[2026] VCAT 49
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2026-01-16
Original judgment source is linked above.
(a) Bank Guarantee No 202204-0098 with a value of $2,772,500;
(b) Performance Bond No 202204-0099 with a value of $2,772,500; and
(c) Bank Guarantee DG1119833418 with a value of $555,630.50
(a) Bank Guarantee No DG1078963418 with a value of $2,500,000; and
(b) Bank Guarantee No DG1067763418 with a value of $1,319,999.
Mr R Harris of senior counsel with Mr D Peacock of counsel
The Contractor failed to achieve Practical Completion of Separable Portions 1, 2, 3, 4 and 5a and 5b by the relevant Adjusted Dates for Practical Completion, as set out in the table below.
Pursuant to clause 34.7 of the Contract, if the Contractor fails to bring the Works to Practical Completion by the Date for Practical Completion, the Contractor will be immediately liable to pay (as a debt due) to the Principal liquidated damages in the amount identified in Item 29 for every day after the Date for Practical Completion up to the earlier of the Date of Practical Completion or the date of termination of the Contract. Any liquidated damages payable under clause 34.7 will be due and immediately payable by the Contractor regardless of whether or not:
To date the Contractor has failed to pay the liquidated damages demanded in the First, Second, Third, Fourth, Fifth, Sixth, Seventh or Eighth LD Demands.
The Contractor shall provide Security to the Principal in the amount stated in Item 14(a) on or before the date of the Contract.
(a) for the security to be held until practical completion, an approved unconditional bank guarantee without an expiry date given by the authorised deposit-taking institution within the meaning of the Banking Act 1959 (Cth) with branches in the State or Territory in which the site is located; or
(b) for the security to be held after practical completion, an unconditional undertaking in the form of an insurance bond, approved by the Principal and the Financier.
Security is provided to ensure the due and proper performance of the Contract by the Contractor.
The Principal may, at any time and on 2 days prior notice to the Contractor, have immediate recourse to or convert a security that does not consist of money, into money where:
(a) the Contractor is in breach of any of its obligations under the Contract or the Principal has become entitled to exercise a right under the Contract in respect of the security;
(b) the Principal has become entitled to be indemnified by the Contractor under the Contract;
(c) there is any amount or debt due, or due and payable by the Contractor to the Principal under the Contract; or
(d) the Principal asserts acting reasonably a bona fide entitlement to payment of money (including by way of set off) by the Contractor under or in connection with the Contract;
If it is established that the Principal was not entitled to call on the security at the date of conversion into money, the Principal shall pay interest on the amount converted at a rate appearing in Item 14(b) from the date of conversion until the first to occur of the date of repayment or the date that the Contractor defaults in the due and proper performance of the Contract.
(d) the Principal has a right to convert security which does not consist of money into money at any time;
(e) in the event of such conversion, the amounts payable by the Principal under clause 5.2 are an adequate remedy for the Contractor; and
(f) the Contractor has no entitlement to obtain an injunction or otherwise restrain:
(i) the Principal from converting any security;
(ii) any issuer of any security provided under this clause 5 from paying the Principal pursuant to that security;
(iii) the Principal from taking any steps for the purposes of making a demand under such security or receiving payment under any security;
(iv) using any retention money held by the Principal; or
(v) the Principal using the money received under any such security.
Subject to clauses 5.2 and 5.7, upon the issue of the certificate of practical completion the Principal's entitlement to security shall be reduced by the percentage or amount in Item 14(c), and the reduction shall be released and returned within 14 days to the Contractor.
The Principal shall ensure that at all times there is a Superintendent. The Superintendent will give directions and carry out all its functions under the Contract (including the receipt of payment claims and the issue of payment certificates) as agent of the Principal (and not as an independent certifier, assessor or valuer).
