[2021] QDC 280
General information, not legal advice.
District Court of Queensland
2021-12-10
Original judgment source is linked above.
CONTRACTS - REMEDIES - LIQUIDATED DAMAGES - PENALTY - where plaintiff claims liquidated damages from defendant under a subcontract - where defendant challenges liability for liquidated damages on three bases - where defendant contends that the liquidated damages clause in the subcontract is uncertain - where defendant contends that the liquidated damages clause is void as a penalty - where defendant contends that plaintiff is not entitled to liquidated damages because its acts prevented defendant from reaching Practical Completion and the so-called prevention principle is not excluded by the terms of the subcontract - whether the liquidated damages clause is void for uncertainty - whether the liquidated damages clause is void as a penalty - whether plaintiff's entitlement to recover liquidated damages for delay under the subcontract was lost in circumstances where it is assumed that plaintiff was the cause of defendant's delay or the delay was caused by plaintiff's breach of the subcontract
Uniform Civil Procedure Rules 1999 (Qld), r. 483, Part 5 of Chapter 13
Andrews v ANZ Banking Group Ltd [2012] HCA 30; (2012) 247 CLR 205
C B Darvall & Darvall v Moloney [2006] QSC 345; (2006) 236 ALR 796
Clydebank Engineering and Shipbuilding Company v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6
Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd [1914] UKHL 1; [1915] AC 79
Grocon Constructors (Qld) Pty Ltd v Juniper Developer (No 2) Pty Ltd [2015] QCA 291
Hervey Bay (JV) Pty Ltd v Civil Mining and Construction Pty Ltd [2008] QSC 58
Kane Constructions Pty Ltd v Sopov [2005] VSC 237
Law v Local Board of Redditch [1891] UKLawRpKQB 219; [1892] 1 QB 127
Paciocco v ANZ Banking Group Ltd (2016) 258 CLR 525
Peninsula Balmain Pty Limited v Abigroup Contractors Pty Limited [2002] NSWCA 211
Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151; (2017) 95 NSWLR 82
Ringrow Pty Ltd v BP Australia Pty Ltd [2005] HCA 71; (2005) 224 CLR 656
Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd (No 2) [2012] WASCA 53; (2012) 287 ALR 360
620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491
J D Heydon, Heydon on Contract (Lawbook Co., 2019)
(a) The liquidated damages clause in the subcontract is uncertain; or alternatively > > (b) The liquidated damages clause is void as a penalty; or alternatively > > (c) Midson is not entitled to liquidated damages because Midson's acts prevented Haggarty from reaching Practical Completion, and the so-called "prevention principle" is not excluded by the terms of the subcontract.
(a) the date certified by the Superintendent in a Certificate of Practical Completion issued pursuant to Clause 42.5, to be the date upon which Practical Completion was reached; or
(b) where another date is determined in any arbitration or litigation as the date upon which Practical Completion was reached, that other date;
'Drawings' means the drawings referred to in the Contract and any modification of such drawings notified to the Contractor by the Superintendent and includes such other drawings as may from time to time be supplied to the Contractor by the Superintendent, or the use of which has been permitted by the Superintendent, for the purposes of the Contract;
'person' includes a firm or body corporate or unincorporate or an individual;
'Practical Completion' is that stage in the execution of the work under the Contract when ---
(a) the Works are complete except for minor omissions and minor defects ---
(i) which do not prevent the Works from being reasonably capable of being used for their intended purpose; and
(ii) which the Superintendent determines the Contractor has reasonable grounds for not promptly rectifying; and
(iii) rectification of which will not prejudice the convenient use of the Works; and
(b) those tests which are required by the Contract to be carried out and passed before the Works reach Practical Completion have been carried out and passed; and
(c) documents and other information required under the Contract which, in the opinion of the Superintendent, are essential for the use, operation and maintenance of the Works have been supplied;
(b) By clause 35.2:
The Contractor shall execute the work under the Contract to Practical Completion by the Date for Practical Completion.
Upon the Date of Practical Completion the Contractor shall give possession of the Site and the Works to the Principal.
(c) By clause 35.5, the Head Contract contained a contractual regime providing for the extensions of time on the application of Midson for specified delays;
35.6 Liquidated Damages for Delay in Reaching Practical Completion
If the Contractor fails to reach Practical Completion by the Date for Practical Completion, the Contractor shall be indebted to the Principal for liquidated damages at the rate stated in the Annexure for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is terminated under Clause 44, whichever first occurs.
# The Date for Practical Completion: Tender to nominate in their tender submission
Project Description: San Damiano Yarrabilba Secondary Catholic College Stage 1 (Q066)
If nothing stated, the date notified by Midson Construction (QLD) Pty Ltd
If nothing stated, the date notified by Midson Construction (QLD) Pty Ltd
+ at Cost of Midson Construction (QLD) Pty Ltd @ $1000 per day.
(b) By Attachment 2: Special Conditions of Contract:
6. For Practical Completion to be achieved, all warranties, certificates including Form 15 & 16, Maintenance schedules, As Builts (if Required), Deed of Release signed and returned unamended to Midson and all works (Including any Defects or incomplete works) and documents required and requested are issued & completed to the satisfaction of the Client, Superintendent and the Principal Contractor.
(c) By Attachment 3: Subcontract General Conditions:
The Subcontractor must complete the work under the Subcontract by the Date for Completion, in accordance with the Subcontract and any applicable laws and standards.
(a) The Subcontractor must give Midson written notice five (5) Business Days before it anticipates achieving Completion.
(b) When the Subcontractor is of the opinion that Completion has been achieved, the Subcontractor must make a written request to Midson to issue a certificate of Completion.
(c) Upon receipt of a request under sub-clause 11(b) Midson will give to the Subcontractor:
(i) a notice certifying Completion has been achieved and the Date of Completion; or
(ii) a notice setting out reasons for rejecting the Subcontractor's request for a certificate of Completion (and the provisions of sub-clause 11(b) will reapply).
(a) Within two (2) Business Days of becoming aware of anything which will delay any party of the work under the Subcontract, the Subcontractor must notify Midson in writing of the nature of the delay. A notice under this sub-clause 13.1(a) is a condition precedent to the Subcontractor's entitlement to an extension of time.
(b) Within two (2) Business Days of the cause of the delay commencing (and weekly thereafter if the delay exceeds five (5) Business Days), the Subcontractor must provide Midson with details of the likely extent of the delay and its impact on the Date for Completion. A notice (or notices) under this sub-clause 13.1(b) must be in writing and is a condition precedent to the Subcontractor's entitlement to an extension of time.
13.2 Entitlement to and Claims for an Extension of Time
The Subcontractor may be entitled to an extension of time for Completion if:
(a) The Subcontractor is or will be delayed in reaching Completion by the Date for Completion by any of the following causes of delay:
(i) an act or omission of Midson (including an act of prevention), Separate Contractors, the Principal, the Principal's employees, agents or contractors, or the Superintendent;
(iii) a delay in granting Site access in accordance with sub-clause 7.1 [Non-exclusive possession];
(iv) a qualifying cause of delay stated in the Subcontract Particulars; or
(v) a cause of delay giving the Subcontractor an entitlement to an extension of time under another clause of the Subcontract,
(i) has provided the notices required under sub-clause 13.1 [Notifying Delays]; and
(ii) used all reasonable endeavours to mitigate the effects of the delay (inclusive of re-sequencing the work under the Subcontract),
(c) If the Subcontractor considers itself entitled to an extension of time for Completion it must within five (5) Business Days of the delay ceasing:
(i) give to Midson a written claim for an extension of time together with a statement of the facts upon which the claim is based; and
(ii) supply to Midson an updated Subcontractor's Program demonstrating the impact of the delay on the planned critical path network.
(d) If the Subcontractor is entitled to an extension of time Midson will determine a reasonable extension of time following receipt of the Subcontractor's claim under sub-clause 13.2(c)(i) and the updated Subcontractor's Program under sub-clause 13.2(c)(ii).
If the Subcontractor has been granted an extension of time for a delay caused by a breach of the Subcontract by Midson, Midson will pay the direct costs reasonably and necessarily incurred by the Subcontractor up to the maximum amount stated in the Subcontract Particulars. The Subcontractor agrees this is the only compensation it may recover from Midson for any delay or disruption, including any delay or disruption arising from a breach of contract by Midson.
Notwithstanding that the Subcontractor is not entitled to, or has not claimed, an extension of time, Midson may at any time and from time to time, award an extension of time for any reason. Midson is not required to exercise its discretion under this sub-clause for the benefit of the Subcontractor.
(a) If the Subcontractor fails to achieve Completion by the Date for Completion, the Subcontractor must pay to Midson the liquidated damages stated in the Subcontract Particulars for every day after the Date for Completion until the Date of Completion or termination (whichever occurs first).
(b) The parties agree the amount for liquidated damages stated in the Subcontract Particulars is an agreed genuine pre-estimate of Midson's loss and damages in the event Completion occurs after the Date for Completion.
(c) If the Head Contract Works do not reach Practical Completion by the date for Practical Completion under the Head Contract due to:
(i) a failure of the Subcontractor to reach Completion by the Date for Completion; or
(ii) a breach of any other obligation under the Subcontract by the Subcontractor,
the Subcontractor shall indemnify Midson against any liquidated damages under the Head Contract or any other damages that Midson becomes liable to pay under the Head Contract.
Completion means that stage in the execution of the work under the Subcontract when in Midson's opinion, the Works are complete except for minor omissions and minor defects, and all requirements for completion set out in the Trade Package have been met (inclusive of delivery, to Midson's satisfaction, of all as-built documentation and /or plans (if required)).
Date for Completion means the date (or period of time) stated in the Subcontract Particulars for Completion (if period of time the last day of that period).
Date of Completion means the date certified by Midson in a certificate of Completion pursuant to clause 11 [Completion] to be the date on which Completion was reached.
Head Contract means the contract between Midson and the Principal as amended at the date of execution of the Subcontract.
Head Contract Works means the whole of the work to be executed and completed in accordance with the Head Contract (including variations).
Practical Completion means practical completion of the Head Contract Works (as certified by the Principal or the Superintendent as the case may be).
Trade Package means the document entitled 'Trade Package' referred to in the Subcontract Agreement.
