[2013] VCAT 1862
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2013-10-29
Original judgment source is linked above.
The applicant's failure to give any notice, whether in writing or given orally, deprived the respondent of the opportunity to make an assessment of the nature of the variation; the reasons for it; the effect it would have upon the building work as a whole; whether it would result in any delays in the conduct of the building work, and the cost of the specific variation and its effect upon the contract price."
"I think in the circumstances of this case and bearing in mind the casual relationship between the parties, arising as it did from the very friendly relationship that they had, that it would be most unfair to the Builder not to allow him to recover a reasonable price for the variations that the Owners wanted. It would certainly not be unfair to the Owners to allow it. I am satisfied that they knew they were variations and that they would be at an extra cost, albeit they were never told how much the cost would be. For these reasons I am satisfied that the Builder ought to be able to recover for these variations."
The enforcement and permit amendment proceedings
"there's not a thing that was changed on that house that was done without Eddie's knowledge, or without mine, or without consultation between Mario, Eddie and me ..."
"...frame stage means the stage when a home's frame is completed and approved by a building surveyor;"
"Around the end of September 2008 I attended the subject site at the request of Mario Sumic to informally inspect the frame. At this point in time, the frame was completed however Mario advised me that Eddy and Joe had requested changes which, in turn, required re-engineering and changes to the architectural plans and engineering design. Whilst these changes to the plans and design were being prepared, Mario wanted to put in for a claim for the fame as it was built and completed in accordance with the plans notwithstanding that it would subsequently be amended.
Mario asked me to take a look at the frame to make sure that it was okay. At this time I recall the frame was up and complete. It looked okay to me but I did not inspect it in any detail. In the course of discussing various aspects of the project with Mario I told him the frame looked okay but I did not consider that I was making a formal inspection of the frame."
(1) For the purposes of Part 4 of the Act the mandatory notification stages are-
(b) prior to pouring an in situ reinforced concrete member nominated by the relevant building surveyor; and
(2) The relevant building surveyor may vary a stage set out in subregulation (1) in relation to building work if it is inappropriate to the building work.
(3) The mandatory notification stages for building work determined in accordance with subregulation (1) or (2) must be set out in the building permit for that building work."
"2) A builder must not demand or recover or retain under a major domestic building contract of a type listed in column 1 of the Table more than the percentage of the contract price listed in column 2 at the completion of a stage referred to in column 3.
Type of contract Percentage of contract price Stage
......................................................
(3) In the case of a major domestic building contract that is not listed in the Table, a builder must not demand or receive any amount or instalment that is not directly related to the progress of the building work being carried out under the contract.
"If the owner is getting finance from a Lending Body, the Owner must give the Lending Body an authority, while this Contract lasts, to make payment direct to the Builder of any amount the Owner agrees has become due under this Contract. The Owner must notify the Lending Body when each stage is completed and the payment is due."
"the stage when a home's external wall cladding and roof covering is fixed, the flooring is laid and external doors and external windows are fixed (even if those doors or windows are only temporary);"
This claim was based upon the photographs but the Builder said that the windows shown as missing in those photographs were removed after lock up. I am satisfied that the windows were all installed at the time the lock up claim was made.
The photographs show some cladding missing from the roof area. The Builder acknowledged that he could not be certain that it was there when he left the site because he did not get up on the roof. There is no apparent reason why the cladding in that area would have been removed if it had been already fixed and I agree with Mr Reid that the timber shown in the photographs is weathered. I think it likely that it was in this condition when the Builder left the site and, since there is no evidence that it had been put on and then removed, I find that it was like that when the lock up claim was made. The same cannot be said for the ground floor cladding at the rear where there appears to have been considerable interference with the work done by the Builder. The Builder said that a lot of cladding appeared to have been removed. In the carport area there is some external cladding missing which the Builder said he could not fix because of the Respondents' indecision about the wiring that was to go underneath. Miss Lardner submitted that this was not required for lock up because it was inside the car port and was to be lined by plaster board. She also said that access to the Unit from the storage area on the other side of the wall had been temporarily blocked off. The plans show there would be no connection with the interior of the Unit when completed. However the plaster was nonetheless to be the external wall cladding. The fascia boards and the undersides of the balconies were not completed and some decorative feature cladding at the front was not there. I do not believe that would prevent lock up being achieved. Overall, I agree with Mr Reid that the external cladding above the roof line was not fitted although I think that the rest was substantially installed.
There is a dispute as to whether a downstairs sliding door had been fitted but I think that the weight of the evidence, particularly that of the Builder and Mr Marke, is that it was. The documentary evidence, notably the invoices relied upon in Mr Reid's submissions, is equivocal.