(a) when exercising the role of certifier, assessor or valuer in assessing the price under clause 29.4 for a variation, granting extensions of time under clause 34.5, assessing delay costs under clause 34.9, valuing variations under clause 36.4, certifying progress claims under clause 37.2, certifying practical completion under clause 34.6, certifying the final certificate under clause 37.4, and certifying costs under clause 39.6 when work is taken out of the hands of the Contractor, the Superintendent:
(i) acts honestly;
(ii) arrived at a reasonable measure or value of work, quantities or time,
but this shall not prevent or place any restriction upon the Superintendent discussing with or receiving submissions or representations from either the Principal or the Contractor about any certification, assessment of valuation before or after it is made, nor place the Superintendent under any obligation to seek any response from a party to, or otherwise raise with that party, any such discussion with or submission or representation received from the other party; and
(b) acts within the time prescribed under the Contract, or where no time is prescribed, within a reasonable time.
(a) Within 28 days after receiving the Contractor's claim for an EOT in respect of which the Contractor has an entitlement under clause 34.3, the Superintendent shall give to the Contractor and the Principal a written direction evidencing the Superintendent's assessment of the provisional EOT to which the Contractor is entitled.
(c) Notwithstanding anything to the contrary in the Contract, the parties acknowledge and agree that:
(i) where the Superintendent directs an EOT in accordance with this clause 34.5, such an EOT is on a provisional basis only; and
(a) Notwithstanding clause 34.5, if the Contractor fails to bring the Works to practical completion by the date for practical completion, the Contractor will be immediately liable to pay (as a debt due) to the Principal liquidated damages in the amount identified in Item 29 for every day after the date for practical completion up to and including the earlier of:
(i) the date of practical completion; or
(ii) the date of termination of the Contract under clause 39.9 or 39A.
Any liquidated damages payable under this clause 34.7 will be immediately payable by the Contractor regardless of whether or not:
(i) practical completion has been reached or the date for practical completion has occurred; and
(ii) the date for practical completion as determined under clause 34.5 is provisional or final.
(b) For the avoidance of doubt, liquidated damages (at the rate identified in Item 29) will accrue and be payable separately and cumulatively for each separable portion, but the cumulative amount of liquidated damages per day will be limited to and will not exceed the amount identified at Item 29.
The Principal shall not be liable to pay for unfixed plant and materials unless they are listed in Item 34 and the Contractor:
(a) provides the additional security in accordance with clause 5 in an amount equal to the payment claimed for the subject plant and materials; and
(b) satisfies the Superintendent that the subject plant and materials have been paid for, properly stored and protected, and labelled the property of the Principal.
Upon payment to the Contractor and the release of any additional security in clause 37.3(a), the subject plant and materials shall be the unencumbered property of the Principal. Any additional security provided for any item of unfixed plant and materials will be released in accordance with clause 5.4.
(a) bank guarantee identified as DG 1078963418 issued by the Australia and New Zealand Bank (ANZ) dated 13 July 2023 in the amount of $1,319,999 in respect of precast and joinery materials; and
(b) bank guarantee identified as DG 1078963418 issued by the ANZ dated 8 September 2023 in the amount of $2,500,000 in respect of glazing/façade materials.