(a) The Subcontract provides that liquidated damages comprise $1,000 plus an additional $1,000 if liquidated damages are applied under the Head Contract; > > (b) Haggarty did not reach Completion under the Subcontract on the Date for Completion; > > (c) As at the date of the statement of claim, liquidated damages of $162,000 had accrued and would continue to accrue at the rate of $1,000 per day until Completion is achieved; > > (d) It is implicit in the particulars that only $1,000 has been sought for the period of the delay, consistent with the conclusion that no liquidated damages were applied under the Head Contract.
(a) It reached Completion by 18 December 2020 because all the works under the Contract had been completed. > > (b) Midson by certain conduct induced Haggarty to adopt the assumption that Midson accepted Haggarty had reached Completion on 18 December (or would not require strict compliance with the whole of the obligations which comprised reaching Completion), and that in reliance on that assumption, Haggarty did not promptly obtain the documentation required to reach Completion. Midson is said thereby to be estopped from asserting that Completion was not reached by 18 December. > > (c) By conduct amounting to giving notice that the Defects Liability Period had commenced under the Subcontract, Midson had elected to rely on rights under those provisions and thereby lost its rights arising out of a failure to reach Completion. > > (d) It had provided all the documents required for Completion under the Subcontract by 1 June 2021 and thereby reached Completion by that date at the latest.
(b) says that the Plaintiff has no entitlement to recover liquidated damages under the Contract because:
(i) the Plaintiff's right to obtain liquidated damages is contained in clause 14(a) of the Contract;
(ii) clause 14(a) of the Contract refers to the rate of liquidated damages specified in the Subcontract Particulars;
(iii) the applicable item in the Subcontract Particulars (LD Item) states that:
"As per Head Contract @ $1000 per day + at Cost of Midson Construction (QLD) Pty Ltd @ $1000 per day";
(v) in the premises of the matters pleaded in sub-paragraph (i) to (iv), clause 14(a) of the Contract and the LD Item are void for uncertainty...
(c) says, alternatively to sub-paragraph (b), that the Plaintiff has no entitlement to recover liquidated damages under the Contract because:
(i) the Plaintiff was engaged, pursuant to a contract with the Corporation of the Trustees of the Roman Catholic Archdiocese of Brisbane (ABN 499 910 068 57) (Head Contract), to perform work for the construction of the San Damiano Yarrabilba Secondary Catholic College (Overall Project);
(iii) the Plaintiff's right to liquidated damages under clause 14(a) and the LD Item of the Contract arose, on a proper construction of those provisions:
(iv) in the premises of the matters pleaded in sub-paragraphs (i) to (iii) herein, clause 14(a) and the LD Item constitute a penalty and, thereby, are unenforceable...
(a) Midson caused Haggarty to be delayed by 13 days because Midson failed to provide access to the site to commence work on the date for commencement under the Subcontract; > > (b) Midson cause Haggarty to be delayed by failing to provide access to Building C until 48 days after Haggarty ought to have been given access to that part of the site under the Subcontract; > > (c) Haggarty may be entitled to an extension of time under clause 13.2(a) of the Subcontract where delay is caused by an act or omission by Midson or by a failure to give access to the site in accordance with the Subcontract; > > (d) Haggarty was entitled to an extension of time under clause 13.2(a) for the each of the delays pleaded; > > (e) Haggarty pleaded clause 13.4 above and alleged that Midson was required to exercise its power under that clause in good faith, reasonably and fairly, to grant extensions for the two delays alleged.
(a) It denies that Haggarty reached Completion under the Subcontract on 18 December, because on the proper construction of the Subcontract, Completion required not only the completion of physical works, but also required the issue of all warranties and similar documents, and Haggarty did not provide all such documents until 5 August 2021; > > (b) It denies any estoppel arises from its conduct on various grounds unnecessary to particularise here; > > (c) It denies that it made an election in the manner alleged by Haggarty; > > (d) It repeats its allegation that provision of necessary documents for Completion occurred on 5 August 2021.
6. The Plaintiff denies the allegation of law pleaded in subparagraph 9(b) of the Defence and believes the allegation to be untrue because:
(a) of the matters pleaded in paragraphs 3(d), 7 and 8 of the amended statement of claim filed dated 25 May 2021 [the statement of claim];
(b) on a proper construction of the Contract, liquidated damages were $1,000 per day, plus an additional $1,000 per day if liquidated damages were applied under the Head Contract;
(c) the Plaintiff's entitlement to liquidated damages and the Subcontract Particulars were capable of being given clear meaning or effect in accordance with those terms;
(d) in the alternative:
(i) by clause 2.1 of the Contract, the Defendant was required to notify the Plaintiff within two business days of it become [sic] aware of any inconsistency or ambiguity in the Subcontract documents;
(ii) the Defendant did not give notice to the Plaintiff of any inconsistency or ambiguity of the kind alleged in subparagraph 9(d) despite the Defendant being on notice of liquidated damages being levied from at the latest 3 November 2020;
(e) in the premises, clause 14(a) of the Contract and the Subcontract Particulars are not void for uncertainty.
7. As to the allegations pleaded in subparagraph (c) of the Defence, the Plaintiff:
(a) admits the allegations pleaded in subparagraph (i);
(b) denies the allegations pleaded in subparagraph (ii) and believes the allegations to be untrue because:
(i) the physical works under the Contract were required to be performed or carried out by the Plaintiff under the Head Contract and part of the Overall Contract;
(ii) the Works under the Contract were identified by reference to the express terms of the Contract;
(1) Clauses 1.1, 1.9, 1.10, 2.3, 15, 20.10, 21.1, Attachment 4: Trade Package.
(c) denies the allegations pleaded in subparagraph (iii) and believes the allegations to be untrue because on a proper construction of the Contract:
(i) the Plaintiff's right to liquidated damages under clause 14(a) of the Contract and the Subcontract Particulars arose upon the Defendant failing to achieve Completion by the Date for Completion under the Contract in accordance with its express terms;
(ii) liquidated damages would not apply in part, to the extent of $1,000 per day, if liquidated damages were not levied against the Plaintiff under the Head Contract and the Defendant had failed to reach Completion by 1 November 2020;
(iii) the $1,000 per day was a genuine pre-estimate of the loss the Plaintiff would suffer if the Defendant failed to achieve Completion by the Date for Completion under the Contract in circumstances where the Defendant's estimated overhead costs were in the order of between $1,450 and $2,000 per day.
(1) the parties agreed that the liquidated damages in the Subcontract Particulars represented a genuine pre-estimate of the loss the Plaintiff may suffer should the Defendant not achieve Completion under the Contract;
(2) the Plaintiff was at risk of suffering loss in the payment of its overheads should the Defendant fail to achieve Completion by the Date for Completion;
(3) the Plaintiff was at risk of suffering loss in the payment of liquidated damages under the Head Contract, should the Principal or Superintendent (as the case may be) levy the same against the Principal for the Plaintiff's Failure to achieve Practical Completion on the Date for Practical Completion under the Head Contract;
(v) the achieving of Practical Completion or some other matter in the Head Contract were irrelevant to the Plaintiff's right to liquidated damages under clause 14(a) of the Contract and the Subcontract Particulars;
(vi) as a matter of law, clause 14(a) and the Subcontract Particulars did not constitute a penalty.
(a) The program for the Subcontract works provided for 60 days for the completion of those works, giving Haggarty 29 days contingency; > > (b) Midson gave sufficient access to the Site in accordance with the Subcontract for Haggarty to carry out works from 7 August 2020 and Haggarty could have commenced mobilisation works before then. Accordingly, any delay in providing access to the Site did not cause any delay to Haggarty in performing the works and any delay in commencing was caused by Haggarty's own acts; > > (c) Midson gave sufficient access to Building C to Haggarty in time for Haggarty to complete the Building C works, or alternatively, Haggarty could have dealt with any such delay by reprogramming its works. Accordingly, any delay in providing access to Building C did not cause any delay to Haggarty in performing the works and any delay in the Building C works was caused by Haggarty's own acts.
(i) was to be exercised in the Plaintiff's sole direction [sic]; and
(ii) was not required to be exercised for the benefit of [Haggarty]
(a) Whether clause 14(a) of the Subcontract is void for uncertainty (the uncertainty question); > > (b) Whether clause 14(a) of the Subcontract is void as a penalty (the penalty question); > > (c) Whether, properly construed, Midson's entitlement to recover liquidated damages for delay under the Subcontract was lost in circumstances where the following factual circumstances are assumed for the purposes of this hearing: > > > (i) Midson was the cause of Haggarty's delay; or > > > > (ii) The delay was caused by Midson's breach of the Subcontract (the prevention question).
Part 5 Separate decision on questions
482 Definition for pt 5
question includes a question or issue in a proceeding, whether of fact or law or partly of fact and partly of law, and whether raised by pleadings, agreement of parties or otherwise.
483 Order for decision and statement of case for opinion
(1) The court may make an order for the decision by the court of a question separately from another question, whether before, at, or after the trial or continuation of the trial of the proceeding.
If a question is decided under this part, the court may, subject to rule 475, make the order, grant the relief and give the directions that the nature of the case requires.
The court may, in relation to a decision of a question under this part, as the nature of the case requires -
(a) dismiss the proceeding or the whole or part of a claim for relief in the proceeding; or
(b) give judgment, including a declaratory judgment; or
(c) make another order.
(a) set out the question or questions to be decided; and
(b) be divided into paragraphs numbered consecutively.
[42] The Court has a wide discretion whether to order the separate determination of questions, and the contemporary approach is to do so where questions can conveniently be so decided, even though this may not necessarily resolve the whole dispute. In Reading Australia Pty Ltd v Australian Mutual Provident Society Branson J reviewed the principles relevant to the application of a cognate provision in the Federal Court Rules. Her Honour noted that -
"(d) where the preliminary question is one of mixed fact and law, it is necessary that the question can be precisely formulated and that all of the facts that are on any fairly arguable view relevant to the determination of the question are ascertainable either as facts assumed to be correct for the purposes of the preliminary determination, or as agreed facts or as facts to be judicially determined."
[43] Here the parties presented the Court with a list of separate questions in relation to the estoppel and indemnity questions. In relation to the former they said -
"The following are the facts agreed upon by the parties"
and then set out in separate paragraphs more than 4 pages of facts upon which the Court was asked to determine certain questions. By agreement, those facts were supplemented at the hearing by a number of affidavits and a further agreed fact. In relation to the indemnity questions they said -
"The Court is asked to assume the following facts and contentions"
and then set out in separate paragraphs more than a page of facts and contentions, before saying -
"In light of the assumed facts and contentions, the following questions are stated for determination by the Court."