The significance of the frame not having been approved
"73. In any event, in the circumstances of the case, there is considerable doubt as to whether the frame stage was completed when the demand was made for payment of the lock-up stage on 13 February 2007. The issuing of the progress claim certificate for the frame stage on 4 December 2006 was clearly premature, as the requirement under the definition of 'frame stage' for a home's frame to have been approved by a building surveyor was not met. At this time no verbal approval of any kind had been given, even by Mr Kidd's assistant (who was not in any case a qualified building surveyor). The later approval on 12 February 2007, while preceding by one day the progress claim certificate for the lock-up stage on 13 February 2007, was given by Mr Kidd in reliance upon what he had been told by the builders, and he gave it without conducting a further inspection since his earlier inspection of 17 January. Moreover, Mr Kidd gave his approval on 12 February 2007 in the knowledge that there had been deficiencies in the trusses that required rectification.
74 It is necessary for there to be 'effective and satisfactory completion of the required stage ... [as] a condition of any instalment payment'( Hudson's Building and Engineering Contracts (Sweet and Maxwell, 12th ed, 2010), para 3-076) and while trivial failures, or failures borne of impracticalities, do not preclude effective and satisfactory completion, it is noteworthy that the dispute in relation to the trusses was not resolved until the first day of the hearing before VCAT. That resolution involved work being done on the trusses to strengthen them in accordance with the recommendations of a consultant engineer. The 'final approval' was not given until Mr Kidd undertook a personal inspection on 13 March 2007.
75 The marred history of the progress payment claim for the frame stage does not permit any finding to be made with confidence that the frame stage had been completed by the time the progress payment claim was made for the lock-up stage on 14 February 2007. It is most likely that the frame stage had not been completed by 14 February 2007 either because there had not been effective and satisfactory completion of the home's frame (given the deficiencies in the roof trusses, a major structural component of the home) or because the approval given by the building surveyor on 13 February 2007 was deficient (as it was based on assurances from the builders of what they had read and what adjustments they had made and not upon a personal and independent inspection of the completion of the frame stage when, at least in the circumstances, this appeared necessary). Alternatively, the frame stage had not been completed by 14 February 2007 because the final approval was not given until 13 March 2007 which post-dated the claim for lock-up stage."
This letter is in the reference of the contract that was signed on 14th of November, 2006.
Please regard this as our official written notice to terminate all contractual arrangements that we have with your company, regarding the building of the Property at U2/59 Clifton Street, Essendon. We would also like to inform you to remove all of your belongings from this property as from 12th of January, 2010.
To finalise the financial matters, further notifications will take place.
"The Respondents did advise the Applicant that he was not responding to the demands of completing the lock up stage and therefore had no choice but to terminate the Building Contract" (Paragraph 53);
"As the Applicant did not comply with the Respondents' request to rectify the lock up stage, the Respondents sent the letter to the Applicant to terminate the Building Contract " (Paragraph 65).
"It is a long established rule of law that a contracting party, who, after he has become entitled to refuse performance of his contractual obligations, gives a wrong reason for his refusal, does not thereby deprive himself of a justification which in fact existed, whether he was aware of it or not"
"Repudiation of a contract is a serious matter and is not to be lightly found or inferred: Ross T. Smyth & Co., Ltd. v. T.D. Bailey, Son & Co. (1940) 3 A11 ER 60, at p 71. In considering it, one must look to all the circumstances of the case to see whether the conduct "amounts to a renunciation, to an absolute refusal to perform the contract_": Mersey Steel and Iron Co. v. Naylor, Benzon & Co._ (1884) 9 App Cas 434, at p 439."
"Repudiation is not ascertained by an inquiry into the subjective state of mind of the party in default; it is to be found in the conduct, whether verbal or other, of the party in default which conveys to the other party the defaulting party's inability to perform the contract or promise or his intention not to perform it or to fulfil it only in a manner substantially inconsistent with his obligations and not in any other way."
"35.0 The Builder may suspend the Building Works if the Owner:
35.1 If the Builder suspends the Building Works, the Builder must immediately give notice in writing by registered post to the Owner. The Owner must remedy the breach within 7 days after receiving the notice. The Builder must recommence the Building Works within 21 days after the Owner remedies the breach and gives notice of this to the Builder."
"Miss Lardner: Now was there any other part of that discussion that you recall, other than what you've already identified?
Builder: Other than we wouldn't continue works until such time that we knew that he had funding in place and that we would get paid.
Builder: Yes I did. Because he'd refinanced, or he was in the process of refinancing and that we would need the same terms and conditions of the finance that we had already in the contract, which is a formal approval and moneys withheld for construction by the bank."
He said that he later found out that the re-finance had already occurred.