(a) In order to establish an entitlement to interlocutory relief an applicant must show that there is a serious question to be tried. The applicant must make out a prima facie case of success at trial to justify the preservation of the status quo pending the determination of the parties' rights at trial, in the circumstances. How strong the probability needs to be depends upon the nature of the rights asserted and the practical consequences likely to flow from the relief sought. > > (b) The applicant must also establish that the balance of convenience favours the granting of an injunction. The court should take whatever course appears to carry the lowest risk of injustice, should it turn out to have been wrong in the sense of granting an injunction to a party who fails to establish its right at trial or failing to grant an injunction to a party who succeeds at trial. > > (c) Incorporated within the consideration of "balance of convenience" or sometimes considered as a separate matter, is the question whether damages would be an inadequate remedy, meaning that unless the injunction is granted the applicant will suffer irreparable injury for which damages will not be adequate compensation. > > (d) Those questions are not to be considered in isolation from one another, but must be considered together. In considering where the lower risk of injustice lies all relevant factors are to be weighed in the balance. The strength of the applicant's case and their chances of success may be a relevant matter when assessing the balance of convenience. > > (e) In cases of this kind these principles are applied in a particular way. > > (f) As Callaway JA explained in Fletcher Construction Australia Ltd v Varnsdorf Door Pty Ltd (Fletcher Construction), a beneficiary may, broadly speaking, stipulate for a guarantee for two reasons. One is to provide security against the risk from the defaulting party. The second is, "to allocate the risk as to who shall be out of pocket pending resolution of the dispute. The beneficiary is then able to call upon the guarantee even if it turns out, in the end, that the other party was not in default." The intended purpose is determined by construing the underlying contract. > > (g) Performance bonds such as unconditional bank guarantee are regarded as "a type of currency" and as being, "as good as cash"'. A contract stipulating or incorporating an unconditional guarantee may, depending on its terms, create a "pay now, argue later" regime. > > (h) Where a performance bond is intended to allocate risk in this way, the grant of an interlocutory injunction might frustrate the parties agreed commercial purpose by preventing the use of the agreed mechanism.
(i) The frustration of risk allocation regime agreed between the parties is a prospect about which courts considering applications to restrain reliance on performance bonds must be vigilant.
(j) The first requirement then, is to construe the Contract to determine whether the parties intended by stipulating for security, to create an interim risk allocation mechanism. It is permissible to have regard to the terms of the performance guarantee where they are stipulated by the contract or where the guarantee is itself contained in the contract. Indeed, the terms of the guarantee may be important in discerning contractual intent.
(k) That question of construction should be decided on an as-if final basis if the factual matrix before the court permits...
(l) If the security was intended to allocate risk pending a final determination of rights there is a further question, namely, whether there is any relevant qualification or prohibition affecting the beneficiary's ability to call on the security - that is, a contractual promise not to call on the security unless certain conditions are satisfied...
(m) That question too, is one of construction... Where the contract does impose a condition on the right to access the security, the party seeking to restrain recourse must establish the existence of a serious question to [be] tried as to whether the beneficiary has in fact met the contractual requirements.
(n) Even when there is no contractual condition or fetter on the beneficiary's right to call on security, courts will enjoin a party in whose favour the performance guarantee has been given from acting fraudulently or unconscionably in calling on the security. Some principles relevant to unconscionability are discussed below.
(o) Absent those considerations, the beneficiary of a performance guarantee intended to operate as a risk allocation device will be entitled to call on the guarantee even if it turns out, ultimately, that the other party was not in default and notwithstanding the existence of a genuine dispute and a serious issue to be tried as to its underlying entitlement.[5]
[18] Although it cannot be said that it is always the duty of a court on an interlocutory application to decide a question of law upon which the decision of the case depends, more often than not performance bonds stand in a separate category, his Honour's reasoning demonstrates that he did not give adequate weight to the essential character and evident commercial purpose of GC 5.2 as agreed by the parties. Conversely, on examination, the circumstances identified by his Honour are of insufficient weight to justify postponement of the question of construction. Furthermore, it was necessary to construe GC 5.2 in order to identify the criteria by reference to which to access the respondent's submission that on the facts the appellant had no entitlement under the contract to seek recourse to the bank guarantees.
Any security provided by the Contractor in accordance with the Contract shall be available to the Principal whenever the Principal may claim (acting reasonably) to be entitled to:
(i) the payment of monies by the Contractor under or in consequence of or in connection with the Contract;
(ii) reimbursement of any monies paid to others under or in connection with the Contract; or
(iii) other monies payable by the Contractor to the Principal (whether by way of set off or otherwise).