[44] At the hearing it became apparent that those representing Darvalls saw a significant difference between "facts agreed upon between the parties" and "assumed facts and contentions" - a difference not recognised by those representing the liquidators. Senior counsel for Darvalls was at pains to dispel any suggestion that his clients had sought some forensic advantage. He submitted that there was utility in proceeding on the basis that if the Court considered the assumed facts to be sufficient to arrive at conclusions on the indemnity issues, that would foreclose the issue on those questions, but if it considered them insufficient, that would not foreclose the issue. The essence of his submission seemed to be that if the Court took the view that because of the assumed facts, no matter what other facts might be proved, his clients could not succeed, then a long factual inquiry would be obviated.
[45] It is not the Court's function to determine questions on a hypothetical basis. The questions in relation to legal expenses incurred from 17 December 1999 are of mixed fact and law. In Bass v Permanent Trustee Co Ltd the High Court said -
"Special problems can arise where the preliminary question is one of mixed fact and law. As Brooking J pointed out in Jacobson v Ross, it is necessary in that situation that there be precision both in formulating the question and in specifying the facts upon which it is to be decided. His Honour added:
'Care must be taken to ensure that, in one way or another, all the facts that are on any fairly arguable view relevant to the determination of the question are ascertainable ... as facts assumed to be correct for the purposes of the preliminary determination, or as facts which both sides accept as correct, or as facts which are to be judicially determined. Failure to do this, and in particular failure to perceive that the facts alleged in a pleading are some only of the facts relevant to the determination of the preliminary question, may make the order for preliminary determination unfruitful.'
Quite apart from rendering the 'order for preliminary determination unfruitful', the failure to identify the relevant facts or the means by which they are to be ascertained may result in procedures which do not conform to the judicial process. That is a matter to which it will be necessary to return."
Assumed and admitted facts: uncertainty question
(a) That Haggarty did not comply with the EOT claim process in clauses 13.1 and 13.2 in respect of any Midson-caused delay; and > > (b) The only basis upon which Haggarty could avoid liability for liquidated damages resulting from that delay is if Haggarty can rely on the prevention principle as setting time at large, despite the provision for extension of time in those clauses.
Even if a contract seems to have more than one possible meaning or lead to more than one result or use very wide language or throw up difficulties in its interpretation, it is not necessarily void if the processes of construction lead to the choice of the meaning. It is only void "if the court is unable to put any definite meaning upon the contract". "[C]ourts will not lightly accept defeat in the search for meaning".
The court's reluctance to nullify contracts by demanding unrealistically high standards of clarity is reflected in a willingness to face up to difficulty in construction. The court, said Lord Wright, will not uphold any purported contract which is "so obscure and so incapable of any definite or precise meaning that [it] is unable to attribute to the parties any particular contractual intention". Impossibility of identifying meaning, in that sense, is one thing. Mere difficulty in doing so is another. In approving the words just quoted, Barwick CJ said in Upper Hunter County District Council v Australian Chilling and Freezing Co Ltd:
[A] contract of which there can be more than one possible meaning or which when construed can produce in its application more than one result is not therefore void for uncertainty. As long as it is capable of a meaning, it will ultimately bear that meaning which the courts, or in an appropriate case, an arbitrator, decides is its proper construction: and the court or arbitrator will decide its application. The question becomes one of construction, of ascertaining the intention of the parties, and of applying it... In the search for [contractual] intention, no narrow or pedantic approach is warranted, particularly in the case of contractual arrangements. Thus will uncertainty of meaning, as distinct from absence of meaning or of intention, be resolved.
(a) First, liquidated damages clauses are ubiquitous in commercial construction contracts; and > > (b) Second, Haggarty, as a participant in the construction industry, would be taken to be aware that it was likely such terms existed, especially where there was a reference to the Head Contract in the LD Item in its own Subcontract.
(a) The remedies are distinct. The LD Item creates an absolute obligation to pay liquidated damages under the Head Contract if they are payable by Midson. As is the way with such clauses, it makes it unnecessary to prove causation or quantum. The indemnity clause, on the other hand, requires proof of causation; > > (b) The remedies are likely to complement each other in their operation. If liquidated damages are paid under the LD Item for liquidated damages under the Head Contract, then there will be no loss to which the indemnity can apply. If the liquidated damages clause is invalid, or not applied, then the indemnity will operate if Midson can prove causation.
(a) $1,000 per day plus; > > (b) A further $1,000 per day for each day Midson is obliged to pay liquidated damages to the Principal under the terms of the Head Contract in the period between the Date for Completion under the Subcontract and the date of Completion.
(a) At the time of entry into the Subcontract, the principal interest which Midson could properly protect by its liquidated damages clause in the Subcontract was the costs of maintaining its establishment on site later than it otherwise would have (establishment costs); > > (b) This proposition is supported by the fact that Midson contends that its liquidated damages were a reasonable pre-estimate of loss by reference to establishment costs; > > (c) At the time of entry into the Subcontract, reasonable persons in the position of the parties would have understood that liquidated damages could by payable under the Subcontract after Practical Completion under the Head Contract; > > (d) It was inevitable that on reaching Practical Completion under the Head Contract, Midson would cease to maintain its establishment on site, and therefore would not be exposed to the risk of incurring establishment costs as a result of delay in Completion under the Subcontract; > > (e) Midson has no other interest in Haggarty reaching Completion by the due date which could sustain the liquidated damages at $1,000 per day, particularly where all substantive work is completed and the only part of the Completion obligation outstanding is the provision of warranties and the like. Not only would the damage resulting from such non-compliance be minimal, but it was not consequent on the failure to reach Completion, but rather on the failure to comply with the substantive obligation to provide the warranties; > > (f) The liquidated damages clause was a penalty because it could operate in a manner which required payment of $1,000 per day for late Completion, despite Practical Completion under the Head Contract, and despite the fact that Midson had no exposure to substantive loss in the form of establishment costs after that time. The operation of the clause in that way required payment of an exorbitant sum which constituted a punishment for the failure to reach Completion, rather than a genuine pre-estimate of loss.
(a) Midson relies on authorities which reject the proposition that the validity of Practical Completion clauses can be assessed by reference to the range of individual obligations which comprise Practical Completion. Midson contends that Haggarty's argument focuses on a particular incident of the single obligation (in this case, providing warranties), and is thereby inconsistent with those cases; and > > (b) Midson submits that even if the establishment costs come to an end, there would remain additional costs incurred by Midson in administering the process of pursuing Haggarty for incomplete work, including incomplete provision of warranties. These costs would be difficult to assess, but it cannot be said that the $1,000 per day amount is so exorbitant as to make it a penalty.
[10] The law of penalties, in its standard application, is attracted where a contract stipulates that on breach the contract-breaker will pay an agreed sum which exceeds what can be regarded as a genuine pre-estimate of the damage likely to be caused by the breach.
[11] The starting point for the appellant was the following passage in Lord Dunedin's speech in Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd:
"2. The essence of a penalty is a payment of money stipulated as in terrorem of the offending party; the essence of liquidated damages is a genuine covenanted pre-estimate of damage ...
3. The question whether a sum stipulated is penalty or liquidated damages is a question of construction to be decided upon the terms and inherent circumstances of each particular contract, judged of as at the time of the making of the contract, not as at the time of the breach ...
4. To assist this task of construction various tests have been suggested, which if applicable to the case under consideration may prove helpful, or even conclusive. Such are:
(a) It will be held to be penalty if the sum stipulated for is extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved to have followed from the breach ...
(b) It will be held to be a penalty if the breach consists only in not paying a sum of money, and the sum stipulated is a sum greater than the sum which ought to have been paid ...
(c) There is a presumption (but no more) that it is penalty when 'a single lump sum is made payable by way of compensation, on the occurrence of one or more or all of several events, some of which may occasion serious and others but trifling damage'."
[12] Neither side in the appeal contested the foregoing statement by Lord Dunedin of the principles governing the identification, proof and consequences of penalties in contractual stipulations. The formulation has endured for ninety years. It has been applied countless times in this and other courts. In these circumstances, the present appeal afforded no occasion for a general reconsideration of Lord Dunedin's tests to determine whether any particular feature of Australian conditions, any change in the nature of penalties or any element in the contemporary market-place suggest the need for a new formulation. It is therefore proper to proceed on the basis that Dunlop Pneumatic Tyre Co Ltd v New Garage and Motor Co Ltd continues to express the law applicable in this country, leaving any more substantial reconsideration than that advanced, to a future case where reconsideration or reformulation is in issue.
[31] Thirdly, consideration of the purpose of the law of penalties shows why this must be so. The law of contract normally upholds the freedom of parties, with no relevant disability, to agree upon the terms of their future relationships. As Mason and Wilson JJ observed in AMEV-UDC Finance Ltd v Austin:
"[T]here is much to be said for the view that the courts should return to ... allowing parties to a contract greater latitude in determining what their rights and liabilities will be, so that an agreed sum is only characterised as a penalty if it is out of all proportion to damage likely to be suffered as a result of breach."
[32] Exceptions from that freedom of contract require good reason to attract judicial intervention to set aside the bargains upon which parties of full capacity have agreed. That is why the law on penalties is, and is expressed to be, an exception from the general rule. It is why it is expressed in exceptional language. It explains why the propounded penalty must be judged "extravagant and unconscionable in amount". It is not enough that it should be lacking in proportion. It must be "out of all proportion". It would therefore be a reversal of longstanding authority to substitute a test expressed in terms of mere disproportionality. However helpful that concept may be in considering other legal questions, it sits uncomfortably in the present context.
[9] Mason and Deane JJ observed in Legione v Hateley that, as the term suggests, a penalty is in the nature of a punishment for non-observance of a contractual stipulation and consists, upon breach, of the imposition of an additional or different liability.
[10] In general terms, a stipulation prima facie imposes a penalty on a party (the first party) if, as a matter of substance, it is collateral (or accessory) to a primary stipulation in favour of a second party and this collateral stipulation, upon the failure of the primary stipulation, imposes upon the first party an additional detriment, the penalty, to the benefit of the second party. In that sense, the collateral or accessory stipulation is described as being in the nature of a security for and in terrorem of the satisfaction of the primary stipulation. If compensation can be made to the second party for the prejudice suffered by failure of the primary stipulation, the collateral stipulation and the penalty are enforced only to the extent of that compensation. The first party is relieved to that degree from liability to satisfy the collateral stipulation.