"...as far as I was concerned, that the contract was not going proceed, unless somebody could prove that they could pay for the balance of the works. Hence the reason for I wasn't even going to send a welder there to weld one cleat until I knew that somebody was going to pay for what I was - firstly, what I was owed and, secondly, what I was going to continue to do."(sic.).
Party accepting repudiation not ready and willing to perform
"satisfactory evidence of the Owner's capacity to pay the sum of the Contract Price and where moneys are to be borrowed, satisfactory evidence that any loan has been approved by the Lending Body and that the mortgage documents have been signed."
"30 At trial and again on appeal, it was contended for the Principal that proof of the costs incurred in performing the work did not establish the value of the work.... It was also contended that there had been no proof by Kane that the costs were reasonable. In our view, these submissions should be rejected. First, it is well-established that the value of the work done can be proved by evidence of costs actually incurred....It is hardly surprising that this should be so. The (reasonable) cost of constructing a building seems a perfectly sensible measure of the value of the benefit conferred.... Ex hypothesi, the owner would have incurred that cost had it undertaken the construction itself.
31 Secondly, Kane's entire quantum meruit case was founded on the proposition that the costs the subject of the detailed evidence led were reasonably incurred...So much should have been readily apparent to those representing the Principal, as it was to the trial judge. The Principal chose not to put in issue the reasonableness of the costs - either in the pleadings...or by cross-examination of Kane's witnesses or by the calling of expert evidence to challenge the quantum claimed. Had that matter been put in issue, it would have fallen to Kane to seek to meet the challenge. That not having occurred at trial, it is not an objection which can be raised on appeal."
"35 The existence of the entitlement to a profit margin seems entirely consistent with the restitutionary objective of measuring the value of the benefit conferred. The inclusion of a margin for profit and overhead means that the calculation approximates the replacement cost of the works. As we have said, it is an appropriate index of value to ascertain what it would have cost the Principal to have had these works carried out by another builder in comparable circumstances".
"If the work the subject of the variations has been carried out - and there was no dispute here that it had been - the only question is the fair and reasonable value of the work. It is irrelevant whether or not the work fell outside the original contractual scope. All that matters is that the performance of the work has conferred a benefit on the owner, for the reasonable value of which the builder should be remunerated."
"In my opinion, "benefit" in this context must be seen from the benefit of the recipient who is, after all, the person to be charged. It may be that for some idiosyncratic reason a defendant seeks the performance of work which another would see as without benefit , or indeed, as a positive dis-benefit.....But where a person requests another to so something , it is not unreasonable for the law to conclude that the former sees some benefit in its performance however wrong this view may be on an objective basis and for the law to act on the perception of the recipient."
Item D1.Frame to south party wall in subfloor out of alignment
The wall is out of alignment and the top and bottom plates have not been secured to the adjoining structure. Mr Browning pointed out that the wall was out of alignment because it was not fixed. That does not seem to be disputed. I think it is properly categorised as incomplete work. Of course the framing stage payment had been made and so the frame ought to have been completed. The problem though is that after the building surveyor had visited the site and formed his opinion that the frame "looked okay", further work was done to the frame to modify it to the Respondents' requirements. After the Builder was terminated, there were others on the site and there is no clear evidence of what they did. It would seem unlikely that if a wall had not been fixed at the time the building surveyor visited, he would not have noticed it. I am not prepared to find that there was an unfixed stud wall at the time the framing payment was claimed. I think it is unfinished work because there can be no doubt that, had the Builder not been excluded from the site this would necessarily have been attended to before the wall was plastered.
Item D2 (a)-(c) Water tank not supplied / or in wrong position
The Original Plans showed a 5000 litre tank at the rear of the property. As part of the stormwater drainage variation it was relocated under the Unit. I do not find this to be a defect. Mr Pavlekovich-Smith suggested that there were access problems to do with the current location and that a square tank should be substituted and the present round tank cut up and removed. I had no difficulty accessing the tank at the on-site inspection. The Builder's evidence was that the required pump well was too large to locate in the back yard and that it required an openable grate and an electrical control panel. He said that it was Joseph and Mr Muzaferovic who decided to locate them under their respective units. He said that the Respondents had then moved the tank to its current position. This is not a defect.
Item D3. Window heads not installed above windows and sliding door
It was acknowledged that the window heads were not installed and I agree with Mr Browning that this is incomplete work.
Mr Pavlekovich-Smith said this should have been done before the timber framing work on Level one commenced to avoid additional costs due to difficulty of access. He said that the grinding machine is large and heavy and would be hard to get down to the lower level later on. In his oral evidence he said that the grinding had to be substantial in order to expose the aggregate. The Builder denied any difficulty of access. Mr Browning said that the builder's decision to leave it to the end of the construction was appropriate because the finished surface may get damaged by construction work. This is a scheduling decision to be made by the builder and I do not see any defect. The grinding is not done but that is incomplete work.
