[2010] VCAT 1896
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2010-10-12
Judge P, Mr J
Original judgment source is linked above.
"Unless shown otherwise in Items 4 and 5 of Schedule 1 the Builder has included in the Contract Price fees payable for the building permit and planning approvals."
"(1) A builder who wishes to vary the plans or specifications set out in a major domestic building contract must give the building owner a notice that -
(a) describes the variation the builder wishes to make; and
(b) states why the builder wishes to make the variation; and
(c) states what effect the variation will have on the work as a whole being carried out under the contract and whether a variation to any permit will be required; and
(d) if the variation will result in any delays, states the builder's reasonable estimate as to how long those delays will be; and
(e) states the cost of the variation and the effect it will have on the contract price.
(2) A builder must not give effect to any variation unless -
(a) the building owner gives the builder a signed consent to the variation attached to a copy of the notice required by subsection (1); or
(i) a building surveyor or other authorised person under the Building Act 1993 requires in a building notice or building order under that Act that the variation be made; and
(ii) the requirement arose as a result of circumstances beyond the builder's control; and
(iii) the builder included a copy of the building notice or building order in the notice required by subsection (1); and
(iv) the building owner does not advise the builder in writing within 5 business days of receiving the notice required by subsection (1) that the building owner wishes to dispute the building notice or building order.
(3) A builder is not entitled to recover any money in respect of a variation unless -
(ii) can establish that the variation is made necessary by circumstances that could not have been reasonably foreseen by the builder at the time the contract was entered into; or
(i) that there are exceptional circumstances or that the builder would suffer a significant or exceptional hardship by the operation of paragraph (a); and
(ii) that it would not be unfair to the building owner for the builder to recover the money.
(4) If subsection (3) applies, the builder is entitled to recover the cost of carrying out the variation plus a reasonable profit.
(5) This section does not apply to contractual terms dealing with prime cost items or provisional sums."
"Q. SENIOR MEMBER: All right, thank you. The next thing that you wanted to tell me about was Mr Shaw says, "The contract says that what you have to do when the owner asks for a variation" and you says, "Yes" and he says, "You didn't comply with what you were supposed to do, not even once. "You says, "Correct" and you wanted to say why. So if you want to say why now? ---
Additional three concrete steps and concrete landing support on brickwork
" (1) Subject to subs(2), if at any time after a domestic building work contract is entered into a variation is made to the contract, the builder is not entitled to recover in any court the cost of any work performed or materials supplied under the variation unless the variation is in writing and signed by the builder and the building owner personally or by an agent authorised to act on behalf of the builder or building owner.
(2) subs(1) does not apply to a variation that is made necessary by--
(a) any written directions lawfully given by a building surveyor; or
(b) circumstances that could not reasonably have been foreseen by the builder at the time the contract was entered into-- if the builder gives to the building owner within seven days after the variation is made a statement setting out the reason for, and the cost to be incurred in consequence of, the variation and a copy of the directions (if any) given by the building surveyor."
" In my opinion, the meaning of s19(1) is clear, namely that unless a variation to a domestic building work contract is in writing and signed by the builder and the building owner personally or by an agent, the builder is not entitled to recover in any court the cost of any work performed or materials supplied under the variation, and it does not matter whether any claim by a builder in respect of such cost is brought in contract in indebitatus assumpsit or otherwise."[11]
Item 13(1) Walls between Painting Room and Garage
"In the present case, the respondent was entitled to have a building erected upon her land in accordance with the contract and the plans and specifications which formed part of it, and her damage is the loss which she has sustained by the failure of the appellant to perform his obligation to her. This loss cannot be measured by comparing the value of the building which has been erected with the value it would have borne if erected in accordance with the contract; her loss can, prima facie, be measured only by ascertaining the amount required to rectify the defects complained of and so give to her the equivalent of a building on her land which is substantially in accordance with the contract." [26]
"The qualification, however, to which this rule is subject is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt. No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of demolishing the walls and re-erecting them in second-hand bricks. In such circumstances the work of demolition and re-erection would be quite unreasonable or it would, to use a term current in the United States, constitute "economic waste". (See Restatement of the Law of Contracts, (1932) par. 346). We prefer, however, to think that the building owner's right to undertake remedial works at the expense of a builder is not subject to any limit other than is to be found in the expressions "necessary" and "reasonable", for the expression "economic waste" appears to us to go too far and would deny to a building owner the right to demolish a structure which, though satisfactory as a structure of a particular type, is quite different in character from that called for by the contract. Many examples may, of course, be given of remedial work, which though necessary to produce conformity would not constitute a reasonable method of dealing with the situation and in such cases the true measure of the building owner's loss will be the diminution in value, if any, produced by the departure from the plans and specifications or by the defective workmanship or materials."[27]
[1] Paragraphs 5, 10, 13, 14 and 15 were deleted as inadmissible.
[2] Part of paragraph 6 was deleted as admissible. The applicant and the respondent agreed to be bound by the conclusion reached by the previous Tribunal member that the contents of paragraph 9 was to be given limited weight.
[3] There is an earlier quotation also signed by the applicant and the respondent. It was superseded by this quote.
[6] The table is reproduced from Ms Kirton's written submissions. The numbering is consistent with the identification of the variations in the pleadings and by the building experts. The items not referred to (1-4) are not an issue.
Sayed Rustom (trading as Snab Home Improvements)
Ismail