[2023] VCAT 660
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2023-06-16
Original judgment source is linked above.
(1) A builder must not demand or receive a deposit under a domestic building contract of more than -
(a) 5% of any contract price that is $20 000 or more;
(b) 10% of any contract price that is less than $20 000 -
before starting any work under the contract. Penalty: 100 penalty units.
(2) For the purposes of subsection (1), the Governor in Council may make regulations fixing a higher dollar amount than that referred to in subsection (1).
(3) If a builder does not comply with subsection (1), the building owner may avoid the contract at any time before it is completed.
(4) However, subsection (3) does not apply if VCAT believes it would be unfair in the particular circumstances of a case for a building owner to do this".
"We refer to our Cash Client Trust Account Introduction Letter, which we sent to you explaining that you would be required to pay your final completion payment (as set out in your HIA New Homes Building Contract) into the Enterprise Law Trust Account prior to your site start.
We now provide the details for you to make payment of your final completion payment so we can commence construction. We confirm that payment is required at least two (2) weeks prior to allocating a site start date. ...
We confirm the final completion payment you are required to pay is: $40,779.40. ...
Any interest which accrues on your payment will be paid to you after the appropriate release document has been signed by all parties, with the balance being paid to Carlisle Homes in payment of the final Completion amount".
"6G In the alternative to paragraph 6E, by demanding the full payment of the Completion Stage before the building works had commenced, the Applicant breached s40(3) of the DBCA by demanding or receiving any amount of instalment that is not directly related to the progress of the building work being carried out under the contract.
The respondent [applicant] demanded the payment of the 'Completion' Stage of the work which is the final stage in the Method 2 Progress Payment table in Schedule 3. The applicant was not entitled to demand this stage of the work before it was completed.
6H By reason of the matters set out in paragraph 6G, the respondent is entitled to avoid the payment of the final claim.
The respondent relies on the reasoning in Stephens v Cameron [2021] VSCA 208 at [96] - [97]".
"6. Section 40(3) of the DBCA does not apply to this Contract as:
b. the parties agreed that subsections (2) and (3) do not apply".
(2) A builder must not demand or recover or retain under a major domestic building contract of a type listed in column 1 of the Table more than the percentage of the contract price listed in column 2 at the completion of a stage referred to in column 3.
(3) In the case of a major domestic building contract that is not listed in the Table, a builder must not demand or receive any amount or instalment that is not directly related to the progress of the building work being carried out under the contract.
(4) Subsections (2) and (3) do not apply if the parties to a contract agree that it is not to apply and do so in the manner set out in the regulations".
"For the purposes of s 40(4) of the Act, when parties to a major domestic building contract agree that section 40(2) and (3) of the Act do not apply to that contract, the manner of agreement is to include in the major domestic building contract -
(a) a warning in the form of Form 1 in Schedule 1, which is signed by the building owner before the building owner signs the major domestic building contract; and
(b) a clause in the form of Form 2 in Schedule 1, which is signed by the building owner and the builder before they sign the major domestic building contract".
"There is ample authority that the proffering of cash or its equivalent in the full amount demanded constitutes a valid tender, even if proffered 'without admissions' or 'under protest', provided only it is unconditional".
Is Carlisle entitled to a maintenance cost of $500.00 per week?
38.6 Where the Owner pays the Final Claim but does not take Possession of the Land or any part of the Land, the Owner agrees and acknowledges that it, the Owner must:
"The Builder must maintain the insurance from the date the Owner gives the Builder Possession of the Land under Clause 25 to the earlier of:
The Owner must pay the Builder a reasonable amount to cover the pro-rata cost of the insurance for any period during which the Final Payment is unreasonably withheld from the date the money is due".
"The term 'Settlement Damages' shall mean those sums that the Builder is entitled to be paid by the Owner as damages, to compensate the Builder in the following circumstances:
(i) To compensate the Builder for those expenses to secure and maintain the property in the circumstances described at Clause 38.5 of the General Conditions, in the amount of $500 per week; ...".
"41.0 If the Building Works have not reached Completion by the end of the Building Period the Owner is entitled to agreed damages in the sum set out in Item 9 of Schedule 1 for each week after the end of the Building Period to and including the earlier of:
41.1 The Owner may deduct the amount of any such damages from the Final Payment".
"35 It is clear that the parties to an agreement may, as part of their agreement, fix an amount that is to be payable by way of damages in the event of a breach of the agreement. Provided the amount so fixed is a genuine pre-estimate of the damage that would arise from the breach, and not so out of all proportion as to be by way of a penalty, that amount is recoverable without proof of the actual loss caused by the breach. It is immaterial that the amount of the actual loss turns out to be less than the amount specified. Equally, if the actual loss turns out to be greater than the amount of the liquidated damages, the claimant cannot ignore the liquidated damages clause and sue for unliquidated damages: Diestal v Stevenson [1906] UKLawRpKQB 92; [1906] 2 KB 345; Talley v Wolsley-Neech (1978) 38 P & CR 45 (CA). That is, ordinarily a valid liquidated damages clause fixes the amount that is recoverable in the event of a breach, regardless of whether the claimant's actual loss is greater or less than the amount specified.
"179 If the actual loss turns out to be greater than the amount of liquidated damages, the claimant cannot ignore the liquidated damages clause and sue for unliquidated damages. That is, ordinarily, a valid liquidated damages clause fixes the amount that is recoverable in the event of a breach, regardless of whether the claimant's actual loss is greater or less than the amount specified.
(a) if a positive sum of liquidated damages has been stipulated under the contract. In this case, Schedule E of the Subcontract sets out a positive sum for liquidated damages in relation to each milestone date of $9,500 per day capped at 5% of the contract price; and > > (b) if the liquidated damages clause is mandatory.
Calculation of amounts owing by and to the parties
Carlisle Homes Pty Ltd
Dawn
(2012) 35 VR 538