Mr Pavlekovich-Smith points out that the stainless steel grate to the patio area has been omitted and criticised the level at which the water was to be collected from the lowest collection point. All this relates to the stormwater drainage system and the rear yard that had to be re-designed due to there being no pipe in the stormwater easement. It is a variation. I find no defect.
Item D7. Concrete landing steps to the internal stair
Mr Pavlekovich-Smith has said that because there was a special concrete mix and polished concrete on the floor these three stairs should have matched it. He said that it will be difficult to match the mix when landings are poured separately at a future date. The Builder relies on the plans which shows the stairs to be clad in stone. On that basis, it was unimportant when the stairs were laid. This is properly categorised as incomplete work.
This was specified to be double glazing of "Low E" glass. Instead, 6mm toughened glass has been installed. This resulted from the changes to the windows and sliding doors in order to save money. It is a variation and not a defect.
This is 85mm lower than the specified finished floor level and the ceiling level is 600mm higher than the designed height because the Living Room finished floor level is 835mm higher than designed. Mr Browning said that the level changes of the whole Unit were changed because, as designed, it exceeded the maximum height and set-back requirements of the planning scheme. He said that this impacted on the height differences between the upper and lower levels. The evidence was that all these changes were the result of extensive discussion and agreement on site between the Builder, Mr Muzaferovic and Joseph. Again, this is a variation not a defect.
The sitting room floor Level is out of level by 22mm across the room and 19mm to the northern areas of the room. Mr Pavlekovich-Smith pointed out that this is well in excess of the limits sent out in the Guide to Standards and Tolerances. Mr Browning says that he was instructed by the Builder that the floors were to be screeded level at completion to remove the variation in level and an epoxy finish was to be applied which would resolve the problem of out of level floors. I think the important point here is that it was a concrete slab that was to be ground and finished. The present surface is not the final surface. On that basis I think that this is incomplete work.
This was not installed in accordance with the manufacturer's recommendations. Mr Browning agreed that this was a defect and that the EzyClad system should be stripped and replaced with a Uni-Tex system or similar.
Mr Browning agreed that this was also defective. It will be rectified as part of the previous item.
The Builder attached a Harditex wall cladding ("Blueboard") to clad external walls in various locations. The Builder's instructions to Mr Browning were that this was used to provide temporary protection and it was to be replaced by a product called Sycon compressed cement sheet cladding which would be the basis for "Stack stone" cladding and this was used on the carport west wall. I think that the Builder's suggestion that this would put in temporarily is unlikely and I find a defect.
Mr Pavlekovich-Smith said that sub-sills were required to prevent water penetration and that these needed to be set into the slab. Mr Browning said that at the time of his inspection the doors and windows had all been replaced with new and that they had sub-sills. I do not know what to make of this claim. I accept that aluminium windows generally require sub-sills unless it is to be a completely sealed window system but it is unclear whether they were originally supplied or not because the windows have now been replaced by others. No defect in the work and materials supplied by the Builder has been established.
The top rows of boundary wall block brickwork have been demolished and the tops left open to water ingress. They need capping. This was not disputed but I find it to be incomplete work.
Item D16. No sarking or thermal insulation to verandah floor
No sarking or thermal insulation has been installed underneath the compressed fibre cement floor and sheeting to the verandah floor. This is acknowledged. Mr Browning points out that it would be installed after tanking has been done. Since it seems to be a matter of scheduling I find this is incomplete work.
The specifications required any exposed steel to be galvanised. Mr Pavlekovich-Smith pointed out that steelworks supporting the rear balcony are not galvanised but since they are intended to be clad and so would not be exposed I do not find a defect established.
Mr Pavlekovich-Smith has pointed out that the design intent of the architect was that aluminium windows and doors be installed flush against steel columns at the corners and the Builder has not done that. It was agreed to use cheaper windows to save money and, as a consequence, the design intent of the architect could not be realized. The change in appearance is the consequence of this variation.
Mr Pavlekovich-Smith says that the floor on Level 2 is 240mm lower than designed, the timber deck is 965mm higher than designed, the finished floor level of the kitchen is 915mm higher than designed and the finished floor level of the living room is 835mm higher than designed. All of this was acknowledged. According to the Builder's evidence this was driven by two considerations. First, the substitution of a timber floor for a suspended concrete floor and the fall of the land which was not as shown on the plans. The floor levels were then, he said, adjusted to take account of these differences and preserve the stairways. As a consequence, as pointed out by Mr Pavlekovich-Smith, the side wall of the kitchen had to be chamfered to keep the building within the envelope. The construction as built is now in accordance with the final plans sealed by the Council. This a variation and not a defect.