[19] In Fletcher Construction Australia Ltd v Vansdorf Pty Ltd, Charles and Callaway JJA addressed the commercial purpose of contractual provisions of the type in issue.
[20] Callaway JA observed:
There are broadly two reasons why the beneficiary may have stipulated for a guarantee. One is to provide security. If it has a valid claim and there are difficulties about recovering from the party in default, it has recourse against the bank. The second reason, which is additional to the first, is to allocate the risk as to who shall be out of pocket pending resolution of a dispute. The beneficiary is then able to call upon the guarantee even if it turns out, in the end, that the other party was not in default. It is a question of construction of the underlying contract whether the guarantee is provided solely by way of security or also as a risk allocation device. Remembering that we are speaking of guarantees in the sense of standby letters of credit, performance bonds, guarantees in lieu of retention monies and the like, the latter purpose is often present and commercial practice plays a large part in construing the contract.
"... The principal dilemma about the grant of interlocutory injunctions, whether prohibitory or mandatory, is there is by definition a risk that the court may make the 'wrong' decision, in the sense of granting of an injunction to a party who fails to establish his right at the trial (or would fail if there was a trial) or alternatively, in failing to grant an injunction to a party who succeeds (or would succeed) at trial. A fundamental principle is therefore that the court should take whatever course appears to carry the lower risk of injustice if it should turn out to have been 'wrong' in the sense I have described..."
Does clause 5.2 of the Contract also operate as a risk allocation device?
A party shall not convert into money security that does not consist of money until the party becomes entitled to exercise a right under the contract in respect of the security...
It would, as Charles JA said in Fletcher, be strange if the clauses construed in that case and this - Clause 3.13 (b) and Clause 22.4 - conferred the practical right of recourse only where monies were "due" from the supplier to the purchaser in some such sense as actually or indisputably due. I would treat Clauses 5.5 and 22.4 of the present contract, read in conjunction, as entitling the purchaser, as between itself and the supplier, to have recourse to the security where according to a bona fide claim made by the purchaser monies are due to it from the supplier which exceed any monies due from it to the supplier.[9]
The Company shall have the right under this guarantee to invoke the Banker's guarantee and claim the amount thereunder [sic] in the event of the Contractor failing to honour any of the commitments entered into under this Contract. [464]
[92] The essential question then is whether, cl 3.3.3 of the contract, when read with cl 2 of the performance guarantee, imports an express or implied negative stipulation in the contract that ONGC would not invoke the security absent actual breach. More particularly, was there an express or implied negative stipulation precluding ONGC from calling upon the guarantee in the event that Clough was able to establish a genuine dispute as to whether it was in breach of the contract? See Reed at 165.
[93] In our view there was no such stipulation. We reject Clough's submission that the words "on breach of contract" in the performance guarantee indicate that the intention of the parties was that there must be actual breach before the guarantee could be invoked. To so confine the terms of the contract would be to ignore the words "notwithstanding any dispute(s) pending" in cl 2 of the performance guarantee.
[94] It seems to us to be plain that upon proper construction of cl 3.3.3 of the contract, when read together with cl 2 of the performance guarantee, ONGC was entitled to invoke the guarantee notwithstanding the existence of a dispute between Clough and ONGC as to whether Clough had failed to honour any of its commitments under the contract.
[95] The whole tenor of the performance guarantee is that it was payable on demand by ONGC on breach by Clough but without reference to Clough and without any "demur, reservation, contest or protest" by that company. In our view this emphasises the proposition that the intention of the parties to the contract was that Clough was not entitled to raise the existence of a dispute as to whether it was in actual breach as an answer to the invocation of the guarantee and a claim under it.[12]
[77] Nevertheless, the authorities have recognised three principal exceptions to the rule that a court will not enjoin the issuer of a performance guarantee, or bond, from performing its unconditional obligation to make payment. The exceptions were succinctly stated, with references to relevant authorities, by Austin J in Reed Construction Services Pty Ltd v Kheng Seng (Aust) Pty Ltd 15 BCL 158 at 164-5 (Reed):
First - the court will enjoin the party in whose favour the performance guarantee has been given from acting fraudulently...
