CPB CONTRACTORS PTY LTD -v- JKC AUSTRALIA LNG PTY LTD [No 2] [2017] WASCA 123 (30 June 2017)
[2017] WASCA 123
At a glance
Source factsCourt
Court of Appeal (WA)
Decision date
2017-06-30
Before
Buss P
Source
Original judgment source is linked above.
Judgment (221 paragraphs)
1 The respondent (JKC) is the head contractor for the Ichthys LNG Project. The appellant (CPB) entered a subcontract (the Subcontract) with JKC as contractor for CPB as subcontractor to perform engineering procurement, construction and commissioning works relating to the on‑shore buildings associated with the Ichthys LNG Project.
2 Under the terms of the Subcontract the subcontractor was obliged to procure performance bonds in favour of the contractor in total amounts of about $26.1 million, that being 10% of the Subcontract price. The contractor has demanded from the subcontractor payment of liquidated damages of more than $39 million. The subcontractor disputes the contractor's entitlement to those liquidated damages. The contractor has given notice that, based on its claimed entitlement to liquidated damages, it intends to have recourse to the performance bonds.