Mr Pavlekovich-Smith refers to numerous respects in which the levels of the floor do not accord with the Guide to Standards and Tolerances 2007 edition. However it is the former edition that is relevant and in that regard, Clause 12.5 provides:
"Generally, the floor is to be within plus or minus 10mm of level over the entire room and at all times within plus or minus 5mm of level over any three metre length within the first 24 months".
Mr Pavlekovich-Smith says that the kitchen and sitting room are out of level by 19mm over 9 metres. This breaches the earlier Guide as well as the 2007 edition referred to by Mr Pavlekovich-Smith. Mr Browning said that his instructions from the Builder were that the floors were to be screeded level at completion to remove the variation and an epoxy finish applied. It was not suggested that this was provided for in the contract documents or by any variation. I find that the out of level floors are a defect.
Item D21. Gap between flooring and kitchen sliding door
There is a 30mm gap that needs to be made good. This was acknowledged by Mr Browning but it relates to the instructions of Mr Muzaferovic to refit the door so that the top of the sill was level with the particle board flooring. Making good the resulting gap would be part of that and I think that this is properly regarded as incomplete work.
Item D22. Sarking and insulation to Level 2 balcony
For the reasons already given in regard to the other balcony I think this is incomplete work.
Item D23. No capping to mini parapet on north west corner of courtyard
This was not denied. It seems to be incomplete work but it has to be replaced anyway when the polystyrene cladding is replaced.
Stormwater is running down the face of the walls. According to the Builder the flashing has not been completed. This is incomplete work.
The levels given by Mr Pavlekovich-Smith would exceed those specified in the relevant Guide to Standards and Tolerances. I accept this item. I do not accept the Builder's explanation that it was to be rectified by screeding and an epoxy finish. I find the defect proved.
This is the feature window at the front of the Unit facing the street and the criticism is that no over-flashing was installed. The plywood was a substrate over which shingles would have been placed and the capping would have been placed over the shingles. This is incomplete work.
I find that the gap should not be there and that it is a defect. However, since it is acknowledged that the polystyrene cladding has to be replaced it is of no practical consequence.
This is a variation. Steps installed by the Builder were temporary and so the steps are incomplete work.
Footings, retaining walls and suspended slab for stair landing omitted. It was acknowledged by the Builder that the stair landing and stairs have not been constructed as shown in the Original Plans and that the levels are quite different from those shown. However I accept that these were the result of changes to the back yard requested by Mr Muzaferovic. The amended plans at Tribunal Book ("TB") 702.21 and at TB 693 endorsed pursuant to the amended Town Planning Permit show a single level at the back yard and the steps as were later constructed by the Respondents. This was a variation.
In situ concrete stair from patio to the landing and from the landing to the verandah are omitted. That is also acknowledged and is as a result of a variation. The amended plans (see TB 693 and 702.21) show no landing. The stairs are shown but not what they are to be made from. The steps in the Original Plans were to be made of concrete but steel steps were later constructed by the Respondents. This was a variation.
Steel framing to the verandah to accommodate connection of the concrete steps omitted. There was an architectural detail as to how this was to be finished involving a strip drain and the support of a glass wall. It is acknowledged that that has not been constructed. The present steel stairs were constructed by the Respondents. Mr Browning said that the architect's detail was deficient and could not be constructed because it did not take account of the shapes of the various components. Mr Pavlekovich-Smith said the difficulties could have been accommodated. I think this was incomplete work.
The first three concrete steps to the internal stair omitted. This is the same item as the alleged defect mentioned above. The steps were to be stone clad and rendered. The rendering and cladding has not been done. That is incomplete work.
Stepped solid wall with stone cladding not constructed. The wall has not been clad. That is incomplete work.
An obscure glass privacy screen required by the original plans within the north boundary wall omitted. That is acknowledged. Mr Browning said that the Builder claims that this was a variation required by the engineer. Elevation 03 on the endorsed architectural plan on TB 697 shows a solid wall. That being so I find no defect.
Portion of the concrete slab to the end of the pool and adjoining steps were omitted. This is again part of the variation to the agreed re-arrangement for the backyard reflected in the endorsed plans...
Level one floor level and the patio level are lower than required by the Original Plans. This has already been referred to above. I am satisfied that the changes to the floor levels were agreed and the position is now regularized in the endorsed amended Town Planning drawings. This was a variation.
