of Appeal (Vic)
2025-04-03
Niall CJ, Emerton P
Original judgment source is linked above.
[2023] VCAT 660 (Judge Anderson, Vice President)
BUILDING CONTRACTS - Disputes between builder and building owner - Dispute about completion of building works under major domestic building contract - Domestic Building Contracts Act 1995 ss 11, 40, 42.
ADMINISTRATIVE LAW - Victorian Civil and Administrative Tribunal - Appeal from tribunal - Objections to jurisdiction on asserted constitutional grounds - No real prospects of success - Application for leave to appeal refused - Victorian Civil and Administrative Tribunal Act 1998 s 148.
PRACTICE AND PROCEDURE - Adjournment - Applicant a self-represented litigant who appointed legal representatives the day before the hearing - Application for adjournment to enable review and potential amendment of grounds of the application for leave to appeal - Whether prejudice to self-represented litigant - Whether applicant had impaired ability to present case - Reliance on mental state of applicant - No claim of impaired financial capacity - Reasons for delay not adequately explained - Applicant opposed any undertaking or condition requiring payment of judgment debt owing to respondent as condition of adjournment - Prejudice to respondent - Prejudice to administration of justice and other litigants - Adjournment refused.
PRACTICE AND PROCEDURE - Amendment - Application to rely on proposed amended application for leave to appeal raising matters under the Commonwealth Constitution ss 75(iv), 76(ii) - Asserted constitutional matters did not arise - Application refused.
CONSTITUTIONAL LAW - Asserted matter as to VCAT's lack of jurisdiction to hear and determine disputes involving residents of different States - Asserted matter as to VCAT's lack of jurisdiction to hear and determine proceedings involving claims under the Australian Consumer Law in its application as a law of the Commonwealth - Asserted constitutional matters did not arise - the Commonwealth Constitution ss 75(iv), 76(ii) - Judiciary Act 1903 (Cth) s 78B.
Commonwealth Constitution, ss 75(iv), 76(ii).
Domestic Building Contract Regulations 2017, reg 13(1).
Judiciary Act 1903 (Cth), ss 78AA, 78B.
Supreme Court (General Civil Procedure) Rules 2015, r 19.03(4).
Victorian Civil and Administrative Tribunal Act 1998, ss 97, 98(1), 148(1)(a).
Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27; (2009) 239 CLR 175; Citta Hobart Pty Ltd v Cawthorn [2022] HCA 16; (2022) 276 CLR 216; Sali v SPC Ltd [1993] HCA 47; (1993) 67 ALJR 841; (1993) 116 ALR 625, applied.
Business Service Brokers Pty Ltd v Optus Mobile Pty Ltd (No 3) [2022] VSC 283; Creative Building Services v Jolene Investments [2013] NSWSC 391; Renbar Constructions Pty Ltd v Sader [2022] NSWSC 172, considered.
Eaton v ISS Catering Services Pty Ltd [2013] VSCA 361; (2013) 42 VR 635; Mackenzie v Head, Transport for Victoria [2021] VSCA 24; Tucker v Commissioner of State Revenue [2023] VSCA 125, followed.
Andrews v Australia and New Zealand Banking Group Ltd [2012] HCA 30; (2012) 247 CLR 205; Australasian Temperance and General Mutual Life Assurance Society Ltd v Howe [1922] HCA 50; (1922) 31 CLR 290; British American Tobacco Australia Ltd v Western Australia [2003] HCA 47; (2003) 217 CLR 30; Crouch v Commissioner for Railways (Qld) (1985) 159 CLR 22; Mitsubishi Motors Australia Ltd v Begovic [2023] HCA 43; Paciocco v Australia and New Zealand Banking Group Ltd [2016] HCA 28; (2016) 258 CLR 525; Thurin v Krongold Constructions (Aust) Pty Ltd [2022] VSCA 226; (2022) 73 VR 403, referred to.
