BUILDING CONTRACTS - Recourse to unconditional bank guarantees - Security for the purpose of ensuring the due and proper performance of the contract - Interlocutory application by contractor seeking injunctive relief pursuant to ss 232 and 234 of the ACL to restrain principal from taking steps (or further steps) to have recourse to security - Where contractor alleges that principal engaged in misleading and deceptive conduct in contravention of s 18 and (statutory) unconscionable conduct in contravention of s 21 of the ACL - Construction of security clause, recourse clause and restraint clause in building contract - Where terms of the contract provides that principal may convert all or part of the security into cash at any time subject to providing 3 days' prior written notice of its intention to have recourse to the security (recourse clause) - Where contractor restrained by terms of the contract from taking steps to injunct or otherwise restrain the principal from having recourse to the security (restraint clause) - Whether plaintiff has properly articulated a serious question to be tried in this application - Whether plaintiff has articulated the discrimen alleged to render the conduct of defendant unconscionable conduct in the relevant contravening sense - Whether balance of convenience favours granting of injunctive relief - Plaintiff's claim for injunctive relief not granted; ss 21, 22 Australian Consumer Law, Schedule 2 to the (Cth).
BUILDING CONTRACTS - Recourse to unconditional bank guarantees - Security for the purpose of ensuring the due and proper performance of the contract - Interlocutory application by contractor seeking orders to require principal to return 50% of the security it held - Where contract provides for reduction and release of security subject to principal's rights under recourse clause - Where the 'reduction and release' clause pertaining to 50% of the security is expressly subject to the principal's rights in relation to the security, including rights to convert all or part of the security into cash at any time subject to providing 3 days' prior written notice of its intention to have recourse to the security - On proper construction of cl 5.4 (reduction and release clause) and 5.2 (recourse clause), where notice of intention to have recourse to the security having been given, principal's entitlement has vested (subject to any order of the Court to the contrary) - Plaintiff's claims for return of 50% of the security dismissed.
1 On 22 August 2025, the plaintiff, L.U. Simon Builders Pty Ltd, commenced a proceeding by Writ in the Building Cases List of the Commercial Division of the County Court against the defendant, Cardigan Commercial Pty Ltd. In that proceeding L.U. Simon seeks relief in relation to a contract entered into between Cardigan (as 'Principal') and L.U. Simon (as 'Contractor') dated 20 May 2022 for the construction and development of a mixed commercial and residential building on land at 121-131 Cardigan Street, Carlton, Victoria known as the 'Argyle Square' development (Project), in consideration of payment of the sum of $51,707,571.20 (excluding GST) (Contract Sum) (Contract). When commencing the proceeding, L.U. Simon also filed a summons seeking (inter alia) an injunction to restrain Cardigan, its servants or agents, until further order, from having, or attempting to have recourse to the security L.U. Simon had provided to it pursuant to the Contract, in the form of two bank guarantees issued by the Australia and New Zealand Banking Group Limited (ANZ Bank) (each in the amount of $[redacted])[1] (Security), together with an order requiring Cardigan to return one of the bank guarantees to LU Simon.
2 The County Court proceeding was subsequently transferred to the Supreme Court pursuant to s 21 of the Courts (Case Transfer) Act 1991 (Vic) and L.U. Simon's application for injunctive relief was listed for an urgent hearing before the Commercial Court Duty Judge on 17 September 2025.
3 Prior to the transfer, whilst the proceeding was in the County Court, Cardigan had given an undertaking to facilitate the urgent hearing on the basis that the parties would co-operate in having the summons listed before the Commercial Court Duty Judge in the Supreme Court as soon as possible, and preferably in the week commencing 15 September 2025. The undertaking was framed in terms that Cardigan would not have recourse to the Security until the day of final hearing of L.U. Simon's summons or 19 September 2025 at 5.00pm, whichever is earlier.
4 When the proceeding came on for hearing in this Court on 17 September 2025, the Cardigan undertaking remained in place and the Security had not been called on. At the close of oral reply submissions, senior counsel for L.U. Simon noted that time was running and informed the Court that he has 'instructions to pay the money'[2] - a reference to the Security (being the sum of $[redacted] x 2 = $[redacted]) - into Court at the conclusion of the hearing that day, in essence as a pro tem way of effectively holding the status quo pending delivery of the Court's decision, and thereby avoiding any reputational risk to L.U. Simon arising from the guarantee being called on. However, senior counsel for Cardigan responded, stating that the course L.U. Simon proposed was not necessary as he had instructions 'to extend the undertaking' to the Court, to the effect that Cardigan will not take steps (or further steps) to have recourse to the security the subject of this proceeding before midnight on the day in which this Court delivers its judgment.[3] Accordingly, that undertaking has remained in place.
5 In its Writ, L.U. Simon pleads claims against Cardigan for alleged breaches of the Australian Consumer Law (ACL),[4] in addition to its contract claims for extension(s) of time, delay damages and other payments. Relevantly, for present purposes, L.U. Simon's claim for injunctive relief is founded on:
(a) an alleged breach of s 18 of the ACL - that Cardigan engaged in conduct which was misleading or deceptive, or likely to mislead or deceive, in contravention of s 18, by representing to L.U. Simon that it had sufficient funds to pay L.U. Simon the Contract Sum progressively as required by the Contract − for which an injunction is sought under s 232 of the ACL to prevent Cardigan from having recourse to the Security and thereby causing further loss and damage to L.U. Simon; and
(b) a claim for alleged (statutory) unconscionable conduct in contravention of s 21 of the ACL - contending that Cardigan has acted or proposes to act 'unconscionably', by inducing L.U. Simon by its misleading and deceptive conduct to enter into the Contract in circumstances where Cardigan lacked funds sufficient to pay the costs of the Project, and by Cardigan's other conduct under the Contract including its failure to make progress payments in full and on time, its threatening to have recourse to the Security at a time late in the day before a long weekend when it is difficult for an applicant to approach a court for a hearing, and in circumstances where having recourse to the Security would cause a substantial prejudice to L.U. Simon − for which an injunction is sought under s 232 of the ACL to restrain Cardigan from having recourse to the Security.
6 In bringing its application for interlocutory relief, L.U. Simon expressly 'accepts that the terms of the Contract in this case provide Cardigan with a right to have recourse to the Security at any time, in relation to a debt or claim, or an asserted debt or claim, provided that such claim is bona fide and not specious, and subject to providing L.U. Simon with 3 days' prior written notice of such intention.[5]'[6]
7 When opening the case, counsel for L.U. Simon reiterated that position and said '[t]hat means there should be no argument in this case about the construction of Clause 5.2', and he confirmed that this is not a case where L.U. Simon is arguing that Cardigan has failed to satisfy the pre-condition for the right to have recourse.[7] Rather, he submitted:[8]
...this case is concerned with Cardigan's breaches of the Australian Consumer Law and this, we say, distinguishes the case from most of the authorities including the case of Fletcher Constructions, upon which Cardigan has placed much emphasis in its written submissions.
Cardigan's written submissions seek to establish that the contractual regime [in] Clause 5 alters the status quo and it is asserted that LU Simon has agreed to bear the financial risk pending the final determination, for example, of disputes about EOT's [[9]] or variation claims. Cardigan's submission then concludes that because of that construction of the clause, the application should be dismissed. That's at paragraphs 18 and 19.
We submit, with respect, Your Honour, that this misses the point. The point is this, that whatever LU Simon agreed to in the contract must come second to the ACL claims because it never contracted to permit itself to be misled or treated in the manner that we contend, which I will deal with in a moment.
8 In that regard, L.U. Simon submits that the courts have consistently recognised cases where an injunction may be granted to restrain a beneficiary from having recourse to security, and it contends that the principle enunciated by Austin J in Reed Construction Services v Kheng Seng (Aust)[10] − to the effect that 'the party in whose favour the performance bank guarantee has been given may be enjoined from acting unconscionably in contravention of s 51AA of the TPA' - is relevant to the present application. It submits that this principle 'also applies to a case where the injunction is to prevent loss and damage, or further loss and damage, being incurred as a result of misleading and deceptive conduct contrary to s 18 of the 'Australian Consumer Law'.[11]
9 Cardigan refers to this acceptance by L.U. Simon as correctly acknowledging that cl 5.2 of the Contract establishes what is known as a 'pay now, argue later' regime,[12] and Cardigan contends that '[i]t is well settled that under such a regime, recourse to security will not be restrained on an interlocutory basis absent proof of fraud or unconscionability.'[13] Cardigan submits that as neither fraud nor unconscionability has been established, L.U. Simon's application for injunctive relief should be dismissed with costs.
Material relied on by the parties on the hearing of the summons
10 A substantial body of material was filed by each the parties on the hearing of the summons.
11 I remind myself that this is an interlocutory application, where there has been no cross-examination of any witnesses and 'my present function is to identify the areas of dispute, not to resolve them.'[14]
12 The facts relied on by L.U. Simon in this application are set out in:
(a) the affidavit of Jim Moschoyiannis, former director of L.U. Simon,[15] sworn 22 August 2025 (Moschoyiannis Affidavit);
(b) the affidavit of Scott Reid, construction manager in the employ of L.U. Simon, sworn 22 August 2025 (Reid Affidavit);
(c) the affidavit of Jim Moschoyiannis in reply sworn 3 September 2025 (Moschoyiannis Reply Affidavit);
(d) the affidavit of Peter Devitt in reply sworn 4 September 2025 (Devitt Reply Affidavit);
(e) the first affidavit of Scott Reid in reply sworn 4 September 2025 (Reid First Reply Affidavit);
(f) the second affidavit of Scott Reid in reply sworn 17 September 2025 (Reid Second Reply Affidavit); and
(g) the expert report on delays of Andy Chew dated 24 July 2025 contained in the statement of expert evidence dated 25 August 2025 (TBH report).
13 L.U. Simon also relied on its written submissions dated 25 August 2025 (L.U. Simon outline (25.08.2025)), and its reply submissions dated 4 September 2025 (L.U. Simon reply submissions (4.09.2025)) in support of its application.
14 The facts relied on by Cardigan in this application are set out in:
(a) the first affidavit of Graham Duncan Fraser, sole director of Cardigan, sworn 29 August 2025 (First Fraser Affidavit);
(b) the second affidavit of Graham Duncan Fraser sworn 16 September 2025 (Second Fraser Affidavit); and
(c) the affidavit of Luke Mathew van Grieken, partner of Norton Rose Fulbright Australia, sworn 24 August 2025 (van Grieken Affidavit).
15 Cardigan also relied on its written submissions dated 29 August 2025 (Cardigan outline (29.08.2025)) in opposing the grant of the relief sought in the summons.
16 The business known as 'L.U. Simon Builders' was founded in 1955. Subsequently, L.U. Simon was incorporated under the name 'L.U. Simon Builders Pty Ltd' ACN 006 137 220 on or about 31 March 1983.
17 L.U. Simon carries on business as a building contractor and it is regularly engaged to perform building works under contracts of substantial value. In particular, Mr Moschoyiannis deposes that during his time at L.U. Simon, from 1983 until 2024, he has 'worked on over 150 projects with a combined initial contract value of over 3 billion dollars' including many Federal, State and local government-funded and private sector projects.[16]
18 Cardigan (being 'Cardigan Commercial Pty Ltd' ACN 634 598 520) was incorporated on 2 July 2019, under its former name of 'Totara Holdings Pty Ltd'. According to the ASIC Current and Historical Company Search, the shareholders of Cardigan are predominantly companies and individuals based in Singapore.
19 Cardigan is described by L.U. Simon as being a 'project specific' property developer,[17] that was established for the purposes of developing a mixed commercial/residential building on the land in Carlton, and it carries on business principally in connection with the Project development on the land.
Cardigan's tender process for the Project
In response to changed market conditions driven by the Covid-19 pandemic, Cardigan re-designed the project to a residential development with minimal ground floor commercial space, consisting of 79 apartments (later amended to 80 apartments) over 9 levels, and planning permission for this development was agreed in mid-2021, with a final permit issued in December 2021.
In August 2021, I commenced discussions with Mr Moschoyiannis of LU Simon about LU Simon's capability to undertake the works, and on 17 August 2021 I emailed Mr Moschoyiannis a bundle of material described as a "tender package" although no formal tender was undertaken with contractors beyond LU Simon. A copy of this email (excluding attachments) is at page [132] of exhibit bundle GF-1.
On about 13 September 2021, Mr Moschoyiannis sent me LU Simon's tender response, copying his solicitor Mr Toumazou. A copy of LU Simon's tender response dated 13 September 2021 is at page [134] of exhibit bundle GF-1.
Armed with confidence about the cost and duration for the works to enable Cardigan to complete negotiations with its financiers, by 24 December 2021, Cardigan had entered the final tranche of financing facilities with its senior lender PAG totaling $[redacted] (plus other fees which were to be capitalised), of which the construction sub-limit was to be initially set at $[redacted] which exceeded the expected construction costs for the project plus novated consultants, authority costs and contingencies (having had regard to the written pricing provided by LU Simon in its tender submissions above).
On 20 May 2022, Cardigan entered into the Contract with LU Simon. A copy of the Contract is in the SR Affidavit bundle at page 139.
Since 26 June 2020 to the present, being the duration of my involvement as director of Cardigan, Cardigan has not been subject to any action by ASIC relating to its solvency, in external administration, in liquidation, under receivership or subject to any statutory demand.
Until April 2025, LU Simon had not formally raised with me any issues regarding Cardigan's financial position.
Cardigan's Funding and Financing for the Project
- The debt structure for Cardigan was secured for the Project in 2021, well before LU Simon became involved.
- Cardigan has both a senior lender and a junior lender for the Project as follows:
(a) The senior lender is PAG. PAG is a global investment fund based in Hong Kong. PAG has over USD $55 billion under management and is one of the leading non-bank lenders/ investors in the Asia Pacific region. Its Australian real estate debt book is circa A$2 billion. PAG's lender vehicle for the project is Brighten Lead Opportunity Limited. A copy of the PAG's website documents is at page [182] of exhibit bundle
GF-1.
(b) The junior lender is 121 Cardigan Pte Ltd, which is a syndicate of investors via a fund controlled by Havenport Investments Pte Ltd, a company incorporated in Singapore, also a current shareholder of Cardigan.
- Under the financing arrangements, the funds could be used as follows:
(a) to refinance existing indebtedness secured against the Property;
(b) to fund construction, civil, infrastructure and development costs in respect of the Project; and
(c) for the capitalisation of interest and other fees payable in respect of the financing facilities.
- Critically, the financing available to Cardigan for the Project was always greater than the Contract Sum payable to LU Simon. In particular, the PAG financing facilities in place since 24 December 2021 provided funding for construction of at least $[redacted] million, well in excess of the Contract Sum under the Contract, which was circa $[redacted] million excluding GST on execution. I explain this further below.
- On or around 1 June 2021, Cardigan executed a Loan Note Subscription Agreement (LNSA) with its senior lender, PAG, for an initial two facilities A & B totaling $[redacted] (plus other fees which were to be capitalised). PAG entered the LNSA via its lending vehicles Brighten Lead Opportunity Limited ARBN 649 651 034 (as Security Trustee and Agent) and Brighten Lead Opportunity VIII Limited (company number 2057784).
- On 24 December 2021, Cardigan and the PAG parties amended the LNSA with PAG including three facilities A, B and C totaling $[redacted] (plus other fees which were to be capitalised). Importantly, the amended LNSA now expressly allowed for the facility funds to be used for construction and development costs in respect of the Project up to the Construction Sub-Limit (initially $[redacted]).
- The LNSA was amended over the course of the project to increase the facility limits and Construction Sub-Limits to accommodate the changes made during the project, including agreed variations or additional costs validly claimed by LU Simon, as set out below:
First Amendment Deed to incorporate construction sub- limit amount
21 As noted above, on 20 May 2022, L.U. Simon entered into a design and construct contract with Cardigan for the Project.[20]
22 The contract sum, provided for in cl 4 of the Formal Instrument of Agreement, was $51,707,571.20, comprised as follows:[21]
4.1 The Contract Sum is the lump sum amount of $51,707,571.20 (excluding GST) including Provisional Sums but excluding any additions or deductions which may be required to be made under the Contract Documents.
4.2 The contract sum comprises $50,132,659.20 for the domestic building work and $1,574,912.00 for the commercial building works.
23 The provisions concerning the 'Commencement of the Contract' are set out in cls 7.1-7.8 of the Formal Instrument of Agreement. Relevantly, cls 7.3, 7.5 and 7.6 provide for conditions precedent, that must be satisfied or waived, concerning whether financial accommodation has been obtained and whether a 'Builder's Side Deed' has been executed (Builder's Side Deed), as follows:
7 Commencement Date
. . .
7.3 It is a condition precedent to the Commencement Date that the following conditions have been satisfied or waived:
(1) financial accommodation being the senior debt funding has been obtained by the Principal; and
(2) the Builder's Side Deed between the Principal, the Principal's Financier, the Security Trustee, the Agent and the Contractor has been executed.
...
7.5 The Principal will notify the Contractor:
(1) that the conditions precedent in clause 7.3 of this Formal Instrument of Agreement have been met or waived, as the case may be; and
(2) of the Commencement Date,
by issuing a Notice to Proceed.
7.6 The conditions precedent referred to in clauses 7.3(1) and 7.3(2) of this Formal Instrument of Agreement are for the benefit of both the Principal and the Contractor and may only be waived by agreement in writing by the Principal and the Contractor.
24 Mr Moschoyiannis, who was a director of L.U. Simon at the time the Contract was negotiated and executed, deposed that L.U. Simon took care to negotiate suitable terms of the Builder's Side Deed in order to protect L.U. Simon's commercial interests.[22] In this regard, by way of example of the care taken, Mr Moschoyiannis exhibited an email from L.U. Simon's solicitors, Giannakopoulos Solicitors, to the Financier's solicitors (Clayton Utz) requesting amendments to three clauses in the Builder's Side Deed, in which L.U. Simon's solicitors stated in relation to the revised draft Builder's Side Deed:[23]
Accordingly, LU Simon requests that Clause 4.10 be deleted and replaced with the following:
The Company irrevocably authorises and directs the Security Trustee and Agent to make payment direct to the Counterparty of all progress payments due to the Counterparty under the Contract out of funds which would otherwise be available to the Company under the Loan Note Subscription Agreement.
