[2008] VCAT 854
Victorian Civil and Administrative Tribunal
2008-05-12
Original judgment source is linked above.
Major domestic building contract - scope of works - extrinsic evidence irrelevant where contract documents complete and unambiguous - variations - whether allowable despite non-compliance with s.37 and s.38 of Domestic Building Contracts Act 1995 - claim and counterclaim - amounts offset and single order made for the balance
Bodnarcuk v Gibbs (Domestic Building) [2008] VCAT 854
"Where conveying, connecting or installation of services and facilities are not included in the contract price, the owner must pay for those services or facilities to be brought to the land and connected to the works and the builder must provide an estimate of that cost".
There then follows a table of services and facilities stating that gas is not included in the contract price but that sewerage and stormwater are. Water and electricity are said to be included but the supply to the building is said to be not included. The telephone is also not included.
"In relation to the services and facilities that are included in the contract price, the owner must pay for the fees which have been excluded from the contract price in the table below and the builder must provide an estimate of those fees".
In the following table, connection to water supply and connection to electricity supply are specified and in each case the estimate of the excluded fees is said to be unknown. It would seem from other evidence that the electricity was brought from the Existing House and the water supply was from tanks which, it is conceded, were not within the scope of the Contract.
All plumbing fittings i.e. sinks, troughs, toilet, spa taps
According to Mr Lees, this dropped away from the guttering but at the time of inspection it had been replaced. The Builder agreed with Mr Lees that the relevant standard required the downpipe to be supported at no greater than 2 metre centres but said that, because it was less than 4 metres long, that meant it only needed to be supported in the middle. Whether that is a proper interpretation of the Standard (and I do not decide whether it is) the downpipe still had to be adequately secured to keep it in position and it was not. This defect is established. Allow $34.
The criticisms here were the lack of the usual gap below the window frame and the general uneven line of the brickwork. I do not find that there was not the appropriate gap at the time of construction but the criticism of the quality of the brickwork of the sill is established. That in itself warrants the relaying of the sill. Costing is included in Item 3.
Criticisms were made of the great variation in the thicknesses of the perpend joints and the mortar beds and the strength and colour variation of the mortar. I saw no indication of mortar having insufficient strength but I accept Mr Lees' evidence that the brickwork is very much sub-standard. In this regard, the Builder laid the bricks himself. He is not a bricklayer but a carpenter. The very poor quality of the brickwork may be contrasted with the excellent quality of the strip flooring in the New House which he also laid but which was within his area of expertise. I accept that substantial sections of the brickwork will need to be re-laid, to the extent suggested by Mr Lees. Allow $32,107, noting that this figure includes a number of the other items as well.
A section of quad has fallen off and there are large gaps present in various places that need to be covered by moulding. This is established. Allow $721, which also includes Item 12.
Mr Lees criticises the variation in the widths of the grouting and the levels in the rows of tiles adjacent to the north bedroom wall. He also pointed out that the tiles had been laid unevenly. I accept his opinion that the tiles will need to be replaced. Allow $1,916.
Mr Lees pointed to gaps in the junctions with the eaves linings and between the boards and said that these would need to be sealed and repainted. I accept his evidence. Allow $3,611.
Again, there were variations in perpend widths and areas of unsatisfactory brickwork. Costing is included in Item 3.
Mr Lees pointed out that the Builder had used structural grade treated pine for the handrails instead of smooth machined handrails. The Builder said the material that he had used is what is normally used in that area, where construction style tends to be rustic in keeping with the rural surroundings. I accept the Builder's argument in this regard and I find no defect.
The area in question is bushfire prone and so the vents must be screened. The Builder said that he had screened the vents but it was apparent on inspection that a number of them did not have screens and at least in one instance, the screen has fallen over. It seems to me that screens will have to be properly fitted and flyscreens also will need to be installed to all openable windows. I accept Mr Lees' evidence in this regard. Allow $1,585.