Second - the party in whose favour of the performance bank guarantee has been given may be enjoined from acting unconscionably in contravention of s 51AA of the TPA...
Third - the most important exception for present purposes, is that, while the court will not restrain the issuer of a performance guarantee from acting from an unqualified promise to pay (Reed Construction Services at 164 per Austin J):
... if the party in whose favour the bond has been given has made a contract promising not to call upon the bond, breach of that contractual promise may be enjoined on normal principles relating to the enforcement by injunction of negative stipulations in contracts.
Any security provided by the Contractor in accordance with the Contract shall be available to the Principal whenever the Principal may claim (acting reasonably) to be entitled to:
(i) the payment of monies or an indemnity by the Contractor under or in consequence of or in connection with the Contract;
[139] In the present case, clause 5.2 contains three preconditions to the exercise by the appellant of its right to access a security specified in clause 5.1. First, the appellant must be "acting reasonably" in making the claim to the entitlement to payment or reimbursement. Secondly, the claim by the appellant must be in relation to an entitlement to one of three categories of payment, reimbursement or indemnity specified in sub- clauses (i), (ii) and (iii) of clause 5.2. Thirdly, the appellant must first give the respondent five days' notice of its intention to have recourse to the security.
[141] In construing clause 5.2, it is important to bear in mind, first, that that provision does not require the appellant to establish or demonstrate an entitlement to the payment, indemnity or reimbursement referred to in the clause. Rather, it is sufficient that the appellant has a "claim" to such an entitlement. In that respect, it is relevant that the clause only requires the appellant to provide five days' notice to the respondent of its intention to have recourse to the security. In that way, it is clear that the security, provided under clause 5.2, was intended to serve both purposes described by Callaway JA in Fletcher Construction, namely, to provide security to the appellant, and also to allocate the risk to the respondent as the party which should be out of pocket pending resolution of any dispute between the parties.
[142] On the other hand, the requirement, that the appellant be "acting reasonably" in making the claim, is an express qualification to the appellant's right to access the security provided in clause 5.1. The qualification is expressed to require that the appellant be "acting reasonably" in making the claim. Thus, it does not, in express terms, require that the claim itself be reasonable. In particular, the clause does not make it necessary that the claim, ultimately, be proven to be a reasonable claim by the appellant. Rather, what must be established is at the appellant, in making the claim, was then "acting reasonably". In that way, the phrase "acting reasonably" has an important temporal aspect. It focuses attention on the conduct of the appellant at the time at which the appellant made the claim stated in the recourse notice.
[143] It was argued on behalf of the appellant that the phrase "acting reasonably" required the appellant to do no more than act bona fide in a subjective sense. That submission does not give adequate weight to the requirement that the appellant be acting "reasonably". Ordinarily, concepts of reasonableness are construed as importing an objective standard of conduct...
[144] Thus, in my view, clause 5.2 required the appellant, at the time it made the claim, then be acting reasonably, in an objective sense, based on the information and facts. Or which reasonably ought to have been known, to the appellant at the time. However, as I stated, at the same time, clause 5.2 did not require the appellant to have such knowledge that would decisively establish its entitlement to payment, indemnity or reimbursement of the monies claimed in the recourse notice. Rather, the clause required no more than that the appellant had acted reasonably in making the claim, based on the facts and circumstances, which it knew, or ought to have known, concerning the validity of that claim.
Security shall be subject to recourse by a party who remains unpaid after the time for payment where at least 5 days have elapsed since the party notified the other party of intention to have recourse.