Mr D L Epstein on the application for an adjournment
(a) whether Carlisle's notification of the final claim before certain appliances were installed breached s 42 of the Domestic Building Contracts Act 1995 ('DBCA');
(b) whether Special Condition 5 of the building contract, allowing for the installation of appliances after payment of the final claim, breached s 42 of the DBCA, and was void under s 132 of the DBCA;
(c) whether Mr Dawn satisfied his obligation to make the final payment, and Carlisle's claim to the final payment, by him tendering a signed release authority to Carlisle on 22 March 2019 marked 'under protest', and by Carlisle's refusal to accept the document;
(d) whether the lodgement by Mr Dawn with Carlisle's solicitors, Enterprise Law Legal Group Pty Ltd ('Enterprise Law') on 27 July 2018 of the amount of the final payment under the building contract, at the request of Carlisle, was a further 'deposit' exceeding 5 per cent of the contract price, in breach of s 11(1)(a) of the DBCA, entitling Mr Dawn to avoid the building contract at any time before completion;
(e) alternatively, whether Carlisle, by demanding the lodgement of the amount of the final payment before the commencement of the building works, breached s 40(3) of the DBCA, entitling Mr Dawn to avoid paying the final claim;
(f) a counterclaim by Mr Dawn for common law damages for the delay by Carlisle in completing the building works by the completion date.
(a) the building works were 'complete' for the purposes of the building contract 'by the end of October 2019'[14] or - at the latest - in November or 'by the end of November 2019';[15]
(b) Carlisle was entitled to the final payment of $40,779.40;[16]
(c) Mr Dawn was entitled to 'liquidated' (ie, agreed) damages from 3 May 2019 (being the date VCAT found completion to be due) to 30 November 2019, at $250 per week, in the sum of $7,500;[17]
(d) Carlisle was entitled to recover settlement damages for the periods from 1 December 2019 to 23 March 2021 and 8 August 2022 to 25 January 2023 at $500 per week in the sum of $46,000;[18]
(e) Carlisle's claim for interest on the net amount of $79,279.40 was allowed, in the sum of $23,669.93;[19] and
(f) the final payment sum of $40,779.40 plus its accrued interest would be available to contribute toward meeting the total sum of $102,949.33 owing by Mr Dawn to Carlisle.[20]
(a) Grounds 1, 2, 4 (in part), and 14, raising the questions: did VCAT err in law in concluding that the building works required under the building contract were completed by Carlisle by November 2019 and (on that basis) calculating and awarding settlement damages from December 2019?
(b) Ground 3, raising the questions: did VCAT err in law in concluding that Mr Dawn's lodgement of the final payment amount under the building contract with Enterprise Law on 27 July 2018, at Carlisle's demand, was not a deposit exceeding the amount permitted by the DBCA (s 11) or a progress payment or instalment demanded contrary to the DBCA (s 40)?
(c) Ground 5, raising the question: did VCAT err in law in awarding settlement damages to Carlisle (for periods from December 2019) in circumstances where it found Carlisle was itself liable to Mr Dawn for delayed performance (between May and November 2019), which led to an award of 'liquidated' (or agreed) damages?
(d) Ground 6, raising the question: did VCAT err in law in concluding that Carlisle's demand for payment of the final claim before the appliances were installed was not in breach of s 42 of the DBCA?
(e) Grounds 4 (in part) and 7, raising the question: is Mr Dawn permitted to raise new arguments not properly raised before VCAT about alleged 'repudiation' and 'fraud'?
(f) Grounds 8, 9, 10, 11, 12, and 13, raising the question: did VCAT err in law in not permitting Mr Dawn to rely on his proposed 'further amended points of counterclaim' provided to VCAT on 17 November 2022?
'Building Works' means the works to be carried out and completed by the Builder as shown in the Contract Documents and as varied in accordance with this Contract.
'Contract Documents' means this signed Contract and the Conditions, signed Specifications, signed Plans, an Engineer's Design, Tender, Colour Selection and any other documents attached to the Contract Documents.
'Tender' means the Contract Document specifying the Builder's offer to construct and includes the details of the materials to be supplied as entitled and attached to this Contract.
'Completion' means that the Building Works to be carried out under the Contract have been completed in accordance with the Plans and Specifications set out in the Contract and is the day on which the Builder provides the Owner with the Notice of Completion (as issued pursuant to Clause 36.0).
'Completion' means the Building Works are complete in accordance with the Contract Documents.
'Building Period' means the building construction time estimated by the Builder to carry out the Building Works as stated in Item 1 of Schedule 1, subject to Clause 34.
'Final Claim' means the Builder's claim setting out the balance of the Contract Price due for payment by the Owner to the Builder, taking into account all monies paid by the Owner and all other amounts to be added to or deducted from the Contract Price under this Contract.
'Final Payment' means the payment of the amount of the Final Claim.