Again, I accept Mr Lees' opinion that some areas of brickwork will need to be replaced. Costing is included in Item 3.
The same criticisms are made and in addition, it is said that the bricks in the south wall have not been blended. That is certainly the case on observation. I accept this item. Costing is included in Item 3.
Timber quads are falling off around the eave lining. That was demonstrated on site. Costing is included in Item 4.
Cover strips have not been installed to the bathroom window. The Builder acknowledged this and said that he had not had them made before he left the site. Allow $526.
The overflow relief pipe does not extend and discharge away from the unit as required by the relevant standard. That was pointed out. This is a very minor item but a new relief pipe will have to be installed. Allow $158.
The complaint here is established. I repeat my comments in regard to earlier items. Costing is included in Item 3.
Metal stirrups have not been installed to the junctions of the rafters of the pergola and so the rafters are insecure and are twisting. I accept that the Builder did not use the metal connectors for aesthetic reasons which are entirely defensible. However, it is clear that the various pieces of timber needed to be joined in such a way that they did not separate thereafter and this has not been done. This item has been established. Allow $1,034.
There were a number of criticisms. Mr Lees says that incorrect nails have been used to fix the decking boards. He said that narrow shank un-galvanised gun driven nails should not have been used. One nail was removed during the inspection. The shank diameter was as Mr Lees referred to in his report and I am satisfied that it was not 'hot dip' galvanised but it certainly had some coating on it although what that was is impossible to say.
Mr Lees also said that it was "good practice" to install water proof flashings across the top of the joists of the deck to protect them from moisture but he did not say that this was a requirement so I am not satisfied that the work is defective on that account.
He said that the joists were ineffectively joined to the bearers and that the stumps, some up to 2 metres high, have not been braced.
He said that the stumps were noticeably "out of plumb" but really there was only one stump that fitted that description.
He pointed out that the bearers were centred at 1500 mm which exceeded the 1200 mm specified in the drawings. I notice that it was the Builder himself who specified this spacing on the drawings that he prepared. Mr Lees said as to this "... although the current layout would satisfy the structural requirements for areas it is not necessarily acceptable for deck areas that a design for greater loads than the internal areas".
He recommended that a structural engineer assess the deck's structure and that an allowance should be made to reinforce the structure by installing extra stumps. He said in his report the stumps over a height of 1500mm were to be replaced with larger timbers but on site he qualified that by saying that an engineer might approve the existing stumps.
It seems to me in regard to this item that some of the matters requiring the opinion of an engineer arise from the additional height of the deck and that bracing, which was not provided for in the Plans, should be treated as an extra. The dimensions of the stumps are according to the Contract and any larger stumps would be an extra. The extent to which the engineer's visit is required by reason of exceeding the space and for the bearers would not be an extra since the spacing needs to be according to the Contract. The proposed rectifications are as follows:
Working from Mr Lees' figures I allow $1,571for materials, labour and margin. Adding 28.425%, being the average proportion of preliminaries attributed to each item, the total allowance becomes $2,017.
Joist hangers have been installed on one side of a hanging beam and so extra joist hangers need to be installed. I accept this item. Allow $1,831, which includes 19, 20 and 22. (Mr Lees' composite figure of $2,577 included item 21 which I disallow.)
These have not been installed to the toe of the rafters. I accept Mr Lees' opinion that blocking needs to be installed together with nailing brackets. Costing is included in Item 18.
I accept that additional collar ties need to be installed and must be bolted rather than nailed. Costing is included in Item 18.
In this regard Mr Lees said that further investigation would be required but it is not established that anything needs to be done because it is possible that the investigation will find no fault.
I accept that the ridge prop is undersized and needs to be replaced with one of larger dimensions. Costing is included in Item 18.