A sum out of all proportion to the interests protected
[51] Lord Dunedin said in Dunlop that there may be no reason to suspect that the figure agreed by the parties, in the case where loss is difficult to estimate, is "a penalty to be held in terrorem", "provided that figure is not extravagant". Lord Atkinson and Lord Parmoor also held that the figure in question was not extravagant, unconscionable or extortionate.
[52] The process to be undertaken in order to determine whether an amount is unconscionable or extravagant was not further explained in Dunlop and Clydebank. The figure agreed to be paid cannot be compared with a sum certain, as is the case with Lord Dunedin's first "test". It can only be gauged against the identified interests of the party in whose favour the stipulation is made. It may be inferred from Dunlop and Clydebank that the interests in question were regarded as substantial and the possibility of damage to them real. The sum agreed to be paid in those cases was not incommensurate with the relevant interests.
[53] In Clydebank, the Earl of Halsbury LC did not consider that a rule could be laid down as to when a stipulation could be said to be extravagant or unconscionable and that much would depend upon the circumstances of each case. However, it is to be inferred from the adjectives chosen that not every sum in excess of what might be strictly compensatory will amount to a penalty. This is confirmed by the example, admittedly extreme, which his Lordship then gave of an agreement to build a house for £50 but "to pay a million of money as a penalty" if the house was not built. This suggests that a person contending that a sum is a penalty will be facing a high hurdle. Lord Hodge was later to observe in Cavendish that the criterion of exorbitant or unconscionable should prevent the enforcement of only egregious contractual provisions.
[54] In Ringrow, it was held that a sum which was merely disproportionate to the loss suffered would not qualify as penal. It was explained that exceptions from freedom of contract "require good reason to attract judicial intervention to set aside the bargains upon which parties of full capacity have agreed", which is why the law on penalties is expressed as an exceptional rule and in exceptional language. The Court went on:
"It explains why the propounded penalty must be judged 'extravagant and unconscionable in amount'. It is not enough that it should be lacking in proportion. It must be 'out of all proportion'."
In Cavendish, Lord Neuberger and Lord Sumption said that the true test is whether the provision is a secondary obligation which imposes a detriment on the party in breach "out of all proportion to any legitimate interest of the innocent party in the enforcement of the primary obligation".
[55] Australian and United Kingdom law are not alone in maintaining a standard to be applied to a requirement to pay money, or some other detriment, which is imposed in the event of default. In many other western legal systems something like the penalty doctrine exists. In Andrews, reference was made to s 343 of the German Civil Code, which provides that a "disproportionately high" penalty may be reduced by a court after taking into account "every legitimate interest" of the party for whose benefit the stipulated sum is made. Such interests are not limited to that party's economic interests. In Cavendish, Lord Hodge referred to provisions in other modern civil codes and international instruments which use tests such as whether the sum stipulated is "manifestly excessive" or "substantially disproportionate" in order to modify or restrict contractual penalties.
[56] It has earlier been observed that the nature of an interest and of the injury to it may make for difficulties of proof that the sum stipulated is a penalty. In Clydebank, Lord Robertson acknowledged that the problem was not one for the Spanish government:
"But, in truth, the only apparent difficulty in the present case arises from the magnitude and complexity of the interests involved and of the vicissitudes affecting them, and as the question is whether this stipulation of £500 a week is unconscionable or exorbitant, these considerations can hardly be considered a formidable difficulty in the way of the respondents."
[65] It was her Honour's view that loss provisions and regulatory capital costs are part of the costs of running a bank in Australia. Banks may, and do, seek damages for default, but they are limited to the sums outstanding, enforcement costs and interest. However, as has been explained, the question is not what the ANZ could recover in an action for breach of contract, but rather whether the costs to it and the effects upon its financial interests by default may be taken into account in assessing whether the Late Payment Fees are penalties.
[66] The primary judge accepted and applied Mr Regan's evidence. Her Honour considered that the main difficulty with Mr Inglis' evidence was that he did not calculate actual loss or damage, but rather engaged in a broad-ranging exercise of identifying "costs" that might be affected by late payment, in a more theoretical, accounting, sense. In her Honour's view this did not assist in answering the question which she had earlier identified: to what extent (if any) did the amount stipulated to be paid exceed the quantum of the relevant loss or damage which can be proved to have been sustained by the breach. But of course framing the question in this way takes no account of the ANZ's other interests which were said to be addressed by the Late Payment Fees and which extend beyond the recovery of compensation for loss.
[67] The primary judge accepted that whilst the actual losses suffered by the ANZ by reason of the late payments could not be precisely determined, they were probably no more than $3 for each event of late payment (based on Mr Regan's evidence) and in any event much less than the $20 or $35 charged as a Late Payment Fee. They were therefore extravagant and unconscionable.
[68] Mr Inglis' evidence identified the costs to which the ANZ would be subject in the event of a late payment as a range which exceeded the amounts of the Late Payment Fee. His calculations were criticised as overly generous. It is not necessary to resolve any such controversy. The effect of Mr Inglis' evidence was to identify potential costs to the ANZ, from late payments, which reflect injuries to its financial position. They were real because they had to be taken into account by the ANZ. The evidence called for the appellants did not address damage of this kind. It cannot therefore be concluded that the sums of $20 and $35 were out of all proportion to the interests so identified.
[69] It may be accepted that it is difficult to measure the loss to the ANZ as a result of a late payment. Consistently with Clydebank, Dunlop, Ringrow and Andrews, the relevant question in this case is whether the Late Payment Fee is out of all proportion to the ANZ's interest in receiving timeous payment of the minimum Monthly Payment. Applying this test, the appellants did not establish that the Late Payment Fee was a penalty. The appeal should be dismissed with costs.
[157] In O'Dea v Allstates Leasing System (WA) Pty Ltd, Wilson J asked of the stipulation in issue in that case whether it "can be considered to be a 'genuine pre-estimate of the creditor's ... probable or possible interest in the due performance of the principal obligation'" (citing Hills) or "whether it is a penalty inserted 'merely to secure the enjoyment of a collateral object'" (citing Sloman v Walter). That succinct framing of the inquiry is consistent with Andrews and Dunlop. It is also very useful.
[158] The ultimate question of whether a stipulation imposing a detriment on a contracting party in the event of non-observance of another stipulation is a penalty is reflected in the formulation Wilson J drew from Sloman v Walter. To ask whether a stipulation serves merely to secure the enjoyment of a collateral object is to ask whether the conclusion objectively to be drawn from the totality of the circumstances is that the only purpose of the stipulation was to punish: to impose a detriment on a contracting party in the event that a principal contractual stipulation is not observed, in order to deter non-observance of that principal stipulation. To ask that question in the context of a stipulation for the payment of money on breach of contract accords with the statement of Lord Dunedin in Dunlop that "[t]he essence of a penalty is a payment of money stipulated as in terrorem of the offending party".
[159] The formulation Wilson J drew from Hills does not indicate some separate or different inquiry but rather indicates the nature of the inquiry involved in considering whether a stipulation has some purpose other than to punish. The formulation captures in positive and more elaborate terms what Lord Dunedin reflected in negative and cryptic terms when he added, as a reflex of the essence of a penalty, that "the essence" of a payment of money on breach of contract that is not a penalty is that the amount of the payment "is a genuine covenanted pre-estimate of damage". To ask whether a stipulated payment is a genuine pre-estimate of the innocent party's probable or possible interest in the due observance of the principal contractual stipulation is to ask whether an interest which the innocent party has in the observance of that principal stipulation explains the stipulation for payment as having a purpose other than to punish the offending party. Such an interest of the innocent party in the observance of a principal contractual stipulation need not be an interest in respect of which the offending party would otherwise be compelled to compensate the innocent party at law (or in equity) in the event of non-observance.
[160] Where the stipulated detriment is in the form of an obligation to pay a specified sum of money in the event of a breach of contract, a comparison of the specified sum with the amount of the unliquidated damages which might be expected to be recovered by the innocent party in an action for breach of contract will often be probative of whether the only purpose of the stipulation is to punish. Such a comparison might sometimes be decisive. Not always.
[161] The facts in Clydebank and Dunlop both sufficiently illustrate that interests of the innocent party beyond the protection of an award of unliquidated damages in the event of a breach of contract can justify a different conclusion. The protection afforded by the stipulation of an obligation to pay a specified sum of money in the event of a breach of contract might be to interests that the innocent party has in contractual performance which are intangible and unquantifiable. A party seeking contractually to protect its interests by insisting on a stipulation that another party pay a specified sum of money in the event of breach cannot be limited by considerations of common law causation of damage to protecting only against incremental loss that the party would sustain as the direct result of that breach.
[162] Nor can a party seeking contractually to protect that party's interests by insisting on such a stipulation be compelled by considerations of common law remoteness of damage to absorb actual damage to those interests consequential on breach merely because the nature and extent of that damage might not be apparent to the other party at the time of entering into the contract. The English Law Commission correctly observed in 1975 that "[t]here would seem to be no reason why the parties in Hadley v Baxendale could not have contracted for liquidated damages assessed on the footing that the mill would continue to be at a standstill".
[164] And as the facts in Clydebank and Dunlop again both sufficiently illustrate, the fact that the amount of a payment stipulated to be made on breach of contract is set at a level which provides a negative incentive - even a very strong negative incentive - to perform the contract is not enough to justify the conclusion that the stipulation served only to punish. The prospect of paying compensatory damages to be assessed by a court in the event of breach itself provides a negative incentive to perform a contract. The relevant indicator of punishment lies in the negative incentive to perform being so far out of proportion with the positive interest in performance that the negative incentive amounts to deterrence by threat of punishment.
[176] Each category of costs identified by Mr Inglis represented a commercial interest of ANZ in ensuring observance by its consumer credit card customers of the principal stipulation in each of their contracts for payment of the minimum monthly payment by the due date. The customers' grounds of appeal to this Court do not encompass any challenge to Mr Inglis' evidence of their quantification. In light of those interests, it cannot be concluded that the inclusion in the credit card contracts of the stipulation for charging and payment of the late payment fee properly had no purpose other than to punish the account holder in the event of late payment. The stipulation was not merely in terrorem; the late payment fee was not just a punishment.