Please confirm whether the amendments requested by LU Simon to Clause 4.7 and Clause 4.10 are acceptable to your clients.
25 Clause 5 of the AS 4902-2000 General Conditions of Contract addresses the 'security' for the Contract. Under cl 1, the expression 'Security' is defined to mean 'an unconditional undertaking in a form approved by the Principal (the form in Annexure Part B is approved) given by [(inter alia) named Australian banks]'.
26 Clause 5.1 provides for the security to be given by the Contractor, as follows:[24]
5 Security
5.1 Provision
Security and performance undertakings are for the purpose of ensuring the due and proper performance of the Contract.
The Contractor shall deliver the Security in the amount stated in Annexure Part A to the Principal no later than the Date of the Contract, and maintain the Security in accordance with this clause 5. The Contractor is not entitled to claim or to be paid any moneys until the Security has been delivered to the Principal.
27 Annexure Part A to the AS 4902-2000 General Conditions provided that [redacted]% of the Contract Sum be provided as Contractor's Security.[25] Pursuant to this cl 5, LU Simon provided Cardigan with the Security in the form of two ANZ bank guarantees totalling $[redacted], being:
(a) ANZ guarantee No GOP52252413418 in the amount of $[redacted]; and
(b) ANZ guarantee No GOP52252033418 in the amount of $[redacted].
28 Clause 5.2 of the AS 4902-2000 General Conditions establishes what is colloquially described as a 'pay now, argue later' regime.[26] It provides Cardigan with a right to have recourse to the Security at any time, in relation to a debt or claim, or an asserted debt or claim, provided that such claim is bona fide and not specious, and subject to providing LU Simon with 3 days' prior written notice of such intention.
(a) Subject to providing the Contractor with 3 days' prior written notice of its intention to have recourse to the Security, the Principal may convert all or part of the Security into cash at any time and use the proceeds of the Security:
(i) in relation to any debt or money due or claimed to be due from the Contractor to the Principal under the Contract (including liquidated damages under subclause 34.7) or any cost, expense, loss or damage of any kind which the Principal has incurred or claims that it has incurred or might in the future incur in connection with what the Principal contends constitutes any act, default or omission of the Contractor; or
(ii) whenever the Principal is otherwise permitted to do so in accordance with the terms of the Contract, or if an event described in subclause 39.11 occurs in respect of the Contractor.
(b) The Contractor must not take any steps to injunct or otherwise restrain:
(i) any issuer of any Security provided under subclause 5.1 from paying the Principal under that Security;
(ii) the Principal from taking any steps for the purposes of making a demand under any Security or receiving payment under any Security; or
(iii) the Principal using the money received under any Security;
even where the Contractor disputes the Principal's right to payment (including where dispute resolution proceedings have been commenced under this Contract).
30 Clause 5.4 of the AS 4902-2000 General Conditions, which governs the conditions for release of the Security under cl 5.2, provides as follows:[28]
(a) Subject to the Principal's rights in relation to the Security under subclause 5.2, upon the last to occur of the following:
(i) issue of the Certificate of Practical Completion (or where there are multiple Separable Portions, issue of the Certificate of Practical Completion for the last Separable Portion to achieve Practical Completion);
(ii) the Contractor has given the Principal an executed Deed of Release - Practical Completion (or where there are multiple Separable Portions, the Contractor has given the Principal Deeds of Release - Practical Completion in respect of all of the Separable Portions);
(iii) the Contractor has given the Project Manager the Subcontractor warranties required under subclause 9.6 and all other warranties and certificates required under the Contract;
(iv) the Contractor has given the Project Manager all final versions of shop drawings and as-built drawings for the Works and operation and maintenance manuals for all plant and equipment forming part of the Works; and
(v) the Contractor has provided copies of each Moral Rights Consent to the Project Manager in accordance with subclause 10.3(b),
the Principal's entitlement to the Security shall be reduced to the percentage of the Security stated in Annexure Part A[29] or, if no percentage is stated, 50%.
(b) If the Contractor has given the Principal:
(i) a Deed of Release - Final Completion executed by the Contractor; and
(ii) Final Completion Certificates in the form of Annexure Part O from relevant Consultants for the benefit of the Principal;
then within 10 Business Days after the issue of a Final Payment Schedule, the Principal shall release to the Contractor any Security then held by the Principal (subject to any claim of the Principal on the Security).
(c) The Principal's entitlement to Security for any item of unfixed plant and materials under subclause 37.3 shall cease 10 Business Days after the later of:
(i) receipt of a claim by the Contractor; and
(ii) the incorporation into the Works of the plant and materials for which that Security was provided.
(d) The Principal shall release Security in excess of the entitlement within 10 Business Days of the entitlement being so reduced.
Pursuant to clause 7.5 the Superintendent hereby provides a notice to proceed on behalf of the Principal (Cardigan Commercial). This notice confirms that the conditions precedent of clause 7.3 of the FIA [Formal Instrument of Agreement] have been met and the date of commencement is 7th June 2022.
32 Mr Moschoyiannis deposes that after receiving the Notice to Proceed, L.U. Simon mobilised to site and started its work under the Contract.[32]
L.U. Simon encounters difficulties with receiving payment of progress claims from Cardigan on a timely basis
33 L.U. Simon submits that in late 2024 and early 2025, Cardigan experienced difficulties in making payments under the Contract in full and on time. Mr Scott Reid, who is a Construction Manager employed by L.U. Simon, deposed that:[33]
...
- The amounts certified by the Project Manager were not only payable under the Contract, they were also scheduled amounts owing under the Building and Construction Industry Security of Payment Act 2002.
34 Mr Reid's evidence was that he had numerous discussions with Mr Fraser about these payment issues and defaults over the course of the Project. He deposed:[35]
. . .
I had numerous discussions with Mr Fraser about these payments issues and defaults, over the course of the Project. Mr Fraser said that he was endeavouring to arrange funding to pay the outstanding payments.
Despite Mr Fraser's assurances and promises, payment of the outstanding amounts was random and sporadic.
In March 2025, the situation of shortfalls in payment was causing concern to LU Simon because the work was nearing completion and there were substantial sums unpaid for progress claims between September to December 2024 exceeding $800,000. Accordingly, on or about 25 and 27 March 2025, I caused LU Simon to serve two Notices of Intention to Suspend the Works under the Building and Construction Industry Security of Payment Act 2002, to try and force Cardigan to pay.
I understand from the discussions that I had with Mr Fraser that upon receipt of these Notices of Intention to Suspend, that he arranged for the financier, PAG, to provide funds to make the payment required, in order to avoid a suspension of the work.
These issues with payment were a serious concern to LU Simon throughout the Project, but they were not the only concerns. Other concerns included delays caused by issues which I refer to below.
. . .
- . . . I reiterate that if LU Simon had known that Cardigan was having these financial issues, then it would have never entered into the Contract.
35 Mr Moschoyiannis gave similar evidence to that of Mr Reid about the importance of cash flow and L.U. Simon's practice not to sign up for a contract without knowing there was sufficient money to pay for the work. He deposed:[36]
36 As was noted earlier, L.U. Simon's solicitors had requested amendments to cl 4.10 of the Builder's Side Deed to ensure that funds which are owed by Cardigan to L.U. Simon under the Building Contract are paid directly from the Financier to L.U. Simon. The solicitors stated that '[a]n irrevocable authority and direction from the Company to the Security Trustee and Agent is a fundamental requirement of L.U. Simon.'[37] Mr Moschoyiannis explained this practice, deposing:[38]
37 Mr Reid also gave evidence to the effect that until 20 August 2025 when he was informed by L.U. Simon's solicitor, Mr Paul Toumazou, that Cardigan had earlier been placed into external administration on or about 11 May 2020, and that the external administration ended on or about 5 November 2020, he was unaware of that information.[39] Further, he said 'Mr Fraser never informed me or anyone else at LU Simon that Cardigan had experienced financial problems and had previously been placed into external administration.'[40]
38 Mr Fraser, who became the sole director of Cardigan at or after the time of the external administration, and manages the company on behalf of the Singaporean investors, responded to Mr Reid's evidence of 'lack of knowledge' with incredulity. He deposed:[41]
(a) On 30 July 2021 the financing adviser to the project, Mr Geroge Giovas of Axius partners sent me and Mr Moschoyiannis. a director of LU Simon at that time, an email introducing the project to LU Simon. Mr Giovas was able to give comfort to Mr Moschoyiannis that the project was bankable, and had funding in place (as it was being arranged by Mr Giovas, and the initial facilities were in place as of 1 June 2021).
(b) Subsequently on 17 August 2021,1 emailed Mr Moschoyiannis of LU Simon a tender package of documents for the Project.
(c) Between about August 2021 and February 2022, l met with Mr Moschoyiannis and Mr Terry Lewis (who was a co-director of LU Simon) on several occasions. I recall those meetings were typically in the office of MetierS Architects. I also recall having a several phone calls with Mr Moschoyiannis during this period, and exchanged emails on commercial matters related to the Project.
(d) On 10 March 2022 Project Control Group (PCG) Meetings for the project formally commenced, approximately 3 months prior to LU Simon executing the Contract. On this day, Mr Moschoyiannis. Mr Lewis and Mr Reid of LU Simon joined a Teams call with myself, the project manager and executives from both the senior and junior financiers. The financiers said words to the effect that their role in the project was to provide funding and gave an update on the status of the project. I do not recall any question directed to either set of financiers regarding Cardigan from Messrs Moschoyiannis, Reid or Lewis.
39 Mr Fraser also disagreed with the evidence given by Mr Reid about late payments, and to the effect that Cardigan was experiencing 'financial difficulties'. He deposed:[42]
Late Payments
- I refer to paragraphs 21 to 33 of Reid's Affidavit about Cardigan's "financial difficulties", or LU Simon's receipt of payments as being "random and sporadic". I disagree with these statements. They are not supported by the facts, which I explain below.
- Since May 2022, when the Contract was executed, until Practical Completion on or around April 2025 and May 2025, Cardigan has not experienced any lack of finance or funds or difficulties making payments to LU Simon. I, on behalf of Cardigan, requested its senior financier make payments as required under the LNSA and Builder's Side Deed directly to LU Simon in cleared funds consistent with the certified amounts calculated by the Quantity Surveyor for the Project on a monthly basis.
- As shown in the table at page [265] of the exhibit bundle GF-1 between February 2023 and October 2024, Cardigan made payments to LU Simon that were on average 1 day after the date for payment as shown on the tax invoice.
- There was no lack of funds or financing, no misrepresentation or unconscionability. Instead, there were minor and infrequent delays to payment, as is common in construction projects. Indeed, the Contract expressly provides LU Simon remedies for late payment: interest (which Cardigan/PAG has already paid to the sum of $61,282.72), a show cause regime, suspension of works or ultimately termination.
- In that context, in glaring omissions, the Reid Affidavit and the Moschoyiannis Affidavit fail to provide the full context, including:
(a) from June 2022 to June 2025, Cardigan has paid LU Simon the amount of $58,398 million (plus GST), which represents the full portion of the Contract Sum payable under the Contract to date;
(b) the usual process for the payment of monthly progress claims in project financed project;
(c) the agreement between Cardigan and LU Simon regarding purchaser change variations;
(d) the contractual remedies LU Simon had agreed in the Contractor would apply for late payment; and
(e) the fact that Cardigan has already paid $61,282.72 in interest.
40 Mr Fraser continued, to outline the 'Payment process' adopted between the parties pursuant to paragraph [37.1] of the Contract and then observed:[43]
41 Mr Moschoyiannis also gave evidence in his reply affidavit responding to the allegations made by Mr Fraser in paragraph [50] of his affidavit (reproduced above). Mr Moschoyiannis responded to the effect that he 'was not aware of Cardigan's previous external administration prior to the execution of the Contract by LU Simon and Cardigan' and he confirmed that Mr Fraser did not inform him that Cardigan had previously been under external administration.[44] Further he deposed:[45]
(d) I have recently been informed by Mr Toumazou and believe that prior to LU Simon executing the Contract he undertook a title search to verify that Cardigan was the registered proprietor of the Property but that he did not undertake a company search of Cardigan;
(e) I did not at any time undertake my own company search of Cardigan.
42 In his Reply Affidavit, Mr Moschoyiannis also took issue with Mr Fraser's assertion that he had failed to mention that there was a verbal agreement reached between L.U. Simon and Cardigan, as negotiated with the Project Manager, in or around early 2024, regarding purchaser change variations. In his First Affidavit, Mr Fraser had outlined the background to the agreement[46] and deposed that it was to the effect that 'L.U. Simon would not claim amounts for purchaser variations until the works reached Practical Completion (Agreement).'[47]
43 Mr Moschoyiannis refuted the existence of any such 'Agreement', deposing:[48]
44 Mr Peter Devitt, a director of L.U. Simon who assumed director responsibilities for the Project after Mr Moschoyiannis resigned, also refuted Mr Fraser's evidence that there was of any such 'Agreement', deposing:[49]
45 Mr Devitt then continued to set out his recollection of the events which took place from February 2025 concerning the Purchaser Change Variations, L.U. Simon's EOT Claims and Cardigan giving notice of its intention to cash the bank guarantees. He deposed as follows:[50]
(a) the first mortgagee was financially safe;
(b) the second mortgagee was financially safe; and
(c) the Singaporean equity partners will be taking a haircut (which I understood to mean taking a loss) but to what extent was unknown at that stage.
- Mr Fraser also told me that the financier was not funding the Purchaser Change Variations of approximately $1.2million. I restated to Mr Fraser the message that I had asked Mr Moschoyiannis to convey months earlier that LU Simon would not provide funding for the Project and that we required all progress certificates to be paid in full.
- On 4 March 2025, I attended a meeting at Gallagher Jeffs' office with Mr Fraser, Mr Scott Reid, Mr Andrew Minty of Gallagher Jeffs and Mr Chris Burton of Gallagher Jeffs to discuss my concerns with the Project, including outstanding payment claims and unresolved claims for extensions of time. At that meeting, I told Mr Fraser that LU Simon would be providing further information in relation to its EOT Claims for review and consideration by Gallagher Jeffs. Mr Fraser stated that he would rely on Gallagher Jeffs with respect to the review of LU Simon's EOT Claims and variations and that he would not be trying to influence them for the review of the resubmitted EOT claims. Mr Fraser stated that on the basis of Gallagher Jeffs' assessment of the Date for Practical Completion and the current estimated Date of Practical Completion, he believed that the liquidated damages were in the order of approximately $6.2 million and he expected to use the liquidated damages payment to reduce the Singaporean Equity Investors' losses. At that meeting, I told Mr Fraser words to the effect that LU Simon required all unpaid progress certificates to be paid in full.
- After my meetings with Mr Fraser on 6 February 2025 and 4 March 2025, it became apparent that Cardigan was either unable or unwilling to make payment in full of all of the outstanding progress certificates. I instructed LU Simon's solicitor, Mr Dimi Toumazou, to issue formal letters of demand to Cardigan pursuant to the Building and Construction Industry Security of Payment Act 2002 (Vic). I gave this instruction as I was concerned that the Project was due to be completed and that LU Simon would have large sums unpaid. A copy of the letters of demand issued by Mr Toumazou on 25 March 2025 and 27 March 2025 are contained at [6-12] of the Bundle.
- After making these demands for payment of the outstanding progress certificates Cardigan gave notice of its intention to cash the bank guarantees.
46 Mr Reid also gave evidence (in his First Reply Affidavit) about the 'Purchaser Change Variations', in similar terms to that given by Mr Moschoyiannis and Mr Devitt, as follows:[51]
Purchaser Change Variations
I refer to paragraphs 70 to 72 of the Fraser Affidavit where Mr Fraser deposes that LU Simon and Cardigan agreed for LU Simon to forgo its entitlement to claim payment in respect of the purchaser change variations on the Project (Purchaser Change Variations). In response to the allegations contained in paragraph 71 of the Fraser Affidavit, to the best of my knowledge and belief, neither Mr Moschoyiannis of LU Simon nor anyone else on behalf of LU Simon agreed to forgo LU Simon's entitlement to receive payment for the Purchaser Change Variations as alleged by Mr Fraser.
While I recall being informed in or about early 2024 that Cardigan had asked whether LU Simon would agree to fund the payment of the Purchaser Change Variations on the Project, Mr Moschoyiannis told me that LU Simon did not agree to fund the Purchaser Change Variations.
I confirm that I attended a meeting with Mr Fraser and Mr Devitt in or about 4 March 2025. To the best of my knowledge and belief, I recall that during this meeting, Mr Devitt advised Mr Fraser words to the effect that LU Simon required all unpaid progress certificates to be paid in full.
. . .
47 While Mr Fraser of Cardigan filed a second affidavit sworn on 16 September 2025, shortly before the hearing, in which he stated that he had read Mr Reid's First Reply Affidavit, he did not respond to Mr Reid's evidence about the 'Purchaser Change Variations' set out above. Nor did Mr Fraser's second affidavit make any reference to him having read Mr Devitt's Affidavit in Reply, and he did not give any further evidence about what transpired at the meetings he had with Mr Devitt and others on or about 6 February 2025 and 4 March 2025. In his first affidavit, however, Mr Fraser had deposed about what took place at the 4 March 2025 meeting, as part of the 'background' to the (asserted) agreement regarding the 'Purchaser Change Variations':[52]
(k) On 4 March 2025,1 attended a meeting with Mr Devitt and Mr Reid of LU Simon in the offices of the Project Manager. At the conclusion of the meeting Mr Devitt formally asked me to arrange that Cardigan's financier pay the purchaser change claims made at the end of 2024. I agreed to do so. This was the first time such a request was made to me. Following this meeting, Cardigan's financier PAG paid for the outstanding purchaser changes in full.