The block work of the retaining walls to the patio area is omitted. The Builder has constructed the whole wall from brick. Since the wall is nonetheless masonry and is to be clad with stone no practical consequence is demonstrated. The absence of cladding is incomplete work.
Omitted block work and suspended slab feature column. The column has not been constructed. Miss Lardner suggested that this was incomplete work but it seems to me to be a consequence of the redesign of the back yard. It was part of the original step plan and the final endorsed plans do not show it. It was a variation. If it had not been it would have been incomplete work.
The step from sitting room to the patio is in the wrong position and the sliding door and bottom rail are not rebated into the slab. The drawing relied upon in support of this claim was not a contractual drawing. There was also a dispute as to how this would be constructed. No design was provided by the architect as to how it should be done. Mr Browning also pointed out that in Section N10 the sill was not shown as being rebated into the slab. I am unable to make a finding that this is a breach or as to if or how the rebate, if required, could have been done.
Pre cast concrete panel wall substituted by block work. After some confusion between the experts this matter was resolved in favour of the view of Mr Pavlekovich-Smith. According to the Original Plans, the boundary wall in question ought to have been constructed of pre-cast panels whereas in fact it is constructed of filled block work. As well as supporting its own weight the wall in question is a supporting wall. After some discussion the experts concluded that this would require the certification of the engineer to ensure that what was built was structurally sufficient. No other consequence was suggested. In her submissions Miss Lardner includes a comment by the Builder to the effect that the change was agreed to and that it was due to difficulty of access for a crane. He did give evidence as to difficulty of access to this part of the site but that was only in relation to the construction of the swimming pool. The matter appears to have been resolved by the approval of the engineer to be found in the revised engineering drawings at TB 702.15 Section S 2.1 which specifies a reinforced concrete block wall. Ultimately, this boundary wall as constructed was part of the final endorsed plans agreed to by the Respondents. As such, I find no defect.
Multitude of footing departures as a consequence of above departures and substitutions. The lack of specificity here indicates that this is a comment.
The window in powder room has opaque glazing in lieu of clear, two panels in lieu of a single panel; windows numbered W02 similarly changed and windows and doors have Bradnams frames in lieu of Capral 40 narrow line series. I am satisfied that the windows were changed by agreement. This was a variation.
The windows specified were very expensive commercial grade windows and cheaper windows were substituted by agreement. This was a variation.
The substituted windows specified have not been covered with medium anodized bronze aluminium cladding but have been powder coated. According to the Builder's evidence it would have added an additional $30,000 per unit to anodize the windows in bronze. He said that it was agreed to have powder coated windows as close as possible in colour to save money. I find this was a variation.
Part of a stair landing has been omitted and the kitchen has been correspondingly enlarged. The Builder said this was done because the Respondents wanted to increase the size of the kitchen. It is a variation.
This was due partly to the change in the landing and partly due to the change of windows. Both changes were agreed to by the Respondents. It is a variation.
Mr Pavlekovich-Smith said that the entire stair detail was compromised due to the alteration of levels. That is undoubtedly true but the change in levels was agreed. It is a variation.
This is a repeat of Item C12. . I am unable to make a finding that this is a breach.
This was a consequence of the deletion of the internal garden and fireplace and the change to that part of the design that was requested by Mr Muzaferovic to increase the living room area. It is a variation.
Two skylights located within planter and providing natural lighting omitted. This is a consequence of the same variation.
Windows in the design garden area omitted This is a consequence of the same variation.
The south wall to the living room is changed. This is a consequence of the same variation.
The fireplace has been omitted. According to Mr Browning it would be supplied after lock up and so would be incomplete work. However its omission is, in any case, a consequence of the same variation.
Shelving structure to living room omitted. The same comment applies as for the last item.
Windows and doors have Bradnams frames instead of Capral frames and 6mm "Low E" glass instead of double glazing. The Builder alleges that many of the doors he supplied were in fact double glazed. I do not need to determine that dispute because the Respondents agreed with the substitution of the windows to save money. It is a variation.
The kitchen floor was to be concrete but a timber floor was constructed. This has already been referred to and was a variation.
Floor levels have been changed. This has been referred to above. It is a variation.
The garden bed and other features in the courtyard have been replaced with a graded concrete paving and timber deck. I am satisfied that this was an agreed change and has now been regularized in the endorsed plans. It is a variation.
A timber fence 1,800mm high on top of retaining wall is shown in the contract drawings. Instead, a masonry brick wall has been constructed. I find that this was requested by the Respondents. As part of the settlement with the Council this is to be reduced in height. The change was requested by the Respondents. It is a variation.