If there is an extension of time due to anything done or not done by the Owner or by an agent, contractor or employee of the Owner, the Builder is, in addition to any other rights or remedies, entitled to delay damages worked out by reference to the period of time that the Building Period is extended and the greater of $250 per week or that amount set out in Item 12 of Schedule 1. Delay damages will accrue on a daily basis.
5. Appliances
The following appliances (if included in the Tender) are to be installed by the Builder as part of the Building Works after the Final Payment is made under Clause 38:
(a) Oven(s)
...
(l) Decorative Lighting
36.0 When the Builder considers that the Building Works have reached Completion (except for the installation of the appliances (as applicable) listed in Special Condition 5), the Builder is to give to the Owner:
• a Notice of Completion; and
• the Final Claim.
36.1 Notwithstanding any other provision of this Contract, the Builder must not demand Final Payment until after the Builder has given to the Owner ...:
• a copy of the occupancy permit under the Building Act 1993, if the building permit for the Building Works requires the issue of an occupancy permit; ....
36.2 The Builder and the Owner must meet on the Building Site within 7 Days of the Owner receiving the Notice of Completion and Final Claim to carry out an inspection in accordance with Clause 37.
...
(original emphasis)
37.0 When the Owner and the Builder meet on the Building Site to inspect the Building Works, the Builder will prepare a written list of all known defects and incomplete work (other than the installation of the appliances (as applicable) listed in Special Condition 5). Items identified by the Owner's private consultant will be added to the list if the Builder determines these items are defective or incomplete (at the Builder's discretion). The Builder and the Owner are to sign the list and each must keep a copy.
37.1 If the Owner does not sign the written list of items or there are no items to list as defective or incomplete (pursuant to Clause 37.0), the Owner must pay the Final Claim within a further period of 3 Business Days.
37.2 The Builder agrees to complete all works required to rectify any defects or to complete any works noted on the list prepared pursuant to Clause 37.0.
37.3 The Builder is to give the Owner a written notice when the work under Clause 37.2 has been done.
37.4 The Owner must pay the Final Claim within a further period of 3 Business Days after the Owner receives the Builder's notice under Clause 37.3.
...
(original emphasis)
38.0 When the Owner pays the Final Claim in cleared funds, and the payment of the Final claim is received by the Builder, the Builder must hand over Possession of the Land to the Owner together with all keys, certificates and warranties in the Builder's possession.
...
38.4 When the Owner takes possession under this Clause 38, the Owner must give the Builder reasonable access to install the appliances (as applicable) listed in Special Condition 5.
38.5 Where either:
(a) the Builder has provided the Owner with written notice that the works under Clause 37.2 have been completed (in accordance with Clause 37.3);
or
(b) the Owner does not list any known defects or incomplete work,
and
(c) the Owner has failed to pay the Final Claim and take Possession as required under the Contract, the Owner is liable to pay Settlement Damages as defined in the Special Conditions.
38.6 Where the Owner pays the Final Claim but does not take Possession of the Land or any part of the Land, the Owner agrees and acknowledges that it, the Owner must:
(a) insure the property and provide such details to the Builder;
(b) authorise the Builder to trip the locks (so as not to open with the Builder's key) and the Owner must retain all keys, remotes and settlement pack; and
(c) release, discharge and indemnify the Builder in relation to any claim, demands and costs relating to the security of the property.
(original emphasis)
The term "Settlement Damages" shall mean those sums that the Builder is entitled to be paid by the Owner as damages, to compensate the Builder in the following circumstances:
(i) To compensate the Builder for those expenses to secure and maintain the property in the circumstances described at Clause 38.5 of the General Conditions, in the amount of $500 per week;
...
If the Building Works have not reached Completion by the end of the Building Period the Owner is entitled to agreed damages in the sum set out in Item 9 of Schedule 1 for each week after the end of the Building Period to and including the earlier of:
• the date the Building Works reach Completion;
• the date this Contract is ended; and
• the date the Owner takes Possession of the Land or any part of the Land.
(original emphasis)
Completion of the building works and final payment under the building contract
A further inspection and handover meeting was agreed to take place on 29 March 2019. Mr. Dawn attended the site and asked Mr Durrant where the appliances were. Mr Durrant said that a plumber had been booked to install the appliances later that morning. Mr Dawn left the site without accepting possession of the home.