48 An affidavit of Cardigan's solicitor, Mr Luke van Grieken, a partner of Norton Rose Fulbright, was also filed on behalf of Cardigan. In his affidavit, Mr van Grieken outlines the factual background to the proceeding; the limited undertakings that were given by Cardigan, as amended and extended from time to time between late April 2025 and late August 2025; the status of (alleged) defects at the Project; the number of apartments currently owned by Cardigan, and information pertaining to the current application.
Cardigan gave notice of its intention to have recourse to the Security based on its contractual right to liquidated damages
49 On 24 April 2025, Mr Fraser of Cardigan sent a letter to Mr Devitt, director of L.U. Simon, in relation to L.U. Simon's (alleged) debt to Cardigan for liquidated damages under the Contract, and gave notice of Cardigan's intention to have recourse to the Security in accordance with cl 5.2 of the Contract. Relevantly, in the letter, Cardigan stated:[53]
Liquidated Damages
Under clause 34.1 of the Contract, the Contractor shall ensure that the WUC reaches Practical Completion by the Date for Practical Completion. The Date for Practical Completion was 13 September 2024. As at the date of this letter, the Works have not reached Practical Completion.
In accordance with clause 34.7 of the Contract, if the WUC does not reach Practical Completion by the Date for Practical Completion, the Contractor is indebted to the Principal for liquidated damages at the rate stated in Annexure Part A for every day after the Date for Practical Completion to and including the earliest of the Date of Practical Completion or the termination of the Contract or the Principal taking the whole of the remaining WUC out of the hands of the Contractor. Annexure Part A states that the rate of liquidated damages is $32,000 per day.
As at the date of this letter, the Contractor is indebted to the Principal for liquidated damages as follows:
The Principal notes additional liquidated damages may be payable in respect of further delays to achieving Practical Completion.
Notice of Intention to have Recourse to Security
In accordance with clause 5.2 of the Contract, the Principal gives the Contractor written notice of its intention to have recourse to the Security.
All of the Principal's rights are reserved.
50 At the hearing, counsel for Cardigan referred to Mr van Grieken's affidavit to demonstrate the two relevant dates of practical completion, the development having split into two severable portions, 'SP 1' and 'SP 2'. Counsel pointed to the 'SP 1' certificate (dated 1 May 2025)[54], certifying that 'the Works' for Separable Portion 1 'have reached the stage of Practical Completion at 4pm on Tuesday 29th April 2025', but noting 'the following [list of] incomplete works and minor defect items.'
51 Counsel for Cardigan submitted that 29 April 2025 was an 'important date' because that date 'comes after the notice of recourse to the security was issued', which was served on L.U. Simon on Thursday 24 April 2025 (being the day before the ANZAC Day public holiday). Counsel for Cardigan explained the 'importance' of the date, stating:[55]
Now, that's an important date, Your Honour, because it comes after the notice of recourse to the security was issued and so that this is the project manager saying, well I'm satisfied that you have sufficiently completed the works to certify these are being practically complete subject to the following defects, and you'll see that in the middle of the page there, Your Honour.
See 'This certificate is issued noting the following incomplete and minor defect items', and then you'll see, Your Honour, what follows in the hundred and - next 148 pages is more than 550 defects. Now, I don't need to take you through them all, Your Honour, but you can see there is a very large number of defects - and this is six or seven months after the original date for practical completion or the date at which the works should have been completed, they're completed very, very late and with many, many defects.
52 The certificate for 'SP 2'[56] was issued on 16 May 2025, certifying completion on 9 May 2025. Counsel for Cardigan explained that this certificate 'crystalises ... entitlements to liquidated damages' - that is to say, 'the certificate for practical completion under the contract, that's the machinery by which the liquidated damages is crystalised.'[57]
53 The Superintendent's Direction − 'Notice - Certification of Liquidated Damages' − was issued by the Project Manager on 16 June 2025. Relevantly, the Superintendent's Direction stated:[58]
Pursuant to Clause 34.7 of the Design and Construct Contract between Cardigan Commercial Pty Ltd (The Principal) and L.U. Simon Builders Pty Ltd (The Contractor) we hereby provide notice of the certification of liquidated damages of $7,221,619.20, with respect to the time period set out below, which is now due and payable to the Principal by the Contractor:
Separable Portion 1:
Adjusted Contract date for Practical Completion: 13th September 2024
Practical Completion Certified: 29th April 2025
Total number of calendar days: 228
Liquidated Damages payable per calendar day as per Annexure A Item 29 minus SP2 LD rate: $31,500.80
SP1 Liquidated Damages Total = $7,182,182.40
Separable Portion 2:
Adjusted Contract date for Practical Completion: 19th February 2025
Practical Completion Certified: 9th May 2025
Total number of calendar days: 79
Liquidated Damages payable per calendar day as per SD No.96: $499.20
SP2 Liquidated Damages Total = $39,436.80
Final overall Liquidated Damages Total = $7,221,619.20
54 In his affidavit, Mr van Grieken referred to the Superintendent's Direction certifying the liquidated damages for SP 1 and SP 2 as being $7,221,619.20, and deposed that:[59]
As at the date of this affidavit,[[60]] the Plaintiff [L.U. Simon] has failed to pay the liquidated damages which it is indebted to the Defendant [Cardigan].
55 Mr Reid deposed that on 24 April 2025, the parties agreed to a 'stand still' arrangement pending a mediation of the parties' disputes under clause 42, however, at the mediation held on 20 August 2025 the matter did not settle.[61]
56 As mentioned earlier, in the period since then, Cardigan has given (and refreshed) an undertaking not to have recourse to the Security pending determination of L.U. Simon's summons seeking injunctive relief.
57 In the present case, L.U. Simon seeks injunctive relief against Cardigan to prevent it from having recourse to the Security (in the form of the two ANZ bank guarantees, each being for the sum of $[redacted]) L.U. Simon provided under the Contract.
58 Counsel for L.U. Simon opened its case by outlining the applicable legal principles. He commenced by referring to Byrne J's 'classic statement of principles' in Rejan _Constructions Pty Ltd v Manningham Medical Centre Pty Lt_d,[62] that 'have been referred to and relied on in a number of important cases and remain good law'.[63]
59 Counsel noted that in Rejan Constructions, his Honour refers to the 1992 version of the standard form contract produced by Standards Australia, which is a precursor to the AS 4902-2000 General Conditions that apply in this case, under which the stated 'purpose of the provision of security is to ensure the due and proper performance by the Contractor of the building contract'.[64] Counsel then focussed on Byrne J's observations on the 'notice' requirement in cl 5.6 of the parties' contract, being the right to recourse which was the equivalent of cl 5.5. of the 1992 version, where his Honour stated, as follows:[65]
. . .
- The drafters of the 1992 version of the Standards Australia contract and of the building contract presently under consideration have demonstrated a great care that the grantor of the security, the Contractor, should not be disadvantaged by inappropriate action against the security by a party in dispute. The evident reason for this is that the maintenance of the security is in effect no disadvantage to either disputant; it simply means that there is a secure fund available to satisfy the Principal's claim when, in due course, it is shown to be well-founded. The exercise by the Principal of rights under cl. 5.6 in the case where no money is later found to be owed to it risks imposing a grave disadvantage upon the Contractor. In the circumstances, I construe the present building contract to oblige the Principal, which wishes to exercise rights under cl. 5.6 as a consequence of an ex-contract liability, to demonstrate that this liability in fact exists. This it may do by agreement or by some authoritative determination whether by judicial order or arbitral award. Until this has been achieved the purpose for the granting of the security expressed in cl. 5.1 is sufficiently achieved by requiring that the security remain in place.
60 Counsel for L.U. Simon then referred to the decision of Judge Ginnane (as his Honour then was) in Mackie Pty Ltd v Republic of Turkey.[66] where the building contract was in the form of AS 2124-1992 but the parties had inserted into cl 5.5 (which dealt with 'Recourse to Retention Moneys and Conversion of Security') the following additional wording which is similar to that found in cl 5.2 in the present case. The additional wording added into cl 5.5 was framed as follows:[67]
"A party is not entitled to commence any proceeding, seeking relief by way of injunction or any other relief, which has as its objective the obtaining of an order preventing the other party from having recourse to retention moneys and/or security even though the party contemplating the commencement of proceedings may assert that there is no right to have recourse to retention moneys and/or security."
61 His Honour observed that the additional wording raises an 'ouster of jurisdiction' issue, stating:[68]
62 Counsel for L.U. Simon pointed to the similarity between the language added to cl 5.5 in Mackie, and the wording in cl 5.2 in the present case, which he submitted is likewise an 'ouster of jurisdiction'.[71] In Mackie, his Honour found that the plaintiff had established a serious question to be tried, being 'whether the defendant is entitled to have recourse to the security and whether the pre-conditions for having access to that security have been established.'[72] Counsel for L.U. Simon observed that:[73]
Of course, that's different from this case because LU Simon says the serious question here relates to the ACL claims and not the satisfaction of any pre-conditions.
63 In Mackie, when Judge Ginnane considered the 'balance of convenience' his Honour again proposed adopting the approach of Byrne J in Rejan Constructions, to the effect that:[74]
The exercise by the Principal of rights under cl. 5.6 in the case where no money is later found to be owed to it risks imposing a grave disadvantage upon the Contractor.
64 In the present case, counsel for L.U. Simon also adopted that approach and elaborated further, stating:[75]
We say that the great disadvantage here is not only the usual disadvantage of having a guarantee cashed and the damage that does to a contractor, but also the fact that this is a project specific property developer and the likelihood of the return of the moneys - - -
65 He explained that the 'usual disadvantage' was that where a building contractor's guarantee is cashed there is 'a reputational issue on its government contract' and the builder has 'to disclose it and explain it and go through loopholes'[76] as discussed in the affidavits of Mr Reid and Mr Devitt.[77]
66 Another case counsel for L.U. Simon relied on in relation to 'ouster of jurisdiction' was CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd,[78] a decision of Le Miere J in the Supreme Court of Western Australia. In that case, under Article 35 of the Subcontract General Terms & Conditions, the Subcontractor agreed to provide irrevocable guarantees by an approved financial institution, referred to in the General Terms as Bank Guarantees. Issues of proper construction arose in respect of two provisions of Article 35.3, which deals with demands by Contractor for payment under the Bank Guarantee. Article 35.3(a) provided for 'recourse' to the Bank Guarantees, as follows:
Contractor may have recourse to the Bank Guarantee(s) at any time in order to recover any amounts that are payable by Subcontractor to Contractor on demand.
67 Article 35.3(b) provided for a waiver of rights on the part of the Subcontractor, as follows:
Subcontractor waives any right that it may have to obtain an injunction or any other remedy or right against any party in respect of Contractor having recourse to the Bank Guarantee(s).
68 At the hearing before Le Miere J, both parties agreed that if cl 35.3(b) was construed according to its ordinary meaning it was an impermissible ouster of the court's jurisdiction and consequently was invalid and unenforceable. However, each of them submitted that the clause was to be read down and interpreted so that it did not effect an ouster, with each party advancing a different submission as to how cl 35.3(b) was to be construed so as to achieve that outcome. In his reasons, Le Miere J conveniently outlined the relevant principles applicable to contractual provisions that seek to oust the jurisdiction of the courts and the basis upon which they are found invalid, as follows:[79]
Impermissible ouster of the jurisdiction of the court
It is common ground that if Article 35.3(b) is construed to have the meaning which it appears to have on its face then it is an impermissible ouster of the court's jurisdiction to grant the only appropriate remedy. Those concessions are properly made.
The general principle is that contracts which seek to oust the jurisdiction of the courts are invalid. On the other hand, limitations placed on the rights and remedies available to the parties have not been treated as an ouster of the court's jurisdiction. In Dobbs v National Bank of Australasia Ltd [1935] HCA 49; (1935) 53 CLR 643 Rich, Dixon, Evatt and McTiernan JJ said that negative restrictions upon the right to invoke the jurisdiction of the courts have always been invalid. Their Honours said at 652:
No contractual provision which attempts to disable a party from resorting to the Courts of law was ever recognized as valid. It is not possible for a contract to create rights and at the same time to deny to the other party in whom they vest the right to invoke the jurisdiction of the Courts to enforce them.
Their Honours said at 652 653:
What no contract can do is take from a party to whom a right actually accrues, whether ex contractu or otherwise, his power of invoking the jurisdiction of the Courts to enforce it.
- In Bateman Project Engineering Pty Ltd v Resolute Ltd [2000] WASC 284 Owen J held that a clause in a contract which provided that the principal was entitled to convert a bank guarantee and the contractor shall not hinder, obstruct, restrain or injunct the principle from doing so was an ouster of the jurisdiction of the court and void as being against public policy. The provision affected one aspect of the contractual rights arising under the contract, namely the right of the plaintiffs to have the guarantee called on only in strict accord with the relevant terms of the contract. While the right to have the overall dispute between the parties adjudicated in the court survived, so far as concerns the guarantee it was defeated. The contractual provision took away from a party to whom a right accrues − his power of invoking the jurisdiction of the courts to enforce it.
- In this case Article 35.3(b) takes away from CPB its right to enforce all and any rights it may have in respect of JKC having recourse to the Bank Guarantees. The provision takes away not only CPB's right to obtain an injunction to restrain JKC from having recourse to the Bank Guarantees unlawfully but also CPB's right to obtain damages, or any other remedy, in respect of JKC's breach of contract in having recourse to the Bank Guarantees in breach of the relevant terms of the Subcontract. The provision takes away CPB's right to compel performance of JKC's contractual obligations in respect of having recourse to the Bank Guarantees. Article 35.3(b) is a provision which ousts the jurisdiction of the court and is void.
69 The subcontractor (CPB) then appealed to the Court of Appeal of the Supreme Court of Western Australia, contending that the primary judge (Le Miere J) had misconstrued the provision entitling the contractor (JKC) to have recourse to the performance bonds. The Court of Appeal dismissed the subcontractor's appeal, stating:[80]
70 The Court of Appeal, when considering the proper construction of cl 35.3(a) (which permits the contractor to have recourse to the Bank Guarantees at any time in order to recover amounts that are payable by the subcontractor to the contractor on demand), referred to and considered the significance of cl 35.3(b) (by which the subcontractor waives any right it may have to seek injunctive relief etc in respect of the contractor having recourse to the Bank Guarantees) and the role it may legitimately play in the process of construction of cl 35.3(a). The Court stated:[81]
71 The subcontractor applied to the High Court for an interim injunction to preserve the status quo pending determination of an application for special leave to appeal from the dismissal by the Court of Appeal. The application was heard before Nettle J but in the result, it was dismissed with costs.[82]
72 I note at this point that, following the approach taken by the courts in the CPB Contractors case, if as L.U. Simon contends, relying upon Mackie and CPB Contractors, cl 5.2(b) of the Contract does effect an ouster of the Court's jurisdiction and as such will not be enforced, it appears to be the case that the Court may nevertheless have regard to cl 5.2(b) in the process of the construction of cl 5.2(a) and of the Contract generally, and also when considering the construction of cl 5.4 and L.U. Simon's claim that 50 per cent of the Security should be returned to it now that the date for Practical Completion has been certified.
73 L.U. Simon pleads that prior to it entering into the Contract, Cardigan represented to it that Cardigan had sufficient funds to pay L.U. Simon the monthly progress payments under the Contract as certified by the Project Manager (the Representation). As matters transpired, however, L.U. Simon says that the Representation was not true, alternatively not correct, as Cardigan did not have sufficient funds to pay L.U. Simon the Contract Sum progressively, as required by the Contract with the result that during the course of the Project Cardigan was unable to make full and/or timely payment amounts owing under the Contract.
74 In essence, L.U. Simon submits that if it had known that Cardigan lacked sufficient funds to pay moneys due under the Contract, it would not have entered into the Contract, and it would have avoided the loss and damage that it has suffered. Counsel for L.U. Simon submitted:[83]
75 Accordingly, L.U. Simon seeks injunctive relief under s 232 of the ACL and in equity.
76 L.U. Simon seeks an injunction under s 232 of the ACL to prevent Cardigan from causing it further loss and damage, arising from its breach of s 18 of the ACL.
77 Section 18 of the ACL is framed as follows:
78 L.U. Simon also relies on s 4 of the ACL insofar as the Representation was as to a future matter.
79 L.U. Simon submits that Cardigan's inability to make payments owing under the Contract became apparent in early to mid-2025. While Mr Fraser deposed to the effect that 'the financing available to Cardigan for the Project was always greater than the Contract Sum payable to LU Simon' and that the financier, PAG, had 'provided funding for construction of at least $[redacted] million'[84], the position was that under the financing arrangements, the funds could be used as follows:[85]
(a) to refinance existing indebtedness secured against the Property;
(b) to fund construction, civil, infrastructure and development costs in respect of the Project; and
(c) for the capitalisation of interest and other fees payable in respect of the financing facilities.
80 In other words, L.U. Simon submits that 'not all of the $[redacted] million that he refers to was available to pay L.U. Simon under the Contract' and if it had been, Cardigan would not have experienced the difficulties it did with making payment to L.U. Simon on a timely basis. In this regard, L.U. Simon refers to the evidence given by Mr Reid, where he refers to the cashflow problems being encountered in late 2024 or early 2025. Mr Reid deposes that when he spoke with Mr Fraser about the lack of funds, he was informed to the effect that 'Cardigan did not have funding to pay for purchaser variations and other adjustments required to be paid by Cardigan under the Contract', and at a later point in time Mr Fraser informed him that '"some of the investors will need to take a hair cut" by which [Mr Reid] understood he meant that the Project was unprofitable and the investors would have to make up for shortfalls.'[86]
81 L.U. Simon submits that that evidence has not been contradicted, and the evidence given by Mr Devitt of L.U. Simon in reply confirms the position.