[268] Fourthly, Lord Dunedin's summary was meant as a guide to the application of the rule. His Lordship's propositions were not intended to be applied as if they were the provisions of a statute. The terms "extravagant" and "unconscionable" in Lord Dunedin's proposition 4(a) are not used in contradistinction to reasonable, much less as free-standing criteria of invalidity. In proposition 4(a), the terms "extravagant" and "unconscionable" function as pointers towards the punitive purpose which imbues the challenged provision with the character of a punishment. And as Lord Neuberger and Lord Sumption said in Cavendish Square, "the real question" is whether the impugned provision "is penal, not whether it is a pre-estimate of loss".
[269] In Cavendish Square (344), Lord Neuberger and Lord Sumption accepted that, although there was "a case" for judicial abrogation of the penalty rule on the ground that it is "antiquated, anomalous and unnecessary, especially in the light of the growing importance of statutory regulation", the penalty rule should be retained because it serves the useful purpose of preventing a party from exercising a remedy where "the adverse impact of [the remedy] on the defaulter significantly exceeds any legitimate interest of the innocent party". Lord Neuberger and Lord Sumption considered that the courts can avoid inappropriate application of the penalty rule:
"(i) by [proceeding upon] a realistic appraisal of the substance of contractual provisions operating on breach, and (ii) by taking a more principled approach to the interests that may properly be protected by the terms of the parties' agreement."
[270] In Andrews, this Court summarised the "critical issue" as being "whether the sum agreed was commensurate with the interest protected by the bargain". This Court's discussion in Andrews of the decision in Dunlop focused upon the reasons of Lord Atkinson, who accepted that an agreed payment upon breach should not be unenforceable where, though it "appeared imprecise as a pre-estimate of damage, it protected the [seller's] interest in preventing undercutting, which would disorganise its trading system". Accordingly, the question to be addressed in order to distinguish a penalty from a provision protective of a legitimate interest is:
"whether the sum or remedy stipulated as a consequence of a breach of contract is exorbitant or unconscionable when regard is had to the innocent party's interest in the performance of the contract."
[280] The appellants argued that the Full Court misapplied Lord Dunedin's proposition 4(a). They noted that the expression used in Dunlop - "the greatest loss that could conceivably be proved to have followed from the breach" - speaks only of damages recoverable by action in consequence of a breach of contract and not of loss which is too remote to be compensated by an award of damages. The appellants' submission was that it is not the case that any set of circumstances resulting in loss that might be hypothesised can be taken into account in assessing whether a clause is penal.
[281] The appellants submitted that the primary judge was correct to reject ANZ's submission that "increase in loss provisions" and "increase in the cost of regulatory capital" were losses incurred as a result of late payment and to conclude that these matters were too remote to form part of compensable damage. The appellants also argued that, to the extent that the Full Court held that collection costs exceeding the amount of the late payment fee could be taken into account, that finding should be set aside.
[282] It is not the case that authoritative formulations of the test of punitive extravagance are invariably stated in terms of a comparison between the impugned payment and what might be recovered by litigation. This Court said in Ringrow:
"The law of penalties, in its standard application, is attracted where a contract stipulates that on breach the contract-breaker will pay an agreed sum which exceeds what can be regarded as a genuine pre-estimate of the damage likely to be caused by the breach."
[283] It will be noted that this formulation of the rule does not depend upon a demonstration of the quantum of damages which would be recovered in an action. To speak of damage, as opposed to damages, is to speak of the loss caused by the breach, not the remedy which might be awarded by a court. To speak of a "genuine pre-estimate of the damage" is to speak of the damage liable to be suffered by those parts of the bank's legitimate business interest that it is trying to protect. A genuine pre-estimate of that damage may encompass items of loss actually suffered, albeit too remote to be compensable by way of damages by virtue of the rules in Hadley v Baxendale. An agreement for the recovery of such loss is consistent with the absence of a punitive purpose. For a party to stipulate for a more ample remedy than is available at law is not to visit a punishment on the other party.
[284] An agreed provision avoids the uncertainty and expense of litigation. The benefit of such a provision to both parties and to the legal system is obvious. Even in medieval times, the authority we know as Bracton considered that a clause providing for the payment of an agreed sum upon a breach of contract served the legitimate purpose of removing the uncertainty and expense of litigation involved in establishing the quantum of damages recoverable for a breach of contract.
[4] The critical issue is whether the definition of "Practical Completion" set out in the contract had the effect of attracting the operation of proposition 4(c) articulated by Lord Dunedin in Dunlop Pneumatic Tyre Company Limited v New Garage & Motor Company Limited:
"(c) There is a presumption (but no more) that it is penalty when 'a single lump sum is made payable by way of compensation, on the occurrence of one or more or all of several events, some of which may occasion serious and others but trifling damage'."
[20] It is not in issue here that the penalties doctrine applies. A necessary element at law, but not in equity, is that the stipulation is payable on breach of a term of the contract. For present purposes there is no relevant distinction between equity and contract. The agreed premise here is that Grocon breached the contract triggering the liquidated damages clause.
[21] The onus is on the party alleging that the penalties doctrine is applicable.
[22] Whether a provision is a penalty at law is a question of construction that must be determined as a matter of substance viewing the contract as a whole. That question of construction however "is one of construction in a wide sense, falling to be decided by the meaning and content of the words and on the inherent circumstances of each particular contract, judged at the time of its making": Paciocco v Australia and New Zealand Banking Group Ltd [2015] FCAFC 50 per Allsop CJ at [95].[5]
[23] The provision will not be a penalty unless it is "extravagant and unconscionable in amount in comparison with the greatest loss that could conceivably be proved." This is the "essential element (at law or in equity)" that the sum be "extravagant, exorbitant and unconscionable": Dunlop Pneumatic Tyre Company Ltd v New Garage & Motor Co Ltd [1914] UKHL 1; [1915] AC 79 at 86-87; Ringrow Pty Ltd v BP Australia Pty Ltd [2005] HCA 71; 224 CLR 656 at 669 [31]- [32]; Clydebank Engineering and Shipbuilding Company v Don Jose Ramos Yzquierdo y Castaneda [1905] AC 6 at 10 and 17; AMEV-UDC Finance Ltd v Austin [1986] HCA 63 ; 162 CLR 170 at 197 and 201.[6]
[24] The question is to be assessed as at the time of entry into the contract. It is not a mechanical task.
[47] The obligation in Law was that "the works shall be completed in all respects, and cleared of all implements, tackle, impediments, and rubbish, on or before April 30, 1889" and in default stated damages to be paid. Like here, the argument was put that trifling failures involving no conceivable loss of significance to the Board - one example given being the leaving of a wheelbarrow on site - would trigger the payment. To this Kay LJ said:
"I cannot agree with the ingenious argument that, because there may be many matters, some very small, which would constitute non-completion, these sums may be regarded as payable on several events. According to that argument, it must be considered to be several different non-completions of the works. There may be different causes of non-completion; but non-completion is only one single event."
[72] Generally speaking there is no reason to think that the various matters that the parties considered essential to Practical Completion as contemplated in the Deed were not of importance. They were very likely to be of importance to someone buying a residential unit. The particularity suggests that Juniper expected close attention to detail. However most of Grocon's allegedly "minor breaches" find no place in these "conditions precedent" that were plainly intended to guide the Certifier. Indeed the only minor breach left from the list in Grocon's Outline that I can see is the complaint that a failure to provide a single manual may result in a refusal to achieve Practical Completion (see (i) above). I am not prepared to hold that any different effect is brought about by that one example. As Lord Woolf said in Philips "the use in argument of unlikely illustrations should therefore not assist a party to defeat a provision as to liquidated damages." As well, the point made by Clarke LJ in Makdessi is relevant: "...the fact that a breach may give rise to trifling ... damage may not be determinative if the parties can be regarded as having regarded the trifling as unlikely." I think it highly unlikely that the parties considered that a failure to attend to a trivial matter would lead to any delay.
It was Juniper's intention to sell the retail part of the project and the residential units. Juniper had entered into finance agreements with external creditors, to carry out the project. Juniper contemplated that it would generate revenue from the project, to repay the external creditors, through the sale of the retail part of the project, and the sale of residential units. Thus Juniper would suffer financial loss if the contemplated revenue stream was postponed by any delay in completion of the contract.
(a) The delay in reaching Completion under the Subcontract was caused by Midson's conduct in failing, in breach of its obligations under the Subcontract, to give Haggarty access to the Site and to one of the buildings on the Site; and > > (b) That conduct prevented Haggarty from reaching Completion by the due date, and consequently, time under the Subcontract was set at large and Midson lost the right to claim liquidated damages.
(a) By clauses 13.1 and 13.2, the Subcontract had a suite of provisions which entitled Haggarty to seek an extension of time and provided a remedy for principal-caused delay pursuant to the contract; and > > (b) Haggarty failed to seek an extension of time in respect of those delays in accordance with the contract.
47 Against that background, I turn to the law on the subject. The most comprehensive and comprehensible discussion of the topic is in Hudson's Building and Engineering Contracts (12th ed, 2010) [6-025] - [6-035]. I rely on that source, which in my assessment reflects the law in Australia. The essence of the prevention principle is that a party cannot insist on the performance of a contractual obligation by the other party if it itself is the cause of the other party's non-performance. This may be regarded as a particular manifestation of the obligation to cooperate implied as a matter of law in all contracts: Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd [1979] HCA 51; (1979) 144 CLR 596, 607 (Mason J).
48 The prevention principle clearly applies to delays in practical completion caused by a breach of contract by the principal. In a construction law context, it also applies to other acts (or omissions) of the principal within the scope of the contract that prevent practical completion within the fixed period. Variations are an obvious example. However, the prevention principle has no application to delays that are not caused by the act or default of the principal.
49 If as a result of the prevention principle the contractual date for practical completion has ceased to be the proper date for the completion of the works and there is no contractual mechanism for the substitution of a new date in the events which have occurred, then there is no date from which liquidated damages can run and the right to liquidated damages will be lost: Peak Construction (Liverpool) Ltd v McKinney Foundations Ltd (1970) 1 BLR 111; MacMahon Construction Pty Ltd v Crestwood Estates [1971] WAR 162, 167 (Burt J). The nominated time fixed for practical completion is replaced by an obligation to complete within a reasonable time.