The concrete water feature was required by the Original Plans to be cast in concrete but it has been constructed instead of core-filled block work which the builder intended to tank. Construction of the feature is at an early stage and as such, it is incomplete work. What has been built matches the architectural drawing 004 (TB164) but core-filled block work is not what page S4 of the engineering plans required (TB 155). Mr Browning said that the method of construction adopted was commonly used and that did not appear to be disputed by Mr Pavlekovich-Smith. A section (2.6) on page S4 of the amended engineering drawings (TB 702.16) now shows the method of construction the Builder has used. Because of the involvement of Mr Muzaferovic in the construction process I am satisfied that he was aware of the method used. It was also in accordance with the original architectural plans and the amended engineering drawings. I find no defect.
The verandah has not been constructed to accommodate a frameless glazed balustrade and grated drains. Mr Browning said that this was a design error. There was a lot of discussion between the experts about this item. It appears that the detail could not have been built without modification and that the Builder would have needed to obtain instructions from the architect and engineer on how to deal with the problem. It seems from the evidence that the necessary provision could be made after those instructions were obtained and so I think this is incomplete work.
These were a sun control measure provided in the Original Plans. According to the Builder this was a variation to save money. They were deleted on the final endorsed plans.
The kitchen ceiling has been sloped to keep the building within the envelope. This was as a consequence of the change in floor levels. That has already been dealt with above. It is a variation.
There was to have been a pivoted glass door to provide maintenance access to the water feature. Instead there is a fixed window in that position. Access for maintenance must now be obtained under the timber deck. In general, because the changes to the doors and windows were requested by the Respondents and because of his constant attendance on site Mr Muzaferovic must have been aware of this change. The Builder pointed out that, due to the change in levels, stairs would have been required to access the water feature via the glass door if it had been built. Mr Browning said that a landing would have been required to have been constructed within the water feature area. Mr Pavlekovich-Smith acknowledged these problems but said that the door could have been kept locked and only used for service access. It is not simply a small service access door that is shown on the plans. Architectural drawing 004 in both the Original Plans (TB 164) and the final plans (TB 702.22) shows a full length and full width frameless glass door. I accept the evidence of Mr Browning and the Builder that, given the change in levels it could not have been lawfully constructed without a landing and steps on the other side which would have intruded into the water feature and light well. Its replacement with a window was therefore a consequence of the changes made to the levels. The window that has been constructed in its place is aesthetically pleasing whereas a door in that position with a landing as described by Mr Browning would have destroyed the appearance as well as the function of the water feature and light well. I think that this is part of the wider variation to do with the floor levels.
There were supposed to be steel stairs over the water feature. The steel frame has been built but only timber treads have been put on them. There is also no steel handrail. The number of stairs has been reduced, due to the change in levels. Both the treads and the timber hand rails did look temporary to me. I accept Mr Browning's evidence that this is incomplete work.
The original plans called for the windows to be anodised. Instead they have been powder coated. This was a variation to reduce costs.
This window was to have been four panels with an awning opening from the bottom. I am satisfied that the windows were changed by agreement. It is a variation.
The party wall between the units was to be stepped but it is raked at present. The Builder said that it would have been stepped before completion. Whether or not it would have been, the Builder has been denied the opportunity of doing it. This is incomplete works.
This is to do with the window substitution and has already been dealt with. It is a variation.
This has already been dealt with in C 8 above. It is a variation.
The landscaped area in the carport was replaced with a concrete slab. .This was at Mr Muzaferovic's request as detailed above. It is a variation.
Item C 50 & 51 North boundary and car port fence replaced with wall
I am satisfied that this was done at the request of Mr Muzuferovic. The endorsed plans (TB696) show a "brick fence".
It is claimed that, after the Builder left the site, an additional "I" beam needed to be put in to stiffen the floor. Mr Pavlekovich-Smith said that the beams for the floor were put in the wrong way. Mr Browning disagrees and said they were correctly installed. This claim is partly based upon a report of Mr Atchison, another building expert and an engineer, who was not called to give evidence. His report was appended to that of Mr Pavlekovich-Smith. The Builder denies the claim and I am referred to an invoice at TB1235 with a view to establishing that this beam was installed by the Builder but the document was not explained to me and I cannot make anything of it except that it shows a delivery of steel to the Builder. Given the conflict of the expert evidence that I have and in the absence of further evidence on this issue from the Builder and Mr Atchison I cannot make any finding. The framework in this area had not been covered and so if it were simply the absence of a beam that would seem to be incomplete work.
It is said that two raised paved areas at the stair entrance at the front of the property have been replaced by one raised paved area. It was suggested that this was a variation, although it appears to me that the plans do not specify two separate pads. There is a garden bed to go in that area but that is incomplete work.