82 In its statement of claim, at paragraphs 14 to 61, L.U. Simon pleads Cardigan's failure to pay the Progress Claims in full and in a timely way, which it says culminated in L.U. Simon serving on or about 25 and 27 March 2025, two Notices of Intention to Suspend the Works under the Building and Construction Industry Security of Payment Act 2002 (Vic) (Security of Payment Act) 'as it was entitled to do, due to non-payment of scheduled amounts.'[87] Counsel for L.U. Simon explained that because L.U. Simon had insisted on Cardigan making payments to it, 'some adverse action' took place. First, he said, Cardigan arranged to make payment of the (approx.) $1.7 million that was outstanding, and then on 14 May and 6 June 2025 L.U. Simon served two further Notices of Intention to Suspend the Works under the Security of Payment Act due to non-payment of scheduled amounts, and Cardigan arranged for additional funds to pay those amounts in May and June 2025. Meanwhile, however, on Thursday 24 April 2025 (being the day before the ANZAC Day holiday) at 3.01pm, Cardigan 'purported to serve on [L.U. Simon] a notice of intention to have recourse to the Security.'[88]
83 Against that background, L.U. Simon submits that Cardigan's conduct in seeking to have recourse to the Security is unconscionable, contrary to s 21 of the ACL. L.U. Simon relies on the matters pleaded in paragraph [142] of its Statement of Claim, namely:
UNCONSCIONABLE CONDUCT
142. By:
(a) inducing the Contractor [L.U. Simon] by its misleading and deceptive conduct to enter into the Contract when it lacked sufficient finance to pay for the costs of the Project, as set out above;
(b) failing to make progress payments in full and on time, as required by the Contract, as set out above;
(c) instructing the Contractor (via its agent the Project Manager) to carry out the Purchaser Changes, and then not paying for same, as set out above;
(d) failing to ensure that its agent (the Project Manager) at all times acted reasonably when assessing claims for EOT and/or in respect of the exercise of the Reserve Power, as set out above[[89]];
(e) threatening to have recourse to the Security late in the afternoon on the day before a long weekend, making it impossible for the Contractor to have a hearing in a court or tribunal during working hours;
(f) having recourse to the Security which would cause a substantial prejudice to the Contractor:
the Principal has acted unconscionably, alternatively proposes to act unconscionably, in contravention of s 21 of the ACL (Cth).
84 During oral submissions, counsel for L.U. Simon said 'We put it this way' ─[90]
Cardigan couldn't pay in March after the discussions at the café and the haircut discussion when they said they couldn't fund it. When LU Simon said, 'Well we want payment', and they served the notice under the Act, and this was before practical completion, what the developer did was to say in effect, 'Oh well, we'll have your guarantees for 2.5 million.' From LU Simon's perspective, what that means is you want to be paid? All right. We'll cash your guarantee. You can be paid.
From the perspective of commercial morality, Your Honour, we say that that was a provocative act. It's a very serious matter to cash a bank guarantee as the cases demonstrate. We've now completed practical completion. There's some [quibbling] in the affidavit last night as to whether that's been completed. Mr Reid in his affidavit answers those issues. We should have half of it back by now, but they've retained it and they say we're not entitled to it even if - as I understand it, their argument is because they claimed it before - because they gave notice before practical completion. That's a right that crystalises in them to have it even after practical completion.
85 Counsel for L.U. Simon also confirmed during oral submissions that it is only statutory unconscionable conduct that is alleged against Cardigan - and not unconscionable conduct within the meaning of the unwritten law under s 20.[91] That is to say, L.U. Simon submits it is entitled to relief under s 21, which prohibits a person from engaging in unconscionable conduct more generally in connection with the supply or possible supply or acquisition or possible acquisition of goods or services.
21 Unconscionable conduct in connection with goods or services
(1) A person must not, in trade or commerce, in connection with:
(a) the supply or possible supply of goods or services to a person; or
(b) the acquisition or possible acquisition of goods or services from a person;
engage in conduct that is, in all the circumstances, unconscionable.
(2) This section does not apply to conduct that is engaged in only because the person engaging in the conduct:
(a) institutes legal proceedings in relation to the supply or possible supply, or in relation to the acquisition or possible acquisition; or
(b) refers to arbitration a dispute or claim in relation to the supply or possible supply, or in relation to the acquisition or possible acquisition.
(3) For the purpose of determining whether a person has contravened subsection (1):
(a) the court must not have regard to any circumstances that were not reasonably foreseeable at the time of the alleged contravention; and
(b) the court may have regard to conduct engaged in, or circumstances existing, before the commencement of this section.
(4) It is the intention of the Parliament that:
(a) this section is not limited by the unwritten law relating to unconscionable conduct; and
(b) this section is capable of applying to a system of conduct or pattern of behaviour, whether or not a particular individual is identified as having been disadvantaged by the conduct or behaviour; and
(c) in considering whether conduct to which a contract relates is unconscionable, a court's consideration of the contract may include consideration of:
(i) the terms of the contract; and
(ii) the manner in which and the extent to which the contract is carried out;
and is not limited to consideration of the circumstances relating to formation of the contract.
87 Section 22 provides a list of matters the Court 'may have regard to' for the purposes of s 21, as set out below:
22 Matters the court may have regard to for the purposes of section 21
(1) ...
(2) Without limiting the matters to which the court may have regard for the purpose of determining whether a person (the acquirer) has contravened section 21 in connection with the acquisition or possible acquisition of goods or services from a person (the supplier), the court may have regard to:
(a) the relative strengths of the bargaining positions of the acquirer and the supplier; and
(b) whether, as a result of conduct engaged in by the acquirer, the supplier was required to comply with conditions that were not reasonably necessary for the protection of the legitimate interests of the acquirer; and
(c) whether the supplier was able to understand any documents relating to the acquisition or possible acquisition of the goods or services; and
(d) whether any undue influence or pressure was exerted on, or any unfair tactics were used against, the supplier or a person acting on behalf of the supplier by the acquirer or a person acting on behalf of the acquirer in relation to the acquisition or possible acquisition of the goods or services; and
(e) the amount for which, and the circumstances in which, the supplier could have supplied identical or equivalent goods or services to a person other than the acquirer; and
(f) the extent to which the acquirer's conduct towards the supplier was consistent with the acquirer's conduct in similar transactions between the acquirer and other like suppliers; and
(g) the requirements of any applicable industry code; and
(h) the requirements of any other industry code, if the supplier acted on the reasonable belief that the acquirer would comply with that code; and
(i) the extent to which the acquirer unreasonably failed to disclose to the supplier:
(i) any intended conduct of the acquirer that might affect the interests of the supplier; and
(ii) any risks to the supplier arising from the acquirer's intended conduct (being risks that the acquirer should have foreseen would not be apparent to the supplier); and
(j) if there is a contract between the acquirer and the supplier for the acquisition of the goods or services:
(i) the extent to which the acquirer was willing to negotiate the terms and conditions of the contract with the supplier; and
(ii) the terms and conditions of the contract; and
(iii) the conduct of the acquirer and the supplier in complying with the terms and conditions of the contract; and
(iv) any conduct that the acquirer or the supplier engaged in, in connection with their commercial relationship, after they entered into the contract; and
(k) without limiting paragraph (j), whether the acquirer has a contractual right to vary unilaterally a term or condition of a contract between the acquirer and the supplier for the acquisition of the goods or services; and
(l) the extent to which the acquirer and the supplier acted in good faith.
88 Here, L.U. Simon also relies on Cardigan's (alleged) misleading and deceptive conduct as a predicate for, or foundation of, the unconscionable conduct alleged. In that regard, it is also relevant to note that s 22A of the ACL (headed 'Presumptions relating to whether representations are misleading') provides that:
22A Presumptions relating to whether representations are misleading
Section 4[[92]] applies for the purposes of sections 21 and 22 in the same way as it applies for the purposes of Division 1 of Part 3-1.
89 Section 232 provides for injunctive relief to be granted by a court, if the court is satisfied that a person has engaged in contravening conduct. Relevantly, s 232 is framed as follows:
(1) A court may grant an injunction, in such terms as the court considers appropriate, if the court is satisfied that a person has engaged, or is proposing to engage, in conduct that constitutes or would constitute:
(a) a contravention of a provision of Chapter 2, 3 or 4;[[93]] or
(b) attempting to contravene such a provision; or
(c) aiding, abetting, counselling or procuring a person to contravene such a provision; or
(d) inducing, or attempting to induce, whether by threats, promises or otherwise, a person to contravene such a provision; or
(e) being in any way, directly or indirectly, knowingly concerned in, or party to, the contravention by a person of such a provision; or
(f) conspiring with others to contravene such a provision.
(2) The court may grant the injunction on application by the regulator or any other person.
(4) The power of the court to grant an injunction under subsection (1) restraining a person from engaging in conduct may be exercised:
(a) whether or not it appears to the court that the person intends to engage again, or to continue to engage, in conduct of a kind referred to in that subsection; and
(b) whether or not the person has previously engaged in conduct of that kind; and
(c) whether or not there is an imminent danger of substantial damage to any other person if the person engages in conduct of that kind.
(5) Without limiting subsection (1), the court may grant an injunction under that subsection restraining a person from carrying on a business or supplying goods or services (whether or not as part of, or incidental to, the carrying on of another business):
(a) for a specified period; or
(b) except on specified terms and conditions.
(6) Without limiting subsection (1), the court may grant an injunction under that subsection requiring a person to do any of the following:
(a) refund money;
(b) transfer property;
(c) honour a promise;
(d) destroy or dispose of goods.
(7) The power of the court to grant an injunction under subsection (1) requiring a person to do an act or thing may be exercised:
(a) whether or not it appears to the court that the person intends to refuse or fail again, or to continue to refuse or fail, to do that act or thing; and
(b) whether or not the person has previously refused or failed to do that act or thing; and
(c) whether or not there is an imminent danger of substantial damage to any other person if the person refuses or fails to do that act or thing.
90 L.U. Simon submits that, as is evident from the text of s 232(1), the purpose of an injunction granted under s 232 'is to prevent contraventions of the ACL', both past and present, and its purpose is 'not confined to merely preventing conduct, but also preventing loss and damage.'[94] It says that the power under s 232 would, in the present case, extend to 'prevent Cardigan from engaging in conduct which, if persisted in, will contravene s 21 of the ACL, and to prevent further loss and damage being caused to LU Simon, arising from Cardigan's breach of s 18 of the ACL.'
91 Section 234 empowers a court to make an interim injunction pending the determination of an application for an injunction made under s 232, as follows:
(1) If an application is made under section 232, the court may, if it considers it is desirable to do so, grant an interim injunction under this subsection pending the determination of the application.
(2) If a responsible Minister or the regulator made the application under section 232, the court must not require the applicant or any other person to give any undertakings as to damages as a condition of granting the interim injunction.
(3) If:
(a) in a case to which subsection (2) does not apply the court would, but for this subsection, require a person to give an undertaking as to damages or costs; and
(b) a responsible Minister gives the undertaking;
the court must accept the undertaking by the responsible Minister and must not require a further undertaking from any other person.
[Section] 232 (and by extension s 234) provides the Court with the widest possible injunctive powers, devoid of traditional constraints, though the power must be exercised judicially and sensibly.[96]
93 L.U. Simon acknowledges that s 234 addresses the grant of an 'interim injunction', which is sought and made pending the determination of an application for an injunction under s 232.
As a Certificate of Practical Completion has issued for 'SP 2', L.U. Simon now seeks to have 50% of the Security returned to it
94 L.U. Simon now claims that pursuant to cl 5.4 of the AS 4902-2000 General Conditions, Cardigan's entitlement to the Security is reduced by 50% upon the issue of a Certificate of Practical Completion for the last separable portion comprising the Works and satisfaction of the conditions set out in cl 5.4.
95 Relevantly, with the Project Manager having, on or about 9 May 2025, issued a Certificate of Practical Completion under the Contract in respect of 'SP 2', it submits that:[97]
LU Simon has satisfied the conditions for the return and release of its security pursuant to clause 5.4 and Friday, 11 July 2025 [being, the last of the specified events to occur] has now passed. Accordingly, Cardigan is no longer is entitled to retain 50% of the Security held by it pursuant to the Contract and is required to release that Security to LU Simon.
L.U. Simon contends cl 5.2 is an 'ouster' clause and cannot be relied on by Cardigan to prevent it obtaining 'meaningful [injunctive] relief' under the ACL
96 L.U. Simon anticipates that Cardigan will seek to rely on the fact that cl 5.2(b)(ii) of the Contract establishes a 'pay now, argue later' regime. But, L.U. Simon contends that 'such a clause is an ouster of the jurisdiction of the Court'[98] and the Court is not foreclosed from granting injunctive relief, as Judge Ginnane (as he then was) did in Mackie Pty Ltd v Republic of Turkey.[99] where the contract had a similar clause. Further, counsel for L.U. Simon submitted, a 'pay now, argue later' clause 'cannot be relied on to oppose an injunction to restrain a breach of the Australian Consumer Law, or to avoid further losses arising from a breach of the Australian Consumer Law' and 'Cardigan cannot rely on a clause of the Contract to prevent LU Simon obtaining meaningful relief under s 232 of the Australian Consumer Law.'[100] However, no authority is cited in support of that submission.
L.U. Simon says if Cardigan has recourse to the Security this will cause prejudice to L.U. Simon
97 Mr Reid deposes that if Cardigan has recourse to the Security this will cause prejudice to L.U. Simon, in that: [101]
(a) LU Simon will suffer reputational damage with its financiers; and
(b) LU Simon will suffer reputational damage and may lose government work as all government tenders require LU Simon to state whether it has ever had any of its security cashed.
98 Further, Mr Reid deposes to the effect that 'Cardigan lacks financial resources'[102] and, 'if it receives the money from the Security, then that money will likely be disbursed offshore to either its financiers or investors or to pay off debts',[103] rendering it unlikely that Cardigan will be able to repay that money.
Cardigan contends that L.U. Simon has failed to make out any proper basis to restrain Cardigan's recourse to the Security
99 As noted earlier, Cardigan's case is simply that the Contract establishes a 'pay now, argue later' regime, a matter which L.U. Simon expressly acknowledges. Cardigan contends that '[i]t is well settled that under such a regime, recourse to security will not be restrained on an interlocutory basis absent proof of fraud or unconscionability.[104]'[105] Cardigan submits that as neither has been established by L.U. Simon, its application for injunctive relief should be dismissed with costs.
Contractual status quo as to certified liabilities
100 Counsel for Cardigan commenced by focusing attention on the contractual status quo as to certified liabilities of the respective parties under the Contract.
101 In the case of Cardigan, counsel pointed to the fact that on 16 June 2025, the Project Manager issued a Superintendent Direction providing 'notice of the certification of liquidated damages of $7,221,619.20,' with respect to the time period of 307 days (SP 1 228 days and SP 2 79 days), 'which is now due and payable to [Cardigan] by [L.U. Simon]. Cardigan contends that subject to the giving of three days' notice, its right to call on the Security is otherwise unfettered by cl 5.2 of the AS 4902-2000 General Conditions, and it says there is 'no dispute,[106] that immediate right vested on 27 April 2025, following the delivery to LU Simon of a notice to have recourse to that Security on 24 April 2025.[107]'[108]
102 In the case of L.U. Simon, Cardigan contends the position is:[109]
• the Project Manager has assessed L.U. Simon's EOT Claims for SP1 of 46 Days as "0" and SP2 of 8 Days as "0"[110];
• L.U. Simon's variation claims have been assessed by the Project Manager and those assessments have been paid.[111] (No collusion between the Project Manager and Cardigan is alleged); and
103 Further, Cardigan says that even if the claims advanced by L.U. Simon are bona fide, (which is not admitted but denied, for the reasons outlined in the Fraser Affidavit),[114] 'the existence of such a dispute provides no basis for restraining Cardigan's right to have recourse to the Security in the way the parties agreed.[115]'[116]
104 Cardigan submits that it is plain from the evidence that L.U. Simon, being a highly sophisticated commercial party, 'suffered from no special disability or inequality in bargaining power.'[117] On the contrary, it says the evidence, and in particular the negotiation of the Builder's Side Deed[118], 'confirms that LU Simon had equal or better bargaining power, insisting on and obtaining the terms of the contract it required to protect its interests.'[119] Further, Cardigan observes that:[120]
none of the factors recited by s.22 of the Australian Consumer Law (ACL) are said to be relied by on by LU Simon to even attempt to demonstrate statutory unconscionability under s.21 of the ACL, nor, on the evidence, could there be.
105 Cardigan takes issue with the purported relevance of L.U. Simon's reliance upon Cardigan's failure to disclose that it had earlier been placed in external administration, submitting that:[121]
106 Further, counsel for Cardigan contended:[126]
Lastly, it beggars belief, for example, that a reasonable person in the position of LU Simon,[127] when entering into a $50M+ contract with a private company, would not have taken the most basic of steps to protect its interests of obtaining an ASIC extract of the company it is about to contract with.[128]
107 Counsel for Cardigan submits that in a case such as the present, when considering whether to grant an application for an interlocutory injunction it is necessary for the Court to resolve the proper construction of the relevant clause.[129] However, he observed that in the present case 'we don't have to worry about that in this context because we know that it is a risk allocation applies'[130] - given the earlier concession made by counsel for L.U. Simon at the commencement of oral submissions.
108 Here, Cardigan submits that the 'pay now, argue later' regime the parties agreed upon (adapting the language used by Whitby J in Primero) 'informs the manner in which the court goes about determining the application' − and 'necessitates a different approach' to that which would ordinarily be taken on an application for an interlocutory injunction - because the regime 'alters the "status quo" for the purposes of an interlocutory application such that the parties have agreed that LU Simon is to bear the financial risk pending the final determination of, for example, its EOT and variation claims.[131]'[132] In those circumstances, Cardigan contends that once that construction question is resolved, L.U. Simon's application for injunctive relief is to be dismissed.