Mr Lees says that the roof is not sealed at the junction of the roof and the gable end. That was based upon his observation but the Builder's evidence was that he had installed a blanket of insulation so I am not satisfied as to that part of this item. However I do accept that a licensed plumber needs to alter the layout of the sheets and fix up various gaps and insert the missing bolts. The roof is, as the Builder admitted, incomplete and it was also laid by him and not by a licensed plumber. The Builder said that he did it under the supervision of a licensed plumber but no compliance certificate has been given. Hence this item is accepted. Allow $3,306 which includes the following two items.
There is no back blocking in the ceiling plaster. I accept that these back blocks need to be installed. Costing is included in Item 23.
I refer to my comments in regard to item 24. A plumber needs to go over the roof and fix up any problems. I do not find that the roof needs to be replaced. There is some evidence of some leaking into the bedroom ceiling in two places. Costing is included in Item 23.
Storm water pipes beneath the floor are supported on nylon hanging straps instead of proper brackets. This is established. This item was not costed, presumably because the cost would be minimal and would be attended to with other items.
There are no ant caps on the tops of the stumps but the Contract did not require them. All the Plans require is "Termite barrier physical or chemical in accordance with AS3660". The Builder's evidence is that the area was sprayed for termites which constitutes a chemical barrier and he produced supporting documentation. I am not satisfied as to this item.
Mr Lees suggested that inadequate support has been provided to the end of the bearer below the bedroom lounge room wall where it is partially supported by the attached pier. I could not see this from the access door but Mr Lees provided a photograph. However the Builder said that the bearer in question was attached to the adjacent overlapping bearer so I am not satisfied as to this item.
The physical damp proof course has not been installed in the sub-floor brickwork. The Builder said that a chemical had been added to the mortar for the lower courses in order to provide a damp course but, according to Mr Lees' evidence, at the time of construction this did not comply with the Building Code of Australia (BCA 3.3.4.4). This item is established. Allow $6,993 which includes the following two items.
Mortar dags bridge the cavity between the timberwork and the brickwork. I accept that these, where present, will need to be removed. Costing is included in Item 29.
There is insufficient sub floor ventilation, particularly at the rear of the New House and along the south side. I accept that extra sub floor vents need to be installed. Costing is included in Item 29.
There is no evidence that brick ties have been used to secure the brick piers to the sub-floor brickwork. The Builder said that he had provided such ties and in the absence of any other evidence I disallow this item.
Unseasoned hardwood has been specified on the design drawings and used as sub-floor framework. Mr Lees says that this style of timber is not recommended for use with polished timber floors. Nevertheless, the timber used appears to be in accordance with the contract documents and the polished timber floor seems to be in excellent condition. This item is not allowed.
Extra backfilling is required around the strip footings to prevent water build up around the footings. I accept that it has to be done. Allow $949.
The overhead cupboard doors are slightly smaller than the carcasses and the white melamine can be seen below the bottom of the doors. This was pointed out on the inspection but I think that the problem really is that the carcass edge strip has been covered with melamine instead of a material matching the doors. This matter was discussed at the time of installation between Mrs Ivanac and the Builder and according to the Builder Mrs Ivanac was going to paint the edges of the carcasses. This would be an unsatisfactory solution as the Builder pointed out but there seems no reason why timber edging could not be affixed to the front of the carcasses to match the rest of the cabinetwork. I think replacing the doors is excessive. I will allow $127.
The bench top is scratched. On inspection I saw only one faintly visible scratch which is said to have arisen as a result of the Builder having to sand back the last coat of lacquer which had to be done by hand because Mrs Ivanac had moved in. Compared to other marks on the bench top the scratch in question is trivial and almost invisible. It would be quite unreasonable to allow for the sanding and resealing of the bench top because it is so trifling that no-one would do it. It is a de minimis situation. I am not allowing this item.
The glass pane of the kitchen window is alleged to be scratched and not siliconed into position. I could not see the absence of silicone nor could I see the scratch at the appropriate distance recommended by the Guide to Standards and Tolerances. This item is disallowed.
The bottom drawer adjacent to the pot drawer is catching and requires adjustment. The fact that it is catching now does not mean that it was defectively constructed. It is adjustable, as most doors and drawers are, and like most doors and drawers will need periodic adjustment. I am not satisfied as to this item.