(a) Clause 23 of AS2124 relevantly provides:[17]
The Principal shall ensure that at all times there is a Superintendent and that in the exercise of the functions of the Superintendent under the Contract, the Superintendent-
(a) acts honestly and fairly;
(b) acts within the time prescribed under the Contract or where no time is prescribed, within a reasonable time; and
(c) arrives at a reasonable measure or value of work, quantities or time.
(b) Clause 35 of AS2124 relevantly provides:[18]
35 TIMES FOR COMMENCEMENT AND PRACTICAL COMPLETION
The Contractor shall execute the work under the Contract to Practical Completion by the Date for Practical Completion.
Upon the Date of Practical Completion the Contractor shall give possession of the Site and the Works to the Principal.
35.5 Extension of Time for Practical Completion
When it becomes evident to the Contractor that anything including an act or omission of the Principal, the Superintendent or the Principal's employees, consultants, other contractors or agents, may delay the work under the Contract, the Contractor shall promptly notify the Superintendent in writing with details of the possible delay and the cause.
When it becomes evident to the Principal that anything which the Principal is obliged to do or provide under the Contract may be delayed, the Principal shall give notice to the Superintendent who shall notify the Contractor in writing of the extent of the likely delay.
If the Contractor is or will be delayed in reaching Practical Completion by a cause described in the next paragraph and within 28 days after the delay occurs the Contractor gives the Superintendent a written claim for an extension of time for Practical Completion setting out the facts on which the claim is based, the Contractor shall be entitled to an extension of time for Practical Completion.
(a) events occurring on or before the Date for Practical Completion which are beyond the reasonable control of the Contractor including but not limited to -
(b) any of the following events whether occurring before, on or after the Date for Practical Completion -
- the Principal's employees, consultants, other contractors or agents;
(ii) actual quantities of work being greater than the quantities in the Bill of Quantities or the quantities determined by reference to the upper limit of accuracy stated in the Annexure (otherwise than by reason of a variation directed under Clause 40);
(v) repudiation or abandonment by a Nominated Subcontractor;
(vii) directions by municipal, public or statutory authorities but not where the direction arose from the failure of the Contractor to comply with a requirement referred to in Clause 14.1;
(viii) delays by municipal, public or statutory authorities not caused by the Contractor;
(xi) any other cause which is expressly stated in the Contract to be a cause for extension of time for Practical Completion.
If the Contractor is entitled to an extension of time for Practical Completion the Superintendent shall, within 28 days after receipt of the notice of the number of days extension claimed, grant a reasonable extension of time. If within the 28 days the Superintendent does not grant the full extension of time claimed, the Superintendent shall before the expiration of the 28 days give the Contractor notice in writing of the reason.
In determining a reasonable extension of time for an event causing delay, the Superintendent shall have regard to whether the Contractor has taken all reasonable steps to preclude the occurrence of the cause and minimise the consequences of the delay.
Notwithstanding that the Contractor is not entitled to an extension of time the Superintendent may at any time and from time to time before the issue of the Final Certificate by notice in writing to the Contractor extend the time for Practical Completion for any reason.
A delay by the Principal or the failure of the Superintendent to grant a reasonable extension of time or to grant an extension of time within 28 days shall not cause the Date for Practical Completion to be set at large but nothing in this paragraph shall prejudice any right of the Contractor to damages.
78 I accept that, in the absence of the Superintendent's power to extend time even if a claim had not been made within time, Abigroup would be precluded from the benefit of an extension of time and liable for liquidated damages, even if delay had been caused by variations required by Peninsula and thus within the so-called "prevention principle". I think this does follow from the two Turner cases and the article by Mr. Wallace referred to by Mr. Rudge.
79 In my opinion, no error is shown regarding the primary judge's acceptance of the referee's conclusion based on the Superintendent's power. In my opinion, this power is one capable of being exercised in the interests both of the owner and the builder, and in my opinion the Superintendent is obliged to act honestly and impartially in deciding whether to exercise this power. Of course, if a timely claim has not been made, and the ground on which an extension is claimed is one which is difficult to decide because of the time that has elapsed since the time when the claim should have been made, that may be a ground on which the Superintendent can fairly refuse the extension; but there is no suggestion that that is the case here.
80 In my opinion also, the power to extend time, including the power to do so even if no claim has been made within time, does not automatically come to an end with the termination of the contract for the builder's breach. Clause 35.6, providing for liquidated damages, expressly operates after the contract has been terminated under cl.44; and in order for it to so operate there must be a date for practical completion on which the clause can operate after termination of the contract. If an application had been made within time before termination and not yet determined by the Superintendent at the time of termination, it is plain in my opinion that the Superintendent would have power to determine that claim after termination. If a claim had been made before termination but outside the time provided by cl.35, and the Superintendent had not made a decision in exercise of the Superintendent's power to extend time notwithstanding non-compliance, in my opinion the Superintendent could still do so after termination. In those circumstances, I do not think the Superintendent's power is lost on termination, even if the claim for exercise of the power to extend notwithstanding non-compliance had not been made until after termination.
81 For those reasons, it was in my opinion open to the referee to do what he considered the Superintendent should have done in response to the claims made to the referee; and it was open to the referee to conclude that the Superintendent, acting fairly, would have granted the extensions which the referee found to be justified. This view may have some further support from the referee's finding that Peninsula was itself in breach of cl.23 in failing to ensure that the Superintendent arrive at a reasonable measure of time in respect of delays caused by Peninsula and the Superintendent.
(a) The Superintendent's power is one capable of being exercised in the interests of both the owner and the builder; and > > (b) The Superintendent is obliged to act honestly and impartially in deciding whether to exercise it.
155. It is relevant that Clauses 23 and 35.5 in AS 2125-1992 are virtually the same as Cls 23 and 35.5 in the subject Contract. The first lines of the tenth paragraph of Cl 35.5 are:
'Notwithstanding that the Contractor is not entitled to or has not claimed an extension of time, the Superintendent may ...' [emphasis added].
156. The words 'or has not claimed' incorporated in AS 4300 and this Contract were not included in the AS 2124 clause considered in Peninsula Balmain by the Court of Appeal. In my view, this incorporation somewhat strengthens the application to this Contract of the finding in Peninsula Balmain.
[24] These articles advance the view that the reserve power given to the Superintendent under the penultimate provision of cl.35.5 (in its standard form) is only to be exercised for the benefit of the Principal. Unless the power is so construed, it is contended the power has the capacity to destroy the prescribed time limits forming the agreed framework for the performance of the contract.
[25] The Arbitrator then summarised the contentions of the parties (award [162]-[163]) and concluded:
"164. It seems to me that (having regard to Peninsula Balmain), if the Superintendent's discretionary power contained in the penultimate clause can be exercised in the interest of the Contractor, one must ask how can this situation sit comfortably with the mandatory steps precedent to an EOT entitlement as set out earlier in Cl 35.5?
165. In my view, the answer to the above question lies within the penultimate paragraph itself. If the Contractor fails to comply with the mandatory notice provision for an EOT, the Contractor is not entitled to an EOT as the claim is time barred. Such circumstances are expressly considered ('is not entitled to ... an extension of time') in the penultimate paragraph of Cl 35.5 and do not fetter the wide discretion of the Superintendent who (under Cl 23) is required to act 'honestly and fairly'. A similar situation applies to circumstances where the Contractor has not claimed an EOT. In applying Peninsula Balmain, the more difficult question to consider is what is fair in the circumstances.
166. Peninsula Balmain represents a change in direction of the law in respect of standard forms of the AS 2124/AS 4300 type which clothe the Superintendent with the independent discretion to extend time. The articles by Messrs Bellemore and Baron particularly defend the traditional view. However, I think there is force in Mr Jones' commentary which the Court of Appeal appears to have accepted. It is also clear that the Court of Appeal considered the commentary of Professor I.N.D. Wallace QC (Prevention and Liquidated Damages: A Theory Too Far? [2002] 18 BCL 82-86) which, in effect, respectfully disagreed with the decision on this point at first instance.
167. In my respectful opinion, in relation to the application of the penultimate paragraph of Cl 35.5, it seems that Peninsula Balmain was decided correctly both at first instance and on appeal.
168. Because of the Australia-wide use of contracts such as AS 2124/AS 4300, it also seems to me that it is appropriate to apply Peninsula Balmain in Victoria in the circumstances where there is no inconsistent decision of the Victorian Supreme Court."
[26] In my view the Arbitrator was correct in his decision:
(a) The primary mechanism of cl.35.5 gives the contractor an entitlement to an extension of time, subject to compliance with special conditions;
(b) The penultimate paragraph reserves a discretionary power to grant an EOT in other circumstances effectively where it is just and equitable to do so;
(c) Such power is expressly directed to situations where "the contractor is not entitled to or has not claimed an extension of time ...";
(d) It is expressed to arise on a separate and distinct basis from the provision for the extension of time pursuant to the primary mechanism;
(e) The grounds for exercise of the reserve power are expressed in the broadest possible terms as "for any reason".
(f) The potential prejudice to the principal flowing from a failure by the contractor to comply with s.35.5 is a matter going squarely to the equitable exercise of the Arbitrator's discretion.
[27] There is no basis in the objective language of the contract read as a whole to read down these last words by reference to one party alone.
[28] The words are as the Arbitrator observed subject to the obligation of the Superintendent to act "honestly and fairly".
[29] It was open to the parties to modify the contract to give effect to the limitation for which 620 contends, by the use of relatively simple language. They did not do so.
[30] To the contrary, as the Arbitrator observed, the parties adopted a form of condition which emphasised the independence of the Superintendent's discretion, by use of the words "or has not claimed an extension of time".
23A Principal's and Superintendent's discretion
The Contractor agrees that except to the extent expressly provided in the Contract:
(a) the Principal and Superintendent may exercise those discretions and rights given to them under the Contract in whatever way the Principal or Superintendent decide in their absolute discretion; and
(b) the Principal or Superintendent may grant, refuse or grant subject to reasonable conditions any consent required from the Principal or Superintendent in their absolute discretion.
(b) The Superintendent's discretion in clause 35.5 of AS2124 was omitted and the following included:
Notwithstanding that the Contractor is not entitled to or has not claimed an extension of time, the Superintendent may at any time and from time to time before the issue of the Final Certificate by notice in writing to the Contractor extend the time for Practical Completion for any reason in the Superintendent's absolute discretion and without being under any obligation to do so.