109 Cardigan does acknowledge, however, that there are two exceptions to that general proposition - an exception in the case of fraud - but counsel says 'there's been no assertion of fraud, nor could there be.'[133] A second exception that has been recognised is 'unconscionability in having access to the security.'[134] In the present case, Cardigan's solicitors notified the solicitors for L.U. Simon later on the day of issue of the notice that their client has no basis to apply for an injunction, because 'the law is well settled that a court will not grant an injunction to restrain payment under a guarantee except if one of three recognised exceptions applies' and added that '[n]one of those exceptions applies here.'[135] (The third exception referred to is when the exercise of the right of recourse is subject to a condition, and as counsel observed, 'there's no condition in this clause, other than the giving of the notice.)
110 Counsel for Cardigan described L.U. Simon's case as being misconceived and as appearing to be 'a lawyer's construct to try and dance around a very well-established principles recognised by numerous Courts of Appeal.'[136] As for L.U. Simon's 'attempt to invoke a s18, misleading and deceptive conduct claim,' counsel observed 'precisely how it's relevant, is completely left unexplained... nor is it supported in any of the 30 odd years of authorities that one can bring a claim under s18 and somehow that gives rise to [an] injunction.'[137] Further, he submitted, despite L.U. Simon having confined its unconscionable conduct case to s 21 of the ACL 'nowhere in the last 30 years has anyone extended that proposition to s18, ... and no case in the last 30 years has found an injunction relying on s21.'[138] Counsel added that in a couple of cases 'it's been argued that s21 applied, but in each of those cases the evidence failed to establish unconscionability.'[139]
Court's jurisdiction to grant an interim injunction under the ACL is subject to the same principles that govern the grant of interlocutory injunctions generally
111 Cardigan submits that the jurisdiction conferred on the Court under s 232 of the ACL is in respect of final injunctions, whereas the power to order interim injunctions is provided by s 234. (As noted earlier, L.U. Simon now agrees with that position.)
112 Cardigan contends that the exercise of the power under s 234 is 'governed by the same principles' as those that govern the grant of interlocutory injunctions generally[140] and is directed to preventing or reducing 'the likelihood of future contraventions of relevant provisions of ACL.'[141] It submits that '[t]he power provided by s.232 and s.234 is not for the purpose relied on by LU Simon.'[142]
113 Cardigan contends there is no evidence of any unconscionable conduct. In essence, Cardigan submits that it was entitled to issue a notice to call on and have recourse to the Security on 24 April 2025, because the Works had not reached Practical Completion (having been delayed by L.U. Simon for seven months at that point) with liquidated damages running at (the agreed figure of) $32,000 per day, such that L.U. Simon was indebted to Cardigan for liquidated damages of $6,784.000.[143] Further, when the Certificate of Practical Completion for 'SP 1' issued on 1 May 2025, certifying that the Works for SP 1 'have reached the stage of Practical Completion at 4pm on Tuesday 29th April 2025' it noted 'the following incomplete works and minor defect items' (listed in Appendix A).[144] Counsel for Cardigan observed that Appendix A occupies some 148 pages and lists more than 550 defects.[145]
[MR HARRIS:] ...So, that crystalises, Your Honour, entitlements to liquidated damages, the certificate for practical completion under the contract, that's the machinery by which the liquidated damages is crystalised and you'll see, if we can go back to p20 of the exhibit, and you'll see that's the superintendent's direction there in relation to liquidated damages, do you see that in the subject, note the certification of liquidated damages. And you'll see that they're certified, Your Honour, as a total of $7.2m-odd. So, that's the status quo, Your Honour, in relation to this project.
HER HONOUR: What's the date of issue, 16 June.
MR HARRIS: 16th June, Your Honour. So, unlike what often happens in these security cases, Your Honour, where the person calling the security is asserting a claim which is - has not been certified, but they're contending that it is a claim that they're entitled to be paid and they're going to call the security, this is a claim in which we are certified as being entitled to liquidated damages, certified that the works are defective at particular dates.
115 Counsel for Cardigan further clarified the position a little later, stating:[148]
MR HARRIS: So, separable portion 1, Your Honour, was certified on 1 May to be 29 April, so it's a retrospective certification, if I can put it that way. And then separable portion no.2, which is the document at 172, is also certified retrospectively on the 16th to have occurred on 9 May. Now what that crystalises, Your Honour, is an entitlement, as at those dates, to 7.2 million in liquidated damages, which makes the deficit even more, that we are not secured against.
116 In those circumstances, it would appear that the 'Notice of Intention to have Recourse to the Security' letter Cardigan gave to L.U. Simon on the afternoon of 24 April 2025 was proleptic, in that it anticipated the crystallisation of its claim for liquidated damages but as at 24 April 2025 its entitlement had not crystallised.
117 As to the contractual status quo, L.U. Simon 'disputes that Cardigan has a right to have recourse to the Security.[149] It also disputes the Project Manager's assessment of its claims for EOT, which it says are supported by the TBH expert report on delays (prepared by Mr Andy Chew of Tracey Brunstrom & Hammond).[150]
118 L.U. Simon submits that the fact that Cardigan was earlier placed in external administration 'is relevant to establish that it is a company which has experienced financial issues in the past, and that if it has recourse to the Security, it is unlikely that L.U. Simon will be able to recover the Security should the Court make an order for return of the Security after the trial.'[151]
119 Further, it says the evidence is that L.U. Simon did not conduct a company search of Cardigan, and '[g]iven that it was a company represented by Norton Rose Fulbright, appeared on the title, and appeared to have finance for the project, there would not be any need to [do so].[152]
120 As to its claim for unconscionable conduct, L.U. Simon submits s 21 of the ACL is not limited by the unwritten law relating to unconscionable conduct.[153] It says that 'Cardigan's conduct in seeking to have recourse to the Security is unconscionable, contrary to s 21 of the ACL.'[154] It also relies on Cardigan's (alleged) misleading or deceptive conduct.[155]
121 L.U. Simon submits that the purpose of an injunction that is granted on an interim basis under s 234 'is to preserve the status quo or prevent further loss and damage, pending the determination of an application under s 232.'[156] In the case of an injunction sought under s 232, it says the purpose is to prevent contraventions of the ACL, including past contraventions, and 'is not confined to merely preventing conduct, but also preventing loss and damage.'[157]
123 L.U. Simon submits that 'the case turns on L.U. Simon's ACL claims' and 'it is clear that a remedy is available under s 232 for relief against Cardigan's threat to have recourse to the Security.'[161]
124 As to the construction of cl 5.2, L.U. Simon reiterated:[162]
125 In relation to L.U. Simon's claim to have 50% of the Security returned to it, counsel for L.U. Simon submitted that:[164]
• there is no dispute that Practical Completion has been achieved and certified by the Project Manager;
• Cardigan has not issued any notice disputing the validity of the Project Manager's certification, nor is there a dispute raised in Cardigan's submissions;
• L.U. Simon has issued a Deed of Release for SP 1 and SP 2;[165]
• to the extent that Mr Fraser has given evidence that the Project Manager has informed him that L.U. Simon has not provided all operational manuals or morals rights consents, that evidence is 'vague'; and
• Mr Reid has given evidence about L.U. Simon satisfying the requirements in Cl 5.4.[166]
126 Accordingly, it contends that pursuant to cl 5.4 of the AS 4902-2000 General Conditions, 'Cardigan's entitlement to the Security is reduced by 50% and it should return half the security.'[167]
127 L.U. Simon makes no argument about the proper construction of cl 5.2. While it does not say so expressly, it effectively acknowledges that under cl 5.2 the ANZ bank guarantees given to Cardigan are provided both by way of security and as a risk allocation device, and L.U. Simon does not suggest that Cardigan has failed to satisfy any pre-condition for the right to have recourse to the Security. Rather, counsel for L.U. Simon contends that the 'serious question' that arises here 'relates to the ACL claims and not the satisfaction of any pre-conditions'[168] and submits that 'whatever LU Simon agreed to in the contract must come second to the ACL claims because it never contracted to permit itself to be misled or treated in the manner that we contend [it was].'[169]
128 Given the concession made by L.U. Simon, Cardigan also agrees it is not necessary for the Court to resolve the proper construction of the clause.
129 Notwithstanding that neither party has encouraged me to express any view about the proper construction of cl 5.2, I nevertheless propose to do so. That is because, given the observations made by Osborn and Ferguson JJA in Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd,[170] it is necessary for the court to construe the recourse clause in order to identify the criteria by reference to which Cardigan's entitlement under the Contract to seek recourse to the bank guarantees is to be assessed, and whether that right of recourse is affected by (alleged) unconscionable conduct of the kind contended for by L.U. Simon.
There are broadly two reasons why the beneficiary may have stipulated for a guarantee. One is to provide security. If it has a valid claim and there are difficulties about recovering from the party in default, it has recourse against the bank. The second reason, which is additional to the first, is to allocate the risk as to who shall be out of pocket pending resolution of a dispute. The beneficiary is then able to call upon the guarantee even if it turns out, in the end, that the other party was not in default.[173] It is a question of construction of the underlying contract whether the guarantee is provided solely by way of security or also as a risk allocation device. Remembering that we are speaking of guarantees in the sense of standby letters of credit, performance bonds, guarantees in lieu of retention moneys and the like, the latter purpose is often present and commercial practice plays a large part in construing the contract.
131 Performance bonds such as unconditional bank guarantees of the kind required under the Contract in this case are generally regarded by the courts as creating 'a type of currency'[174] and as being, 'as good as cash'[175].[176] A contract stipulating for or incorporating an unconditional guarantee may, depending on its terms, create a 'pay now, argue later' regime.[177]
132 Where a party to a contract that includes a risk allocation regime approaches the Court seeking injunctive relief directed to restraining reliance by a beneficiary upon a bank guarantee or performance bond, the court must be vigilant to ensure it does not frustrate the parties' agreed commercial purpose by preventing use of the risk allocation mechanism agreed between them.[178]
133 In Sugar Australia, the Court of Appeal agreed with the view expressed by Charles and Callaway JJA in Fletcher Construction, and explained the approach that is to be taken by a court in cases where a decision is required to be made as to whether a party should be enjoined from accessing security prior to a final determination of rights. In a joint judgment, Osborn and Ferguson JJA, outlined the approach, stating:[179]
It follows that if a party in whose favour a bank guarantee has been given has bound itself to a contractual fetter or qualification under which that party promises not to call upon the guarantee in the circumstances defined, breach of that contractual promise, or a threatened breach, may be enjoined by applying the usual principles relating to the enforcement by injunction of negative stipulations in contracts.[180]
Whilst it may be accepted that the usual principles governing interlocutory injunctions fell to be applied in the present case, it must also be accepted that they fell to be applied in respect of an unusual form of contract, if it be the case that the commercial purpose of the performance bond was to allocate risk pending final determination of the dispute. Such a contractual provision fundamentally alters the context in which the Court must exercise its discretion by changing the complexion of the status quo and raising the prospect of substantial injustice if the purpose of the provision is defeated. That is, the status quo in such circumstances becomes what the parties have agreed as to which of them should bear the financial risk pending final determination, not the continuation of where that risk would naturally fall in the absence of a performance bond to call upon.
...
If the commercial purpose of a contractual provision is defeated that must bear squarely on the ultimate risk of injustice inherent in the grant of an injunction. In Bradto Pty Ltd v State of Victoria,[181] the Court of Appeal constituted by Maxwell P and Charles JA applied the following statement of fundamental principle by Hoffman J in Films Rover International Ltd v Cannon Films Sales Ltd:
... The principal dilemma about the grant of interlocutory injunctions, whether prohibitory or mandatory, is that there is by definition a risk that the court may make the 'wrong' decision, in the sense of granting an injunction to a party who fails to establish his right at the trial (or would fail if there was a trial) or alternatively, in failing to grant an injunction to a party who succeeds (or would succeed) at trial. A fundamental principle is therefore that the court should take whichever course appears to carry the lower risk of injustice if it should turn out to have been 'wrong' in the sense I have described ...[182]
134 The courts have also observed in this context that in determining whether the underlying contract confers an unfettered right to call upon the performance bond or guarantee, 'the importance of such instruments in the construction industry both nationally and internationally is a factor which bears upon the question of construction of the contract.'[183]
135 In Uber Builders and Developers Pty Ltd v MIFA Pty Ltd, Nichols J summarised the position that applies where injunctive relief is sought to restrain a beneficiary having recourse to security, as follows:[184]
(m) ... Where the contract does impose a condition on the right to access the security, the party seeking to restrain recourse must establish the existence of a serious question to tried as to whether the beneficiary has in fact met the contractual requirements.[185]
(n) Even when there is no contractual condition or fetter on a beneficiary's right to call on security, courts will enjoin a party in whose favour the performance guarantee has been given from acting fraudulently or unconscionably in calling on the security. ...
Construction of the contractual provisions re Contractor's provision of 'Security' and Principal's right to 'Recourse'
136 The relevant contractual provisions pertaining to the provision of the Security and the Principal's right to 'Recourse' have been set out in full earlier in these Reasons. In the present case, as Whitby J observed of the relevant 'recourse' clause in Primero Group Ltd v Coburn Resources:[186]
The use of the word 'recourse' is important in construing each of the subclauses which follow. The ordinary meaning of the word 'recourse' in this context is the legal right to demand payment. The use of the word 'recourse' in the heading of and chapeau to [the clause] is consistent with a purpose of the Security being to permit the defendant to have recourse to the Security on the terms provided for in the Security, those being on demand and without notice to the plaintiff.
137 While the contract in the present case differs from that under consideration in Primero, − in that cl 5.1 states the purpose of the Security and performance undertakings as being 'for the purpose of ensuring the due and proper performance of the Contract.' and cl 5.2 provides for the giving of three days' notice to the Contractor − I do not regard the presence of the notice provision as detracting from the notion that the purpose of the Security is to ensure the due and proper performance of the Contract and permit the Principal to have recourse to the Security on the terms provided for, as contemplated in cl 5.2. (In that regard, it will be recalled that the reason for the introduction of a notice provision in the 1992 version of the AS General Conditions of Contract was explained by Byrne J in Rejan Constructions.[187])
138 The 'Security' is defined in cl 1 of the AS 4902-2000 General Conditions to mean an 'unconditional undertaking in a form approved by the Principal ... given by [a listed bank or financial institution].
139 Clause 5.2(a) provides that subject to the Principal giving 3 days' prior written notice of its intention to have recourse to the Security 'the Principal may convert all or part of the Security into cash at any time and use the proceeds of the Security:[188]
(i) in relation to any debt or money due or claimed to be due from the Contractor to the Principal under the Contract (including liquidated damages under subclause 34.7) or any cost, expense, loss or damage of any kind which the Principal has incurred or claims that it has incurred or might in the future incur in connection with what the Principal contends constitutes any act, default or omission of the Contractor; or
(ii) whenever the Principal is otherwise permitted to do so in accordance with the terms of the Contract, or if an event described in subclause 39.11 occurs in respect of the Contractor.
140 As will be noted, cl 5.2(a) does not impose any certification requirement as a precursor to the Principal giving notice of an amount claimed to be due, or any deemed indebtedness, and it permits the Principal to convert the Security or part of it 'at any time'.
141 In the present case, the Principal's Notice of Intention to have Recourse to Security was given under cover of its letter dated 24 April 2025, in respect of claimed indebtedness for 'Liquidated Damages' under cl 34.1 in the sum of $6,784,000.00, calculated for a period of 'no less than 212 days' at the Liquidated damages rate agreed under the Contract at '$32,000 per day'[189].[190]
142 Clause 34.7, which deals with 'Liquidated damages', is not reproduced earlier, and is set out below:
(a) If WUC does not reach Practical Completion by the Date for Practical Completion, the Contractor shall be indebted to the Principal, for liquidated damages at the rate stated in Annexure Part A for every day after the Date for Practical Completion to and including the earliest of the Date of Practical Completion or termination of the Contract or the Principal taking the whole of the remaining WUC out of the hands of the Contractor.
(b) The Contractor's maximum aggregate liability for liquidated damages under this subclause 34.7 will not exceed the Liquidated Damages Cap.
(c) If an EOT is directed after the Contractor has paid or the Principal has set off liquidated damages, the Principal shall forthwith repay to the Contractor such of those liquidated damages as represent the days the subject of the EOT.
(d) The Contractor acknowledges that all sums payable by the Contractor to the Principal under this subclause 34.7 represent the Principal's genuine pre-estimate of the damages likely to be suffered by it if the Works do not reach Practical Completion by the Date for Practical Completion and such sums shall not be construed as a penalty.
(e) If liquidated damages are found to be void, voidable or unenforceable in any way or on any basis so that the Principal is not entitled to claim or recover liquidated damages for the Contractor's failure to reach Practical Completion by the Date for Practical Completion, the Principal is entitled to claim and recover general law damages if the Contractor fails to reach Practical Completion by the Date for Practical Completion.
(f) If Annexure Part A is completed so as to indicate that liquidated damages do not apply to the Contract (for example by the use of the words "Nil" or "Not applicable" or similar), then the Principal's right to claim general damages at law from the Contractor in connection with delay by the Contractor (including in achieving Practical Completion) is preserved however the Contractor's liability for damages will accrue at a rate not exceeding the rate for liquidated damages stated in Annexure Part A and will not exceed the Liquidated Damages Cap.
143 The term 'Liquidated Damages Cap' is defined in cl 1 to mean '20% of the Contract Sum' (the Contract Sum being the 'lump sum amount of $51,707,571.20 (excluding GST) ... as per cl 4.1 of the Formal Instrument of Agreement).[191]
144 L.U. Simon does not suggest that there was any precondition to the giving of the notification under cl 5.2(a) that was required to be satisfied by Cardigan other than the three days' notice, and it acknowledges that the requisite notice was given. Nor does counsel for L.U. Simon point to any other provision of the Contract that is relevant to the construction of the 'recourse provision'.