There is a hole in the sink cupboard carcase that requires patching. This was cut in the rear of the cabinet to allow the hoses from the dishwasher. It requires some sort of collar to be put around it to cover the cut-out. This item was not separately costed. It is a small matter of providing a collar. I will allow $84.
There is evidence that the overhead window above the sink cupboard has been leaking causing water damage to the plaster lining. This was shown to me and is proven. Allow $334.
Plastic caps have not been installed to cover any of the fixing screws inside the cupboard. This was also demonstrated. This item was not separately costed. The price of the caps would be trifling but they will need to be purchased and fitted. I will allow $127.
The skirting of the return bench has not been polished. That was also demonstrated. This item was not separately costed. I will allow $84.
No one was able to make them creak at the inspection. I am not satisfied that the floors are creaking. Indeed, the strip flooring seems to be of excellent quality in contrast to other parts of the work.
The door handle to the sliding flywire door has been altered and the previous screw holes have not been repaired. This is proven but I think replacement of the door is excessive. I will allow $169 to cover the screw holes.
There is said to be obvious plaster patching to the central section of the lounge/dining room ceiling. Although not obvious to the casual observer, it is nonetheless a defect and requires repair. Allow $509.
Timberwork throughout the house has a clear finish. Mr Lees says that throughout the house the timber has been inadequately sanded between coats of clear finish. He says that the grain of the timber is raised and requires re-sanding and further painting. This is a matter of finish and, particularly bearing in mind the contract price, I do not think that the finish presented by the Builder is unreasonable. I am not satisfied as to this item.
The joints in many of architraves have not been pinned and glued allowing the joints to open. I accept Mr Lees' evidence that they need to be pinned. Allow $585 which includes item 49.
Floor tiling to the bathroom, laundry and toilet has not been finished under the line of the door. When the door is closed there is a band of tiling approximately 25mm wide that can be seen outside the line of the door. Again, this is a matter of aesthetics. The tiling clearly had to be carried over the chipboard flooring for the laundry so as to join the tongue and groove flooring. I am not satisfied as to this item.
Bedroom door to the back bedroom is binding on the head and requires adjustment. This item is proven. Costing is allowed in Item 47.
There were said to be three water stains in the ceiling paintwork in the front bedroom. I accept that the first two are water stains, that is, the stain in front of the window and the one above the bed, but the one in front of the wardrobe seems to be an irregularity in the paintwork. However, whether it is an irregularity or a stain, it still needs to be rectified and I accept the ceiling will need to be repainted. This item is not separately costed but was included with Item 46 which is a very substantial painting item that I have not allowed. These three marks only require a touch up and since the allowance to repaint the living room ceiling is a generous one I think it should be included in that.
The caulking of the junction between the bench top and the tiles in the laundry is cracking and uneven and the timber trim at the end of the tiling has fallen off. The cuts around the door jambs of the laundry door are also uneven leaving wide grout joints and there are various other criticisms made. All of this item is established. Mr Lees' figure for this includes Item 46 which I have not allowed. That latter item is more substantial and would account for most of the composite figure. For this single item I will allow $903.
I accept that the bath has not been siliconed around the rim. Mr Lees also said that there is insufficient support to the base of the bath but with the bath in place I cannot see how he was able to form that opinion. The Builder said that it has been supported on mortar. I am satisfied that the bath needs to be siliconed but I am not satisfied that it has been insufficiently supported. To put a silicone bead around the bath is a simple matter. I will allow $84.