It is claimed that the brick party wall has to be modified between the carport and the front boundary to accommodate the metre box. Mr Browning said there was no .instruction on the plan as to where it should be placed. I accept Mr Browning's evidence that the location is acceptable. I find no defect.
Floor levels to Bedroom 2, Bedroom 3 adjoining passage to Level 3. This relates to the levels issue and it follows on from the levels of Level two dealt with at C 32 & C 34 and Level one dealt with at C 8. It is a variation.
These were a sun control measure provided in the original plans. According to the Builder this was a variation to save money. They were deleted on the final endorsed plans. It is a variation.
Item C.58 Obscure glass screens omitted Level three
Obscure glass screens were to be installed on either side of the balcony but they have been omitted. The area in question is sheeted with blue board but since that area, as distinct from the surrounding areas, have not been rendered, the Builder's claim that he was intending to supply the screens is credible. This is incomplete work.
The balcony on Level three has not been constructed according to construction details. This raises the same issues as item C 38 and the same findings are made.
Bedroom 1, and adjoining walk-in robe, north walls are to be set further off the north boundary by 390 mm due to floor levels, areas of floor, light well and wardrobe diminished. Mr Pavlekovich-Smith said however in his report that the area of the bedroom overall had increased but that its architectural ambience and its effect upon Level two design features was significant. These changes are said to be due to the need to comply with the consent order of the Tribunal. However that order was agreed to by the Respondents. Any work following that settlement must have been done by others because the Builder was excluded from the site before he could resume work. This issue is based upon Mr Atchison's report and he was not called to give evidence. Insofar as this was to comply with the settlement of the proceedings before the Tribunal, the Respondents agreed to it. Insofar as it is due to the changes in levels, that was an agreed variation. Apart from that I cannot make any finding.
Items C.61 Bedroom 1 dimensions and then impact on Level three
Bedroom 1, and adjoining walk-in robe, north walls are to be set further off as screens were to be installed on either side of the balcony but they have been omitted. The area in question is sheeted with Blueboard but since that area, as distinct from the surrounding areas, have not been rendered, the Builder's claim that he was intending to supply the screens is credible. I find this to be incomplete work.
Items C.62 to C 65 Changes to windows on Level three
I am satisfied that the changes to the windows were at the request of the Respondents. This is a variation.
The spandrel has not been completed. Quite obviously, that is incomplete works.
The dimensions of these areas have been diminished for the same reason as the works to Bedroom 1. This would appear to be to comply with the consent order of the Tribunal. It is not as a result of defective work by the Builder.
Items C 68. Change of Level three windows to Bradnams
This issue is discussed above and the same findings are made.
This is a repeat of C18 and the same comments are made..
The walkway is said to have been modified so that it no longer resembles the design. That comment could be applied to a great deal of the Unit but I am satisfied that the changes to the walkway were agreed to by the Respondents. It was incomplete when the Builder was terminated but that is incomplete work
This is a repeat of C 44 and the same finding is made.
These are a repeat of C 42 & C 43 and the same findings are made.
These were set out in Mr Atchison's report but he was not called. He also did not inspect the frame until well after others purported to work on it. I am unable to make any finding as to defects in the frame, whether due to the Builder or to others.
Timber fascia half round profile Colorbond spouting specified in the original plans have been replaced with metal fascias and quad profile spouting. It was not suggested that any loss arose from the substitution. An elevation in the final plans (TB 702.24) shows Colorbond roof sheeting gutters and downpipes but does not seem to specify the profile. The fascias are to be rendered. Another elevation (TB 702.26) shows Colorbond Fascia. It would appear that the Respondents agreed upon the Colorbond fascia and that what is there is what the final plans require.
It is agreed that this is defective and will be replaced.
The original plans required doors to be 2400 high where ceilings were raked. The doorways were constructed for lower doors. This was acknowledged. The doorways will need to be extended in order to comply with the Original Plans. Since no doors have been fitted it was acknowledged that the cost of doing that would be modest. This is a defect.
Sumic
Muzaferovic
39. The determination of whether a document is a sham in the sense discussed above involves an examination of the parties' subjective intentions. Coppleson v Federal Commissioner of Taxation (1981) 52 FLR 95 at 99; Sharrment Pt Ltd v Official Trustee in Bankruptcy [1988] FCA 179; (1988) 18 FCR 449 at 456-7. Despite the law's aversion to admitting evidence of subsequent conduct as an aid to the construction of contracts, such evidence is admissible in cases of alleged sham in relation to the subjective intentions of the parties at the date they entered into the impugned document. Sharrment at p.456-7. It is evidence going to the existence of the parties' contractual relationship rather than to the terms of that relationship."
(1966) 40 ALJR 265
(1981) 52 FLR 95
(1988) 18 FCR 449