145 In the period since the notification was given, the Project Manager has issued, on 16 June 2025, The Superintendent's Direction − 'Notice - Certification of Liquidated Damages' in which it provided notice of the certification of liquidated damages for SP 1 and SP 2 in the sum of $7,221,619.20 with respect to the relevant time periods. [192]
146 Clause 5.2(b) of the AS 4902-2000 General Conditions, which purports to restrict the right of the Contractor to take steps to injunct or otherwise restrain the Principal from (inter alia) receiving payment under any Security, is framed as follows:[193]
(b) The Contractor must not take any steps to injunct or otherwise restrain:
(i) any issuer of any Security provided under subclause 5.1 from paying the Principal under that Security;
(ii) the Principal from taking any steps for the purposes of making a demand under any Security or receiving payment under any Security; or
(iii) the Principal using the money received under any Security;
even where the Contractor disputes the Principal's right to payment (including where dispute resolution proceedings have been commenced under this Contract).
147 L.U. Simon submitted that this purported restraint on the Contractor is an ouster of the jurisdiction of the Court'[194] and the Court is not foreclosed from granting injunctive relief, as Judge Ginnane (as he then was) did in Mackie Pty Ltd v Republic of Turkey.[195] where the contract had a similar clause.
148 Even if that submission be correct, and the clause is not enforceable, it is clear that the restraint clause is not regarded as being void, and regard may nevertheless be had to cl 5.2(b) in the process of the construction of cl 5.2(a) and of the Contract generally. As the Western Australian Court of Appeal stated in CPB Contractors (No 2) 'a finding that [a restraint clause] ousts the court's jurisdiction does not require that [the restraint clause] be ignored in the process of construction of [the recourse clause]'.[196] Further, the Court of Appeal was of the view that it is nevertheless appropriate to take a restraint clause into account when construing a companion clause such as the recourse clause, because '[c]ontractual prohibitions or limits on seeking an injunction restraining a party's recourse to a performance bond may shed light on the purpose of the right to recourse.'[197]
149 In CPB Contractors (No 2), the Court had regard to the restraint clause in GC 35.3(b) when construing the companion provision in GC 35.3(a), and stated:[198]
150 In my view, when cl 5.2(a) and cl 5.2(b) of the present Contract are construed together, it is clear that the object of the provision of the Security in the present case, by requiring the Contractor to provide two unconditional ANZ bank guarantees to the Principal, was to establish a 'pay now, argue later' regime as a risk allocation mechanism. That position is reinforced by the express provision in cl 5.1 that '[t]he Contractor is not entitled to claim or be paid any moneys until the Security has been delivered to the Principal.'[199] That is to say, the requirement (in cl 5.1) that the Contractor provide the Security (in the form of an unconditional bank guarantee) to the Principal before the Contractor may claim any entitlement to be paid, when read together with the Principal's right to convert all or part of the Security into cash at any time and use the proceeds of the Security upon giving 3 days' notice of its intention to do so, makes clear that the provision of Security is intended to allocate risk pending the determination of the parties' rights. Further, in my view, when regard is had to the terms of the restraint imposed on the Contractor under clause 5.2(b), it confirms that the object of the provision of the Security is to allocate risk between the parties pending final resolution of any dispute between them.
151 Once it is accepted that cl 5.2 was intended to effect an allocation of risk pending resolution of the dispute between the parties, and the Contract allocated to L.U. Simon the risk that a claim might not ultimately be vindicated against it, then as the Court of Appeal observed in Sugar Australia, this 'constitutes a consideration of fundamental importance in assessing whether the grant of an injunction carries with it the lower risk of injustice.'[200]
Whether there are grounds for the grant of an injunction restraining recourse to the security
152 Having considered the issue of construction, I turn to consider whether an injunction will lie to restrain recourse to the security.
153 The principles governing the grant of interlocutory relief to restrain a beneficiary from calling on a guarantee or performance bond under a contract are well established, and were conveniently stated by Nichols J in Uber Builders and Developers Pty Ltd v MIFA Pty Ltd, as follows:[201]
(a) In order to establish an entitlement to interlocutory relief an applicant must show that there is a serious question to be tried. The applicant must make out a prima facie case in the sense of demonstrating that there is a sufficient likelihood of success at trial to justify the preservation of the status quo pending the determination of the parties' rights at trial, in the circumstances. How strong the probability needs to be depends upon the nature of the rights asserted and the practical consequences likely to flow from the relief sought.[202]
(b) The applicant must also establish that the balance of convenience favours the granting of an injunction. The court should take whichever course appears to carry the lowest risk of injustice, should it turn out to have been wrong in the sense of granting an injunction to a party who fails to establish its right at trial or failing to grant an injunction to a party who succeeds at trial.[203]
(c) Incorporated within the consideration of "balance of convenience" or sometimes considered as a separate matter, is the question whether damages would be an inadequate remedy, meaning that unless the injunction is granted the applicant will suffer irreparable injury for which damages will not be adequate compensation.[204]
(d) Those questions are not to be considered in isolation from one another, but must be considered together. In considering where the lower risk of injustice lies all relevant factors are to be weighed in the balance. The strength of the applicant's case and their chances of success may be a relevant matter when assessing the balance of convenience.[205]
154 The summons issued by L.U. Simons seeks (inter alia):[206]
(a) ANZ guarantee No GOP52252413418 in the amount of $[redacted]; and
(b) ANZ guarantee No GOP52252033418 in the amount of $[redacted].
155 There is limited scope for challenging a beneficiary's right to have recourse to a bank guarantee or a performance bond. Courts will generally only enjoin a party in whose favour the performance guarantee has been given where it is demonstrated that the party is acting 'fraudulently' or 'unconscionably' in calling on the security. In Clough Engineering Ltd v Oil and Natural Gas Corporation[207] the Full Court of the Federal Court stated the position , as follows:
[77] Nevertheless, the authorities have recognised three principal exceptions to the rule that a court will not enjoin the issuer of a performance guarantee, or bond, from performing its unconditional obligation to make payment. The exceptions were succinctly stated, with references to relevant authorities, by Austin J in _Reed Construction Services Pty Ltd v Kheng Seng (Aust) Pty Lt_d (1999) 15 BCL 158 at 164-5 (Reed):
First - the court will enjoin the party in whose favour the performance guarantee has been given from acting fraudulently: see, for example, Wood Hall per Gibbs J (at CLR 451; ALR 391-2). As the primary judge observed at [36] Clough does not assert that ONGC [the first respondent] has made a fraudulent claim. Accordingly, the first exception has no application in the present case.
Second - the party in whose favour the performance bank guarantee has been given may be enjoined from acting unconscionably in contravention of s 51AA of the TPA: Olex Focas Pty Ltd v Skodaexport Co Ltd [1998] 3 VR 380 (Olex Focas). On this point, different views have been expressed about the reach of s 51AA. The High Court has not determined which of these views is correct: Australian Competition and Consumer Commission v CG Berbatis Holdings Pty Ltd (2003) 214 CLR 51; 197 ALR 153; [2003] HCA 18 at [44]-[45] (CG Berbatis Holdings). In any event, none of the categories of unconscionable conduct recognised in Australian Competition and Consumer Commission v Samton Holdings Pty Ltd (2002) 117 FCR 301; 189 ALR 76; [2002] FCA 62 at [48] (Samton Holdings) apply in this case. Accordingly, the second exception has no application.
Third - the most important exception for present purposes, is that, while the court will not restrain the issuer of a performance guarantee from acting on an unqualified promise to pay (Reed Construction Services at 164 per Austin J):
... if the party in whose favour the bond has been given has made a contract promising not to call upon the bond, breach of that contractual promise may be enjoined on normal principles relating to the enforcement by injunction of negative stipulations in contracts.
It may be preferable not to describe this as an exception but rather as an over-riding rule because it emphasises that the "primary focus" will always be the proper construction of the contract: Bateman Project Engineering Pty Ltd v Resolute Ltd (2000) 23 WAR 493; [2000] WASC 284 per Owen J at [30]. Stephen J recognised this in Wood Hall at CLR 459; ALR 398-9 by observing that the provisions of the contract may qualify the right to call on the undertaking contained in a performance guarantee.
[78] Numerous authorities have accepted the third proposition. Many were referred to in Reed at 165. Others include Fletcher Construction at 826-7; Bachmann Pty Ltd v BHP Power New Zealand Ltd [1999] 1 VR 420; [1998] VSCA 40 at [28] (Bachmann); Baulderstone Hornibrook Pty Ltd v Qantas Airways Ltd [2000] FCA 672 at [10]; Rejan Constructions Pty Ltd v Manningham Medical Centre Pty Ltd [2002] VSC 579 at [37].
156 As noted earlier, counsel for L.U. Simon observed that in the present case the 'serious question' 'relates to its ACL claims and not the satisfaction of any pre-conditions'.[208] L.U. Simon submits that 'the case turns on L.U. Simon's ACL claims' and says 'it is clear that a remedy is available under s 232 for relief against Cardigan's threat to have recourse to the Security'[209] and it contends that 'whatever LU Simon agreed to in the contract must come second to the ACL claims because it never contracted to permit itself to be misled or treated in the manner that we contend [it was].'[210]
157 What is missing however, is any clear articulation of the 'serious question' contended for as the foundation for the interlocutory relief sought, and some identification of what matters or conduct on the part of the Cardigan as Principal that L.U. Simon relies on as constituting or manifesting Cardigan 'acting unconscionably in calling on the security'.
158 In the absence of any proper articulation of the 'serious question' to be tried, it is difficult to test and arrive at a satisfactory view about whether the applicant has made out a prima facie case in the sense of demonstrating that there is a sufficient likelihood of success at trial to justify the preservation of the status quo pending the determination of the parties' rights at trial. Doing the best I can to discern from L.U. Simon's submissions, and Cardigan's response, what appears to be the serious question contended for, I proffer the following formulation:
Whether it is open to L.U. Simon, notwithstanding the restraint imposed on it by cl 5.2(b) of the Contract, to seek injunctive relief under s 232 and s 234 of the ACL to restrain Cardigan from engaging in contravening conduct - being (alleged) unconscionable conduct under s 21 of the ACL − and thereby enjoin or prevent Cardigan from having recourse to the Security pending a final determination of the dispute.
159 L.U. Simon's reliance on its ACL claims is (at least for the most part) a reference to its claim for (statutory) unconscionable conduct under s 21, which section prohibits a person from engaging in unconscionable conduct more generally in connection with the supply or possible supply or acquisition or possible acquisition of goods or services. L.U. Simon does not point to, or call in aid in support of its claim under s 21, any of the matters set out in s 22 of the ACL, which are matters the court may have regard to for the purpose of determining whether a person (the acquirer - here, Cardigan) has contravened s 21 in connection with the acquisition or possible acquisition of goods or services from a person (the supplier - here, L.U. Simon).
160 The scope and operation of s 21 of the ACL, and the role of the matters or circumstances set out in s 22, was recently the subject of consideration by the High Court in Productivity Partners Pty Ltd v Australian Competition and Consumer Commission.[211] In that case, the appellant operated a college offering online vocational education and training courses. According to the headnote:[212]
From 2012 the college was authorised to provide the relevant courses under a Commonwealth funding scheme where students' tuition fees were paid by the Commonwealth after the "census date" for each unit of study (relevantly two weeks after the unit commenced). Students who stayed enrolled after the census date then incurred a debt to the Commonwealth which was repayable through the taxation system. At the relevant times the college engaged agents, called "career advisers" to recruit students for online courses and sign them up to the funding program. The agents were paid commissions once the students passed census dates and incurred debts for tuition.
The college was aware that the funding scheme was open to abuse, particularly through the external agents' unscrupulous sales tactics. Against the "moral hazard" of receiving payments for which students obtained no benefit, the college put in place certain system controls aimed at ensuring that only engaged students were enrolled in the first place and were still engaged as census dates approached.
In September 2015 falling revenue, budget expectations set by Site and discontent with existing commission rates among the college's agents led to it abolishing the system controls. Enrolments and revenue increased substantially, although almost all of those enrolled did not complete a single unit of study. They nevertheless accumulated substantial debts to the Commonwealth for no concomitant benefit.
The respondent Commission brought proceedings in the Federal Court of Australia alleging that the college engaged in a system of conduct or a pattern of behaviour that was unconscionable contrary to the Australian Consumer Law, s 21. Proceedings were also brought against Wills and Site pursuant to ss 2 and 224(1)(e), alleging that they were knowingly concerned in, or parties to the college's contravention. The primary judge found the allegations proven and those findings were upheld by a majority of the Full Court of the Federal Court on appeal.
161 The appellants appealed to the High Court of Australia. The Court dismissed the appeals, a conclusion in which all seven members of the Court joined. In a joint judgment, Gageler CJ and Jagot J (Gleeson J agreeing; Beech-Jones J agreeing) held that the college had engaged in a system of conduct or pattern of behaviour in respect of people enrolled in online courses in the impugned enrolment period that was in all the circumstances unconscionable in contravention of s 21 of the ACL.[213] Further, when considering the meaning and application of the relevant statutory provisions, Gageler CJ and Jagot J summarised their conclusion about s 22, in terms stating:[214]
Section 22 of the ACL does not require a court to evaluate the impugned conduct by reference to the presence or absence of the circumstances that provision specifies irrespective of the relevance of those circumstances to the impugned conduct or to the cases as put by the parties to the court. ...
162 Their Honours continued in their reasons, to explain the role of s 22, as follows:[215]
[60] That the presence or absence of each matter in s 22(1) is not a mandatory relevant consideration to be weighed by a court in every case, irrespective of the circumstances, does not mean that the required evaluation involves nothing more than, as the College put it, an "instinctive reaction that the legislation sought to avoid". The normative standard set by s 21(1) is tethered to the statutory language of "unconscionability". While that term is not defined in the legislation and, in its statutory conception, is "more broad-ranging than the equitable principles",[216] it expresses "a normative standard of conscience which is permeated with accepted and acceptable community standards",[217] and conduct is not to be denounced by a court as unconscionable unless it is "outside societal norms of acceptable commercial behaviour [so] as to warrant condemnation as conduct that is offensive to conscience".[218] The items listed in s 22(1)(a)-(l) are matters that the legislation requires to be considered, in the overall evaluation of the totality of the circumstances to be undertaken for the purpose of s 21(1), if and to the extent those matters are applicable. This is why both "close attention to the statute and the values derived from it, as well as from the unwritten law"[219] and "close consideration of the facts"[220] are necessary.
163 In the passage above, their Honours referred with approval to observations of Gordon J in the earlier decision of the High Court in Stubbings v Jams 2 Pty Ltd[221] where her Honour addressed the operation of ss 12CB and 12CC of the Australian Securities and Investments Commission Act (2001) (Cth) (ASIC Act), which are the counterpart provisions to ss 21 and 22 of the ACL. Justice Gordon stated:[222]
164 In the present case, the submissions advanced on behalf of L.U. Simon fall well short of meeting the requisite standard.
165 All that L.U. Simon provides in support of its claim under s 21 are the matters pleaded in paragraph [142] of its Statement of Claim (set out at paragraph 84 above) that L.U. Simon relies on in support of the injunctive relief it seeks under s 232 and s 234 of the ACL. Counsel for L.U. Simon said that it also relies on Cardigan's (alleged) misleading or deceptive conduct.[223] But 'misleading or deceptive conduct' is not one of the recognised exceptions that falls within the limited scope for challenge, and it is unclear whether (and if so, how) it forms part of the alleged (statutory) unconscionable conduct under s 21.
166 As Gordon J cautioned in Stubbings v Jams 2 Pty Ltd,[224] allegations of 'unconscionable conduct' are serious allegations that should not be made lightly, and when made must be supported by a proper foundation.
168 In Clough Engineering Ltd v Oil and Natural Gas Corporation[227] the Full Court of the Federal Court observed that the final injunctive relief sought in that case by Clough Engineering would restrain the first respondent (ONGC) from making demand for payment from the banks and would restrain the banks from making payment to ONGC under the performance bank guarantees. In those circumstances, their Honours stated:[228]
[138] As already pointed out, on their proper construction, the performance bank guarantees were unconditioned on any actual breach and did entitle ONGC to call upon them for their full amount. Given the commercial purpose of such guarantees, recognised in Wood Hall l[229]] assuming the absence of fraud, there would seem to be very little, if any, scope for the application of equitable doctrines of unconscionable conduct to restrain the exercise by a party of its legal rights under such guarantees. There may be extreme cases which would merge into the area of bad faith exercises of the power. However that may be, the present is not a case which, on the materials before his Honour, justified any finding of a serious question to be tried of a contravention of
s 51AA. The wide purpose of the performance bank guarantees and their character as reflecting an allocation of risk and a provision of security to their holder militate against any argument as to disproportion in their exercise.
169 Accordingly, their Honours found that the primary judge was right to reject Clough Engineering's contention that there was a serious question to be tried of unconscionable conduct on the part of ONGC in calling upon performance guarantees.
170 In a case such as the present one, where the Contract in question is found to have embodied a risk allocation mechanism agreed between the parties that establishes a 'pay now, argue later' regime, it is difficult to understand how the Principal's exercise of the right to call upon the performance guarantee or bond can be regarded or characterised as 'unconscionable conduct' in the relevant sense, save for e.g. in an extreme case involving a bad faith exercise of the power. This is particularly so in circumstances where the relevant contract is one that embodies Australian Standards General Conditions that are in daily use in the industry.
171 For the foregoing reasons, I am not satisfied that L.U. Simon has demonstrated that there is a serious question to be tried. Further, given the lack of clarity in the formulation of its case, and the absence of any articulation of the discrimen that is said to render Cardigan's conduct 'unconscionable conduct' in the relevant contravening sense, the Court is not in a position to be satisfied that L.U. Simon has made out a prima facie case in the sense of demonstrating that there is a sufficient likelihood of success at trial to justify the preservation of the status quo pending the determination of the parties' rights at trial.