There was a long vanity unit shown in the plans but a shorter vanity unit has been provided because an extra door was put into the room to connect it with the bedroom. In addition, Mrs Ivanac and Mrs Bodnarcuk purchased a particular basin to match the spa bath they had bought. The basin was designed to be set into the side of a narrow vanity unit. When the Builder pointed out to Mrs Ivanac that to install the basin the vanity unit could only be 300mm wide, she said that she wanted the vanity unit to be wider. So a 450 vanity unit top was provided by the Builder. Because of the design of the basin the front of the vanity unit had to be scribed on a very difficult angle to try and fit the curved contour of the basin. Although I am satisfied that the Builder did his best the result is quite inadequate from an aesthetic point of view. Despite having sympathy for the Builder I find that he should not have undertaken this task and should have directed the Owners to obtain another basin instead. The vanity top will have to be replaced to suit another basin that the Owners will have to provide at their own cost. Allow $865.
This also has not been back blocked and that will have to be done. Allow $814.
The finish to the garage floor is said by Mr Lees to be "particularly rough". The evidence in regard to this was, on the Builder's side, that he suggested this rough trowelled finish because of Mrs Ivanac's advanced age and the danger of her slipping on the floor, particularly bearing in mind the muddy nature of the surrounding area. Mrs Ivanac said that the Builder did not ask her what sort of finish she wanted to the garage floor, that he gave her this explanation, that she told him that she wanted to paint it like in her old house. I note that it has been painted. I am not satisfied that this is defective workmanship. The Builder's position is quite defensible. Indeed, the decision to provide a rough surface was probably wise in the circumstances.
I accept Mr Lees' opinion that the twisted timbers need to be replaced and that nailing brackets need to be installed to the junctions. However, I do not accept that polycarbonate roofing should be installed "as per design drawings" because I am satisfied that it was part of a variation that this would be omitted. In view of the amended design that was agreed upon it is now not practicable to cover the relevant area. Of Mr Lees' figure I will allow $1,199 which also covers so much of the next 3 items as I have allowed.
The timber linings to the carport have not been sealed. That is certainly so but I am not satisfied that it was part of the contract work. The evidence is that the pine lining the Builder has installed cost considerably more than the fibrocement sheeting that one normally sees in such applications and no extra has been claimed by the Builder for this. I am also satisfied that no painting was included in the work for the extension. Indeed, such painting as was done there was undertaken by the Owners. No part of the figure I have allowed is with respect to this item.
In regard to this item I am satisfied that the fall on the roof gutters needs to be adjusted but I am not satisfied as to the rest of it. The stormwater disposal beyond the downpipes and the stormwater tanks were not part of the Contract. This is allowed for with Item 56.
I agree that these need to be trimmed. This is allowed for with Item 56.
Mr Lees says that the gap between the bottom weatherboard and the top of the plinth needs to be covered by an appropriate flashing. The Builder maintained that there would be no problem with this because the water simply runs under the house. Mr Lees said that the problem is that it would run inside the weatherboards whereas it is supposed to run outside. I accept this item. This was costed by Mr Lees together with items 61- 65. Working from Mr Lees' figures I allow for so much of Items 60 - 65 as I have allowed, $934.
This was where the new roof was installed. I accept this item. The allowance is included with Item 60.
Mr Lees says that the mortar joints to the brickwork vary in width with perpends joins up to 30mm. Bricks have not been cleaned around windows and doors. The problem here was the bricks from the demolished wall of the Existing House had to be re-used in order to provide a match with the rest of the house. The Builder said that he had only one brick left at the end. It would not have been possible to equalise the perpends by using cut bricks because there were simply no spare bricks available. Unlike the New House, the appearance of this wall is not particularly unsatisfactory and it is generally in keeping with rustic appearance of the rest of the Existing House. I accept the claim relating to the cleaning of the bricks but not the rest of this claim. The allowance is included with Item 60.
Downpipe junctions have not been sealed. This was established. The allowance is included with Item 60.
It is suggested that eave linings have not been sealed and are noticeably out of level along the south side of the extension. I am not satisfied as to this item.
The door has been installed out of wind by more than 8mm. This was demonstrated. This was costed by Mr Lees together with Items 67- 72. Of these I have allowed only Items 66, 68 and 69 which are the small items. Working from Mr Lees' figures I assess those three items at $321.