As a result of this failed settlement meeting, Mr Dawn did not take possession of the property, the Final Claim (the last payment under the building contract) was not released to Carlisle and the property remained in Carlisle's possession for an extended period.
In an email sent by Carlisle to Mr Dawn on 3 April 2019, Carlisle confirmed an offer made by it earlier by telephone that the appliances would be installed prior to Mr Dawn providing the required payment authorisation form. Mr Dawn did not respond to this email.
On 16 April 2019, Carlisle received emails from Mr Dawn dated 27 March 2019 and 5 April 2019, in which Mr Dawn raised 44 allegations of defective or incomplete work, that were not raised previously.
By letter dated 30 April 2019, Carlisle responded to the items in Mr Dawn's emails dated 27 March 2019 and 5 April 2019, noting that seven items had been rectified, and other items were either not defective or would be addressed without admission of responsibility.
Consideration of grounds of Mr Dawn's application
Ground 1: DBDRV assessment report and completion of the building works
Was VCAT required to bind the Respondent to complete the works required standard as per the decision of the Victorian Building Authority 'VBA' report as required by the Domestic Building Contracts Act . Is the VBA the authority of what constitutes proper workmanlike manner as required by the contract . Is the VBA the authority of whether or not the works were complete in accordance with the Building Act 1993.
Ground 2: Notice of completion and finding as to date of completion
If the Works were not complete in accordance with the Contract, Building Act, and ACL at the time the Notice was sent was the Respondent required to serve the Applicant with a new notice in order to claim damages? Was VCAT entitled to calculate damages from the date used within the decision.
Ground 3: Calculation of damages and demand for payment into trust of amount for final payment under the building contract
Was VCAT wrong in its calculation of penalties with respect to the Applicants claim that the Respondents holding of the Final Payment Amount in excess of the Building Contracts Act[?]
(4) Subsections (2) and (3) do not apply if the parties to a contract agree that it is not to apply and do so in the manner set out in the regulations.
(1) For the purposes of section 40(4) of the Act, when parties to a major domestic building contract agree that section 40(2) and (3) of the Act do not apply to that contract, the manner of agreement is to include in the major domestic building contract -
(a) a warning in the form of Form 1 in Schedule 1, which is signed by the building owner before the building owner signs the major domestic building contract; and
(b) a clause in the form of Form 2 in Schedule 1, which is signed by the building owner and the builder before they sign the major domestic building contract.
When the Respondent failed to complete the works determined to be defective by the VBA in accordance with their report did that constitute a repudiation of the Contract? Is the Respondent to claim liquidated damages as defined within the Contract when the Respondent refused to be bound by the terms?
Ground 5: VCAT's award of settlement damages to Carlisle
Is it justified to claim a penalty defined within the contract when the penalty contemplates the offending party having the benefit of retaining monies when those monies have been paid in full. Was VCAT right to allow the calculation when the claiming party is themselves in breech [sic]?
Ground 6: The treatment of appliances and s 42 of the DBCA
Was VCAT wrong to determine that the exclusion of appliances was not a contravention of section 42 of the DBCA[?]
A builder must not demand final payment under a major domestic building contract until -
(a) the work carried out under the contract has been completed in accordance with the plans and specifications set out in the contract; and
(b) the building owner is given either -
(i) a copy of the occupancy permit under the Building Act 1993, if the building permit for the work carried out under the contract requires the issue of an occupancy permit; or
(ii) in any other case, a copy of the certificate of final inspection.
Ground 7: Calculation of time and certain certificates
Was VCAT wrong in its calculation time by allowing the respondent to rely on the certificate of Occupancy fondeded [sic] on a fraudlent [sic] Plumbers Certificate of Complance [sic] made out in contrvention [sic] of the 221ZZH.
Ground 8: Refusal to allow amendment and the Magistrates' Court Rules
Was VCAT wrong to not allow the amendment prior to the start of the trial as per Magistrates' Court General Civil Procedure Rules 2020.
I do not consider that it is appropriate to permit Mr Dawn to raise new issues, particular[ly] at the late stage the proceeding had reached when they were first mentioned. Further, the issues are not raised with sufficient clarity for me to determine whether Mr Dawn wished to raise additional genuine disputes that went beyond the amendments he had earlier sought.[70]
Ground 9: Refusal to allow amendment and VCAT decision [16]
Was VCAT incorrect in its decision at 16 that the facts of the case were not substantially the same? Is it correct that the facts were the same but the rights relied upon were further highlighted?