[39] So in the present case, in applying the reasoning from Peninsula Balmain, the adjudicator construed this contract as imposing an obligation upon the Superintendent under cl 35.5A. The Principal argues that this was in error because it is contrary to the words of the clause. In particular it is inconsistent with the express provision in this clause that the Superintendent is under no obligation. Further, it is inconsistent with the express provision here that the Superintendent's discretion is "absolute".
[40] That submission of the Principal should be upheld. Accepting the correctness of Peninsula Balmain and the cases which have followed it, in this contract however the parties have substituted different terms and the expressed intention was to confer a power on the Superintendent without imposing any obligation as to the exercise of that power. Indeed the deletion of the relevant paragraph in cl 35.5 and the addition of cl 35.5A and cl 35.5B appear to have been drafted with Peninsula Balmain in mind. In my view there is no tenable construction of cl 35.5A by which the Superintendent could be said to be under any obligation and in particular an obligation to extend time if it would be fair to do so. Absent such an obligation there was no entitlement in any sense to an extension of time, if there had not been compliance with cl 35.5. So in the adjudicator's calculation, he was wrong to have included delay costs for which extensions of time have not been granted and for which there was no entitlement to an extension under cl 35.5 or cl 35.5A. This error resulted in the adjudicated amount being excessive by about $740,000.
51 The scheme of cl 35.5 of the first contract is as follows:
- When it becomes evident to the contractor that anything may delay the contract works, the contractor shall promptly notify the superintendent in writing with details of the possible delay and cause;
- If the contractor is or will be delayed in reaching practical completion by one or more of the specified causes, and within 28 days after the delay occurs the contractor gives the superintendent a written claim for an extension of time for practical completion, the contractor shall be entitled to an extension of time;
- If the contractor is entitled to an extension of time, the superintendent shall, within 28 days after receipt of the notice of the number of days for which extension is claimed, grant a reasonable extension of time;
- Notwithstanding that the contractor is not entitled to an extension of time (because, for example, of the failure to lodge a written claim), the superintendent has the power at any time before the issue of the final payment certificate to extend the time for practical completion.
58 Under cl 23 of the General Conditions of the first contract, the principal is under a duty to ensure that the superintendent acts honestly and fairly (cl 23(a)). The appellant seems to rely on the following matters in support of the claim that the prevention principle is enlivened in this case:
1. the respondent had breached its duty to ensure the superintendent acted honestly and fairly as a result of the superintendent's breach of his duty to consider and, if appropriate, grant the appellant's requests for an extension of time regardless of the absence of any relevant notice;
2. in the alternative, by reason of waiver and/or estoppel of the requirement for notice, the superintendent was in breach of his obligation to consider and, if appropriate, grant an extension of time.
59 That is, the appellant relies on the breach of cl 35.5 to re-activate the prevention principle. I infer it does so in order to set the time for practical completion at large so the liquidated damages clause ceases to apply to all of the delay, howsoever caused.
60 The appellant's propositions ignore the last paragraph of cl 35.5 which provides that the failure by the superintendent to grant an extension of time does not cause the date for practical completion to be set at large or prejudice the contractor's right to damages.
61 Whether and to what extent cl 35.5 is intended to exclude the application of the prevention principle is a matter of contractual construction. The objectively determined purpose of cl 35.5 is at least twofold. The first is to provide contractual machinery to prevent the time for practical completion being set at large as a result of the application of the prevention principle. The second is to place on the principal the risk of delay caused loss not attributable to any contractual party. However, it would appear its purpose is not to exclude the prevention principle itself insofar as it applies to delay caused by the principal's breach of the building contract. In the absence of an extension of time under cl 35.5, the contractor would be entitled to damages against the principal for its breach of contract, including any damages (liquidated or otherwise) it suffered as a result of principal-caused delays in practical completion. Whether or not that could be relied on as a defence (such as equitable set-off) does not have to be decided. In the result, cl 35.5 brings the prevention principle back into line with the general contractual principles relating to the implied duty to cooperate. Accordingly, it is unnecessary to determine whether contractual parties are free to exclude the implied duty to cooperate, which is a term implied by law.
62 The same analysis would apply to a (derivative) breach by the principal arising from a superintendent's breach of the duty to consider the exercise of the power in cl 35.5. Moreover, it is arguable that the prevention principle is a relevant consideration in the exercise of the superintendent's discretion to extend time in relation to the 'non-breach' causes of delay specified in cl 35.5. If a court or another decision-maker concludes that the superintendent should have exercised the power and granted an extension of time, the principal will be prevented from claiming liquidated damages for the relevant (proven) delay. In summary, the relevant purpose of cl 35.5 is to prevent the prevention principle having the effect of setting time at large.
63 On this analysis, the respondent would not be entitled to liquidated damages for the period (42 days) for which the appellant should have been given an extension of time under cl 35.5. As the practical outcome is the same as that reached by the trial judge, grounds 3, 4 and 5 should be dismissed.
[27] Clause 41.5 (Notice of Delays) provided a mechanism for DDI to give Probuild notice of any delay in the progress of the Subcontract works and to claim an extension of time to the Date for Practical Completion. Clause 41.5(b) - (i) set out a list of the matters DDI was required to set out in a Delay Notice.
[29] Clause 41.6(b) described the "only" circumstances in which DDI was entitled to an extension of time. Pursuant to the clause, such an entitlement only arose where, among other matters, a delay was directly caused by a Delaying Event, DDI was or would be delayed in progressing the Subcontract Works such that they would not reach Practical Completion by the Date for Practical Completion, DDI had not caused or contributed to the delay and had complied strictly with all obligations imposed on it by cl 41 (including giving Probuild notice of the delay). Clause 41.6(c) provided that the Head Contractor would not be liable on any Claim (including for an extension of time) which had not been made strictly in accordance with cl 41 and any such Claim was barred.
(a) The right of the Subcontractor to make a Claim for an extension of time pursuant to this clause is the Subcontractor's sole remedy under this Subcontract in respect of any delay or delays. The Subcontractor is not entitled to any increase or adjustment to the Subcontract Sum or any other monetary compensation or damages (including damages for breach of contract in respect of any such delay).
(a) Notwithstanding that the Subcontractor is not entitled to or has not claimed an extension of time, the Head Contractor may at any time and from time to time before the issue of the Final Certificate under this Subcontract by notice in writing to the Subcontractor extend the time for Practical Completion for any reason.
(a) A delay or failure by the Head Contractor to grant a reasonable, or any, extension of time shall not cause the Date for Practical Completion to be set at large.
114 In Spiers Earthworks Pty Ltd v Landtec Projects Corp Pty Ltd (No 2), McLure P (with whom Newnes JA agreed), by reference to Hudson's Building and Engineering Contracts, observed that "[t]he essence of the prevention principle is that a party cannot insist on the performance of a contractual obligation by the other party if it itself is the cause of the other party's non-performance". As frequently observed, there is debate about the juridical basis for the principle. In Spiers Earthworks, McLure P observed that it "may be regarded as a particular manifestation of the obligation to cooperate implied as a matter of law in all contracts", referring to Secured Income Real Estate (Aust) Ltd v St Martins Investments Pty Ltd.
115 The prevention principle applies to delays in practical completion caused by variations resulting from the act or default of the principal. Ordering variations after the due date which must substantially delay completion will, unless the contract provides otherwise, and in the absence of an applicable extension of time clause, disable the proprietor from recovering or retaining liquidated damages which might otherwise have accrued after the giving of the order. In the context of delaying variations, whether ordered before or after the due date for completion, the prevention principle "is grounded upon considerations of fairness and reasonableness".
116 The prevention principle may preclude an owner recovering liquidated damages for delay in the completion of works by the contractor where that delay has been caused by an act or omission of the owner in breach of the contract. This is because, if it applies, the contractual date for practical completion ceases to be the proper date for the completion of the works and, if there is no contractual mechanism for the substitution of a new date in the events which have occurred, then there is no date from which liquidated damages can run and the right to liquidated damages will be lost. In other words, the time for performance is "at large", although it should be undertaken within a reasonable time.
117 The operation of the prevention principle can be modified or excluded by contract. The manner in which this can be done, as relevant to the present case, is by extension of time provisions such as cll 41.5 - 41.6. Those clauses established a procedure by which, in the event of an actual or likely delay caused as provided in cl 41.6(b)(i), DDI could advise Probuild of the matters set out in cl 41.5, including whether it sought an extension of time to the Date for Practical Completion.
118 In the event, which Probuild contends occurred, that DDI failed to seek an extension of time pursuant to that provision, it is arguable (depending upon the proper construction of the Subcontract) that the prevention principle did not operate. This is, in essence because, as Cole J explained in Turner (No 1), DDI failed to exercise a contractual right which would have negated the effect of the preventing conduct.
119 Probuild submitted such extension of time provisions were inserted for the benefit of the principal to a building contract. That is only true in part. Clearly they are capable of having that effect to the extent they preclude the operation of the prevention principle. But they are also capable of operating for the contractor's benefit, by enabling an extension of time to be granted and thus meaning the contractor is not exposed to a liquidated damages claim.
126 In Spiers Earthworks, McLure P thought it "arguable that the prevention principle is a relevant consideration in the exercise of the superintendent's discretion to extend time in relation to the 'non-breach' causes of delay specified in cl 35.5" and that "[i]f a court or another decision-maker concludes that the superintendent should have exercised the power and granted an extension of time, the principal will be prevented from claiming liquidated damages for the relevant (proven) delay".
127 Osborn J followed Peninsula Balmain in 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) in relation to a provision almost identical to cl 41.9 save that, as in Peninsula Balmain, the reserve power was vested in the Superintendent. In his Honour's view, the reserve power was to be exercised "effectively where it [was] just and equitable to do so, ... [was] expressly directed to situations where 'the contractor is not entitled to or has not claimed an extension of time ...', is expressed to arise on a separate and distinct basis from the provision for the extension of time pursuant to the primary mechanism [and] [t]he grounds for exercise of the reserve power [were] expressed in the broadest possible terms".
128 In my view, and contrary to Probuild's submissions, Probuild was obliged to exercise the reserve power to grant extensions conferred by cl 41.9 honestly and fairly having regard to the underlying rationale of the prevention principle to which I have earlier referred or, if necessary, because there is an implied duty of good faith in exercising the discretion cl 41.9 conferred.