The scribed joints at scotia junctions are open and require filling and painting. However the painting was not part of the Contract and the small degree of filling required would I think be part of painting preparation.
The filling of the bolts to the beam above the bed is inadequate and requires re-application. This was demonstrated. The allowance is included with Item 66.
The 45o junction to the lining boards in the bedroom 3/rumpus room wall have not been joined in a straight line. I agree that this needs to be covered with a beading. It is more incomplete than defective work. The allowance is included with Item 66.
It is suggested that the scribed joints to the scotia are sub-standard. I am not satisfied they are inadequate.
In his report Mr lees said that installation of the doors was incomplete as they had not yet been installed and that a bottom track was required. This was not demonstrated on my inspection and I am not satisfied as to this item.
Second hand lining boards have been used in the back of the wardrobe in bedroom two and in the laundry. In addition to the ones I was shown during the inspection photographs were produced as to the lining boards in the laundry. The problem here was that, like the bricks, the previous materials were to be re-used in order to provide a match. This has resulted in joints in the laundry that are not entirely satisfactory but are I think reasonable in the circumstances. As to the backs of the wardrobes, this was agreed to by the owners. This item is not established.
There is therefore a total of $9,189.00 to be allowed to the Owners as credits.
The Plans required the ceilings to be this height so this claim is disallowed.
This was an extra area beyond that shown on the Plans that the Owners requested. The Builder originally claimed $1,389.00 but in his counterclaim, claimed $7,300.00. Mr Lees says that a reasonable amount would be $3,600.00 which I will allow.
The Builder originally claimed $230.00 and now claims $830.00. Mr Lees says a fair and reasonable price would be $500.00 and I accept this assessment.
The Builder claims $380.00 and Mr Lees says $300-$350.00 would be reasonable. I will allow $325.00.
The Builder claims $400.00. Mr Lees has allowed $191.00 which I will allow.
The Builder claims $350.00. Mr Lees said a reasonable figure would be between $300.00 and $350.00. I will allow $325.00.
The Builder has claimed $320.00 which Mr Lees says is reasonable.
This was for the piping of the gas to the internal gas fire to the house. This was not included in the Contract price so this is a proper extra and Mr Lees has not provided any estimate to dispute the Builder's claim of $597.00 so that figure will be allowed.
The Builder claims $630.00. Mr Lees has said $500.00 which I will allow.
Mr Lees said the figure of $366.00 was not unreasonable. The question is whether it should be included with the next item.
As stated above, the plans required a longer vanity but a standard builder's range vanity could have been supplied. What has been built is a custom-made vanity which is worth considerably more. The deficiency in the bench top caused by the Builder's attempts to scribe around the basin is certainly there but this is already taken into account as a defect. I therefore propose to allow the claim for the upgrade of $2,575.00 but accept Mr lees view that the previous item should be included in that.
The Builder claims $800.00 for the fire surround and $1,200.00 to build in the gas fire. Mr Lees says that the two should be included and allowed between $750.00 and $800.00 for them. Looking at the Plans it is clear that some sort of surround was contemplated for the "Jetmaster" heater which the gas fire replaced. Hence I accept Mr Lees' evidence that I should only make one allowance, which will be $800.00. The Builder said that installation of the two items was different and that the "Jetmaster" heater would have had to have been flued through the roof whereas the gas heater was vented through the external wall. I cannot see that this makes any difference in terms of additional cost to the Builder. Indeed, it is one less roof penetration.
Mr Lees does not dispute the amount of $350.00 claimed by the Builder.
Mr Lees says that this figure would amount to between 8 and 10 power points and I am not satisfied that any more than about 3 additional power points was provided. I will therefore allow $150.00.
The Builder claims $390 for this. Mr Lees say it should have been allowed for. The plans indicate the presence of the stove but nothing else. The contract provided that electricity was included in the contract price. I am not satisfied as to this item.