Ground 10: Refusal to allow amendment and Mr Dawn's attempt to rely on the proposed further amended points of claim and the Australian Consumer Law
Was VCAT wrong to stipulate that the inclusion of the consumer rights in the Applicants further amended points of claim were new when the ACL rights are an essential term of the Contract?
Ground 11: Refusal to allow amendment and Mr Dawn's attempt to rely on the Australian Consumer Law
Was VCAT required to allow the Applicants amendment to include the Applicants rights contained within the Australian Consumer Laws 'ACL'?
Ground 12: Refusal to allow amendment and principles applicable to amendments
Was VCAT required to allow the amended pleadings to include the rights afforded to the Applicant in accordance with Business Service Brokers Pty Ltd v Optus Mobile Pty Ltd[?][75]
Ground 13: Reliance on certain Federal Court cases
Was VCAT required to allow the amended pleadings to include the rights afforded to the Applicant in accordance with the rules Established in Décor Corporation Pty Ltd v Dart Industries Inc (1991)[77], Advanced Holdings Pty Ltd v Commissioner of Taxation (2020)[78] and Davidson v Official Receiver [2021][79]. Is the argument made in KTC [sic]
'While those two criteria may not represent a "hard and fast rule" (Samsung Electronics Company Ltd v Apple Inc (2011) 217 FCR 238; [2011] FCAFC 156 at [29]), they nevertheless provide "general guidance which the Court should normally accept": Rawson Finances Pty Ltd v Commissioner of Taxation [2016] FCAFC 95 at [39].'
Ground 14:VCAT's calculation of time and the slip rule
On the handing down of the ruling His Honour errored in the calculation of time in his ruling deeming the date for completion to be November 2019. The applicant made submissions to the Judge that this was an error and needed to be corrected however no correction was made and no reply to the request was received.
Additional proposed grounds and asserted constitutional matters
(a) VCAT did not have jurisdiction to determine a 'dispute involving an interstate resident';[80]
(b) the dispute before VCAT involved claims under the Australian Consumer Law, and their determination would have involved an exercise of federal judicial power.
[1] Domestic Building Contracts Act 1995, ss 1(a)-(b), 4(a)-(b).
[3] However, this is not the wording of the Commonwealth Constitution, s 75(iv).
[4] Such a matter would be within federal jurisdiction under the Commonwealth Constitution s 76(ii), and is therefore beyond VCAT's jurisdiction: Thurin v Krongold Constructions (Aust) Pty Ltd (2022) 73 VR 403; [2022] VSCA 226 ('Thurin v Krongold').
[6] Carlisle Homes Pty Ltd v Dawn [2023] VCAT 660 ('Reasons').
[7] Ibid [3]. The building contract was a modified version of the Housing Industry Association's Victorian New Homes Contract as updated in August 2017.
[9] This claim was ultimately withdrawn by Mr Dawn: ibid [21], [59(m)].
[17] Even though VCAT found that the work was completed by the end of October 2019, VCAT allowed Mr Dawn an additional month of agreed damages for November 2019: ibid [222], [252].
[21] Carlisle v Dawn (Costs) [2023] VCAT 718.
[23] Contrary to r 19.03(4) of the Supreme Court (General Civil Procedure) Rules 2015. Section 78B of the Judiciary Act 1903 (Cth), read with s 78AA, requires service of a notice on all nine Attorneys-General.
[25] See, eg, Sali v SPC Ltd (1993) 67 ALJR 841; (1993) 116 ALR 625; [1993] HCA 47; Aon Risk Services Australia Ltd v Australian National University (2009) 239 CLR 175; [2009] HCA 27 ('Aon'); Eaton v ISS Catering Services Pty Ltd [2013] VSCA 361; (2013) 42 VR 635, especially 647-648 [48]-[50] (Neave JA and Hargrave, Dixon AJJA); [2013] VSCA 361; Mackenzie v Head, Transport for Victoria [2021] VSCA 24, especially [44] (Tate and Kennedy JJA).
[26] Aon [2009] HCA 27; (2009) 239 CLR 175, 182 [5] (French CJ); [2009] HCA 27.
[27] Ibid [26], citing Sali v SPC Ltd [1993] HCA 47; (1993) 67 ALJR 841, 843-844 (Brennan, Deane and McHugh JJ); 116 ALR 625; [1993] HCA 47.
