[2023] NSWLEC 32
Land and Environment Court (NSW)
2023-03-01
Pain J
Original judgment source is linked above.
Solicitors: Pogson Cronin Kerr Solicitors & Notary (Applicant) Crown Solicitors Office (Respondent) File Number(s): 2022/18446
JUDGMENT Legislation Issues Chronology Evidence Evidence Book Applicant's evidence Respondent's evidence Mr He's evidence Ms Issaverdis' evidence Engineering evidence Summary of what the parties agreed in light of engineering evidence Plan of Management 2011 Fire Trail and Fire Management Evidence FAFT Fire Trail Standards Fire Management Strategy NPWS Internal Category 9 documents Applicant's submissions Issue 1: effect of Plan of Management 2011 (PoM). Duty owed Thoroughfare Pt 6 of PoM does not apply to Pt 5 duties If Pt 6 does apply to Pt 5 Issue 2, 3: 4WD/ 2WD Standard 4WD includes 4WD vehicle and trailer Meaning of all weather 2WD and 4WD Southern end of Cowdroys Road not a management trail Issue 5: unreasonable delay Respondent's submissions Issue 1: effect of Plan of Management 2011 (PoM) Duty owed Thoroughfare Pt 6 does apply to Pt 5 Issue 5: unreasonable delay Issues 2, 3: 4WD/2WD Standard A 4WD standard does not include 4WD vehicle towing a trailer Meaning of all weather 2WD and 4WD Southern end of Cowdroys Road a management trail Consideration Issue 1 Construction of s 81 NPW Act Construction of POM broadly Application of Pt 6 POM references to oyster growing Timing Construction of POM specific terms Thoroughfare Meaning of 'all weather 2WD standard' and 'all weather 4WD standard' (Issues 2, 3) No requirement in PoM to accommodate towing a boat trailer Conclusion on Issue 1 No unreasonable delay (discretionary application of limited funding) (Issue 5) Cowdroys Road beyond Gate 4 a management trail 4WD access available on Lagoon Trail and Cowdroys Road Conclusion Costs ORDERS
JUDGMENT
Legislation
Issues
Chronology
Figure 1: Road Classifications AMS data Cowdroys and Lagoon Fire Trail
Evidence Book
Applicant's evidence
Respondent's evidence
Mr He's evidence
Ms Issaverdis' evidence
Engineering evidence
Summary of what the parties agreed in light of engineering evidence
Plan of Management 2011
FAFT
Fire Trail Standards
Fire Management Strategy
NPWS Internal Category 9 documents
Issue 1: effect of Plan of Management 2011 (PoM).
Duty owed
Thoroughfare
Pt 6 of PoM does not apply to Pt 5 duties
If Pt 6 does apply to Pt 5
4WD includes 4WD vehicle and trailer
Meaning of all weather 2WD and 4WD
Southern end of Cowdroys Road not a management trail
Issue 5: unreasonable delay
Duty owed
Thoroughfare
Pt 6 does apply to Pt 5
Issue 5: unreasonable delay
A 4WD standard does not include 4WD vehicle towing a trailer
Meaning of all weather 2WD and 4WD
Southern end of Cowdroys Road a management trail
Consideration
Issue 1
Construction of s 81 NPW Act
Construction of POM broadly
Application of Pt 6
POM references to oyster growing
Timing
Construction of POM specific terms
Thoroughfare
Meaning of 'all weather 2WD standard' and 'all weather 4WD standard' (Issues 2, 3)
No requirement in PoM to accommodate towing a boat trailer
Conclusion on Issue 1
No unreasonable delay (discretionary application of limited funding) (Issue 5)
Cowdroys Road beyond Gate 4 a management trail
4WD access available on Lagoon Trail and Cowdroys Road
Conclusion
Costs
ORDERS
DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 24 March 2023
Neilson
Secretary, Department of Planning & Environment
(2019) 268 FCR 424
(1996) 186 CLR 389
(1981) 147 CLR 297
(1949) 80 CLR 533
(2013) 249 CLR 332
(1998) 194 CLR 355
(1983) 58 ALJR 36
(2021) 393 ALR 485
(2017) 262 CLR 362
(2014) 253 CLR 531
(1976) 135 CLR 110