172 The two matters that were raised by L.U Simon as going to the balance of convenience were first, the risk of reputational damage that it will suffer if the ANZ bank guarantees are called on/cashed by Cardigan, and secondly, a concern that because Cardigan is an offshore project specific developer, that had been placed in external administration in 2020, 'it is almost certain that should it later be found that Cardigan is liable to repay the amount of Security, LU Simon will have little prospect of recovering same.'[230] In that regard, L.U. Simon relied on the view expressed by Byrne J in Rejan Constructions to the effect that the exercise by a Principal where it is later found that no money is owing to Cardigan, risks imposing a 'grave disadvantage' on L.U. Simon.[231] But that view falls to be weighed against the cautionary note expressed by Osborn and Ferguson JJA in Sugar Australia, by reference to Bradto, that '[i]f the commercial purpose of a contractual provision is defeated' - as it would be in the present case if the injunctive relief sought were obtained - 'that must bear squarely on the ultimate risk of injustice inherent in the grant of an injunction.'[232]
173 As to the first matter, it will be recalled that evidence was given by Mr Reid as to the reputational damage that L.U. Simon will suffer with its financiers, and that it may also lose government work as those tenders 'require L.U. Simon to state whether it has ever had any of its security cashed.' [233] If that be correct, those risks are risks that L.U. Simon was, or should have been aware of, when it entered into the Contract, in circumstances where the Security was a significant feature of the parties' contractual arrangements.
174 In the CPB Contractors case in the High Court, Nettle J was somewhat sceptical about the asserted risk of 'reputational damage' but acknowledged that each case turns on its facts. In dismissing CPB's application for an interim injunction his Honour said:[234]
In the affidavit of Jason Zeb sworn 10 July 2017 in support of the application, it was deposed that a call by JKC on the bank guarantees could "potentially have an adverse effect on the financial position of CPB" because "[i]f a financial institution assesses CPB or other members of the CIMIC group [of which CPB is a member] as having a high or higher degree of financial risk, this can affect the price of CIMIC obtaining capital generally". Similarly, it was stated that "CPB may also suffer adverse consequences to its lending arrangements as the price of CPB's existing financing will increase". Since that evidence was not challenged, I accept it. But it is to be observed that it is expressed in markedly tentative terms and, although Mr Zeb also stated in the affidavit that it could prove difficult to quantify the amount of loss which CPB might thereby suffer, it was not suggested that the amount of any such loss could not be assessed and recovered in the international arbitration if found to be due.
Mr Zeb further deposed that, if JKC makes a call on the bank guarantees, CPB's "reputation in the industry will be adversely affected" the result of the liability to the bank thus incurred needing to be brought to account in CPB's and CIMIC's books of account, and thus would be perceived negatively by CPB's customers and financiers. Once again, that evidence was not challenged and, therefore, I accept it. But I observe that, although a call on the bank guarantees would need to be reflected in CPB's books of account, so too would need to be recorded the contingent asset constituted of CPB's claim for repayment of the moneys which it says were not payable. The true and fair view of the company's financial position thus stated would represent a true reflex of the facts, namely, that there is a dispute as to CPB's liability for liquidated damages which remains to be determined by international arbitration.
Mr Zeb stated as well that a call on the bank guarantees would be an indication to "the market" that CPB cannot uphold its obligations in delivering projects. Perhaps; but I take leave to doubt it. Granted, as CPB contends, the prospect of reputational harm has been accepted as a relevant consideration by several experienced construction law judges.[235] But each case depends on its facts. Here, it is clear from Le Miere J's and the Court of Appeal's reasons for judgment that there has not yet been a determination of CPB's alleged substantive liability for liquidated damages - that remains to be determined in the international arbitration - and it is clear from the Court of Appeal's reasons for judgment that their Honours' conclusion as to the proper construction of the sub contract is that JKC should "be in the money, to the extent of the Bank Guarantees, pending resolution of any dispute".[236] If that be correct, and until and unless there is a successful appeal it must be accepted that it is correct, the fact that JKC is permitted to draw down under relevantly unconditional bank guarantees pending determination of the issue of substantive liability can hardly be seen as reflecting on CPB's performance or, therefore, reputation as a contractor.
175 Similar comments might be made in response to the 'high level' statements made by Mr Reid. To the extent that there is any real prospect of reputational damage being suffered by L.U. Simon, it is open to it, as Nettle J observed in the CPB Contractors case 'to avoid risk of reputational damage by tendering a sum equal to the amount of the claim, on account, in substitution for the amount payable under the bank guarantees.'[237] It will be recalled that counsel for L.U. Simon expressly raised this prospect at the conclusion of the hearing on 17 September 2025, but it became unnecessary to pursue it as counsel for Cardigan informed the Court that he had instructions to refresh the undertaking that had been given.
176 As to the second matter, Mr Reid deposes to the effect that 'Cardigan lacks financial resources'[238] and, 'if it receives the money from the Security, then that money will likely be disbursed offshore to either its financiers or investors or to pay off debts',[239] rendering it unlikely that Cardigan will be able to repay that money. Counsel for Cardigan responded to this evidence at the hearing by referring the Court to evidence given by Mr Fraser and Mr van Grieken about Cardigan's assets within the jurisdiction.
Cardigan's Assets
The Project consists of 80 apartments, which range in size from
1-bedroom apartments to 3-bedroom apartments and townhouses, with a price range between $[redacted] and $[redacted].
Of the 80 apartments, 67 apartments have been sold, and Cardigan owns the remaining 13 apartments and commercial lots, valued at over $[redacted] million. These apartments and commercial spaces are currently unable to be sold due to the number of outstanding defects to be rectified by LU Simon, and the fact that LU Simon remain in occupancy of the commercial spaces to enable them to use the facilities and site amenities as they rectify the defective works.
178 Mr van Grieken deposed to similar effect, as follows:[241]
The Plaintiff's current ownership of Apartments
- I am informed by Mr Fraser, as at the date of this affidavit, the Defendant owns 13 apartments and commercial lots at the project to the value of over $[redacted] million. These apartments are not currently being marketed due to the state of the defective works affecting those apartments. The Plaintiff also currently occupies the commercial lots of the development notwithstanding vacating those spaces was an element of reaching Practical Completion in late April 2025.
- I am informed by Mr Fraser that as recently as 23 August 2025, Mr Fraser received a telephone call from an employee of the Plaintiff in respect to the defects present in an unsold apartment wherein the Plaintiff was provided with a list of defective works in March 2025 and until the telephone call on 23 August 2025 the Plaintiff had not taken any steps to rectify those defective works in the preceding five months.
- I am informed by Mr Fraser that it is likely that these apartments and commercial spaces may take at least 6 months to market, sell and dispose of given the number of outstanding defects to be rectified by the Plaintiff.
179 In circumstances where it is clear that Cardigan has significant assets within the jurisdiction, I am not satisfied that there is a risk of dissipation of assets. In the event it transpires that L.U. Simon is ultimately successful in its claims against Cardigan, the indications are that Cardigan would be able to satisfy an award of damages.
180 Having considered all of the material before the Court, and the submissions made by counsel for the respective parties I am not satisfied that the balance of convenience favours the grant of the injunctive relief sought by L.U. Simon.
Ground 2 of the Summons − As a Certificate of Practical Completion has issued for 'SP 2', L.U. Simon now seeks to have 50% of the Security returned to it
181 The second limb of the relief sought in the summons issued by L.U. Simons is framed as follows:[242]
182 The relief sought relates to cl 5.4 of the AS 4902-2000 General Conditions, which provides for the 'Reduction and release' of the Security. Clause 5.4 has been reproduced in its entirety earlier in these Reasons (at paragraph 30 above), but, in essence, the relevant part of the clause, which is contained in cl 5.4(a), provides that '[s]ubject to the Principal's rights in relation to the Security under subclause 5.2, upon the last to occur of the following [five specified events or matters], the Principal's entitlement to the Security shall be reduced to [50%].'
183 As noted earlier, with the Project Manager having, on or about 9 May 2025, issued a Certificate of Practical Completion under the Contract in respect of 'SP 2', L.U. Simon now claims that Cardigan is no longer is entitled to retain 50% of the Security held by it pursuant to the Contract and is required to release that Security to LU Simon.[243]
184 Cardigan disputes that each of the five specified events or matters have been satisfied, but it says in any event that 'the reality is the clause is disengaged by the fact that the claim was made before the date for practical completion was certified.'[244]
185 Further, Cardigan says that following the issue of its notification to L.U. Simon on 24 April 2025 of its intention to have recourse to the Security, Cardigan gave an undertaking to L.U. Simon not to have recourse to either of the ANZ bank guarantees, in terms that would permit L.U. Simon to seek injunctive relief. But the correspondence passing between the solicitors for the respective parties expressly records that in so doing, 'Cardigan reserves all its rights.'[245]
186 Counsel for Cardigan submitted that that reservation has continued as each of the further indulgences have been granted over the past few months whilst L.U. Simon has continued to press for injunctive relief. Meanwhile, he said 'our [Cardigan's] vested entitlement to $7.2m of liquidated damages is there, it's still there, it's accumulating interest, we haven't been paid.'[246]
187 L.U. Simon refers to a later exchange of email correspondence between the solicitors for the parties on 8 May 2025,[247] whilst arrangements for a mediation were being discussed, whereby they agreed inter alia that Cardigan's entitlement to Security would not be reduced under cl 5.4 until the last to occur of:
(a) the conditions in cl 5.4(a)(i) to (v) have been fully satisfied; and
(b) 10:00am on Friday 11 July 2025.
188 L.U. Simon submits that as it 'has satisfied the conditions for the return and release of its security pursuant to clause 5.4 and Friday, 11 July 2025 has now passed,' Cardigan is no longer is entitled to retain 50% of the Security held by it pursuant to the Contract and is required to release that Security to LU Simon.[248]
189 Each of Mr Fraser (on behalf of Cardigan) and Mr Reid (on behalf of L.U. Simon) has given evidence respectively about the non-satisfaction and satisfaction of the conditions in cl 5.4(a) of the Contract.
190 L.U. Simon relies on the decision of the Court of Appeal of South Australia in Synergy Construct Australia Pty Ltd v GSA North Terrace Pty Limited ATF GSA North Terrace Unit Trust[249] as authority supporting its claim that Cardigan must return one of the two bank guarantees that together constitute the Security. In my view, however, it does not assist to resolve the issue in the present case.
191 In Synergy Construct Australia, the contractual arrangements under consideration were expressed in different terms, and the factual scenario was markedly different to the present one. The Court of Appeal described the 'essential question' in the case as being:[250]
192 The Court then addressed the proper construction of the contractual arrangements in place between the parties under cl 5.2 (Conversion and Recourse) and cl 5.4 (Reduction and release), which were framed in different terms to those in the Contract in the present case, stating:[251]
193 In my view, in the present case, the resolution of this issue about the return of 50% of the Security turns on the proper construction of the contractual arrangements made between the parties, as set out in cl 5.2 and cl 5.4. The 'reduction and release' of 50% of the Security that takes place under cl 5.4 is expressly subject to 'the Principal's rights in relation to the Security under subclause 5.2'. In the present case, those rights of the Principal under subclause 5.2 were exercised by Cardigan when it gave notice to L.U. Simon on 24 April 2025 of its intention to have recourse to the Security.[252] Accordingly, I agree with the submission advanced by Cardigan, to the effect that Cardigan having exercised its right under cl 5.2, and the period of three days' notice having passed, its entitlement has vested, subject to any order of the Court to the contrary.
194 In the circumstances, I do not propose making an order of the kind sought in paragraph 2 of the summons.
195 For the reasons set out above, I have reached the following conclusions:
(a) I am not satisfied that L.U. Simon has demonstrated that there is a serious question to be tried. Further, given the lack of clarity in the formulation of its case, and the absence of any articulation of the discrimen that is said to render Cardigan's conduct 'unconscionable conduct' in the relevant contravening sense, the Court is not in a position to be satisfied that L.U. Simon has made out a prima facie case in the sense of demonstrating that there is a sufficient likelihood of success at trial to justify the preservation of the status quo pending the determination of the parties' rights at trial.
(b) I am not satisfied that the balance of convenience favours the grant of the injunctive relief sought by L.U. Simon.
(c) I do not propose making an order of the kind sought in paragraph 2 of the summons (seeking that 50% of the Security should be returned).
(d) Accordingly, the summons should be dismissed.
196 I will hear from the parties on the appropriate form of orders, including as to costs.
[1] Here, the relevant bank guarantees, issued by the ANZ Bank, together represented [redacted]% of the Contract Sum: Annexure Part A to the General Conditions of Contract, Item 14.
[2] Transcript 17.09.2025 at 91-92 (Mr Andrew KC).
[3] Transcript 17.09.2025 at 96 (Mr Harris KC).
[4] Schedule 2 to the Competition and Consumer Act 2010 (Cth).
[6] L.U. Simon outline (25.08.2025), [8].
[7] Transcript 17.09.2025 at 3 (Mr Andrew KC).
[8] Transcript 17.09.2025 at 3−4 (Mr Andrew KC) (emphasis in bold italics added).
[9] [Acronym for 'Extensions of Time'. See e.g. Contract, clauses 1.1 and 34.3.]
[11] L.U. Simon outline (25.08.2025), [10].
[12] Siemens Gamesa Renewable Energy Pty Ltd v Bulgana Wind Farm Pty Ltd [2019] VSCA 318 (Siemens) at [14].
[13] Cardigan outline (29.08.2025), [1].
[14] Adopting the approach of Byrne J in Rejan Constructions (referred to below), at [5].
[15] Mr Moschoyiannis was a director of L.U. Simon until 25 October 2024, but he continued to be employed by L.U. Simon on a full-time basis until 21 January 2025.
[16] Moschoyiannis Affidavit, at [5].
[17] L.U. Simon outline (25.08.2025), [12].
[18] First Fraser Affidavit, at [26]-[32] (emphasis in bold italics added).
[19] First Fraser Affidavit, at [33]-[41] (emphasis in bold italics added).
[20] The following documents, contained within the Reid Affidavit, 139-470 are the Contract Documents:
(b) the Contractor's Clarifications and Exclusions Schedule (405-406);
(c) the General Conditions of Contract, being the attached AS 4902-2000 General Conditions of Contract (as amended) including any schedule or annexure to it (154-470); and
(d) those additional documents attached or referred to at Annexure Part P (315-385).
[21] Reid Affidavit, Exhibit SRR-1, at 149.
[22] Moschoyiannis Affidavit, at [12].
[23] Moschoyiannis Affidavit, Exhibit JDM-1, at 8 (emphasis in bold italics added).
[24] Reid Affidavit, Exhibit SRR-1, at 182 (emphasis in bold italics added).
[25] Reid Affidavit, Exhibit SRR-1, at 266.
[26] Siemens Gamesa Renewable Energy Pty Ltd v Bulgana Wind Farm Pty Ltd [2019] VSCA 318, [14].
[27] Reid Affidavit, Exhibit SRR-1, at 182 (emphasis in bold italics added).
[28] Reid Affidavit, Exhibit SRR-1, at 183 (emphasis in bold italics added).
[29] Item 14(f) of Annexure Part A (Reid Affidavit, Exhibit SRR-1, at 267) states:
[31] Reid Affidavit, Exhibit SRR-1, at 474.
[32] Moschoyiannis Affidavit, at [18].
[33] Reid Affidavit, at [21]-[24], [26].
[34] Annexure A, headed 'SCHEDULE OF PROGRESS CLAIMS, PAYMENT SCHEDULES, PAYMENTS AND INTEREST ON LATE PAYMENTS' appears at pp13-15 of the Reid Affidavit.
[35] Reid Affidavit, at [25], [27]-[31], [33] (emphasis in bold italics added).
[36] Moschoyiannis Affidavit, at [10]-[11].
[37] Moschoyiannis Affidavit, at [12].
[38] Moschoyiannis Affidavit, at [12]-[18].
[41] First Fraser Affidavit, at [50]-[51] (emphasis in bold italics added).
[42] First Fraser Affidavit, at [55]-[59] (emphasis in bold italics added).
[43] First Fraser Affidavit, at [62]-[67] (emphasis in bold italics added).
[44] Moschoyiannis Reply Affidavit, at [6].
[45] Moschoyiannis Reply Affidavit, at [6].
[46] First Fraser Affidavit, at [71 (a)-(k)].
[47] First Fraser Affidavit, at [71].
[48] Moschoyiannis Reply Affidavit, at [8]-[10] (emphasis in bold italics added).
[49] Devitt Reply Affidavit, at [5]-[7] (emphasis in bold italics added).
[50] Devitt Reply Affidavit, at [8]-[13].
[51] Reid First Reply Affidavit, at [24]-[26].
[52] First Fraser Affidavit, at [71(k)].
[53] Reid Affidavit, Exhibit SRR-1, at 471-472.
[54] van Grieken Affidavit, Exhibit LVG-1, at 21.
[55] Transcript 17.09.2025, at 35 (Mr Harris KC).
[56] van Grieken Affidavit, Exhibit LVG-1, at 172.
[57] Transcript 17.09.2025, at 36 (Mr Harris KC).
[58] van Grieken Affidavit, Exhibit LVG-1, at 20 (emphasis in bold italics added).
[62] [2002] VSC 579 (Rejan Constructions)
[63] Transcript 17.09.2025, at 4 (Mr Andrew KC).
[64] Under the AS 4902-2000 General Conditions that apply in this case, cl 5.1 states: 'Security and performance undertakings are for the purpose of ensuring the due and proper performance of the Contract. ...'
[65] [2002] VSC 579, at [33], [40]] (emphasis in bold italics added).
[67] [2013] VCC 430, [5].
[68] [2013] VCC 430, [7].
[69] [1935] HCA 49; (1935) 53 CLR 643 at 652.
[71] Transcript 17.09.2025, at 8 (Mr Andrew KC).
[72] [2013] VCC 430, [30].
[73] Transcript 17.09.2025, at 9 (Mr Andrew KC).
[75] Transcript 17.09.2025, at 9 (Mr Andrew KC).
[76] Transcript 17.09.2025, at 10 (Mr Andrew KC).