[28] Sali v SPC Ltd [1993] HCA 47; (1993) 67 ALJR 841, 844 (Brennan, Deane and McHugh JJ); 116 ALR 625; [1993] HCA 47.
[30] Mackenzie v Head, Transport for Victoria [2021] VSCA 24, [44] (Tate and Kennedy JJA).
[32] The only correspondence the Court received was a letter from the Victorian Government Solicitor's Office dated 7 March 2025 on behalf of the Attorney-General for Victoria stating that they were considering the notice and would write to the Court as soon as they received instructions.
[33] Supreme Court Act 1986, s 14C. See also Tucker v Commissioner of State Revenue [2023] VSCA 125, [20]-[21].
[34] However, VCAT noted that a cook top, dishwasher and hot water service were included in the Tender as 'appliances': Reasons, [147].
[35] The Tender included a cook top, dishwasher and hot water service: Reasons, [147].
[54] Similar issues were considered, to similar effect, by the Supreme Court of New South Wales in Creative Building Services v Jolene Investments [2013] NSWSC 391, [29]-[32] (McDougall J), referred to approvingly in Renbar Constructions Pty Ltd v Sader [2022] NSWSC 172, [116]-[118] (Stevenson J).
[55] See [1] of these reasons, above.
[59] Andrews v Australia and New Zealand Banking Group Ltd (2012) 247 CLR 205; [2012] HCA 30; Paciocco v Australia and New Zealand Banking Group Ltd (2016) 258 CLR 525; [2016] HCA 28.
[73] Competition and Consumer Act 2010 (Cth) sch 2 ('Australian Consumer Law').
[75] Business Service Brokers Pty Ltd v Optus Mobile Pty Ltd (No 3) [2022] VSC 283 ('Business Service Brokers') (citation in original text).
[77] Décor Corporation Pty Ltd v Dart Industries Inc (1991) 33 FCR 397; [1991] FCA 844 (citation in original text).
[78] Advanced Holdings Pty Ltd v Commissioner of Taxation (2020) 281 FCR 149; [2020] FCAFC 157 (citation in original text).
[79] Davidson v Official Receiver [2021] FCAFC 73 (citation in original text).
[80] Mr Dawn relied on Burns v Corbett (2018) 353 ALR 386; [2018] HCA 15.
[81] Thurin v Krongold [2022] VSCA 226; (2022) 73 VR 403, 406 [5a], 413-414 [42]-[45] (McLeish, Niall and Walker JJA); [2022] VSCA 226.
[82] Australasian Temperance and General Mutual Life Assurance Society Ltd v Howe [1922] HCA 50; (1922) 31 CLR 290, 295-296 (Knox CJ and Gavan Duffy J), 326-334 (Higgins J agreeing); [1922] HCA 50 (Howe's Case). Howe's Case remains binding: Crouch v Commissioner for Railways (Qld) (1985) 159 CLR 22, 34 (Mason, Wilson, Brennan, Deane and Dawson JJ); [1985] HCA 69; British American Tobacco Australia Ltd v Western Australia [2003] HCA 47; (2003) 217 CLR 30, 51 [37] (McHugh, Gummow and Hayne JJ); [2003] HCA 47.
[83] Thurin v Krongold [2022] VSCA 226; (2022) 73 VR 403, 413-414 [42]-[50] (McLeish, Niall and Walker JJA); [2022] VSCA 226.
[85] Citta Hobart Pty Ltd v Cawthorn [2022] HCA 16; (2022) 276 CLR 216, 234 [35] (Kiefel CJ, Gageler, Keane, Gordon, Steward and Gleeson JJ); [2022] HCA 16.
[88] [2023] HCA 43, [12] (Gageler CJ, Gordon, Steward, Gleeson and Jagot JJ).
Dawn
Carlisle Homes Pty Ltd [2025] VSCA 58
(1993) 116 ALR 625
(2013) 42 VR 635
(2012) 247 CLR 205
(1922) 31 CLR 290
(2003) 217 CLR 30
(2022) 73 VR 403
(2011) 217 FCR 238
(2009) 239 CLR 175
(2022) 276 CLR 216
(1993) 67 ALJR 841
(1985) 159 CLR 22
(2016) 258 CLR 525
(1991) 33 FCR 397
(2020) 281 FCR 149
(2018) 353 ALR 386