(a) The superintendent has failed to follow the procedure in clause 34.5 as the Superintendent was required to, inter alia, assess any claim for an extension of time within 28 days, whether or not the claim was accepted; > > (b) The Applicant has submitted various EOT claims numbered 4, 6-9, 11-15, 19-23, 25-26 and 29-52 that had not been determined as at the date of the various Recourse Notices or are the subject of a formal notice of dispute. The unassessed EOT claims had not been assessed within the 28 day period mandated by the building contract; > > (c) On a proper construction of clause 34.7 read in conjunction with clause 34.5 (c), it is a precondition to the issuing of a certificate for liquidated damages that the Superintendent assess the EOT claim submitted by the applicant under clause 34.5. Axiomatically, the Superintendent is required to carry out such an assessment in order to conclude that 'the Contractor has failed to reach Practical Completion by the Date for Practical Completion'. It would render the EOT regime in clause 34 inutile if the Superintendent was empowered to certify liquidated damages as owing under clause 34.7 regardless of whether certain EOT claims had been assessed and/or that claims the subject of a notice of dispute had not been resolved under the contractual process. > > (d) Recourse Notices issued in breach of clause 34.5 and 34.7 are invalid and of no effect; > > (e) The purported Recourse Notices issued by the Superintendent are infected with the Respondent's breach of clause 20 of the building contract; > > (f) Pursuant to clause 20 of the Contract, the Respondents were required to ensure that the Superintendent (amongst other things) acted honestly and within the time prescribed (or within a reasonable time) and arrived at a reasonable measure or value of work, quantities or time. The Respondents are in breach of this clause; > > (g) Further the Respondents did not provide to the Applicants any adequate opportunity to make submissions to the Superintendent regarding the EOT claims; > > (h) The Respondents' conduct in attempting to have recourse to either the Performance Certificate [sic] or the Materials Security in the context of the above conduct constitutes unconscionable conduct within the meaning of ss 20 to 22 of the ACL: see, for example, Uber Builders and Developers Pty Ltd v MIFA Pty Ltd [2020]; Clough Engineering Ltd v Oil and Natural Gas Corporation Limited (2008); Olex Focas Pty Ltd & Anor v Skodaexport Co Ltd [1998].[14]
(a) the EOT claims that were not assessed within 28 days were deemed to be approved (and therefore not taken into account); and
(b) numerous EOT claims were extant and unassessed at the time when the recourse notices and specifically, the Recourse Notice was served.
Are the EOT claims deemed to be approved if not determined assessed within 28 days?
Within 28 days after receiving the Contractor's claim for an EOT in respect of which the Contractor has an entitlement under clause 34.3, the Superintendent shall give to the Contractor and the Principal a written direction evidencing the Superintendent's assessment of the provisional EOT to which the Contractor is entitled.
(a) In many cases, Crema advised that the delaying event that was the subject of an EOT claim to be "ongoing". In many instances, the Superintendent reserved its determination until after Crema notified the Superintendent that the delay had ceased. Columns C and D of the table at Annexure A to my affidavit shows when Crema first submitted its, and then final EOT claims. > > (b) Many of Crema's EOT claims required further information or documents in order for the Superintendent, and I have been copied to a number of Aconex exchanges to this effect. I understand that the delay in Crema providing this information, or the fact that the information was not made available initially may have delayed the Superintendent's ability to determine the EOT claims quicker; > > (c) Since my involvement on the Project, I have been copied to numerous requests from the Superintendent to Crema to provide a program that accurately reflects the progress of the works. Such program information was necessary for the Superintendent to determine the EOT claims... > > (d) In some cases, Crema withdrew the EOT Claims prior to the Superintendent determining the claim, or they acknowledged that the delay was not experienced on-site...
Do all EOT claims need to be assessed before the Principal is entitled to assert an entitlement to the payment of money?