[77] On an application in the High Court for an interim injunction pending special leave to appeal in CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd, (discussed below), Nettle J observed that 'the prospect of reputational harm has been accepted as a relevant consideration by several experienced construction law judges' (citing Austrak Pty Ltd v John Holland Pty Ltd [2006] QSC 103 at [29]‑[34]; Abigroup Contractors Pty Ltd v Peninsula Balmain Pty Ltd, Supreme Court of New South Wales, unreported, 2 December 1999; Barclay Mowlem Construction Ltd v Simon Engineering (Australia) Pty Ltd (1991) 23 NSWLR 451 at 461; Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158 at 167 per Austin J) but added the cautionary note, stating 'But each case depends on its facts.' (See [2017] HCA Trans 147, at 24.).
[78] [2017] WASC 112 (CPB Contractors).
[79] [2017] WASC 112, at [52]-[56] (emphasis in bold and underlining added).
[80] CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd [2017] WASCA 123, at [4] (Buss P, Murphy and Beach JJA) (CPB Contractors (No 2)).
[81] [2017] WASCA 123, at [93]-[95] (Buss P, Murphy and Beach JJA) (emphasis in bold italics added).
[83] L.U. Simon outline (25.08.2025), [46]-[47].
[84] First Fraser Affidavit, at [36].
[85] First Fraser Affidavit, at [35].
[89] The 'Reserve Power' is pleaded in paragraph [80] as follows:
80. Further, pursuant to clause 34.5(d) of the Contract, the parties agreed that notwithstanding that the Contractor is not entitled to or has not claimed an EOT, the Project Manager may, at any time and from time to time before issuing the Final Payment Schedule direct an EOT (the Reserve Power).
[90] Transcript 17.09.2025, at 26 (Mr Andrew KC)
[91] Transcript 17.09.2025, at 25-26 (Mr Andrew KC).
[92] Section 4 of the ACL is headed 'Misleading representations with respect to future matters'.
[93] [Relevantly, ss 18 and 21 fall within Chapter 2 of the ACL.]
[94] L.U. Simon reply submissions (4.09.2025), [17].
[95] L.U. Simon reply submissions (4.09.2025), [18].
[96] Citing Foster v ACCC [2006] FCAFC 21; (2006) 149 FCR 135 at [30]- [31] per Ryan, Finn and Allsop JJ.
[97] L.U. Simon outline (25.08.2025), [57].
[98] L.U. Simon outline (25.08.2025), [60].
[100] L.U. Simon outline (25.08.2025), [61].
[104] Fletcher Construction Australia Ltd v Varnsdorf Pty Ltd [1998] 3 VR 812 at 826 - 827; Anaconda Operations Pty Ltd v Fluor Daniel Pty Ltd [1999] VSCA 214 at [15] per Brooking JA (Ormiston & Buchanan JJA agreeing); Lucas Stuart Pty Ltd v Hemmes Hermitage Pty Ltd [2010] NSWCA 283, at [5] - [6] per Campbell JA; Clough Engineering Ltd v Oil and Natural Gas Corporation (2008) 249 ALR 458, [75]-[112], [129]-[139]; Sugar Australia Pty Ltd v Lend Lease Services Pty Ltd [2015] VSCA 98, [21]- [31], [43] - [56] per Osborn and Ferguson JJA at [111] - [128], [138] per Kaye JA; Telvent Australia Pty Ltd v Acciona Infrastructure Pty Ltd [2016] QSC 201, [30]-[41] CPB Contractors Pty Ltd v JKC Australia LNG Pty Ltd (No 2) [2017] WASCA 123, at [84] - [96], [112]; Good Living Pty Ltd atf Warren Duncan Trust No 3 v Kingsmed Pty Ltd [2021] FCAFC 33; (2021) 284 FCR 424; Primero Group Ltd v Coburn Resources [2025] WASC 69, [41]-[53]; Synergy Construct Australia Pty Ltd v GSA North Terrace Pty Limited [2025] SASCA 72, [20].
[105] Cardigan outline (29.08.2025), [1].
[107] van Grieken Affidavit, Exhibit LVG-1, at 5-6.
[108] Cardigan outline (29.08.2025), [4].
[109] Cardigan outline (29.08.2025), [5].
[110] Statement of Claim (SOC), [14]-[128].
[113] [Fraser] Affidavit, [58]-[59].
[114] [Fraser] Affidavit, [55]-[72], [76]-[104].
[115] [Citing the cases listed at fn 104 above].
[116] Cardigan outline (29.08.2025), [6].
[117] Cardigan outline (29.08.2025), [8].
[118] It will be recalled that L.U. Simon's solicitors had requested amendments to cl 4.10 of the Builder's Side Deed to ensure that funds which are owed by Cardigan to L.U. Simon under the Building Contract are paid directly from the Financier to L.U. Simon.
[119] Cardigan outline (29.08.2025), [8].
[120] Cardigan outline (29.08.2025), [9].
[121] Cardigan outline (29.08.2025), [11].
[122] [Fraser] Affidavit, [22]-24].
[123] [Fraser] Affidavit, [33]-[41].
[124] Bond Corporation Pty Ltd v Thiess Contractor Pty Ltd [1987] FCA 84; (1987) 14 FCR 215.
[125] Miller & Associates Insurance Broking Pty Ltd v BMW Australia Finance Ltd [2010] HCA 31; (2010) 241 CLR 357.
[126] Cardigan outline (29.08.2025), [12].
[127] Parkdale Custom Built Furniture Pty Ltd v Puxu Pty Ltd [1982] HCA 44; (1982) 149 CLR 191.
[128] [Fraser] Affidavit, [11], [32].
[129] Cardigan outline (29.08.2025), [15], citing Sugar Australia at [43] - [56] per Osborn and Ferguson JJA and at [111] - [128] per Kaye JA. See also Siemens at [94].
[130] Transcript 17.09.2025, at 46 (Mr Harris KC).
[131] Sugar Australia at [31]; Primero Group Ltd v Coburn Resources [2025] WASC 69, [46]-[47].
[132] Cardigan outline (29.08.2025), [17].
[133] Transcript 17.09.2025, at 48 (Mr Harris KC).
[134] Transcript 17.09.2025, at 46 (Mr Harris KC).
[135] van Grieken Affidavit, Exhibit LVG-1, at 182.
[136] Transcript 17.09.2025, at 50 (Mr Harris KC).
[137] Transcript 17.09.2025, at 50-51 (Mr Harris KC).
[138] Transcript 17.09.2025, at 52 (Mr Harris KC).
[139] Transcript 17.09.2025, at 52 (Mr Harris KC).
[140] Cardigan outline (29.08.2025), [24] citing Miller's Australian Competition and Consumer Law Annotated, [ACL234.20] and [CCA.80.120].
[141] Cardigan outline (29.08.2025), [24] citing ACCC v Dataline.Net.AU Pty Ltd [2015] FCAFC 114; (2007) 161 FCR 513, [108].
[142] Cardigan outline (29.08.2025), [24].
[143] Reid Affidavit, Exhibit SRR-1 at 471.
[144] van Grieken Affidavit, Exhibit LVG-1, at 21.
[145] Transcript 17.09.2025, at 35 (Mr Harris KC).
[146] van Grieken Affidavit, Exhibit LVG-1, at 172.
[147] Transcript 17.09.2025, at 36 (Mr Harris KC) (emphasis in bold italics added).
[148] Transcript 17.09.2025, at 40 (Mr Harris KC) (emphasis in bold italics added).
[149] L.U. Simon reply submissions (4.09.2025) at [3].
[150] L.U. Simon reply submissions (4.09.2025) at [4].
[151] L.U. Simon reply submissions (4.09.2025) at [9].
[152] L.U. Simon reply submissions (4.09.2025) at [10].
[153] L.U. Simon reply submissions (4.09.2025) at [5], citing ACL s 21(4)(a).
[154] L.U. Simon reply submissions (4.09.2025) at [7].
[155] L.U. Simon reply submissions (4.09.2025) at [8].
[156] L.U. Simon reply submissions (4.09.2025) at [16].
[157] L.U. Simon reply submissions (4.09.2025) at [17].
[158] L.U. Simon reply submissions (4.09.2025) at [19]-[20].
[159] Cardigan outline (29.08.2025), [24].
[160] Ship "Shin Kobe Maru" v Empire Shipping Company Inc [1994] HCA 54; (1994) 181 CLR 404, at [29] per Mason CJ, Brennan, Deane, Dawson, Toohey, Gaudron, and McHugh JJ, cited in Australian Memory Pty Ltd v Brien (2000) 200 CLR 270 at [17] per Gleeson CJ, McHugh, Gummow, Hayne and Callinan JJ
[161] L.U. Simon reply submissions (4.09.2025) at [24].
[162] L.U. Simon reply submissions (4.09.2025) at [11]-[12].
[163] L.U. Simon outline (25.08.2025), [8].
[164] L.U. Simon reply submissions (4.09.2025) at [21]-[23].
[165] Reid First Reply Affidavit, [18].
[166] Reid First Reply Affidavit, [18]-[23].
[167] L.U. Simon reply submissions (4.09.2025) at [23].
[168] Transcript 17.09.2025, at 9 (Mr Andrew KC) (emphasis in bold italics added).
[169] Transcript 17.09.2025, at 4 (Mr Andrew KC).
[172] Fletcher Construction [1998] 3 VR 812, 826-7 (citation in original).
[173] Compare Burleigh Forest Estate Management Pty Ltd v Cigna Insurance Australia Ltd [1992] 2 Qd. R 54, 59 and Themehelp Ltd v West [1996] QB 84 in the dissenting judgment of Evans LJ at 103.
[174] Westpac B_a_nking Corporation v Commonwealth Steel Co Ltd [1983] 1 NSWLR 735 at 741.
[175] Wood Hall Ltd v Pipeline Authority [1979] HCA 21; (1979) 141 CLR 443 at 457-458.
[176] Simic v New South Wales Land and Housing Corporation [2016] HCA 47; (2016) 260 CLR 85 (Simic), 113 [88] (Gageler, Nettle and Gordon JJ).
[177] Siemens Gamesa Renewable Energy Pty Ltd v Bulgana Wind Farm Pty Ltd [2019] VSCA 318 (Siemens), [14] (Beach, McLeish and Hargrave JJA).
[178] Siemens Gamesa Renewable Energy Pty Ltd v Bulgana Wind Farm Pty Ltd [2019] VSCA 318 (Siemens), [121] (Beach, McLeish and Hargrave JJA).
[179] Sugar Australia, [2015] VSCA 98, [29]-[31], [34] (Osborn and Ferguson JJA).
[181] [2006] VSCA 89; (2006) 15 VR 65, 70 [26].
[183] Uber Builders and Developers Pty Ltd v MIFA Pty Ltd, [2020] VSC 596, at [26(m)] (per Nichols J, citing Clough Engineering Ltd v Oil and Natural Gas Corporation (2008) 249 ALR 458, at [81]-[82]).
[184] [2020] VSC 596, at [26] (emphasis in bold italics added).
[185] Sugar Australia, [2015] VSCA 98 [138]-[142] (Kaye JA); Fletcher Construction, [1998] 3 VR 812, 823 (Charles JA).
[186] [2025] WASC 69, [78] (emphasis in bold italics added).
[187] [2002] VSC 579 at [33].
[188] Reid Affidavit, Exhibit SRR-1, at 182 (emphasis in bold italics added).
[189] Annexure Part A. Item 29 (Reid Affidavit, Exhibit SRR-1, at 270) provides:
[190] Reid Affidavit, Exhibit SRR-1, at 471-472.
[191] In other words, a sum of $10,341,514.20 or thereabouts.
[192] van Grieken Affidavit, Exhibit LVG-1, at 20.
[193] Reid Affidavit, Exhibit SRR-1, at 182 (emphasis in bold italics added).
[194] L.U. Simon outline (25.08.2025), [60].
[196] [2017] WASCA 123, at [95] (Buss P, Murphy and Beach JJA) (emphasis in bold italics added).
[199] Reid Affidavit, Exhibit SRR-1, at 182.
[200] Sugar Australia [2015] VSCA 98, [67] per Osborn and Ferguson JJA.
[201] [2020] VSC 596, at [26].
[202] ABC v O'Neill [2006] HCA 46; (2006) 227 CLR 57, 68 [19], 82 [65] (O'Neill).
[203] Bradto Pty Ltd v State of Victoria [2006] VSCA 89; (2006) 15 VR 65, 73 [35] (Bradto).
[204] Castlemaine Tooheys Ltd v South Australia [1986] HCA 58; (1986) 161 CLR 148, 153.
[205] O'Neill at 82 [65]; Kellogg Brown & Root Pty Ltd v Australian Aerospace Ltd [2007] VSC 200, [48].
[206] Summons filed in the County Court, dated 22August 2025.
[207] See Clough Engineering Ltd v Oil and Natural Gas Corporation (2008) 249 ALR 458, at [77]-[78] (per French, Jacobson and Graham JJ)) (emphasis in bold italics added).
[208] Transcript 17.09.2025, at 9 (Mr Andrew KC).
[209] L.U. Simon reply submissions (4.09.2025) at [24].
[210] Transcript 17.09.2025, at 4 (Mr Andrew KC).
[211] (2024) 98 ALJR 1021; [2024] HCA 27. Another recent case on the operation of s 21 and s 22 of the ACL is AHG WA (2015) Pty Ltd v Mercedes-Benz Australia/Pacific Pty Ltd (2025) 310 FCR 1; [2025] FCAFC 86.
[213] Separate reasons were delivered by Gordon J at [96]-[195], Edelman J at [196]-[281], Steward J at [282]-[309], Gleeson J at [310]-[338] and Beech-Jones at [339]-[370].
[214] (2024) 98 ALJR 1021; [2024] HCA 27, at [11].
[215] (2024) 98 ALJR 1021; [2024] HCA 27, at [60].
[216] Stubbings v Jams 2 Pty Ltd [2022] HCA 6; (2022) 276 CLR 1 at [56]; [2022] HCA 6; 96 ALJR 271. See ACL, s 21(4)(a).
[217] Stubbings v Jams 2 Pty Ltd [2022] HCA 6; (2022) 276 CLR 1 at [57]; [2022] HCA 6; 96 ALJR 271.
[218] Australian Securities and Investments Commission v Kobelt (2019) 267 CLR 1 at [92]; 93 ALJR 743. See also Stubbings v Jams 2 Pty Ltd [2022] HCA 6; (2022) 276 CLR 1 at [58]; [2022] HCA 6; 96 ALJR 271.
[219] Australian Securities and Investments Commission v Kobelt (2019) 267 CLR 1 at [153]; 93 ALJR 743.
[220] Stubbings v Jams 2 Pty Ltd [2022] HCA 6; (2022) 276 CLR 1 at [57]; Australian Securities and Investments Commission v Kobelt (2019) 267 CLR 1 at [217]; 93 ALJR 743.
[221] Stubbings v Jams 2 Pty Ltd [2022] HCA 6; (2022) 276 CLR 1.
[222] Stubbings v Jams 2 Pty Ltd [2022] HCA 6; (2022) 276 CLR 1 at [57]- [58] (footnotes omitted; emphasis in bold italics added.)
[223] L.U. Simon reply submissions (4.09.2025) at [8].
[226] [2023] NSWSC 585 at [26] (emphasis in bold italics added).
[228] (2008) 249 ALR 458, at [138] (per French, Jacobson and Graham JJ)) (emphasis in bold italics added).
[229] The 'seminal decision' of the High Court in Wood Hall Ltd v Pipeline Authority, [1979] HCA 21; (1979) 141 CLR 443.
[230] L.U. Simon outline (25.08.2025), [63].
[231] L.U. Simon outline (25.08.2025), [62].
[232] [2015] VSCA 98, [34].
[234] [2017] HCATrans 147, at 23-24.
[235] Austrak Pty Ltd v John Holland Pty Ltd [2006] QSC 103 at [29]‑[34]; Abigroup Contractors Pty Ltd v Peninsula Balmain Pty Ltd, Supreme Court of New South Wales, unreported, 2 December 1999; Barclay Mowlem Construction Ltd v Simon Engineering (Australia) Pty Ltd (1991) 23 NSWLR 451 at 461; Reed Construction Services Pty Ltd v Kheng Seng (Australia) Pty Ltd (1999) 15 BCL 158 at 167 per Austin J.
[236] CPB Contractors [2017] WASCA 123 at [112].
[237] [2017] HCATrans 147, at 24.
[240] First Fraser Affidavit, at [73]-[74].
[241] van Grieken Affidavit, at [25]-[27].
[242] Summons filed in the County Court, dated 22 August 2025.
[243] L.U. Simon outline (25.08.2025), [57].
[244] Transcript 17.09.2025, at 44 (Mr Harris KC).
[245] van Grieken Affidavit, Exhibit LVG-1, at 183.
[246] Transcript 17.09.2025, at 49-50 (Mr Harris KC).
[247] van Grieken Affidavit, Exhibit LVG-1, at 191-193.
[248] L.U. Simon outline (25.08.2025), [57].
[249] [2025] SASCA 72 (Livesey ACJ, S Doyle and B Doyle JJ).
[250] [2025] SASCA 72, at [5] (emphasis in bold italics added).
[251] [2025] SASCA 72, at [6]-[7] (emphasis in bold italics added).
[252] van Grieken Affidavit, [9], Exhibit LVG-1, at 18-19.
L.U. Simon Builders Pty Ltd
Cardigan Commercial Pty Ltd [2025] VSC 655
(1935) 53 CLR 643
(2003) 214 CLR 51
(2002) 117 FCR 301
(2000) 23 WAR 493
(2008) 249 ALR 458
(1991) 23 NSWLR 451
(2006) 149 FCR 135
(2021) 284 FCR 424
(1987) 14 FCR 215
(2010) 241 CLR 357
(2007) 161 FCR 513
(1994) 181 CLR 404
(2000) 200 CLR 270
(1979) 141 CLR 443
(2016) 260 CLR 85
(2006) 15 VR 65
(2006) 227 CLR 57
(1986) 161 CLR 148