This related to the extension. The Plans provided for glass, which would have been plain glass. At the Owners' request, tinted glass has been provided. The Builder has claimed $280.00. Mr Lees says that $250.00 would be appropriate and I accept his figure.
This has certainly been done. The Builder claims $900.00. Mr Lees says $750.00 would be appropriate and I accept his figure.
This has also been done. Again, the Builder claims $900.00 and Mr Lees has allowed $750.00. Again, I accept Mr Lees figure.
It is not dispute that this was installed. The Builder claims $350.00. Mr Lees says $250.00 would be appropriate and I accept his figure.
French doors were installed between the rumpus room and the carport instead of a single door as per the Plans. The Owners argue that in assessing the amount of this claim it ought to be taken into account that less bricks were used in the walls. However that wall was constructed from bricks taken from the demolished part of the house and so I think there would have been no saving. The Builder claims $1,200.00. Mr Lees says $1,000.00 would be appropriate. I will allow Mr Lees' figure.
It is not disputed that these were changed. The Builder claims $520.00. Mr Lees says $300.00 would be appropriate. I will allow Mr Lees' figure.
The Builder claims $800.00. Mr Lees says $256.00 would be appropriate which, coincidentally, was the amount originally claimed for this item by the Builder. I will allow Mr Lees' figure of $256.00.
The Builder claims $280.00. Mr Lees says $160.00 is appropriate. I will allow Mr Lees' figure.
The Builder claims $1,700.00 which Mr Lees says would be an appropriate figure if it was indeed a variation. The Owners dispute that it was to be a variation and say that the Builder verbally agreed to do that before the contract was signed in order to get the job. There is nothing to that effect in the Contract and no floor coverings are specified in the Plans. In the absence of an admission by the Builder that he had agreed to do this for nothing it is a variation and I will allow the figure of $1,700.00.
The Builder claims $2,976.00 for this. As previously indicated, the Plans are quite misleading. The elevations depicted in the Plans do not show this increased height that the Builder had to build to but the survey levels are written in the Plans. The Builder was required by the Contract to construct what is in the Plans and they show a house of those dimensions built on the levels specified. Since he only did what the Contract required him to do I do not accept that this is an extra.
The Builder claims $2,380.00 and Mr Lees says that $2,000.00 would be appropriate. This would not have been required had the decking been of a height above ground level that the elevations in the drawings showed. Although the Builder did agree to build the New House with the levels indicated, the Plans do not require any railing and so a railing is a variation. I will therefore allow Mr Lees' figure of $2,000.00.
The Builder claims $750.00 for constructing steps down from the deck onto the walkway linking the New House to the Existing House. Again, if the deck had been closer to actual ground level these would not have been required. Although the Builder agreed to construct the deck to those levels, no steps are shown in the Plans and so these are an extra. I will allow Mr Lees' figure of $600.00.
The Builder claims $1,320.00 for this. Mr Lees said that the appropriate figure was between $900.00 and $1,200.00. I will allow $1,050.00.
The hot water service is not shown in the Plans and was not included in the Contract. I will allow the amount of the claim of $960.00.
The Builder claims $300.00 for that. Mr Lees says appropriate figure is between $250.00 and $300.00. I will allow $275.00.
The Builder was given only three town planning drawings by the Owners and went away and finished the plans himself. He has claimed $2,500.00 for doing this and says that it took him three days. Mr Lees says that an appropriate allowance would be $960.00. However, there was no agreement that he would charge anything for finishing the plans and I cannot find from the circumstances that an agreement to pay a reasonable price ought to be implied. I am not satisfied that this is a variation.
There is no doubt that the kitchen has been substantially upgraded from what is shown in the Plans. The Builder claims $5,000.00 and Mr Lees thinks that is a reasonable figure.
(gg) Excavate for water tanks. This was not part of the Contract works. The Builder has claimed $500.00 and Mr Lees says that $250.00 would be reasonable. I will allow Mr Lees' figure.
Cost of rectifying and completing defective and incomplete work: $64,181