(a) Subject to providing the Contractor with 3 days prior written notice of its intention to have recourse to the Security, the Principal may convert all or part of the Security into cash at any time and use the proceeds of the security:
(i) in relation to any debt or money due or claimed to be due from the Contractor to the Principal under the contract (including liquidated damages under subclause 34.7) or any cost, expense, loss or damage of any kind which the Principal has incurred or claims that it has incurred or might in the future incur in connection with what the Principal contends constitutes any act, default or omission of the contractor.
... restriction upon the Superintendent discussing with or receiving submissions or representations from either the Principal or the Contractor about any certification, assessment or valuation before or after it is made, nor place the Superintendent under any obligation to seek any response from a party to, or otherwise raise with that party, any such discussion with or submission or representation received from the other party...
That type of evidence could be, in any given case, very powerful where there is the slightest doubt that the performance bond is being called other than rightfully. The consequences of its call might be catastrophic to the business reputation of a company that has never had a call made on it and whose position would be repairable a damaged or harmed.[23]
... The strength of the applicant's case and their chances of success may be a relevant factor when assessing the balance of convenience.[26]
Unfixed plant and materials for which payment claims may be made
Lifts, Façade, Joinery, Precast concrete subject to the quantity surveyor and Financier's written approval
Subject to clauses 5.2 and 5.7, upon the issue of the certificate of practical completion, the Principal's entitlement to security shall be reduced by the percentage or the amount in Item 14(c), and the reduction should be released and returned within 14 days to the Contractor.
If the Contractor has provided additional security pursuant to clause 37.3, the Principal shall release that additional security within 14 days of the incorporation into the Works of the unfixed plant or materials in respect of which the additional security was provided.
Even if the Principal is otherwise required to release security, the Principal has a right to retain from the security an amount sufficient to cover the reasonable expected cost of rectifying defective work.
... An apparently strong claim may lead a court more readily to grant an injunction where the balance of convenience is fairly even. A more doubtful claim, which nevertheless raises a serious question to be tried, may still attract interlocutory relief if there is a marked balance of convenience in favour of it.[31]
[1] Separable Portion 5 was subsequently split into 5(a) and 5(b), effectively making six separable portions.
[2] Clause 37.4 (b) of the Contract provides that liquidated damages will accrue and be payable separately and cumulatively for each Separable Portion but the cumulative amount of liquidated damages per day will be limited and will not exceed the amount identified at Item 29, which is $22,000 per day.
[3] The Principal has also indicated that it has no immediate intention to have recourse to the additional security provided (referred to as the materials security).
[6] (2015) 31 BCL 407; [2015] VSCA 98.
[7] Applicant's Submissions, dated 1 December 2025, [32]-[33].
[14] Applicant's Submissions, 1 December 2025, [26] (footnotes omitted).
[15] (Building and Property) [2018] VCAT 696.
[16] Clause 34.5(c)(i) of the Contract.
[19] Affidavit of Frank William D'Annibale dated 29 November 2025, [85]-[103].
[20] Affidavit of Frank William D'Annibale dated 29 November 2025, [52]-54] and Appendix A.
[21] Affidavit of Adam Keenan-Dunn; Applicant Submissions dated 1 December 2025, [46].
[24] Thiess Py Ltd v Pacific National (Victoria) Pty Ltd [2009] VSC 670, [17]-[23].
[25] Affidavit of D'Annibale dated 29 November 2025 at [114]. The matters raised by Mr D'Annibale in paragraph 114 of his affidavit dated 29 November 2025 are largely disputed by Mr Keenan-Dunn in his affidavit dated 1 December 2025, at paragraph 27.
[26] [2020] VSC 596 [26(d)].
[27] [2015] VSCA 98, [21].
[28] Affidavit of Frank William D'Annibale dated 29 November 2025, [83].
[32] Affidavit of Adam Keenan-Dunn dated 20 November 2025, [76].
Crema Constructions Pty Ltd
Malvern Project Developments Pty Ltd and Ors
(2017) 59 VR 607
(2022) 276 CLR 1
(2008) 249 ALR 458