129 It needs hardly be said that whether there have been relevant acts of prevention, and whether, in all the circumstances Probuild was entitled to liquidated damages, or DDI was entitled to an extension of time for the entire period encompassed by Probuild's liquidated damages, turned on the terms of the Subcontract in the events which had happened. However, as a matter of general principle, both the liquidated damages and extension of time clauses in printed forms of contract must be construed strictly contra proferentem.
Subject to the Subcontractor having submitted a claim for an extension to the Date for Completion in writing to Growthbuilt within 5 days of the commencement of an Act of Prevention, including details on the nature, cause, effect and duration of the delay, the Subcontractor will be entitled to a reasonable EOT to the Date for Completion in respect of a delay caused by an Act of Prevention. The Subcontractor will not be entitled to any EOT to the Date for Completion for any other reason, event or circumstance. The Subcontractor will have no Claim for any additional or increased costs whatsoever including any delay and/or disruption costs.
Failure by the Subcontractor to give notice to Growthbuilt strictly in accordance with the preceding paragraph within the stated period of 5 days for any delay to the Date for Completion caused by an Act of Prevention will disentitle the Subcontractor from making a claim (including for additional payment or time) against Growthbuilt and the Subcontractor will have no Claim arising out of or in any way connected with any delay to the Works caused by an Act of Prevention.
It is an essential and fundamental term of this Subcontract that, notwithstanding anything to the contrary in this Subcontract, an EOT granted under this Subcontract only entitles the Subcontractor to an EOT to the Date for Completion and not to any delay, disruption costs and/or any other costs. For the avoidance of doubt, the Subcontractor agrees that it has no Claim relating to or in connection with any EOT claim and/or alleged delay including without limitation delay or disruption caused by Growthbuilt or its employees, subcontractors, consultants or other agents.
Growthbuilt may in its absolute discretion at any time and for any reason, without prejudice to its rights or the Subcontractor's obligations under this Subcontract, extend the Date for Completion, but Growthbuilt is under no obligation to extend, or to consider whether it should extend, the Date for Completion.
In this clause 11, "Act of Prevention" means an event or circumstance which results in actual delay to the Works and which is one of the following causes:
(a) an act or omission of Growthbuilt or its employees, other contractors or agents, except for an act or omission authorised or permitted by this Subcontract, or which arises as part of proper exercise of any rights of Growthbuilt, or its consultants, agents or other contractors (not being employed by the Subcontractor under this Subcontract);
(b) a breach of this Subcontract by Growthbuilt; or
(a) First, neither in clause 11 (nor in any other provision) was there a term like clause 23 AS2124; > > (b) Second, although the principal part of the clause uses the language of entitlement to an extension of time, the discretionary clause does not say "notwithstanding that the subcontractor is not entitled to an extension of time" or any similar language which would permit the inference that the discretionary clause is premised on the contractual mechanism not having been complied with; > > (c) Third, the Contractor's discretion is in terms of an "absolute discretion" which the Contractor was under no obligation to exercise.
67 Modern submitted that in view of Probuild and the other authorities to which I was referred, even though Modern had failed to seek EOTs under the subcontracts, Growthbuilt was obliged to act reasonably and in good faith in exercising its discretion under cl 11 having regard to the prevention principle if delays were solely due to Growthbuilt. It submitted that the implied terms obliged Growthbuilt to act reasonably and in good faith in terms of the way cl 11 operated as a whole, both in the exercise of its absolute discretion to extend the Dates for Completion under the subcontract and also in its consideration of whether it should extend those Dates. In other words, Modern contended that Growthbuilt was also obliged to act reasonably and in good faith in deciding whether to rely on that part of cl 11 that stated that Growthbuilt was under no obligation to extend the Dates for Completion or to consider whether it should extend them.
71 However, in this case, the discretionary power to extend the Dates for Completion that is described as "absolute" is contained in a clause that also expressly excludes any obligation on Growthbuilt to exercise the power to extend or to consider whether to do so. In other words, the express terms of the subcontracts make clear that, despite having the discretionary power to do so, Growthbuilt has no obligation to extend or make any decision whether or not to extend time under the subcontracts at all. Unlike the reserve power clauses in Probuild and Peninsula Balmain, cl 11 also states that Growthbuilt's discretion may be exercised without prejudice to Modern's obligations under the subcontracts and the power to do so does not arise solely because Modern is not entitled to or has not claimed an EOT.
72 An obligation of reasonableness and good faith in the exercise of a unilateral contractual power may be implied as a matter of law as an incident of a particular type of commercial contract. However, the implication of such terms cannot extend to imposing obligations on parties that are, in effect, inconsistent with the terms of the relevant agreement itself: Cordon Investments Pty Ltd v Lesdor Properties Pty Ltd [2012] NSWCA 184 at [146], citing Vodafone at [194] and [208].
73 I was of the view that there was no room to impose an obligation on Growthbuilt to exercise the power to extend the Dates for Completion, whether reasonably or fairly in the interests of Modern having regard to the prevention principle or not, in circumstances where the express terms of cl 11 provided for no such obligation. On this point, I note that none of the cases to which I was referred by Modern's counsel contained a contractual provision which stated that the relevant decision maker had no obligation to exercise the discretionary power conferred onto them.
74 I was also of the view that there was no room for a reasonableness or good faith obligation to be imposed on Growthbuilt in deciding whether to rely on the last part of the clause that provides for no obligation on Growthbuilt to extend time or consider whether to extend time. As Growthbuilt submitted, and I accepted, it made little sense and seemed circular to contend for an implied term that obliged Growthbuilt not to rely on an express exclusion of the obligation to exercise that discretion (or consider doing so).
75 To have construed cl 11 in the way contended for by Modern would, in my view, not have been consistent with the well-known principles of construction of commercial contracts in cases such as Electricity Generation Corporation v Woodside Energy Ltd (2014) 251 CLR 640; [2014] HCA 7 at [35] and Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104; [2015] HCA 37 at [47]. The language of "absolute discretion" and "no obligation" reflected a clear intention to confer a discretionary power to extend without any obligation being imposed on Growthbuilt to exercise or to consider whether to exercise that power.
(a) The discretion conferred is not described as an absolute discretion, which distinguishes the clause from those considered in Hervey Bay and Growthbuilt; and > > (b) Notwithstanding the lack of any express requirement that the discretion be exercised reasonably and in good faith, analogous to clause 23 AS2124, such an obligation would be implied in clause 13.4.
(a) The mere conferral of discretion of itself invokes the obligation to exercise it reasonably and fairly; and/or > > (b) The underlying rationale of the prevention principle or an implied term of good faith compels that conclusion.
(a) The prevention principle is a specific example of the general implied term requiring cooperation, and as such, it can be modified or excluded by agreement; > > (b) Extension of time mechanisms of the kind set out in clauses 13.1 and 13.2 have been accepted as being effective to exclude the implication of a term giving effect to the prevention principle; > > (c) Terms which confer a discretion on a contract administrator or principal to extend time, despite failure of the builder to seek or obtain an extension of time under a contractual extension mechanism, have been construed in some cases as giving rise to an obligation to consider extending time for principal-caused delay; and > > (d) Whether a clause conferring such a discretion gives rise to such an obligation depends on the proper construction of the clause.
(a) The Plaintiff was the cause of the Defendant's delay; or > > (b) The delay was caused by the Plaintiff's breach of the Contract;
the answer is that the Plaintiff's entitlement has not been lost in those circumstances.
[1] Paragraph 24(d) of the Reply filed 17 August 2021.
[3] J D Heydon, Heydon on Contract (Lawbook Co., 2019) at [3.320].
[4] See paragraph 38 of Haggarty's submissions and footnote 14 which is an Affidavit of Alexander Paul Tuhtan filed 6 August 2021 at paragraph [14].
[6] Paciocco v ANZ Banking Group Ltd (2016) 258 CLR 525 at [261] to [267].
[7] [2015] QCA 291 at [11].
[9] Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd (No 2) [2012] WASCA 53; (2012) 287 ALR 360; Peninsula Balmain Pty Limited v Abigroup Contractors Pty Limited [2002] NSWCA 211; Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151; (2017) 95 NSWLR 82. So far as I could determine, the prevention principle has not been the subject of specific analysis in the Queensland Court of Appeal.
[10] In recent times, for example: Kane Constructions Pty Ltd v Sopov [2005] VSC 237; 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491; Hervey Bay (JV) Pty Ltd v Civil Mining and Construction Pty Ltd [2008] QSC 58 especially at [33] to [40]. See also Growthbuilt Pty Ltd v Modern Touch Marble & Granite Pty Ltd [2021] NSWSC 290.
[11] J D Heydon, Heydon on Contract (Lawbook Co., 2019) at [21-370].
[13] Ibid at [21-370] especially at page 847; and in the context of the prevention principle specifically: Peninsula Balmain Pty Limited v Abigroup Contractors Pty Limited [2002] NSWCA 211; Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151; (2017) 95 NSWLR 82 at [117].
[14] Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd (No 2) [2012] WASCA 53; (2012) 287 ALR 360 at [50] to [55] and the cases cited there; Probuild Constructions Aust Pty Ltd v DDI Group Pty Ltd [2017] NSWCA 151; (2017) 95 NSWLR 82 at [114] to [121].
[16] There have been successive versions of AS2124, but it does not appear that there were material differences in the form of the General Conditions relevant here in any of the cases under consideration.
[17] [2002] NSWCA 211 at [8].
[19] [2006] VSC 491 at [22].
[20] For 620 Collins Street Pty Ltd v Abigroup Contractors Pty Ltd (No 2) [2006] VSC 491, see [35] to [37].
[21] See Spiers Earthworks Pty Ltd v Landtec Projects Corporation Pty Ltd (No 2) [2012] WASCA 53; (2012) 287 ALR 360 at [57].
[22] See Growthbuilt at [70] and Hervey Bay at [4].
Midson Construction (Qld) Pty Ltd
The Haggarty Group Pty Ltd [2021] QDC 280
(2006) 236 ALR 796
(2016) 258 CLR 525
(2017) 95 NSWLR 82
(2012) 247 CLR 205
(2005) 224 CLR 656
(1979) 144 CLR 596
(2014) 251 CLR 640
(2015) 256 CLR 104
(2012) 287 ALR 360